Professional Documents
Culture Documents
Work Method
Work Method
Work Method
TABLE OF CONTENTS
1.0 General
WORK METHODE
1.0 GENERAL
1.1 Introduction
CONTRACTOR will ensure the following Objectives, which are proposed and committed
to by the CONTRACTOR with limitation condition due to the contract agreement.
۰ Quality Assurance of each phase of the Project will be refer to the Quality Assurance
and Quality Control procedure of the project to meet the code and standard
۰ Achievement of Time Schedule
The best way to achieve the contractual completion date(s) stipulated in the Contract
is sequential achievement step-wise, examining and confirming both quality and
safety.
In order to achieve the time schedule, CONTRACTOR will organize the best project
execution team and proper work force with effective quality and safety control.
This Project Execution Plan will describe CONTRACTOR’s approach to the Project.
CONTRACTOR offers an organisation whose strengths, resources, facilities, experience,
technology and skills constitute a valid basis for the success of the Project Execution. The
project will be undertaken under strict control by single responsibility from start until
completion.
This Project Execution Plan outlines the development of the Project with a logical shift of
the centre of activities according to the progress of the WORK. In this framework, the
successful approach to the Project Execution is assured by a fully integrated Project
organisation and the implementation of the following key elements:
Meet the overall Project schedule
Attain the quality objectives
Maintain effective management control
Co-ordination procedure
Project control
Reporting
Cost control
Project administration of the activities related to the execution of the work
Provision and obtaining government or statutory authority approvals where
required
The Project Management Team will draw its resources from experienced Project
management personnel. The Project Management Team will be located mainly at Project
Home Office with emphasis on the detail engineering phase, then will be relocated to the
Site as the centre of gravity of the Project activities shifts towards Construction.
A Procurement Team will be established as part of the Project Management Team upon
award of the Contract and will direct, co-ordinate and monitor the Project Procurement
activities as well as the interface with OWNER.
The Project Engineering Team will be led by a Project Engineering Manager who,
supported by a team of Lead Specialist Engineers and Lead Process Engineers, will direct
and co-ordinate the continuation design activities since its project start throughout its
conclusion with the Site Engineering.
Site Manager will be also part of the Project Management Team and will jointly work
with the Home Office Construction Co-ordinator for the elaboration of the Construction
plan.
The main site activities will commence around the Assessment and Site investigation
work phase when CONTRACTOR will mobilise to Site, but front site activities will start
earlier to perform preparation work for construction.
The whole site organisation, which will be headed by the Site Manager under the
overall supervision of the Project Manager, shall be gradually built up in the
construction phase. As far as the centre of gravity of the Project activities shifts to the
Construction Site, certain key personnel of the Project Management Team shall also
move from Project Home Office to Site for a better engineering assistance to the site
and also for a more direct interface with OWNER during the key phases of Construction.
CONTRACTOR’s p oje t a d/o eside t Site Manager will arrange regular co-ordination
meetings with OWNER, to discuss the various phases of the Work and its status. During
these meetings, remedial matters for resolving difficulties encountered or foreseen and
other subjects related to the Work shall be discussed.
All correspondence will show the project title, OWNER’s p oje t u e a d spe ifi
subject covered.
Mobilisation will start immediately after the CONTRACT award with the target of setting
up an organisation able to face the efficiently activities in the initial phase of the Project.
The group of key personnel to be mobilised will be generally composed of the personnel
involved in the Project bidding phase i.e.:
۰ Project Director
۰ Project Manager
WORK METHODE Page 3 of 32
۰ Engineering Manager
۰ Site Manager
۰ Construction Manager
۰ Project Control Manager
۰ Project Procurement Manager
۰ Each Discipline Lead Engineer
Project Manager will manage the mobilisation of the engineering staff and in particular
of the leaders of each technical discipline to continuing the remaining engineering work
to completion.
It is anticipated that the mobilisation will be completed and the offices will be rendered
fully operational timely enough to meet urgency of project schedule upon the award of
the CONTRACT.
A CONTRACT Kick-off meeting will be held as per contractual requirements with the
participation of the OWNER a d CONTRACTOR’s ke pe so el.
CONTRACTOR will develop and submit after the contract award to OWNER for approval
a Comprehensive Detailed Project Schedule for the total project based on the WBS
(work Breakdown Structure). The project schedule will be developed using the critical
path method (CPM), will be in bar chart from, and scheduling logic will be provided. The
entire execution of work will be controlled by the project schedule. The project schedule
will have an activity list that will identify all work to be carried out by the CONTRACTOR.
The project schedule will be compatible or in advance of all milestones listed as key
milestone dates in the contract. Once approved, no changes to the project schedule can
be made without OWNER approval.
The CONTRACTOR will also notify OWNER at least once a month by the monthly
progress report the status of the critical action items that could affect the completion of
work. In addition, the CONTRACTOR will include an action plan of proposed remedial
actions for expediting these items to achieve the completion date. Costs for any such
items required to maintain the schedule will be borne by CONTRACTOR.
۰ The CONTRACTOR will prepare and issue after award of contract a schedule detailed
design refer to the previous design as reference to save the engineering phase and
grouped by disciplines. The schedule will show the document title number and the
planned start and completion states.
Monthly Reports
The CONTRACTOR will issue a monthly progress report to OWNER, at the seventh
calendar day of each month following the reporting period.
Format and contents will be submitted to and approved by OWNER, however, the
report will include the following minimum information for the project as a whole and for
each major component of the project, as applicable:
۰ Executive summaries
۰ Overall project status
۰ Time schedules
۰ Work performed during the reporting period, including the critical path activities
and work in progress at the end of the period.
۰ The current status of Work in narrative and graphical demonstration of scheduled
versus actual performed Work for.:
- CONTRACTOR engineering
- Equipment and material commitment
- Equipment and materials received at Site
- Field construction activities
- Commissioning and start-up activities
۰ Work planned during the next reporting period, including the critical path activities
۰ Manpower force and monthly summary of construction force reports
۰ Milestone statuses
۰ Update of the CPM schedule include s-curves indicating in detail actual versus a
schedule progress for all works
۰ Delays, changes and other problem areas and their impact
۰ Proposals for maintaining schedule or recovering lost time and other planned
corrective actions
۰ Monthly summary of the procurement report
۰ Pictures of the Site for progress demonstration
The CONTRACTOR will promptly report in writing to OWNER the occurrence of any
event or condition that might delay or prevent completion of the Work in accordance
with the approved schedule and indicate steps being taken to meet the schedule.
Other Reports
۰ Remaining Procurement Status Report: Will be issued every month in the Monthly
Progress Report. This report will show the status of all requisitions, Bid Requests
and purchase orders for equipment identifiable by tag number, and non-engineered
materials and subcontracts by category. The report will also highlight problem areas.
۰ Shop Inspection Reports: will be issued as soon as they are received from the shop
inspectors highlighting quality and expediting information.
۰ Construction Force Reports: Shall be issued to OWNER’s ep ese tati e o a dail
basis. It will show the total number of employees, contractors and subcontractors,
by craft for manual labor and non-manual staff on site.
۰ Safety Report: The CONTRACTOR will issue a weekly safety report documenting
safety meetings and training sessions that took place, and that are planned in the
future.
۰ Safety Incident Report: An incident report will be issued as soon as possible after
any accident for the following:
- Death from any causes whatsoever.
- A fractured scull, pelvis, arm, thigh, leg, fool or spine.
- A dislocated shoulder.
- The amputation of an arm, hand or of one or more fingers, or leg or a foot.
- The loss of sight of an eye.
- Any other serious bodily injury, including internal bleeding, burns, asphyxia where
such injury is likely to endanger life, cause permanent incapacity or temporary
incapacity of 5 days or more.
In the cases of death, the CONTRACTOR will immediately report the accident and
disposition to the nearest police station so they can make the proper investigation in
accordance with the law.
1.6 Meetings
The CONTRACTOR will be responsible for arranging the meetings, issuing the agenda.
During the project phase the Project Review Meeting will be held monthly or at shorter
intervals if requested by OWNER.
During the construction phase weekly co-ordination meetings shall take place at Site.
The location of the meeting for each work stage will be discussed in detailed after
contract.
The OWNER representatives will be hosted both, where all meetings, reviews and
discussions between OWNER and CONTRACTOR will occur; it will be CONTRACTOR care to
ensure that all necessary information, knowledge and documents are made available at
the Office where the meeting, reviews and discussions will occur.
Soon after award of the CONTRACT, the technical information from the previous
contractor to be continued and used as basic, which constitutes a part of the Project
Master Plan, will include:
Identification of Project data.
List of systems and items and their subdivision to ensure the status of each
condition.
Identification of Critical Items in terms of technical complexity, delivery time,
construction.
Identification of package units.
List of remaining design documents to be produced
Schedule of interdisciplinary reviews of main documents
2.1.1 Systems
Certain topics within the Engineering Design may be treated under the form of
s ste s . I this ase, ea h dis ipli e i ol ed ill de elop ge e al philosophies and
specifications based on contractual requirements and scope of work; typically this
applies to:
Electrical system
Instrumentation and automation
Telecommunications
Fire & Gas detection
Fire protection
Balance of Plant
Excluding the material and equipment that already provide from the previous contractor
will identified and determine by contractor to procurement process.
The design, engineering, construction and maintenance will also consider the
requirements stated in Indonesia codes and standards and any local and/or
governmental/authority rules and regulations except where the requirements in the
Contract are more stringent, in which case the latter will prevail.
All documentation (e.g. balances, process flow diagrams, Piping and Instrument
diagrams, data sheets, manuals, etc.) from Vendors, Subcontractors, sub-suppliers,
suppliers of package units, etc., will also conform to requirements defined below. All
such documents must be suitable for integration into the documentation prepared by
the CONTRACTOR.
The design/engineering services will include all process engineering and detail design
Work, including any studies and calculations required for economic implementation of
the project.
The CONTRACTOR is responsible for covering all other points and items necessary during
its detailed engineering/design.
CONTRACTOR will:
Detailed Engineering will also cover the revision and updating of the main Design
documents (i.e. P&ID’s, Plot Pla s, , etc.) which require constant updating depending on
the pu hase o de s pla i g a d feed a k of Ve do s’ do u e ts.
A timely feedback from Vendors will be obtained by the Engineering team and it will be
accomplished through a tight and constant interface with all the Vendors also by taking
advantage from the Procurement Centres allocated to follow up the supply packages
within their Scope of WORK.
All documents issued to OWNER will be forwarded with a transmittal letter. The
transmittal letter and attached document will state the action to be taken.
All the Engineering activities will be examined and reviewed/approved during dedicated
design reviews conducted in full compliance with the Quality Assurance procedures.
OWNER reserves the right to review and comment on transmitted documents prepared
by CONTRACTOR, Vendors or Subcontractors. OWNER returns one copy of such
documents or fax with its comments.
CONTRACTOR to submit documents of all revision status as requested and all other
documents necessary to complete OWNER information even if not specifically defined.
CONTRACTOR will perform procurement activities in accordance with the guidelines set
forth in procedure.
Equipment and materials will be procured competitively from the world-wide market.
The Project Procurement Manager will constitute the reference point for OWNER for any
matter regarding procurement of equipment and materials and will be responsible for
the preparation of the main procurement documentation such as:
3.1 Scope
3.2 Purchasing
Receipt of a Material Requisition (MR) from an engineering department will mark the
beginning of the procurement activities related to the equipment and material subject to
the MR. Project Vendor List can be amended by CONTRACTOR subject to OWNER’s
approval by adding or deleting some vendors whose capability will be proved through
proper procedures during the course of project execution.
Purchasing will prepare and issue a Request for Quotation (RFQ) to Vendors selected
based on the Project Vendors/Subcontractor List.
The Contract language for all forms, documents, bids, letters and drawings, etc. shall be
English, unless otherwise expressly stated in the contract.
The Project Procurement Manager will monitor the relevant working flow and will assist
the enquiries world-wide expediting.
The Project Procurement Manager will also be responsible for the Enquiries Status Report
(to be included in the Overall Material Status Report) which will include:
۰ Enquiry Number
۰ Description of Equipment/Material
۰ Revisions, if any
۰ Date of issuance
۰ Requested date of submission by Vendors
۰ Contacted Vendors
۰ Responses by Vendors (confirm quotation, decline, waiting)
Once the Technical Evaluation is received from the appropriate Specialist Leader or
Engineer, Purchasing will perform the following:
۰ Select the technically acceptable Vendor Bid (considering also transportation and
packing costs),
۰ Negotiate with the selected Vendor(s) in order to obtain the best possible
commercial conditions.
۰ Prepare the Purchase Order, which will include all the necessary and suitable clauses
including:
- Definition of exact scope of supply, by mentioning the pertinent technical
specifications and standards;
- Definition of delivery point of material/equipment;
- Definition of delivery terms of materials/equipment
- Definition of payment conditions as necessary and appropriate to the kind of order
concerned.
- Definition of requirements to provide representatives at the CONSTRUCTION SITE.
- Price list, commercial conditions and period of price validity for the possible future
purchase by OWNER of two years spare parts, capital spares.
۰ Issue the Purchase Order to the selected Vendor after having been obtained its
signature by the duly authorised signatory person.
The Project Procurement Manager will be responsible for the Purchasing Orders Status
Report (to be included in the Overall Material Status Report) which will include:
The activities required to ensure that the actual delivery times of equipment and bulk
material are in accordance with the established Project schedule and technical
specifications will be carried out by Expediting and Inspection.
3.3.1 Inspection
The CONTRACTOR shall issue reports on each inspection for submission to OWNER. Any
p o le that ould affe t ualit fo deli e ti e shall e highlighted gi i g the easo
and the action to solve the problem.
۰ Scheduled dates of testing inspections during fabrication (intermediate and final) and
scheduled delivery dates
۰ Classification of equipment / material
۰ Inspection data sheets indicating the level of surveillance required for all the type of
material to be supplied. This level (Quality Category) will be defined taking into
account both the product complexity and its function in the Units
۰ Tailo i g of sta da d CONTRACTOR’s ope ati g p o edu es he e e essa
۰ Specialised Inspectors from Qualified International Inspection Agencies.
On this basis, Inspection will execute the testing indicated in the instructions attached to
each Purchase Order. The testing activities can include, as appropriate:
3.3.3 Expediting
The Procurement Manager will be also responsible for the issuance of the overall
Expediting Plan which will be based on the following main topics:
۰ Scheduled significant dates during fabrication and scheduled delivery dates at the
planned delivery points (Ex works Supplier workshop or FOB Departure Port / Airport)
۰ Type and frequency of contacts with Vendors according to the criticality of the
delivery date
۰ Tailo i g of sta da d CONTRACTOR’s ope ati g p o edu es, he e e essa .
On this basis, the Expediters will monitor the intermediate activities carried out by
vendors such as engineering, suborders, progress etc. by paying an adequate number of
visits to the Vendors shops including, when necessary, sub- e do s’ fa to ies.
The overall Material Status Report will include, about expediting, the following:
3.4.1 General/Responsibility
The CONTRACTOR will follow the provisions of the contract and be responsible for the
following items:
The overall Material Status Report will include, about shipping, the following:
The Project Procurement Manager will monitor the working flow and be the official linking
point with the construction site and will assure the necessary co-ordination in the cases in
which materials belonging to different centres can be shipped by the same departure port
in the same periods. The Procurement Manager will also be responsible for the issuance
of overall Shipping Plan.
The CONTRACTOR shall arrange transport insurance covering all risks related to
transportation.
3.4.6 Documentation
The CONTRACTOR shall be responsible for the preparation, drawing up and distribution, if
necessary by courier service, of the relevant shipping documents in due time, e.g.:
3.4.7 Information/Service
The CONTRACTOR shall prepare a shipping schedule taking into account the contractual conditions.
This shipping schedule has to be updated monthly over the entire period of handling. The
shipping schedule shall also contain separate information on heavy/large-size packages.
In connection with shipment scheduling, monthly progress reports/status and shipping
lists have to be submitted to OWNER. Anticipated customs clearance time shall be
included in the shipping schedule.
CONTRACTOR implement the activities related to customs clearance and import duties
for the equipment and material sources.
CONTRACTOR prepare the following documents for the customs clearance of imported
equipment/materials:
Overall project schedule of this project will be depended upon the delivery of long lead
items. The delivery of long lead equipment to be decided to the bidding stage.
4.1 General
The CONTRACTOR shall present to OWNER a construction plan, if any, for the Work and
construction procedure to execute the plan prior to start construction. Depending on the
construction plan
- All labour and supervision, construction equipment, tools, site facilities including
temporary workspace and storage sites for equipment, site utilities, temporary and
ate ials e essa fo the o st u tio of the fa ilities. All the CONTRACTOR’s
supplies, provisions and services have to be in compliance with valid laws, codes, rules
regulations, specifications and approved drawings.
WORK METHODE Page 17 of 32
- The CONTRACTOR shall be responsible for satisfactory execution of installation in
connection with temporary Site facilities and Site utilities and ensure that these
installations comply with all relevant codes, rules, regulations, etc. and do not create
hazards and/or impediments to persons, objects for working orders.
The CONTRACTOR shall remove all temporary Site facilities and restore area to its original
condition prior to Completion of the Work.
CONTRACTOR will plan, manage and control all the construction activities for the Project
with full knowledge of the applicable laws and regulations, conditions of labour, local
conditions, the site conditions and environmental aspects, and will comply with the
requirements thereof.
The work will be carried out by the use of and by the coordination with professional
management, coordination, planning and control with accurate and timely reports
consistent with accepted good practice.
The CONTRACTOR shall establish, operate and maintain a Site organization, constituting
a esse tial pa t of the o t a to ’s ge e al p oje t o ga izatio a d ha i g e e uti e
responsibility, in order to achieve the mutual objective of completion and commissioning,
in compliance with the relevant plans, drawings, technical standards, specifications and
safet egulatio s et ., i his “u o t a to s’ offi es a d ith the “ite ep ese tati es of
OWNER. CONTRACTOR will provide a construction organization chart upon mobilization
at the site.
Site Ma age ’s staff, hi h shall i lude a “afet Ma age , QA/QC Ma age , a d othe s
as required, shall be responsible for the construction Site efforts, direct all Work to be
carried ort in the various fields activity, coordinate the performance of all Work groups
and assign all Work.
The CONTRACTOR will be fully responsible for his staff and work force, including
subcontractor and vendor personnel, and will advise shi employees to refrain from
participating in any illegal gatherings and disorderly acts, but to exhibit only the utmost
in good conduct. OWNER has the right to insist on the dismissal of persons having
violated the above or not following the general safety rules. The CONTRACTOR will fill
the position of the dismissed offender by an employee with a proven, fair record of
conduct and ability without delay and without cost to OWNER.
The CONTRACTOR will ensure that their expatriate personnel as well as all
“u o t a to s’ e pat iate pe so el o tai the e essa passpo ts, isas, ok
permits, and other documents required to enter and leave Site at such a time that the
construction schedule will not be delayed. Such personnel will not violate the
immigration laws of Site.
CONTRACTOR Site management organization will be issued later after the project
effective date run.
A Construction Management Team at the Construction Site will manage the Construction
under the direction of the Site Manager. The Construction Management Team will be set
up integrating experienced personnel of CONTRACTOR organization.
The Construction Management Team assigned to the Project will be drawn from the
esou e pool of CONTRACTOR’s Co st u tio “pe ialists, to e su e ele a t e pe ie e
and familiarity in dealing with labour of various nationalities from diverse culture and
ethnic backgrounds.
Construction personnel will first be mobilized to the Project Home Office to assist in the
development of the project plans and to provide input and direction to the project team.
4.3.3 Constructability
While the major benefits of a constructability program are gained during the detail
design, the program will also move into the construction phase of the project and be a
key tool in achieving the project objectives for Safety, Quality, schedule, budget, and
effective integration of start-up and operation.
۰ Topographic Surveys
۰ Blasting work
۰ Completion of Site Preparation
b) Early Information for Approval (IFA) drawing release to support construction team
c) Timely manpower mobilization
d) Timely construction equipment mobilization
e) Timely delivery of equipment & material to site
f) Timely delivery of tools/consumable and living necessaries to Site
4.3.4 Mobilization
The site construction mobilization for this project will be headed by a Construction
Management Team. The mobilization will be composed of an integrated staff of
expatriate local personnel. With this staff, CONTRACTOR will undertake the overall
management, planning, coordination, inspection, and control of all construction activities
from the site survey, initial planning and design, through the actual construction of
facilities.
During each of these phases, CONTRACTOR will define priorities and schedule the
engineering and procurement activities to ensure that the special requirements of this
project, especially regarding the schedule, material control and safety areas, are met.
Particular attention will be paid to relations with local authorities and at the same time
every arrangement for timely manpower mobilization, timely delivery of equipment &
WORK METHODE Page 21 of 32
ate ial to site ill e take to keep the p oje t s hedule. CONTRACTOR’s ele a t
experience will assist in developing and executing this project on schedule.
CONTRACTOR will initiate remain plans for temporary facilities necessary to support the
construction phase which go in common to support the field activities.
CONTRACTOR will make every effort to maximize employment of skilled workers. In the
early stage of the project, CONTRACTOR will forecast required field manpower by craft.
This forecast would be developed reflecting the information quoted from subcontractors
and reviewed periodically and reported to OWNER in order to assure sufficient
manpower for the execution of the construction work.
The first stage in the supervisory staff mobilization program will be the assignment of
key personnel to engineering / procurement offices for input into the constructability
plans for the design, and for a period of familiarization with the project prior to being
assigned to the site.
Required labor will be forecasted in advance and will be recruited accordingly. Skilled
labor will be tested according to craft and project qualification standards/requirements.
Working hours will be follow the local working time. Overtime work, if deemed
necessary, will be performed. Moreover, CONTRACTOR will be vigilant and remain
flexible with respect to the work schedule to suit any emergency or special requirements
such as work activities involving road crossing, shutdown, tie-ins, and testing.
The Quality control at the site will be an integral part of the overall QC System for this
Project. The plan is intended to specify the methods to be applied in order to achieve the
quality objective of completing the construction in accordance with the Project
Specifications.
It will also establish Procedures for the monitoring and verification of the work as it
progresses. The control of documentation and non-conformances will define the set-up
and organization to handle these functions.
The Quality control at site will address applicable requirements of the Project Quality Plan
and contain the following:
4.9.1 General
CONTRACTOR will make sure that all people working under this contract will be informed
about the security requirements, and the CONTRACTOR will impose disciplinary actions in
case of violation of those rules by and of his employees, subcontractors, labour or other.
For the security of the site, CONTRACTOR will provide fencing in accordance with the
requirements of the work and will safeguard the site. All personnel and visitors involved
in the construction project will only be allowed to give access to the site through
controlled gates in the existing fence.
The CONTRACTOR will ensure that all employees and visitors wear at all times a
numbered security pass, issued by the CONTRACTOR, within the site area. This security
pass ust ea the a e of the CONTRACTOR’s o pa .
CONTRACTOR’s e plo ees ust pa k thei ehi les i a eas desig ated OWNER at the
site. They will use designated entrances and proceed by designated routes to work areas.
Measures will be taken to prevent unauthorized persons from access.
WORK METHODE Page 24 of 32
4.9.3 Security Supervisor
The contractor will appoint a security supervisor who will administer the security
personnel and be responsible for the whole security functions.
5.1 General
The following security and safety instructions are basic requirements and it will not
release the CONTRACTOR of his responsibility.
- CONTRACTOR will make sure that all people working under this Contract are informed
about the safety requirements and the CONTRACTOR will impose disciplinary actions in
case of violation of those rules by any of his employees, Subcontractors, labour or other.
- Where the Work is performed within or at the boundaries of operating facilities, extra
hazards may be present which require special precautions.
- For the security of the Site, CONTRACTOR will provide fencing in accordance with the
requirements of the Work and shall safeguard the Site.
- The vehicle traffic shall also be controlled. Measures shall be taken to prevent
unauthorized persons from access.
- CONTRACTOR will nominate a person responsible for the safety and security of the Site.
CONTRACTOR will provide security guard(s). Safety meetings will be held weekly with a
report to OWNER.
- For safety, CONTRACTOR will maintain a clean work Site and keep those areas free of
rubbish, scrap and wastes.
- Hazardous non-smoking areas will be clearly identified. However, generally all of the
Facilities areas will be regarded as non-smoking. Special smoking areas can be
established only with OWNER’s itte o se t.
- CONTRACTOR will maintain and supply adequate fire-fighting equipment during the
execution of the work.
6.1.1 Introduction
A Quality Plan will be compiled for the implementation of CONTRACTOR Quality Policy on
the project.
The Plan will be based on CONTRACTOR Quality Management System, adopted to meet
the specific requirement of the project.
CONTRACTOR has established and applies Quality System in compliance with ISO 9001 -
2008 for Project Management, Engineering and Design, Procurement, Construction
Management Services for Civil, Building and housing, power plant, Electrical and
Structural Steel Works including Site Construction Activities.
CONTRACTOR's Quality Policy is to provide Client with plant, equipment and services,
which in terms of performance, safety, reliability, ease of operation and maintenance
conform both to the relevant, contractual and regulatory requirements in a cost effective
manner.
The manual acts as a guide to CONTRACTOR System of Procedures which govern the work
process.
A `Quality Assurance Plan' is established during the initiation of a project and covers all
phases of the project.
This document would then be specific to the Project identifying the relevant Project
details such as the organization, specified standards, acceptance criteria and any special
requirements defined by Client including any deviations from CONTRACTOR's standard
Quality System.
The Quality Plan is established during the initiation of a project and covers all phases of
the project.
The document would be specific to Project identifying the relevant Project details such as
the organization, contract strategy, specified standards, contractual obligations,
acceptance criteria and any project specific requirements which will ensure the efficient
management of the Contract.
As the Project develops, the Quality Plan will be reviewed and updated as necessary to
reflect the current Project requirements.
The distribution of the document will ensure that all Project Key personnel have access to
this document.
The role of Quality Assurance on the project is to ensure that the Employer's Quality
Policy and contractual requirements are implemented.
This will be achieved, maintained and monitored on the project by internal auditing of the
applicable departments, ensuring compliance of the Quality Program to the applicable
control procedures.
Additionally, the Project Quality Assurance Manager or his nominated representative will
be responsible for ensuring that CONTRACTOR's Quality Policy is achieved on the
following:
Following the contract review, the Project Manager will prepare a Project Execution
Strategy and issue Contract Instructions to all relevant personnel via a "Kick-Off" meeting
and compile the Project Procedure.
These instructions will define the operational requirements for the project and identify
any methods of working that will deviate from the Employer's established company and
department procedures.
Additionally, the Project Procedures will identify the project reporting infrastructure for
control, approval and issue of the various project documentation.
The execution of the plan is vested within the project through the Project Lead Engineers
being responsible for the Detailed Engineering.
The content of the work will be divided to a pre-determined schedule, determining the
effective utilization of all disciplines and personnel.
A program of internal auditing will be developed to ensure that the Engineering functions
on the project are being conducted accordance with the project strategy.
The basis of design criteria is determined from the application codes and standards
current in the industry, with specific project requirements as amplified by OWNER's
special requirements.
The codes and standards applicable will be copies of the national and international
editions appropriate at contract award
All these activities are subject to audit by the Quality Assurance team throughout the
project's duration.
WORK METHODE Page 28 of 32
6.2.4 Document Control
Responsibility for Quality Assurance will be vested in the Project Manager, the Project
Team Leaders and Site Manager. The Quality Manager will ensure that the system is
being adhered to by internal audits and has direct reporting access to the Project Director.
All activities as defined on the project shall be subject to evaluation by Quality Assurance
Department in the form of internal auditing within the project duration.
Group Managers are responsible for quality control within their groups and it is their duty
to ensure that each group is working to the departmental procedures, including any
additional requirements imposed by the Client.
The philosophy envisaged on the project is that Procurement will administer its activities
in accordance with the OWNER's Quality Manual and its departmental procedures.
This undertaking shall include all relevant activities in determining the most cost effective
approach, to acquire the recognized equipment and material bulks that are consistent
with the project technical, quality and commercial demands.
Engineers are responsible for the preparation of all requisition packages in accordance
with the OWNER's quality manual and procedures.
Prior to issue at the invitation to tender stage, the project commercial and quality
requirements are included in the tender package.
On return of all bid information, the content shall be reviewed for compliance with the
project requirements for:
- design content
- material requirements
- commercial scope
- quality requirements
On return of the bid inquiry documents, each commercially acceptable Vendor shall be
assessed for technical and quality requirements.
This will involve, dependent upon the criticality of the supply, a visit to the Vendor to
resolve any technical or quality queries and will be in the form of technical meetings or
system reviews.
The Vendor will be awarded a Purchase Order, after complying with all the project
requirements.
The procurement activities shall be included within the internal auditing program to
ensure its activities are being conducted in accordance with the project strategy.
The quality control of supplied items shall be through the utilization of Quality Plans from
each Vendor. These plans shall identify all the critical activities applicable to the
fabrication of equipment or the supply of materials.
Copies of the approved Vendor Quality Plan shall be forwarded to the desk expediter,
enabling him to identify to the project inspection administrator when nominated
inspection visits in conjunction with the project program have been reached, although the
project Inspection Administrator is responsible for the control of all inspection activities.
All materials shall undergo full inspection prior to the issue of an inspection release. This
shall also include verification of material certification and relevant inspection dossier
requirements.
Equipment or materials shall not be shipped unless the items have been released by an
inspection waiver has been issued.
6.2.11 Construction
The construction site Quality Assurance plan shall be prepared in accordance with the
OWNER's procedures and with the project Execution Strategy. Review shall be
undertaken by the Project Manager and approved by Client.
The Field Engineering Manager shall ensure that site quality control plans are formulated
by all sub-contractors to identify the specific quality practices needed to administer their
activities. These plans shall be authorized by CONTRACTOR prior to commencement of
their activities.
Distribution of all site quality plans shall be in accordance with the site distribution list,
however, in all cases copies shall be forwarded to Client and the Project Manager for
Home Office distribution and filing.