Professional Documents
Culture Documents
Bridge
Bridge
Assignment One
November 2023
1. Surface and Subsurface drainage
Surface drainage: is the removal and diversion of water from the traffic carriageway and
adjoining land, mainly which comes from and rain water.
● Methods to control surface drainage
Most of the time the road is constructed either by embankment or cutting of sections.
Adequate surface drainage should be provided for these two sections therefore the
methods to control surface drainage are:
➤ Side drain for road in embankment
➤ Side drain for road in cutting
➤ Side drain for road in embankment
For this type road, the side drains are provided on one or both sides of the road beyond
the shoulder, at a minimum distance of about 2 m from the edge of embankment so that
the water flowing in the drains does not enter the earthwork.
Sketch 1:Road side drain for embankment filling road
➤ Side drain for road in cutting
Side drains are situated on both sides of the formation for highways that are in cutting.
Because of their thoughtful construction, it is evident that these drains never overflow
and leave the road completely buried in water. The exposed deep side drains can be
dangerous and ugly, particularly when there is a space constraint. Under such
conditions, it may be possible to provide covered drains, pipe drains, or ditches that are
appropriately filled with materials like gravel and coarse sand.
Sketch 2: Road side drain for road in cutting area
● Method to control subsurface drainage
Subsurface drainage is a key element in the design of pavement systems. For a
pavement system in order to give its intended purpose adequate subsurface drainage
should be provided in sufficient amounts. Methods to control subsurface drainage can
be categorized in to three these are:
➤ Method to control capillary rise
➤ Method to control Seepage flow
➤ Method to lower water table
➤ Method to control capillary rise
Capillary rise is the process of a liquid flowing in a narrow space without the assistance
of, or even in opposition to, any external forces like gravity. This action should be
prevented before it reaches the sub grade and disrupts the pavement structure by
providing suitable capillary cut-off between the subgrade and highest water table level.
As we discussed in the previous part, the road could be an embankment or cutting
section. For the embankment section the cut off for the capillary could be provided in
two ways. These are:
- Inserting an impermeable or a bituminous layer
This method blocks the way of the capillary rise and eliminates the risk on the pavement
structure.
- Providing a layer of granular material of suitable thickness
Granular materials have a high amount of voids between the particles; these reduce the
pressure of capillary and reduce capillary action.
Sketch 3: Method of control of capillary rise by Impermeable material
Sketch 4: Method of control of capillary rise by granular layer
● Substructure
- Piers: is a column or kind of bearing wall made of masonry to carry load as a support
for the bridge which is constructed on a strong foundation in order to carry and transfer
the load from super structure to the foundation to the soil.
- Abutments: is support system located at each end of the bridge, which act as retaining
walls to hold back the earth fill behind them and it also can be considered as anchoring
unit to the ground.
- Bridge approach: is transition between the land(abutment) and main span of the
bridge. It can be part of bridge/ embankment
● Foundation
- Piles and pile caps
Pile is a slender member driven into the surrounding soil to resist the loads. Pile cap is a
thick reinforced concrete slab cast on top of the group piles to distribute loads.
Sketch 17: sketch of components of bridge