SBW-RFAMS-008-Submission of Method Statement For Plastering Work

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 24

CIVIL & STRUCTURAL ENGINEERING CONSULTANTS

DOCUMENT REVIEW REPORT (DRR)


(PRIVATE) LIMITED
CSEC Waterfront Office,
No. 189, Madinnagoda Road, Rajagiriya, DRR No. : 321
Sri Lanka
Tel : 94- 11 – 2882209
Fax : 94- 71 – 8802859 Date : 20.05.2023
Email contact@csec.lk

Project : Proposed Condominium Development for South Beach Weligama Properties (Pvt) Ltd
Employer : South Beach Weligama Properties (Pvt) Ltd
Engineer : Global Project Management Consultants (Pvt) Ltd
Contractor : Buildmart Lanka (Pvt) Ltd.
Contractor's Transmittal No :
To : Mr. Mihiru Perera (Contractor's Representative) - Buildmart Lanka (Pvt) Ltd.

Contractor's Doc Ref. Expected Re-


Rev Description Status *
No. issue Date

METHOD STATEMENT
SBW-RFMAS-008 01 B -
FOR CEMENT PLASTERING WORK

Comments

1. Prior to plastering, a rush coat should be applied for all concrete surfaces by using deck brush.
 Surface must be sound, clean dry and free from any materials which may impair the adhesion of
rush coat
 Pre-wet & saturate the surface with portable water before applying rush coat.
 Chemifix: cement: water proportion will be used as 1:2:1 for preparation of rush coat.
2. Refer the Blockwork Method Statement and the Shop drawings.
3. Refer the comments on DRR 052.

Notes

From:
Civil & Structural Engineering Consultants (Pvt) Ltd
CSEC Waterfront Office, No. 189, Madinnagoda Road, Rajagiriya, Sri Lanka
Tel : 94- 11 – 2882209

Prepared By: Checked By: Approved By:


Eng. Gayan Buddika Eng. Samudaya Waduge Eng. Shiromal Fernando

…………………………..
Samudaya
........................................ ………………………….
Acknowledgement Receipt
Name :
Signature :
Date :

* Status
A – Approved B – Approved with Comments C – Not Approved - Resubmit D – Rejected
RECORD NO: FRM/DES-002 REV NO: 01 ISSUE NO: 321 DATE OF ISSUE: 20 May 2023 PAGE NO: 1 OF 1
Please refer to the attached
comments given by structural
consultant and architect.

Proposed Condominium Development


for South Beach Weligama Properties
(Pvt) Ltd
Engineer's Office - Global Project
Management Consultants (Pvt) Ltd.
(GPMC)

No Exception Taken

Revise & Submit

Approved With Comments

Reject

Submit Specified Item

Signed By :
Date :
CIVIL & STRUCTURAL ENGINEERING CONSULTANTS
DOCUMENT REVIEW REPORT (DRR)
(PRIVATE) LIMITED
No772/A, Wijesinghe Mw, Madinnagoda, Rajagiriya, Sri Lanka DRR No. : 53
Tel : 94- 11 – 2501727
Fax : 94- 71 – 8802859
Email contact@csec.lk Date : 23.06.2022

Project : Proposed Condominium Development for South Beach Weligama Properties (Pvt) Ltd
Employer : South Beach Weligama Properties (Pvt) Ltd
Engineer : Global Project Management Consultants (Pvt) Ltd
Contractor : Buildmart Lanka (Pvt) Ltd.
Contractor's Transmittal No : -
To : Mr. Mihiru Perera (Contractor's Representative) - Buildmart Lanka (Pvt) Ltd.

Contractor's Doc Ref. No. Rev Description Status * Expected Re-issue Date
MS 008 00 Plastering Method Statement B

Comments

• Clearance for MEP sleeves and conduits shall be taken prior to starting plastering works.
• The cement to sand mixing ratio for internal plastering shall be 1:5 and external plastering shall be
1:3.
• Standard gauge box shall be used for mortar mixing.
• Cement and sand material approval shall be taken.
• Block work shall be cured one day prior to plastering.
• Blockwork method statement shall be submitted.
Refer attached commented method statement for further comments.

Notes

From: Reviewed By:

Eng. Shiromal Fernando


Civil & Structural Engineering Consultants (Pvt) Ltd
Eng. Mahinda Chandrasekara
No772/A, Wijesinghe Mw, Madinnagoda, Rajagiriya, Sri Lanka
Tel: +94 11 250 1727
Signature: ……………………………………

Name: ……………………………………

Acknowledgement Receipt
Name :
Signature :
Date :

* Status
A – Approved B – Approved with Comments C – Not Approved - Resubmit D – Rejected
RECORD NO: FRM/DES-002 REV NO: 01 ISSUE NO: 03 DATE OF ISSUE: 04 SEPTEMBER 2020 PAGE NO: 1 OF 1
Structural Consultant's
Comments
PROPOSED SOUTH BEACH WELIGAMA
CONDOMINIUM DEVELOPMENT AT
WELIGAMA

METHOD STATEMENT
FOR CEMENT PLASTREING WORK
Method Statement for Plastering Work

TABLE OF CONTENTS PAGE NO

1 Purpose .................................................................................................................... 2
2 Specification and Drawing Reference ................................................................... 2
3 Equipment ............................................................................................................... 2
4 PPE Materials……………………………………………………………………...2
5 Resources and Manpower…………………………………...……………………3
6 Methodology……………..…………………………………...……………………3
7 Inspections and Approvals……………………………….……………………….5
8 Health and Safety………………………………………………………………….6

Annexures

1. Annexure 01-Check list for Plastering work

Buildmart Lanka (Pvt) Ltd Page 1


Method Statement for Plastering Work

1 Purpose

• The main purpose of this method statement is to outline the procedure of internal
& external plastering work for RCC & masonry elements of the project.

2 Specification and Drawing Reference

➢ CIDA specification and BOQ.


➢ Tender specifications
➢ Working Drawings – Approved Structural Drawings, Architecture Drawings

3 Equipment & Materials Test reports shall be submitted


(Sieve analysis, bulk density, water
absorption, abrasion test)
➢ Sieved river sand
➢ Cement Approved cement
➢ Concrete pot mixture shall be used

➢ Gauge box
➢ Wheel barrow
➢ Foundation thread
➢ Plumb bob
➢ Measuring tape Scaffoldings and clamps
Shovel
➢ Mason trowel Concrete nails
➢ Sprit level Chicken Mesh
Leveling bar
➢ Total station Water

4 PPE Materials

➢ Following PPE (Personal Protective Equipment) should be provide in order


to all work.
• Safety Helmets
• Safety Boots
• Safety Masks
• Hand Gloves
• High visibility vest

Buildmart Lanka (Pvt) Ltd Page 2


Method Statement for Plastering Work

5. Resources and Manpower


• Site Engineers
• Site supervisors QA/QC Engineer
Surveyor
• Skilled labors HSE Officer
• Unskilled labors Mason
Riggers

6. Methodology
➢ Cleaning of the Surface

• Necessary area will be identified earlier referring architectural drawings/


approved shop drawings for the plastering work.
• Surface to receive plastering shall be dry brushed to remove all loose
particles, dust, laitance, efflorescence, etc. and any projecting fines on
concrete surface shall be hacked off. All P-con openings shall be filled
with approved construction grout
• All required openings for mechanical and electrical services, conduits pipes,
plugs shall be installed and test prior to plastering. Where necessary placing
of sunk boxes as for the fixing of switches & socket outlets
Clearance for MEP embeddings shall be taken from the
engineer prior to plastering
➢ Installing the level guides
• Level guides (to control surface flatness & the line of the finishing) up
to required thickness on walls will be fixed with reference to the 200mm
off lines to block walls set out on the floors by using center plumb bob
and nylon thread.

• In order to get uniform thickness of plastering throughout the wall


surface, first fix spot levels on the wall.
• Spot levels are fixed on the wall first horizontally and then vertically at
a distance of about 2 meters covering the entire wall surface.
• Check the verticality of spots, one over the other, by means of plumb-
bob.
• After fixing spot levels, the vertical strips of plaster are formed in
between the spots. These screeds serve as the gauges for maintaining
even thickness of plastering being applied.

Buildmart Lanka (Pvt) Ltd Page 3


Method Statement for Plastering Work

1:5 ratio for internal plastering


1:3 ratio for external plastering
➢ Mixing of mortar
• 1:4 Cement, Sand mix proportion of motor shall be used for internal &
external plaster.
• This may be done by machine or by hand. Machine mixing is preferable.
Hand mixing shall be done on a plywood or steel mixing board.
• Mix no more mortar at a time than can be used within two hours. Mortar
not used within the 1 1/2-hour time shall be disposed off-site.
1 hour of mixing
• Where mixing bed/ mixing bay usage for the manual mixing day to day
proper cleaning of the mixing bay is essential to have quality mortar mixing.

➢ Reinforcement with chicken mesh at the joint of RCC & masonry


elements.

• Vertical joints where structural columns/walls and block masonry will


be treated by fixing of 200 mm width chicken mesh with wire
nails/concrete nails by centering the mesh to the vertical wall joint.
• Horizontal joints of structural beams/slab and block masonry will be
treated by fixing of 200 mm width chicken mesh with wire nails/concrete
nails by centering the mesh to the horizontal joint
Block work shop drawing shall be produced and approval shall be taken prior to conducting any
block work.

➢ Application of plaster

• Allowable Average thickness of the plaster is 20 mm & as per the verticality


tolerance it will varies from location to location. Application of two coats on
same location to get the final finish will be the general practice. Where possible
single coat application will be done to finish the plaster.

• Block/RCC surfaces should be moistened prior to application of the


plaster coat to obtain good adhesion and prevent excessive absorption of
water from the motor by the block works/RCC.
• First coat/Dash coat mortar filling maximum to 10 mm will be applied on
surfaces where required mortar thickness is 20 mm.
• The second coat shall be applied with sufficient material and pressure to
ensure tight contact with dash coat.
• The surface of the second coat shall be brought to a true, even plane with
a straightedge, filling surface defects in place with plaster.

Buildmart Lanka (Pvt) Ltd Page 4


Method Statement for Plastering Work

➢ Surface finishing

• If necessary applied plaster shall be floated as smooth as possible and


then steel-troweled. Steel troweling shall be delayed as long as possible and
used only to eliminate the uneven points and to force aggregate particles in
to the plaster surface.
• Each plaster coat shall be applied to an entire wall panel without interruption
to avoid cold joints and abrupt changes in the uniform appearance of
succeeding coats. Plastering shall always done
from top to bottom.
• Make internal angles and corners square/ right angle.

•Plaster work shall be terminated at end of each day at casting bead,


corners, opening or other acceptable intersection of surface.
Termination shall be done on the body of the wall and it shall at least be
150mm away from any corners. The finished edge shall not be tapered
➢ Curing of the Plaster

• After the plaster has been applied and finished, keeping it moist for a
minimum of 3 days.
• Sufficient moisture shall be provided in the plaster by spraying water as
frequently as required at least twice per day.

Curing shall be done for 7 days

7. Inspections and Approvals

➢ On field site inspections and approvals sign off by team confirming


Consulting Engineer and Contractor representative.

• Inspection shall be carried out after

a. Surface preparation and spot level placing

b. After completion of plaster surface

Note:
When recommencing plastering the next day, the edges of the old plaster shall be
scrapped, cleaned and wetted before plastering the new area.

Buildmart Lanka (Pvt) Ltd Page 5


Method Statement for Plastering Work

8. Health and Safety

➢ In accordance with the BML Health and safety guidelines.

• Safety warning boards and sign boards will be displayed on site. Those sign
boards will be guide line for the workers & always it will be a reminder for
workers when they are involving to site work.
• Workers shall wear all appropriate safety personnel protective equipment
such as helmet, coverall clothing (High visible Jacket) and gloves,
wherever required while they are within the site premises/ working location.
All the working personals will be advices during the tool box talk as well as at
the site safety meeting.
• A first aid box with the necessary medicine will be placed at the site first aid
room in case of an emergency.
• Adequate safe access to the working area shall be provided. Prior to
construction of block wall, necessary scaffolding through the spanning the
work area to be constructed up to the level of the block work completion.
The arrangement of the scaffolding to be able to hold the material that is to
be used for the block work construction as well the weight of the workers.
Scaffolding to be erected so that is to allow each mason may have free
access without being tied off. Adequate & safe access to be ensures before
working on top.
• Sufficient light shall be ensured before start of the work

• Necessary skilled personals to be used for the batching & working with the
pot mixer, power tools handling, etc.:

• While working on top & material handling on top, must secure the bottom
space without being dropping materials, tools, etc.: How ever the bottom
gap to be enclosed/ seal with timber/ plywood decking to protect the peoples
who are working at below levels

Buildmart Lanka (Pvt) Ltd Page 6


Annexure 01

BUILDMART LANKA(PVT) LTD


Proposed South Beach Condominium Development Project At Weligama
Inspection Check List for Plastering Work
Location/ Grid
Floor
Inspection Date
Inspection Time
Item
Site Engineer Result of Re-Inspection
Checked Consultant Checked Description of Site Engineer
General Item Consultant Checked
Inspection Defects/ Relevent Checked
Result Signature Result Signature Result Signature Result Signature

Plastering Work Surface Preparation


Cleanlines
Plumbing work &
Pressure test
Electrical conduiting
Chiken mesh location
Material quality
Wetting surface
Motar mix
Plaster type
Plumbness
Verticality/Alignment
Curing

Remarks

Site Engineer(Contractor) Consultant Approved

Name:................................................................ Name:.......................................................................
Signature:.......................................................... Signature:.................................................................
Date:.................................................................. Date:.........................................................................
Architect's Comments
DOCUMENT REVIEW REPORT (DRR)

PROJECT PROPOSED CONDOMINIUM DEVELOPMENT FOR SOUTH BEACH DRR NO: 01


WELIGAMA PROPERTIES (PVT)LTD

PROJECT NO 19005

EMPLOYER SOUTH BEACH WELIGAMA PROPERTIES (PVT)LTD REVISION

PROJECT ARCHITECT BALMOND STUDIO DATE 27.06.22

TO ATTENTION

Buildmart Lanka Pvt Ltd

Global Project Management consultants Mr. Udayanga alwis

DOCUMENT REFERENCE FROM DESCRIPTION APPROVED

APPROVED WITH COMMENTS

SBW-RFAMS-008 CONTRACTOR METHOD STATEMENT FOR PLASTERING WORK REVISE AND SUBMIT

REJECTED

COMMENTS

 Architectural Specifications in chapter 12 section 2 of the Bid document to be followed and adhered
to with regard to plastering works.
 Metal lath / mesh and anchors have to be galvanized – refer specifications for more details.
 Methodology for Trim / Shadow Gap Design and how it is going to be incorporated into plaster
works not explained by the contractor- submit the same

 Plaster layer which will act as substrate to receive Titanium cement/ High mold applications to be
specified in methodology.
 Specifications for Plastering layers acting as substrates for special applications to be submitted
separately for prior approval where applicable
 Thickness, methodology and mix ratio of Protective plaster works for waterproofing layers (in toilets
walls etc.) to be specified as per specialized contractor’s requirements.

 Sample panels to be demonstrated for all above for prior approval.

Page 1 of 2
DOCUMENT REVIEW REPORT (DRR)

PROJECT PROPOSED CONDOMINIUM DEVELOPMENT FOR SOUTH BEACH DRR NO: 01


WELIGAMA PROPERTIES (PVT)LTD

PROJECT NO 19005

EMPLOYER SOUTH BEACH WELIGAMA PROPERTIES (PVT)LTD REVISION

PROJECT ARCHITECT BALMOND STUDIO DATE 27.06.22

Notes :
Also refer our comments in Orange on document (SBW-RFAMS-008) attached herewith.

From Balmond Studio Handled by


rd Archt. Raveendra Handagama
3 Floor
14 Sir Baron Jayatilaka Mawatha, Colombo Junior Archt. Hashini Wijesinghe
Tel: +94 11 2 302 500
E-mail: sbw@balmondstudio.net
Web Site: www.balmondstudio.com

Acknowledgement Receipt

Date:
………………………………………………………………………………
Signature: ………………………………………………………
Name:
………………………………………………………………………………

Page 2 of 2
See Comments & refer
Document Review Report by
Balmond Studio
PROPOSED SOUTH BEACH WELIGAMA
CONDOMINIUM DEVELOPMENT AT
WELIGAMA

METHOD STATEMENT
FOR CEMENT PLASTREING WORK
Method Statement for Plastering Work

TABLE OF CONTENTS PAGE NO

1 Purpose .................................................................................................................... 2
2 Specification and Drawing Reference ................................................................... 2
3 Equipment ............................................................................................................... 2
4 PPE Materials……………………………………………………………………...2
5 Resources and Manpower…………………………………...……………………3
6 Methodology……………..…………………………………...……………………3
7 Inspections and Approvals……………………………….……………………….5
8 Health and Safety………………………………………………………………….6

Annexures

1. Annexure 01-Check list for Plastering work

Buildmart Lanka (Pvt) Ltd Page 1


Method Statement for Plastering Work

1 Purpose

• The main purpose of this method statement is to outline the procedure of internal
& external plastering work for RCC & masonry elements of the project.

2 Specification and Drawing Reference

➢ CIDA specification and BOQ.


➢ Tender specifications
➢ Working Drawings – Approved Structural Drawings, Architecture Drawings
Architectural Drawings
& Specifications
3 Equipment & Materials

➢ Sieved river sand


➢ Cement grey portland cement

➢ Concrete pot mixture


➢ Gauge box
➢ Wheel barrow
➢ Foundation thread
➢ Plumb bob
➢ Measuring tape
➢ Mason trowel
➢ Sprit level
➢ Total station

4 PPE Materials

➢ Following PPE (Personal Protective Equipment) should be provide in order


to all work.
• Safety Helmets
• Safety Boots
• Safety Masks
• Hand Gloves
• High visibility vest

Buildmart Lanka (Pvt) Ltd Page 2


Method Statement for Plastering Work

5. Resources and Manpower


• Site Engineers
• Site supervisors
• Skilled labors
• Unskilled labors

6. Methodology
➢ Cleaning of the Surface

• Necessary area will be identified earlier referring architectural drawings/


approved shop drawings for the plastering work.
• Surface to receive plastering shall be dry brushed to remove all loose
particles, dust, laitance, efflorescence, etc. and any projecting fines on
concrete surface shall be hacked off.
• All required openings for mechanical and electrical services, conduits pipes,
plugs shall be installed and test prior to plastering. Where necessary placing
of sunk boxes as for the fixing of switches & socket outlets
& Architectural Recessed Fittings/ fixtures or any embedded elements

➢ Installing the level guides


• Level guides (to control surface flatness & the line of the finishing) up
to required thickness on walls will be fixed with reference to the 200mm
off lines to block walls set out on the floors by using center plumb bob
and nylon thread.

• In order to get uniform thickness of plastering throughout the wall


surface, first fix spot levels on the wall.
• Spot levels are fixed on the wall first horizontally and then vertically at
a distance of about 2 meters covering the entire wall surface.
• Check the verticality of spots, one over the other, by means of plumb-
bob.
• After fixing spot levels, the vertical strips of plaster are formed in
between the spots. These screeds serve as the gauges for maintaining
even thickness of plastering being applied.

Buildmart Lanka (Pvt) Ltd Page 3


Method Statement for Plastering Work

➢ Mixing of mortar
• 1:4 Cement, Sand mix proportion of motor shall be used for internal &
1:3 Cement , Sand & 1:4 Cement Sand proportion by volume both
external plaster. specified according to application area- refer Architectural; specifications
Chapter 12
• This may be done by machine or by hand. Machine mixing is preferable.
Hand mixing shall be done on a plywood or steel mixing board.
• Mix no more mortar at a time than can be used within two hours. Mortar
not used within the 1 1/2-hour time shall be disposed off-site.

• Where mixing bed/ mixing bay usage for the manual mixing day to day
proper cleaning of the mixing bay is essential to have quality mortar mixing.

➢ Reinforcement with chicken mesh at the joint of RCC & masonry


elements. Galvanized Expanded Metal Lath To be used as per specification Refer
Architectural Spec Chapter 12 2.2.2, - Lysaght, PL25 unless or otherwise approved
• Vertical joints where structural columns/walls and block masonry will
be treated by fixing of 200 mm width chicken mesh with wire
nails/concrete nails by centering the mesh to the vertical wall joint.
• Horizontal joints of structural beams/slab and block masonry will be
treated by fixing of 200 mm width chicken mesh with wire nails/concrete
nails by centering the mesh to the horizontal joint

➢ Application of plaster
Nominal Thickness 15-18mm Maximum
• Allowable Average thickness of the plaster is 20 mm & as per the verticality
tolerance it will varies from location to location. Application of two coats on
same location to get the final finish will be the general practice. Where possible
single coat application will be done to finish the plaster.

• Block/RCC surfaces should be moistened prior to application of the


plaster coat to obtain good adhesion and prevent excessive absorption of
water from the motor by the block works/RCC.
• First coat/Dash coat mortar filling maximum to 10 mm will be applied on
surfaces where required mortar thickness is 20 mm.
• The second coat shall be applied with sufficient material and pressure to
ensure tight contact with dash coat.
• The surface of the second coat shall be brought to a true, even plane with
a straightedge, filling surface defects in place with plaster.

Buildmart Lanka (Pvt) Ltd Page 4


Method Statement for Plastering Work

➢ Surface finishing

• If necessary applied plaster shall be floated as smooth as possible and


then steel-troweled. Steel troweling shall be delayed as long as possible and
used only to eliminate the uneven points and to force aggregate particles in
to the plaster surface.
• Each plaster coat shall be applied to an entire wall panel without interruption
to avoid cold joints and abrupt changes in the uniform appearance of
succeeding coats.
• Make internal angles and corners square/ right angle.

• Plaster work shall be terminated at end of each day at casting bead,


corners, opening or other acceptable intersection of surface.

➢ Curing of the Plaster

• After the plaster has been applied and finished, keeping it moist for a
minimum of 3 days.
• Sufficient moisture shall be provided in the plaster by spraying water as
frequently as required at least twice per day.

7. Inspections and Approvals

➢ On field site inspections and approvals sign off by team confirming


Consulting Engineer and Contractor representative.

• Inspection shall be carried out after

a. Surface preparation and spot level placing

b. After completion of plaster surface

Buildmart Lanka (Pvt) Ltd Page 5


Method Statement for Plastering Work

8. Health and Safety

➢ In accordance with the BML Health and safety guidelines.

• Safety warning boards and sign boards will be displayed on site. Those sign
boards will be guide line for the workers & always it will be a reminder for
workers when they are involving to site work.
• Workers shall wear all appropriate safety personnel protective equipment
such as helmet, coverall clothing (High visible Jacket) and gloves,
wherever required while they are within the site premises/ working location.
All the working personals will be advices during the tool box talk as well as at
the site safety meeting.
• A first aid box with the necessary medicine will be placed at the site first aid
room in case of an emergency.
• Adequate safe access to the working area shall be provided. Prior to
construction of block wall, necessary scaffolding through the spanning the
work area to be constructed up to the level of the block work completion.
The arrangement of the scaffolding to be able to hold the material that is to
be used for the block work construction as well the weight of the workers.
Scaffolding to be erected so that is to allow each mason may have free
access without being tied off. Adequate & safe access to be ensures before
working on top.
• Sufficient light shall be ensured before start of the work

• Necessary skilled personals to be used for the batching & working with the
pot mixer, power tools handling, etc.:

• While working on top & material handling on top, must secure the bottom
space without being dropping materials, tools, etc.: How ever the bottom
gap to be enclosed/ seal with timber/ plywood decking to protect the peoples
who are working at below levels

Buildmart Lanka (Pvt) Ltd Page 6


Annexure 01

BUILDMART LANKA(PVT) LTD


Proposed South Beach Condominium Development Project At Weligama
Inspection Check List for Plastering Work
Location/ Grid
Floor
Inspection Date
Inspection Time
Item
Site Engineer Result of Re-Inspection
Checked Consultant Checked Description of Site Engineer
General Item Consultant Checked
Inspection Defects/ Relevent Checked
Result Signature Result Signature Result Signature Result Signature

Plastering Work Surface Preparation


Cleanlines
Plumbing work &
Pressure test
Electrical conduiting
Chiken mesh location
Material quality
Wetting surface
Motar mix
Plaster type
Plumbness
Verticality/Alignment
Curing

Remarks

Site Engineer(Contractor) Consultant Approved

Name:................................................................ Name:.......................................................................
Signature:.......................................................... Signature:.................................................................
Date:.................................................................. Date:.........................................................................