Piling &Diaphragm wall works at BMRCL Metro Depot Project

(2A), at Bangalore

DAILY PROGRESS REPORT


Project :- Piling &Diaphragm wall works at BMRCL metro depot Project (2A)
Owner :- Bangalore Metro Rail Corporation Limited Progress Date :- 23-11-2023
Main Contractor :- M/s AIC Infrastructures Pvt Ltd. Day :- Thursday
Sub Contractor :- M/s Keller Ground Engineering India Pvt Ltd. Weather :- Dry & Rainy

Completed
Current Workfront
Activities UOM Scope Workfront Availability Balance Remarks
Till Yesterday Today Upto date availability

No 6 1 1 0 1 5 0 Commenced on 27th June


TEST Pile-800 ∅

No 9 1 1 0 1 8 0 Commenced on 21 st June
TEST Pile-1000 ∅

No 252 147 147 0 147 105 0


Working Piles-800 ∅ (EDS-01)

No 54 47 44 0 44 10 3
Working Piles-1000 ∅ (EDS-01)

RM 301.20 290.20 268.20 0 268.20 33.00 22.00


Guide wall

No 54 52 44 1 45 9 7 Commenced on 28 th August
Diaphragm Wall

Under
Manpower details No. List of Major Equipment No. Working Remarks
repair
STAFF PILING RIG SR-285 R 0 0 0

Project Manager 1 XCMG-XGC 55T Crawler Crane 0 0 0

Production manager / Asst. Manager 2 F17 HYDRA Crane 0 0 0

Engineer / Sr. Engineer 1 SANY-220 Excavator 0 0 0

QA / QC Engineer 1 SANY-220 Excavator 0 0 0

P & M Engineer 0 412 CFM air compressor 1 1 0

HSE Lead / Officer 2 Diesel Generator-125 Kva 1 1 0

Accountant 1 PILING RIG HR-180 (M12) 1 1 0

WORKERS EXCAVATOR-200 1 1 0

Superintendent/Supervisor 0 MANITOWOC -80T Crawler crane 1 1 0

Surveyor 2 XCMG XGC 100A 1 1 0

Mechanic 0

Electrician 2

Welder 3

HR Admin 1

Store Keeper & Asst Store keeper 1

Operators
8
(Piling Rig/Crawler crane/Excavater / Hydra crane)

Foreman 2

Pump Operator 2

Helpers 7

Cage Fabrication Team (Sub-con) 28

Concreting Team (Sub-con) 16

Chipping Team (Sub-con) 14

TOTAL STRENGTH 94

Remarks :- Additional Notes & Comments, Delays, Daily Activities if any :-


1. D wall chipping works under progress.
2. Muck Disposal under progress.
3. Area Preparation and levelling for further guide wall casting is under progress.
4. Anchor Sleeve is being fabricated in site.
5. Capping Beam rebar fabrication is under progress.