Item No

Description Unit Qty Rate Amount

A-SUB STRUCTURE
1 EXCAVATION & EARTH WORK
Clear and remove top soil to an average depth of
1.1 m2 366.54
20 cm.
Bulk excavation in ordinary soil to reduce levels to the
1.2 designed level up to 500mm . m3
309.168
1.3 Pit excavation in ordinary soil from reduced level to m3 92.93
depth not exceeding 1.5m.

1.4 m3 93.05
Trench excavation for masonery wall under oridinary so
1.5 Back Fill m3 401.8815
1.6 Cart away m3 93.266
Total carried to
m3 1356.84
Summary ...................................................
2 CONCRETE WORK
2.1 50mm lean concrete quality C-5, 150 kg of m²
2.1.1 cement/m3: under
a) Under foundation pad m² 39.29
2.1.2 b) Under Trench Masonry m² 54
Reinforced concrete Grade C-25
2.2 For Footing Pad m3 16.68
2.4 For Grade Beam m3 11.095
2.5 For Ground Slab m3 24.162
2.6 For outside Stairs m3
Reinforced concrete Grade C-30
2.3 Foundation column m3 6.62
Total carried to 151.84
Summary ...................................................
Mild steel reinforcement
a) dia 6 mm plain bar kg
b) dia 8 mm deformed bar kg 709.37
c) dia 10 mm deformed bar kg 1270.04
d) dia 12 mm deformed bar kg 478.2527
e) dia 14 mm deformed bar kg 1341.15
f) dia 16 mm deformed bar kg 872.08
g) dia 20 mm deformed bar kg
h) dia 24 mm deformed bar kg
Total carried to summary kg 4671
MASONRY WORKS kg
3
3.1 500mm thick hard trachytic roughly dressed stone m3 72.5
3.2 masonry foundation
250mm basaltic wall below
hardcore underground
groundlevel bedded
supported floor m² 97.76
in cement mortar mix
Total carried to ratio (1:3)
170.26
Summary ...................................................
4 Form Work
4.1 For Footing Pad m² 47.92
4.2 For Foundation Column m² 88.20
4.3 For Grade Beam m² 96.74

B-SUPER STRUCTURE
1 CONCRETE WORK
Reinforced concrete Grade C-15,
1.1 For Lintel Beam m3 1.151
Reinforced concrete Grade C-25,
1.2 For Stair m3 8.4
1.3 For Slab m3 107.10
1.4 For Beam m3 31.35
Reinforced concrete Grade C-30,
1.5 For Foundation Column m3 12.96
2 FORM WORK
2.1 For Slab m² 734.69
2.2 For Elevation Column m² 184.32
2.3 For Beam m² 260
2.4 For Stair m² 61.4
3 BLOCK WORK
3.1 20CM*20CM*40CM HCB m² 654.43
3.2 30CM*20CM*40CM HCB (Two 15cm HCB thick wall) m² 13.02
3.3 15CM*20CM*40CM HCB m² 703.58
3.4 10CM*20CM*40CM HCB m² 29.70
Mild steel reinforcement according to structural
drawings.
a) dia 6 mmPrice
plain includes
bar cutting, bending, Kg
placing in position ,
b) dia 8 mm deformed bar tying wire, concrete spacers Kg
and chairs.
c) dia 10 mm deformed bar Kg 1860.9026
d) dia 12 mm deformed bar Kg 394.33146
e) dia 14 mm deformed bar Kg 4954.53
f) dia 16 mm deformed bar Kg 647.737
g) dia 20 mm deformed bar Kg 400.075
h) dia 22mm deformed bar Kg 731.81
Total carried to Summary ................. Kg 8989.38
4 Finishing Work
4.1 Cement Sand Plastering m² 3510
4.2 Gypsum Plastering m² 1711.6
4.3 Painting m² 2334.6
4.4 Ceiling Finish m² 1170.0
4.5 Ceram Tile Floor Finish m² 901.56
4.6 Ceramic Tile Wall Finish m² 486.41
4.7 Skirting m 422.36

5 Metal Work
5.1 Aluminium N/A 114.3
5.4 Steel for Stair Case m 264.3
5.3 Steel for Sliding m² 13.755

6 CARPENTRY & JOINERY


6.1 Carpenrty
6.1.1 Kitchen Cabinet m² 13.5
6.1.2 Closet m² 114
6.2 JOINERY
6.2.1 Doors
6.2.1.1 size 90x210cm Pcs 3
6.2.1.2 size 70x210cm Pcs 17
6.2.1.3 size 80x210cm Pcs 17
7 GLAZING
7.1 2mm thick clear glass m² 7901.63
7.2 2mm thick Blurred glass m² 1209
8 Waterproof work m² 565.99
SUB STRUCTURE
Item Dimension Squar Unit Description
L(m) W(m) H(m)
1. Excavation and earthwork
1.1 Site Clerance
Top soil removal for depth not ecxeeding 20cm

A1

A2

1 16.8 12.3 206.64 m2

1 12.3 13 159.9 m2 A1=16.8*12.3 & A2=12.3*13


366.54 m 2
Total area of site clerance

1.2 Bulk Excavation


Acoording to earthwork data hmin=0.45 from FFL
when site clerance is made it become 0.65m
hmax=1.05m from FFL
when site clerance is made it become 1.25m
taking the average depth, depth of excavation will be 0.95m

A1

A2
A1=15.8*11.3, A2=11.3*13
A2

1 15.8 11.3 0.95 169.613 m3

1 11.3 13 0.95 139.555 m3


309.168 m3 Total volume of bulk excavation

1.3 Pit Excacation


Pit excavation for isolated footings pad under ordinary soil from
reduced level to depth not exceeding 1.5m.

a. for footing type 1


2 2.2 2.2 1.35 13.068 m3
b. for footing type 2
3
3 2.1 2.1 1.3 17.199 m
c. for footing type 3
3
2 1.9 1.9 1.25 9.025 m
d. for footing type 4
3
7 1.8 1.8 1.25 28.35 m
e. for footing type 5
3
7 1.7 1.7 1.25 25.2875 m
92.9295 m3 Total volume of pit excavation

1.4 Trench excavation


Trench excavation for masonery wall under oridinary soil

a. along Axis-A
L=3.2m+3.2m=6.4m
1 6.4 1 1 6.4 m3
b. along Axis-B
L=3.25m+3.25m+1.25m+3.05m+3.1m=13.9m
1 13.9 1 1 13.9 m3
c. along Axis-C
L=3m+3.05m+1.25m+3.25m+3.25m=13.8m
1 13.8 1 1 13.8 m3
d. along Axis-D
L=3.2m+3.15m+1.2m+3.15m+3.2m=13.9m
1 13.9 1 1 13.9 m3
e. along Axis-1
L=2.8m+2.75m+3.75m=9.3m
1 9.3 1 1 9.3 m3
f. along Axis-2
L=2.5m+2.35m+3.45m=8.3m
1 8.3 1 1 8.3 m3
g. along Axis-3
L=2.75m+2.55m+3.55m=8.85m
1 8.85 1 1 8.85 m3
h. along Axis-4
L=2.6m+3.55m=6.15m
1 6.15 1 1 6.15 m3
i. along Axis-5
L=2.5m+3.45m=5.95m
1 5.95 1 1 5.95 m3
j. along Axis-6
L=2.75m+3.75m=6.5m
1 6.5 1 1 6.5 m3
93.05 m3 Total volume of trench excavation

1.5 Back fill


a. backfill around F1
BF=Ve-Vc
Ve=13.068m3 and Vc=3.133m3
Bf=13.068-3.133=9.935m3
1 9.935
b. ditto but around F2
Ve=17.199m3 and Vc=3.807m3
Bf=17.199-3.807=13.392m3
1 13.392
c. ditto but around F3
Ve=9.025m3 and Vc=1.793m3
Bf=9.025-1.793=7.232m3
1 7.232
d. ditto but around F4
Ve=28.35m3 and Vc=5.5195m3
Bf=28.35-5.5195=22.8305m3
1 22.8305
e. ditto but around F5
Ve=25.2m3 and Vc=4.8195m3
Bf=25.2-4.8195=20.3805m3
1 20.3805
f. ditto but around masonary wall
Ve=93.05m3 and Vm=72.5m3
Bf=93.05-72.5=20.55m3
1 20.55
g. ditto but on bulk excavation
Ve=309.168m3 and Vc=1.6065m3
Bf=309.168-1.6065=307.5615m3
1 307.5615
401.882 m3 Total volume of backfill

1.6 Cart away


Total volume of cart away=Ve-VBf
Ve=495.1475m3 and VBf=401.8815m3
Total volume of cart away=93.266m3
1 93.266 m3 Total volume of cart away

Dimensions
Times L (m) W (m) H(m) Square Unit Description
2. CONCRETE WORK
2.1 C-5 LEAN CONCRETE
2.1.1 UNDER FOOTING PAD
2 1.7 1.7 5.78 m2 F1

3 1.6 1.6 7.68 m2 F2

2 1.4 1.4 3.92 m2 F3

7 1.3 1.3 11.83 m2 F4

7 1.2 1.2 10.08 m2 F5


39.29 m 2
Total C-5 Lean Concrete

2.1.2 Under Trench Maonry

a. along Axis-A
2
1 7.5 0.5 3.75 m
b. along Axis-B
2
1 16.4 0.5 8.2 m
c. along Axis-C
1 15.1 0.5 7.55 m2
d. along Axis-D
2
1 16.4 0.5 8.2 m
e. along Axis-1
2
1 10.8 0.5 5.4 m
f. along Axis-2
2
1 9.85 0.5 4.925 m
g. along Axis-3
2
1 10.35 0.5 5.175 m
h. along Axis-4
2
1 7.15 0.5 3.575 m
i. along Axis-5
2
1 6.95 0.5 3.475 m
j. along Axis-6
2
1 7.5 0.5 3.75 m
54 m2 Total area of lean concrete under masonry wall

Times L (m) W (m) H(m) Square Unit 2.2 C-25 CONCRETE FOR FOOTING PAD
3
2 1.7 1.7 0.5 2.89 m F1

3 1.6 1.6 0.45 3.456 m3 F2

2 1.4 1.4 0.4 1.568 m3 F3

7 1.3 1.3 0.4 4.732 m3 F4

7 1.2 1.2 0.4 4.032 m3 F5


16.678 m 3
Total C-25 Concrete for footing pad

Times L (m) W (m) H(m) Square Unit 2.3 C-30 FOUNDATION COLUMN
3
17 0.3 0.3 3.5 5.355 m CS-01

4 0.3 0.3 3.5 1.26 m3 CS-02


6.615 m 3
Total C-30 Foundation Column

Times L (m) W (m) H(m) Square Unit 2.4 C-25 GRADE BEAM
3
3 14.8 0.2 0.35 3.108 m on axis 1 A to D cb7, cb6, cb5

1 10.3 0.2 0.35 0.721 m3 on axis A 1to3 cb1

3 23.3 0.2 0.35 4.893 m3 on axis D 1 to6 cb2,3,4

3 10.3 0.2 0.35 2.163 m3 on axis 6 A to D cb8,9,10

1 3 0.2 0.35 0.21 m3 cb 12


11.095 m 3
Total C-25 Grade Beam

Times L (m) W (m) H(m) Square Unit 2.5 C-25 GROUND SLAB CONCRETE WORK
2 63.94 0.1 12.788 m3 on axis 1and 2 A to D

1 25.38 0.1 2.538 m3 on axis 3 and 4 B to D

2 44.18 0.1 8.836 m3 on axis 4 and 5 B to D


24.162 m 3
Total C-25 Groun slab concrete work
51.935 m 3
TOTAL C-25 CONCRETE WORK
6.615 m3 TOTAL C-30 CONCRETE WORK
58.55 m3 TOTAL CONCRETE WORK

Times L(m) W(m) H(m) Squaring unit Description


Concrete work for outside stairs
a. located at main entrance
waist slab
1 1.01 1.8 0.14 0.25452 m3
steps
3
3 0.075 1.8 0.14 0.0567 m
b.located at the store entrance
waist slab
1 1.01 1.5 0.14 0.2121 m3
steps
3
3 15 1.5 0.15 10.125 m
landing
3
1 1 1.5 0.14 0.21 m
c. located at changing room entrance
waist slab
1 1.01 1 0.14 0.1414 m3
steps
3
3 0.075 1 0.14 0.0315 m
landing
3
1 4 1 0.14 0.56 m
d.located at the parking entrance
waist slab
1 1.01 1.65 0.14 0.23331 m3
steps
3
3 0.075 1.65 0.14 0.051975 m
11.8765 m3 Total concrete work for outside stair

Times L W H Square Unit 3. MASONRY WORK


3.1 500mm thick masonary wall under grade beam
1 10.3 0.5 5.15 m3 Axis A

3 23.3 0.5 34.95 m3 Axis B, C and D

3 12.8 0.5 19.2 m3 Axis 1, 2 and 3

3 8.8 0.5 13.2 m3 Axis 4,5 and 6


72.5 m3 Total 50cm thick masonary wall under grade beam

Times L W H Square Unit


6 4.2 4.7 118.44 m2 3.2 250mm basaltic hardcore under ground supported floors

1 4.2 2.7 11.34 m2

4 5.2 4.7 97.76 m2

1 5.2 2.7 14.04 m2


241.58 m2 Total 25 cm basaltic hardcore under ground supported floors

4. FORM WORK (m2)


Times L (m) W (m) H(m) Square Unit 4.1 FORM WORK FOR FOOTING PAD (20mm THICK SWAN ZIGBA FORMWORK)
2
2 6.8 0.5 6.8 m F1

3 6.4 0.45 8.64 m2 F2


2 5.6 0.4 4.48 m2 F3

7 5.2 0.4 14.56 m2 F4

7 4.8 0.4 13.44 m2 F5


47.92 m 2
Total Form work for footing pad

Times L (m) W (m) H(m) Square Unit 4.2 FORM WORK FOR FOUNDATION COLUMN (20mm THICK SWAN ZIGBA FORMWORK)
2
17 1.2 3.5 71.4 m CS01

4 1.2 3.5 16.8 m2 CS 02


88.2 m 2
Total Form work for foundation column

Times L (m) W (m) H(m) Square Unit 4.3 FORM WORK FOR GRADE BEAM (20mm THICK SWAN ZIGBA FORMWORK)
1 27.2 0.35 9.52 m2 along axis1 Ato D

1 27.2 0.35 9.52 m2 along axis 2

1 27.2 0.35 9.52 m2 along axis 3

1 18.8 0.35 6.58 m2 along axis 4

1 18.8 0.35 6.58 m2 along axis 5

1 18.8 0.35 6.58 m2 along axis 6

1 9.4 0.35 3.29 m2 along axis A

1 43 0.35 15.05 m2 along axis B

1 43 0.35 15.05 m2 along axis C

1 43 0.35 15.05 m2 along axis D


96.74 m2 Total Form work for grade beam
232.86 m2 TOTAL FORM WORK (20mm THICK SWAN ZIGBA FORMWORK)

SUPER STRUCTURE
Dimensions
Times L (m) W (m) H (m) squaring unit Description
1 CONCRETE WORK
1.1 C-15 CONCRETE FOR LINTEL BEAM (GROUND FLOOR)
1 1.3 0.2 0.2 0.052 m 3
above 90cm wide exterior door offset 20cm from each side

4 1.3 0.15 0.2 0.156 m3 above 90cm wide interior door offset 15cm from each side

5 1.1 0.15 0.2 0.165 m3 above 90cm wide interior door offset 15cm from each side

2 2.4 0.15 0.2 0.144 m3 above 200cm wide interior and exterior door offset 20cm from each side

1 1.4 0.2 0.2 0.056 m3 above 100cm wide exterior door


0.573 m3 Total C-15 concrete for lintel beam (ground floor)

Times L (m) W (m) H (m) squaring unit C-15 CONCRETE FOR LINTEL BEAM (FIRST FLOOR)
1 1.3 0.15 0.2 0.039 m3 above 90cm wide interior door offset 15cm from each side

6 1.1 0.15 0.2 0.198 m3 above 80cm wide interior door offset 15cm from each side
0.237 m3 Total C-15 concrete for lintel beam (first floor)

Times L (m) W (m) H (m) squaring unit C-15 CONCRETE FOR LINTEL BEAM (SECOND FLOOR)
0.237 m3 ditto as above but for second floor
0.237 m3 Total C-15 concrete for lintel beam (second floor)

Times L (m) W (m) H (m) squaring unit C-15 CONCRETE FOR LINTEL BEAM (ROOF)
2 1.3 0.2 0.2 0.104 m3 above 90cm wide interior door offset 15cm from each side
0.104 m3 Total C-15 concrete for lintel beam (roof)
1.151 m3 TOTAL C-15 CONCRETE WORK

Times L (m) W (m) H (m) squaring unit 1.2 C-25 CONCRETE FOR STAIR (GROUND FLOOR)
2 3.25 1.2 0.14 1.092 m3 Waist slab flight from ground floor to first floor

22 1.2 0.28 0.15 1.1088 m3 Triangle part

1 1.5 2.7 0.14 0.567 m3 Landing


2.7678 m3
Total C-25 concrete for stair (ground floor)

Times L (m) W (m) H (m) squaring unit C-25 CONCRETE FOR STAIR (FIRST FLOOR)
2 3.25 1.2 0.14 1.092 m3 waist slab flights from second floor to roof

22 1.2 0.28 0.15 1.1088 m3 steps consisting riser and tread

1 1.5 2.7 0.14 0.567 m3 Landing


2.7678 m3
Total C-25 concrete for stair (First floor)

Times L (m) W (m) H (m)


squaring unit C-25 CONCRETE FOR STAIR (SECOND FLOOR)
2.7678 m3 ditto as above
2.7678 m3 Total C-25 concrete for stair (second floor)
8.3034 Total C-25 concrete for stair
Times L (m) W (m) H (m) squaring unit 1.3 C-25 CONCRETE FOR SLAB (FIRST FLOOR)
1 4.85 4.35 0.14 2.95365 m3 Along Axis-1 and Axis-2 (A-B)

1 4.85 4.3 0.14 2.9197 m3 Along Axis-1 and Axis-2 (B-C)

1 4.85 5.35 0.14 3.63265 m3 Along Axis-1 and Axis-2 (C-D)

1 4.8 4.35 0.14 2.9232 m3 Along Axis-2 and Axis-3 (A-B)


1 4.8 4.3 0.14 2.8896 m3 Along Axis-2 and Axis-3 (B-C)

1 4.8 5.35 0.14 3.5952 m3 Along Axis-2 and Axis-3 (C-D)

1 2.8 5.35 0.14 2.0972 m3 Along Axis-3 and Axis-4 (C-D)

1 4.8 4.35 0.14 2.9232 m3 Along Axis-4 and Axis-5 (B-C)

1 4.8 5.35 0.14 3.5952 m3 Along Axis-4 and Axis-5 (C-D)

1 4.85 4.35 0.14 2.95365 m3 Along Axis-5 and Axis-6 (B-C)

1 4.85 5.35 0.14 3.63265 m3 Along Axis-5 and Axis-6 (C-D)

2 1.5 2.3 0.145 1.0005 m3 Balconies on first floor

2 1.5 1.15 0.14 -0.483 m3 deduction of offset of the corridor


34.6334 m3 Total C-25 concrete for slab (first floor)

Times L (m) W (m) H (m) squaring unit C-25 CONCRETE FOR SLAB (SECOND FLOOR)
34.6334 m3 ditto as above
34.6334 m3 Total C-25 concrete for slab (second floor)

Times L (m) W (m) H (m) squaring unit C-25 CONCRETE FOR SLAB (ROOF)
1 4.85 4.35 0.14 2.95365 m3 Along Axis-1 and Axis-2 (A-B)

1 4.85 4.3 0.14 2.9197 m3 Along Axis-1 and Axis-2 (B-C)

1 4.85 5.35 0.14 3.63265 m3 Along Axis-1 and Axis-2 (C-D)

1 4.8 4.35 0.14 2.9232 m3 Along Axis-2 and Axis-3 (A-B)

1 4.8 4.3 0.14 2.8896 m3 Along Axis-2 and Axis-3 (B-C)


1 4.8 5.35 0.14 3.5952 m3 Along Axis-2 and Axis-3 (C-D)

1 2.8 5.35 0.14 2.0972 m3 Along Axis-3 and Axis-4 (C-D)

1 4.8 4.35 0.14 2.9232 m3 Along Axis-4 and Axis-5 (B-C)

1 4.8 5.35 0.14 3.5952 m3 Along Axis-4 and Axis-5 (C-D)

1 4.85 4.35 0.14 2.95365 m3 Along Axis-5 and Axis-6 (B-C)

1 4.85 5.35 0.14 3.63265 m3 Along Axis-5 and Axis-6 (C-D)

1 4.2 2.7 0.14 1.5876 m3 Roof stair cover along Axis-3 and Axis-4(B-C)

1 2.8 5.35 0.14 2.0972 m3 Roof stair cover along Axis-3 and Axis-4(C-D)
37.8007 m3 Total C-25 concrete for slab (roof)
107.068 m3 Total C-25 concrete for slab
Times L (m) W (m) H (m) squaring unit 1.4 C-25 CONCRETE FOR BEAM (FIRST FLOOR)
6 4.2 0.2 0.35 1.764 m3 Along Axis-1,Axis-2 and Axis-3 between Axis-A&B and Axis-B&C

3 5.2 0.2 0.35 1.092 m3 Along Axis-1,Axis-2 and Axis-3 between Axis-C&D

3 4.2 0.2 0.35 0.882 m3 Along Axis-4,Axis-5 and Axis 6 between Axis B&C

3 5.2 0.2 0.35 1.092 m3 Along Axis-4,Axis-5 and Axis-6 between Axis-C&D

8 4.7 0.2 0.35 2.632 m3 Along Axis-A, Axis-B, Axis-C and Axis-D between Axis-1&2 and Axis-2&3

3 2.7 0.2 0.35 0.567 m3 Along Axis-B, Axis-C and Axis-D between Axis 3&4

6 4.7 0.2 0.35 1.974 m3 Along Axis-B, Axis-C and Axis-D between Axis 4&5 and 5&6
10.003 m3 Total C-25 concrete for beam (first floor)
Times L (m) W (m) H (m) squaring unit C-25 CONCRETE FOR BEAM (SECOND FLOOR)
10.003 m3 ditto as above
10.003 m3 Total C-25 concrete for beam (second floor)

Times L (m) W (m) H (m) squaring unit C-25 CONCRETE FOR BEAM (ROOF)
6 4.2 0.2 0.35 1.764 m3 Along Axis-1,Axis-2 and Axis-3 between Axis-A&B and Axis-B&C

3 5.2 0.2 0.35 1.092 m3 Along Axis-1,Axis-2 and Axis-3 between Axis-C&D

3 4.2 0.2 0.35 0.882 m3 Along Axis-4,Axis-5 and Axis 6 between Axis B&C

3 5.2 0.2 0.35 1.092 m3 Along Axis-4,Axis-5 and Axis-6 between Axis-C&D

8 4.7 0.2 0.35 2.632 m3 Along Axis-A, Axis-B, Axis-C and Axis-D between Axis-1&2 and Axis-2&3

3 2.7 0.2 0.35 0.567 m3 Along Axis-B, Axis-C and Axis-D between Axis 3&4

6 4.7 0.2 0.35 1.974 m3 Along Axis-B, Axis-C and Axis-D between Axis 4&5 and 5&6

2 4.2 0.2 0.35 0.588 m3 Top tie beam Along Axis-3 and Axis-4 between Axis-B&C

2 5.2 0.2 0.35 0.728 m3 Top tie beam Along Axis-3 and Axis-4 between Axis-C&D
11.319 m3 Total C-25 concrete for beam (roof)
146.696 m3 TOTAL C-25 CONCRETE WORK

Times L (m) W (m) H (m) squaring unit 1.5 C-30 CONCRETE FOR COLUMN (GROUND FLOOR)
14 0.3 0.3 3 3.78 m3 on all axis points (1A,1B,1C,1D,2A,2B,2C,2D,3A,3B,3C………..)
3.78 m3 Total C-30 concrete for column (ground floor)

Times L (m) W (m) H (m) squaring unit C-30 CONCRETE FOR COLUMN (FIRST FLOOR)
3.78 m3 ditto as above
3.78 m3 Total C-30 concrete for column (first floor)
Times L (m) W (m) H (m) squaring unit C-30 CONCRETE FOR COLUMN (SECOND FLOOR)
3.78 m3 ditto as above
3.78 m3 Total C-30 concrete for column (second floor)

Times L (m) W (m) H (m) squaring unit C-30 CONCRETE FOR COLUMN (ROOF)
6 0.3 0.3 3 1.62 m3 Along axis 3B,3C,3D,4B,4C,4D
1.62 m3 Total C-30 concrete for column (roof)
12.96 m3 TOTAL C-30 CONCRETE WORK

2. FORM WORK
Times L (m) W (m) H (m) squaring unit 2.1 FORM WORK FOR SLAB (FIRST FLOOR) 20mm thick swan zigaba form work for Slab
1 4.85 4.35 21.0975 m2 Along Axis-1 and Axis-2 (A-B)

1 4.85 4.3 20.855 m2 Along Axis-1 and Axis-2 (B-C)

1 4.85 5.35 25.9475 m2 Along Axis-1 and Axis-2 (C-D)

1 4.8 4.35 20.88 m2 Along Axis-2 and Axis-3 (A-B)

1 4.8 4.3 20.64 m2 Along Axis-2 and Axis-3 (B-C)

1 4.8 5.35 25.68 m2 Along Axis-2 and Axis-3 (C-D)

1 2.8 5.35 14.98 m2 Along Axis-3 and Axis-4 (C-D)

1 4.8 4.35 20.88 m2 Along Axis-4 and Axis-5 (B-C)

1 4.8 5.35 25.68 m2 Along Axis-4 and Axis-5 (C-D)

1 4.85 4.35 21.0975 m2 Along Axis-5 and Axis-6 (B-C)

1 4.85 5.35 25.9475 m2 Along Axis-5 and Axis-6 (C-D)


4 4.2 0.05 0.84 m2 Along Axis-A and Axis-D between Axis-1&2 and Axis 2&3

2 4.2 0.05 0.42 m2 Along Axis-1 between Axis-A&B and Axis-B&C

1 6.7 0.05 0.335 m2 Along Axis-1 between Axis-C&D

1 4.2 0.05 0.21 m2 Along Axis-3 between Axis-A&B

1 4.2 0.05 0.21 m7 Along Axis-6 between Axis-B&C

1 6.7 0.05 0.335 m2 Along Axis-6 between Axis-C&D

2 2.7 0.05 0.27 m2 Along Axis-B&D between Axis-3&4

4 4.7 0.05 0.94 m2 Along Axis-B&D between Axis-4&5 and 5&6

-2.00 1.5 1.15 -3.45 m2 deduction of offset of the corridor


243.795 m 2
total form work for slab (first floor)

Times L (m) W (m) H (m) squaring unit FORM WORK FOR SLAB (SECOND FLOOR) 20mm thick swan zigaba form work for Slab
243.795 m2 ditto as above
243.795 m2 total form work for slab (second floor)

Times L (m) W (m) H (m) squaring unit FORM WORK FOR SLAB (ROOF) 20mm thick swan zigaba form work for Slab
1 4.85 4.35 21.0975 m2 Along Axis-1 and Axis-2 (A-B)

1 4.85 4.3 20.855 m2 Along Axis-1 and Axis-2 (B-C)

1 4.85 5.35 25.9475 m2 Along Axis-1 and Axis-2 (C-D)

1 4.8 4.35 20.88 m2 Along Axis-2 and Axis-3 (A-B)


1 4.8 4.3 20.64 m2 Along Axis-2 and Axis-3 (B-C)

1 4.8 5.35 25.68 m2 Along Axis-2 and Axis-3 (C-D)

1 2.8 5.35 14.98 m2 Along Axis-3 and Axis-4 (C-D)

1 4.8 4.35 20.88 m2 Along Axis-4 and Axis-5 (B-C)

1 4.8 5.35 25.68 m2 Along Axis-4 and Axis-5 (C-D)

1 4.85 4.35 21.0975 m2 Along Axis-5 and Axis-6 (B-C)

1 4.85 5.35 25.9475 m2 Along Axis-5 and Axis-6 (C-D)

4 4.2 0.05 0.84 m2 Along Axis-A and Axis-D between Axis-1&2 and Axis 2&3

2 4.2 0.05 0.42 m2 Along Axis-1 between Axis-A&B and Axis-B&C

1 5.2 0.05 0.26 m2 Along Axis-1 between Axis-C&D

1 4.2 0.05 0.21 m2 Along Axis-3 between Axis-A&B

1 4.2 0.05 0.21 m2 Along Axis-6 between Axis-B&C

1 5.2 0.05 0.26 m2 Along Axis-6 between Axis-C&D

2 2.7 0.05 0.27 m2 Along Axis-B&D between Axis-3&4

4 4.7 0.05 0.94 m2 Along Axis-B&D between Axis-4&5 and 5&6

1 4.2 2.7 11.34 m2 Roof stair cover along Axis-3 and Axis-4(B-C)

1 2.8 5.35 14.98 m2 Roof stair cover along Axis-3 and Axis-4(C-D)
247.095 m2 total form work for slab (roof)

Times L (m) W (m) H (m) squaring unit 2.2 FORM WORK FOR COLUMN (GROUND FLOOR) 20mm thick swan zigaba form work for Slab
14 1.28 3 53.76 m2 on all axis points (1A,1B,1C,1D,2A,2B,2C,2D,3A,3B,3C………..)
53.76 m2 total form work for column (ground floor)

Times L (m) W (m) H (m) squaring unit FORM WORK FOR COLUMN (FIRST FLOOR) 20mm thick swan zigaba form work for Slab
53.76 m2 ditto as above
53.76 m2 total form work for column (first floor)

Times L (m) W (m) H (m) squaring unit FORM WORK FOR COLUMN (SECOND FLOOR) 20mm thick swan zigaba form work for Slab
53.76 m2 ditto as above
53.76 m2 total form work for column (second floor)

Times L (m) W (m) H (m) squaring unit FORM WORK FOR COLUMN (ROOF) 20mm thick swan zigaba form work for Slab
6 1.28 3 23.04 m2 Along axis 3B,3C,3D,4B,4C,4D
23.04 m2 total form work for column (roof)

Times L (m) W (m) H (m) squaring unit 2.3 FORM WORK FOR BEAM (FIRST FLOOR) 20mm thick swan zigaba form work for Slab
6 0.58 4.2 14.616 m2 Along Axis-1,Axis-2 and Axis-3 between Axis-A&B and Axis-B&C Perimeter= 0.19+0.2+0.19

3 0.58 5.2 9.048 m2 Along Axis-1,Axis-2 and Axis-3 between Axis-C&D Perimeter= 0.19+0.2+0.19

3 0.58 4.2 7.308 m2 Along Axis-4,Axis-5 and Axis 6 between Axis B&C Perimeter= 0.19+0.2+0.19

3 0.58 5.2 9.048 m2 Along Axis-4,Axis-5 and Axis-6 between Axis-C&D Perimeter= 0.19+0.2+0.19

8 0.58 4.7 21.808 m2 Along Axis-A, Axis-B, Axis-C and Axis-D between Axis-1&2 and Axis-2&3 Perimeter= 0.19+0.2+0.19

3 0.58 2.7 4.698 m2 Along Axis-B, Axis-C and Axis-D between Axis 3&4 Perimeter= 0.19+0.2+0.19

6 0.58 4.7 16.356 m2 Along Axis-B, Axis-C and Axis-D between Axis 4&5 and 5&6 Perimeter= 0.19+0.2+0.19
82.882 m2 total form work for beam (first floor)

Times L (m) W (m) H (m) squaring unit FORM WORK FOR BEAM (SECOND FLOOR) 20mm thick swan zigaba form work for Slab
82.882 m2 ditto as above
82.882 m2 total form work for beam (second floor)

Times L (m) W (m) H (m) squaring unit FORM WORK FOR BEAM (ROOF) 20mm thick swan zigaba form work for Slab
6 0.58 4.2 14.616 m2 Along Axis-1,Axis-2 and Axis-3 between Axis-A&B and Axis-B&C Perimeter= 0.19+0.2+0.19

3 0.58 5.2 9.048 m2 Along Axis-1,Axis-2 and Axis-3 between Axis-C&D Perimeter= 0.19+0.2+0.19

3 0.58 4.2 7.308 m2 Along Axis-4,Axis-5 and Axis 6 between Axis B&C Perimeter= 0.19+0.2+0.19

3 0.58 5.2 9.048 m2 Along Axis-4,Axis-5 and Axis-6 between Axis-C&D Perimeter= 0.19+0.2+0.19

8 0.58 4.7 21.808 m2 Along Axis-A, Axis-B, Axis-C and Axis-D between Axis-1&2 and Axis-2&3 Perimeter= 0.19+0.2+0.19

3 0.58 2.7 4.698 m2 Along Axis-B, Axis-C and Axis-D between Axis 3&4 Perimeter= 0.19+0.2+0.19

6 0.58 4.7 16.356 m2 Along Axis-B, Axis-C and Axis-D between Axis 4&5 and 5&6 Perimeter= 0.19+0.2+0.19

2 0.58 4.2 4.872 m2 Top tie beam Along Axis-3 and Axis-4 between Axis-B&C Perimeter= 0.19+0.2+0.19

2 0.58 5.2 6.032 m2 Top tie beam Along Axis-3 and Axis-4 between Axis-C&D Perimeter= 0.19+0.2+0.19
93.786 m 2
total form work for beam (roof)

Times L (m) W (m) H (m) squaring unit 2.4 FORM WORK FOR STAIR (GROUND FLOOR) 20mm thick swan zigaba form work for Slab
2 3.25 1.2 7.8 m2 waist slab shuttering for flights from ground to first floor

1 1.5 2.7 4.05 m2 landing shuttering

4 3.25 0.29 3.77 m2 waist slab side shuttering


1 5.7 0.15 0.855 m2 landing side shuttering

22 1.2 0.15 3.96 m2 steps riser


20.435 m2 total form work for stair (ground floor)

Times L (m) W (m) H (m) squaring unit FORM WORK FOR STAIR (FIRST FLOOR) 20mm thick swan zigaba form work for Slab
20.435 m2 ditto as above
20.435 m2 total form work for stair (first floor)

Times L (m) W (m) H (m) squaring unit FORM WORK FOR STAIR (SECOND FLOOR) 20mm thick swan zigaba form work for Slab
20.435 m2 ditto as above
20.435 m2 total form work for stair (second floor)
1239.86 m 2
TOTAL FORMWORK (20mm THICK SWAN ZIGBA FORMWORK)

TIMES L W H SQUARE UNIT 3. BLOCK WORK


3.1 20cm*20cm*40cm HCB for External Ground Floor
2
1 13.62 3 40.86 m Right elevation Axis A-D

1 4.45 3 13.35 m2 Front elevation Axis 1-6

1 12.1 3 36.3 m2 Left elevation Axis A-D

1 23 3 69 m2 Rear elevation Axis 1-6


2
159.51 m

-1.00 0.95 2.1 -1.995 m2 Right elevation Door size deduction Axis A-B

-3.00 0.65 1.8 -3.51 m2 Right elevation window size deduction Axis A-D

-1.00 1.25 1.8 -2.25 m2 Right elevation window size deduction Axis B-C

-1.00 2.5 2.1 -5.25 m2 Front elevation Door size deduction Axis 3-4
-1.00 1.15 2 -2.3 m2 Front elevation window size deduction Axis 5-6

-1.00 1.05 2.1 -2.205 m2 Left elevation Door size deduction Axis C-D

-4.00 0.65 1.8 -4.68 m2 Rear elevation window size deduction Axis 2-6

-1.00 1.25 1.8 -2.25 m2 Rear elevation window size deduction Axis 5-6

-2.00 1.8 1.8 -6.48 m2 Rear elevation window size deduction Axis 4-5

-1.00 2.5 2.5 -6.25 m2 Rear elevation window size deduction Axis 3-4

-1.00 8.5 2.1 -17.85 m2 Rear elevation Door size deduction Axis 2-3
2
-55.02 m
104.49 m2 Total 20cm*20cm*40cm HCB for External Ground Floor

TIMES L W H SQUARE UNIT 3.2 30cm*20cm*40cm HCB for External First Floor
2
1 1.4 3.3 4.62 m
4.62 m2 Total 30cm*20cm*40cm HCB for External First Floor

TIMES L W H SQUARE UNIT 20cm*20cm*40cm HCB for External First Floor


2
1 13.6 3.3 44.88 m 20cm*20cm*40cm HCB for Ground Floor on Right elevation Axis A-D

1 12.1 3.3 39.93 m2 ditto as above for Front elevation Axis 1-6

1 12.1 3.3 39.93 m2 ditto as above for Left elevation Axis A-D

1 9.4 3.3 31.02 m2 ditto as above for Rear elevation Axis 1-6
155.76 m2

-1.00 1.2 1.8 -2.16 m2 Right Side Window size Deduction Axis C-D, Axis 1-2
-1.00 0.75 2.1 -1.575 m2 Front Side Door size Deduction Axis D, Axis 1-2

-2.00 0.65 1.8 -2.34 m2 Front Side Window size Deduction Axis D, Axis 2-5

-1.00 0.85 2.1 -1.785 m2 Front Side Door size Deduction Axis D, Axis 5-6

-1.00 2.5 2.5 -6.25 m2 Front Side Window size Deduction Axis D, Axis 3-4

-1.00 1.2 1.8 -2.16 m2 Left Side Window size Deduction Axis C-D, Axis 5-6

-5.00 0.65 1.8 -5.85 m2 Rear Side Window size Deduction Axis A, Axis 1-3 and Axis B , Axis 4-6

-3.00 1.25 1.8 -6.75 m2 Rear Side Window size Deduction Axis B, Axis 3-4 and Axis A , Axis 1-3

-1.00 2.5 2 -5 m2 Rear Side Window size Deduction Axis B, Axis 3-4
-33.87 m2
121.89 m2 Total 20cm*20cm*40cm HCB for External First Floor

TIMES L W H SQUARE UNIT 30cm*20cm*40cm HCB for External Second Floor


2
2 1.4 3 8.4 m Right and Left side
8.4 m 2
Total 30cm*20cm*40cm HCB for External First Floor

TIMES L W H SQUARE UNIT 20cm*20cm*40cm HCB for External Second Floor


2
1 23.85 3 71.55 m Right elevation Axis A-D

1 21.5 3 64.5 m2 Front elevation Axis 1-6

1 13.6 3 40.8 m2 Left elevation Axis A-D

1 21.5 3 64.5 m2 Rear elevation Axis 1-6


2
241.35 m
-1.00 3 2.1 -6.3 m2 Right Side door size Deduction

-1.00 2.5 1.8 -4.5 m2 Right Side Window size Deduction

-1.00 1.2 1.8 -2.16 m2 ditto as above

-1.00 1.25 1.8 -2.25 m2 ditto as above

-4.00 0.65 1.8 -4.68 m2 Front Side Window size Deduction

-1.00 2 2 -4 m2 Front Side Door size Deduction

-2.00 2 2 -8 m2 ditto as above

-1.00 1.2 1.8 -2.16 m2 Left Side Window size Deduction

-1.00 0.65 1.8 -1.17 m2 ditto as above

-3.00 0.65 1.8 -3.51 m2 Rear Side Window size Deduction

-2.00 1.25 1.8 -4.5 m2 ditto as above

-1.00 2.5 2.5 -6.25 m2 ditto as above


2
-49.48 m
191.87 m2 Total 20cm*20cm*40cm HCB for External Second Floor

TIMES L W H SQUARE UNIT 20cm*20cm*40cm HCB for External Roof


2
1 14.8 1.5 22.2 m Right elevation Axis A-D

1 23 1.5 34.5 m2 Front elevation Axis 1-6


1 15 1.5 22.5 m2 Left elevation Axis A-D

1 23 1.5 34.5 m2 Rear elevation Axis 1-6

1 4.2 3 12.6 m2 Axis B-C, Axis 3-4

1 5.2 3 15.6 m2 Axis C-D, Axis 3-5


2
141.9 m

-2.00 0.95 2.1 -3.99 m2 Door size deduction


2
-3.99 m
137.91 m2 Total 20cm*20cm*40cm HCB for External Roof

TIMES L W H SQUARE UNIT 3.3 15cm*20cm*40cm HCB for Internal Ground Floor
2
1 9.4 3 28.2 m Restaurant Axis B-D

1 10.3 3 30.9 m2 Restaurant, Toilet Axis A-B, Axis 2-3

1 3.95 3 11.85 m2 Restaurant, changing room Axis A-B

1 1.4 3 4.2 m2 Restaurant Axis A-B

1 8.3 3 24.9 m2 Restaurant, changing room Axis A-B

1 14.4 3 43.2 m2 Restaurant, Kitchen Axis A-C

1 14.05 3 42.15 m2 Mini Market Axis C-D, Axis 4-6

1 6.3 3 18.9 m2 Guard Room Axis C-D, Axis 5-6

1 15.8 3 47.4 m2 Water Closet Axis B-C, Axis 4-5


1 6.85 3 20.55 m2 Office Axis B-C, Axis 5-6

1 6.75 3 20.25 m2 Store Axis B-C, Axis 5-6


2
292.5 m

-1.00 2.5 2.1 -5.25 m2 Restaurant Door size Deduction Axis C-D

-1.00 0.95 2.1 -1.995 m2 Restaurant Door size Deduction Axis A-B

-4.00 0.75 2.1 -6.3 m2 Restaurant Door size Deduction Axis A-B. Axis 2-3

-1.00 0.85 2.1 -1.785 m2 Restaurant Door size Deduction Axis A-B. Axis 1-2

-1.00 0.95 2.1 -1.995 m2 Mini Market Door size Deduction Axis C-D. Axis 4-5

-1.00 0.95 2.1 -1.995 m2 Guard Room Door size Deduction Axis C-D, Axis 5-6

-2.00 0.85 2.1 -3.57 m2 water Closet Door size Deduction Axis B-C, Axis 4-5

-1.00 0.95 2.1 -1.995 m2 Office Door size Deduction Axis B-C, Axis 5-6

-1.00 0.85 2.1 -1.785 m2 Store Door size Deduction Axis B-C, Axis 5-6
2
-26.67 m
265.83 m2 Total 15cm*20cm*40cm HCB for internal ground floor

3.4 10cm*20cm*40cm HCB for Internal Ground Floor


TIMES L W H SQUARE UNIT DESCRIPTION
2
1 1.4 3 4.2 m Water Closet Axis B-C, Axis 4-5

2 4.2 3 25.2 m2 Water Closet Axis B-C, Axis 4-5


2
29.4 m
-4.00 0.75 2.1 -6.3 m2 water Closet Door size Deduction Axis B-C, Axis 4-5
2
-6.3 m
23.1 m2 Total 10cm*20cm*40cm HCB for internal ground floor

20cm*20cm*40cm HCB for Internal First Floor


TIMES L W H SQUARE UNIT DESCRIPTION
2
1 4.05 3 12.15 m Reception
12.15 m 2
Total 20cm*20cm*40cm HCB for internal first floor

15cm*20cm*40cm HCB for Internal First Floor


2
2 4.7 3 28.2 m Twin Bed Room Axis C, Axis 1-3

3 4.2 3 37.8 m2 ditto as above Axis A-C, Axis 2

2 3 3 18 m2 ditto as above Axis A-B, Axis 1-3

1 3.3 3 9.9 m2 ditto as above Axis C-D, Axis 2-3

1 10.1 3 30.3 m2 ditto as above Axis C-D, Axis 1-3

2 4 3 24 m2 ditto as above Axis C-D, Axis 3-5

1 3.3 3 9.9 m2 ditto as above Axis C-D, Axis 4-5

1 9.95 3 29.85 m2 ditto as above Axis C-D, Axis 1-6

2 4.2 3 25.2 m2 Laundry Room Axis B-C, Axis 4-5

1 4.7 3 14.1 m2 ditto as above


1 1.9 3 5.7 m2 changing room Axis B-C, Axis 5-6

1 0.6 3 1.8 m2 ditto as above

2 1.4 3 8.4 m2 ditto as above

1 1.1 3 3.3 m2 ditto as above

2 2.37 3 14.22 m2 ditto as above

1 2.8 3 8.4 m2 ditto as above


269.07 m2

-4.00 0.85 2.1 -7.14 m2 Twin Bed Room Door size Deduction

-4.00 0.75 2.1 -6.3 m2 ditto as above

-1.00 0.95 2.1 -1.995 m2 Laundry Room Door size Deduction

-2.00 0.85 2.1 -3.57 m2 Changing Room Door size Deduction

-2.00 0.75 2.1 -3.15 m2 ditto as above


2
-22.155 m
246.915 m2 Total 15cm*20cm*40cm HCB for internal first floor

10cm*20cm*40cm HCB for Internal First Floor


TIMES L W H SQUARE UNIT DESCRIPTION
2
2 1.1 3 6.6 m Changing room WC Axis B-C, Axis 5-6
6.6 m 2
Total 10cm*20cm*40cm HCB for internal first floor

20cm*20cm*40cm HCB for Internal Second Floor


TIMES L W H SQUARE UNIT DESCRIPTION
3 4.2 3 37.8 m2 Stair Case Axis B-C, Axis 3-4

1 3.9 3 11.7 m2 Waiting Area Axis C-D, Axis 3-4

2 4.05 3 24.3 m2 ditto as above

1 4.7 3 14.1 m2
87.9 m2

-1.00 0.85 2.1 -1.785 Single bed room door size deduction
2
-1.785 m
86.115 m2 Total 20cm*20cm*40cm HCB for internal second floor

15cm*20cm*40cm HCB for Internal Second Floor


TIMES L W H SQUARE UNIT DESCRIPTION
2
3 4.7 3 42.3 m Suite Room AXIS A-C, Axis 1-3

1 3.6 3 10.8 m2 ditto as above

1 3.3 3 9.9 m2 ditto as above

1 4.8 3 14.4 m2 Single Bed Room Axis C-D, Axis 1-2

1 2.9 3 8.7 m2 Single Bed Room Axis C-D, Axis 1-3

1 1.95 3 5.85 m2 Single Bed Room Axis C-D, Axis 1-4

1 3.75 3 11.25 m2 Store Axis C-D, Axis 2-3

1 4.7 3 14.1 m2 ditto as above

1 2.9 3 8.7 m2 Single Bed Room Axis B-C, Axis 4-5


1 1.95 3 5.85 m2 ditto as above

1 2.9 3 8.7 m2 Single Bed Room Axis B-C, Axis 5-6

1 1.95 3 5.85 m2 ditto as above

1 3.3 3 9.9 m2 ditto as above

1 4.8 3 14.4 m2 Single Bed Room Axis C-D, Axis 4-5

1 2.95 3 8.85 m2 ditto as above

1 1.8 3 5.4 m2 ditto as above

1 4.85 3 14.55 m2 Single Bed Room Axis C-D, Axis 5-6

1 2.95 3 8.85 m2 ditto as above

1 1.8 3 5.4 m2 ditto as above


2
213.75 m

-2.00 0.85 2.1 -3.57 m2 Suite Room door size deduction AXIS A-C, Axis 1-3

-1.00 0.85 2.1 -1.785 m2 Single Bed door size deduction Room Axis C-D, Axis 1-2

-1.00 0.75 2.1 -1.575 m2 ditto as above

-1.00 0.95 2.1 -1.995 m2 Store door size deduction Axis C-D, Axis 2-3

-1.00 0.75 2.1 -1.575 m2 Single Bed Room door size deduction Axis B-C, Axis 4-5

-1.00 0.75 2.1 -1.575 m2 Single Bed Room door size deduction Axis B-C, Axis 5-6
-1.00 0.85 2.1 -1.785 m2 ditto as above

-1.00 0.85 2.1 -1.785 m2 Single Bed Room door size deduction Axis C-D, Axis 4-5

-1.00 0.75 2.1 -1.575 m2 ditto as above

-1.00 0.65 1.8 -1.17 m2 Single Bed Room window size deduction Axis C-D, Axis 4-5

-1.00 0.85 2.1 -1.785 m2 Single Bed Room door size deduction Axis C-D, Axis 5-6

-1.00 0.75 2.1 -1.575 m2 ditto as above

-1.00 0.65 1.8 -1.17 m2 Single Bed Room Window size deduction Axis C-D, Axis 5-6
2
-22.92 m
190.83 m2 Total 15cm*20cm*40cm HCB for internal second floor
29.7 m2 TOTAL 10cm*20cm*40cm HCB (3.4)
703.575 m2 TOTAL 15cm*20cm*40cm HCB (3.3)
654.425 m2 TOTAL 20cm*20cm*40cm HCB (3.1)
13.02 m2 TOTAL 30cm*20cm*40cm HCB (Two 15cm thick wall)(3.2)

TIMES L W H Square UNIT 4. FINISHING WORK


4.1 Ground Floor Cement-Sand Plastering
EXTERNAL
2
1 27.24 3 81.72 m Right elevation Axis A-D

1 8.9 3 26.7 m2 Front elevation Axis 1-6

1 24.2 3 72.6 m2 Left elevation Axis A-D

1 46 3 138 m2 Rear elevation Axis 1-6


319.02 m2

-1.00 1.9 2.1 -3.99 m2 Right elevation Door size deduction Axis A-B

-3.00 1.3 0.65 -2.535 m2 Right elevation window size deduction Axis A-D

-1.00 2.5 1.5 -3.75 m2 Right elevation window size deduction Axis B-C

-1.00 5 2.1 -10.5 m2 Front elevation Door size deduction Axis 3-4

-1.00 2.3 1 -2.3 m2 Front elevation window size deduction Axis 5-6

-1.00 2.1 2.1 -4.41 m2 Left elevation Door size deduction Axis C-D

-4.00 1.3 0.65 -3.38 m2 Rear elevation window size deduction Axis 2-6

-1.00 2.5 1.5 -3.75 m2 Rear elevation window size deduction Axis 5-6

-2.00 3.6 0.65 -4.68 m2 Rear elevation window size deduction Axis 4-5

-1.00 5 2.5 -12.5 m2 Rear elevation window size deduction Axis 3-4

-1.00 17 2.1 -35.7 m2 Rear elevation Door size deduction Axis 2-3
2
-87.495 m
231.525 m2 Total external cement-sand plastering Ground floor

INTERNAL
TIMES L W H Square UNIT DESCRIPTION
2
1 18.8 3 56.4 m Restaurant Axis B-D

1 20.6 3 61.8 m2 Restaurant, Toilet Axis A-B, Axis 2-3

1 7.9 3 23.7 m2 Restaurant, changing room Axis A-B


1 2.8 3 8.4 m2 Restaurant Axis A-B

1 16.6 3 49.8 m2 Restaurant, changing room Axis A-B

1 28.8 3 86.4 m2 Restaurant, Kitchen Axis A-C

1 28.1 3 84.3 m2 Mini Market Axis C-D, Axis 4-6

1 12.6 3 37.8 m2 Guard Room Axis C-D, Axis 5-6

1 31.6 3 94.8 m2 Water Closet Axis B-C, Axis 4-5

1 13.7 3 41.1 m2 Office Axis B-C, Axis 5-6

1 13.5 3 40.5 m2 Store Axis B-C, Axis 5-6

1 2.8 3 8.4 m2 Water Closet Axis B-C, Axis 4-5

2 8.4 3 50.4 m2 ditto as above


2
643.8 m

-1.00 5 2.1 -10.5 m2 Restaurant Door size Deduction Axis C-D

-1.00 1.9 2.1 -3.99 m2 Restaurant Door size Deduction Axis A-B

-4.00 1.5 2.1 -12.6 m2 Restaurant Door size Deduction Axis A-B. Axis 2-3

-1.00 1.7 2.1 -3.57 m2 Restaurant Door size Deduction Axis A-B. Axis 1-2

-1.00 1.9 2.1 -3.99 m2 Mini Market Door size Deduction Axis C-D. Axis 4-5

-1.00 1.9 2.1 -3.99 m2 Guard Room Door size Deduction Axis C-D, Axis 5-6
-2.00 1.7 2.1 -7.14 m2 water Closet Door size Deduction Axis B-C, Axis 4-5

-1.00 1.9 2.1 -3.99 m2 Office Door size Deduction Axis B-C, Axis 5-6

-1.00 1.7 2.1 -3.57 m2 Store Door size Deduction Axis B-C, Axis 5-6

-4.00 1.5 2.1 -12.6 m2 water Closet Door size Deduction Axis B-C, Axis 4-5
2
-65.94 m
577.86 m2 Total internal cement-sand plastering Ground floor

First Floor Cement-Sand Plastering


EXTERNAL
TIMES L H AREA UNIT DESCRIPTION
1 2.8 3.3 9.24 m2 Left side Axis c, Axis 6

1 27.2 3.3 89.76 m2 Right elevation Axis A-D

1 24.2 3.3 79.86 m2 Front elevation Axis 1-6

1 24.2 3.3 79.86 m2 Left elevation Axis A-D

1 18.8 3.3 62.04 m2 Rear elevation Axis 1-6


2
320.76 m

-1.00 2.4 1.5 -3.6 m2 Right Side Window size Deduction Axis C-D, Axis 1-2

-1.00 1.5 2.1 -3.15 m2 Front Side Door size Deduction Axis D, Axis 1-2

-2.00 1.3 0.65 -1.69 m2 Front Side Window size Deduction Axis D, Axis 2-5

-1.00 1.7 2.1 -3.57 m2 Front Side Door size Deduction Axis D, Axis 5-6
-1.00 4 2 -8 m2 Front Side Window size Deduction Axis D, Axis 3-4

-1.00 2.4 1.5 -3.6 m2 Left Side Window size Deduction Axis C-D, Axis 5-6

-5.00 1.3 0.65 -4.225 m2 Rear Side Window size Deduction Axis A, Axis 1-3 and Axis B , Axis 4-6

-3.00 2.5 1.5 -11.25 m2 Rear Side Window size Deduction Axis B, Axis 3-4 and Axis A , Axis 1-3

-1.00 4 2 -8 m2 Rear Side Window size Deduction Axis B, Axis 3-4


2
-47.085 m
273.675 m2 Total external cement-sand plastering first floor

INTERNAL

1 8.1 3 24.3 m2 Reception

2 9.4 3 56.4 m2 Twin Bed Room Axis C, Axis 1-3

3 8.4 3 75.6 m2 Twin Bed Room Axis A-C, Axis 2

2 6 3 36 m2 Twin Bed Room Axis A-B, Axis 1-3

1 6.6 3 19.8 m2 Twin Bed Room Axis C-D, Axis 2-3

1 20.2 3 60.6 m2 Twin Bed Room Axis C-D, Axis 1-3

2 8 3 48 m2 Twin Bed Room Axis C-D, Axis 3-5

1 6.6 3 19.8 m2 Twin Bed Room Axis C-D, Axis 4-5

1 19.9 3 59.7 m2 Twin Bed Room Axis C-D, Axis 1-6


2 8.4 3 50.4 m2 Laundry Room Axis B-C, Axis 4-5

1 9.4 3 28.2 m2 ditto as above

1 3.8 3 11.4 m2 changing room Axis B-C, Axis 5-6

1 1.2 3 3.6 m2 ditto as above

2 2.8 3 16.8 m2 ditto as above

1 2.2 3 6.6 m2 ditto as above

2 4.74 3 28.44 m2 ditto as above

1 5.6 3 16.8 m2 ditto as above

2 2.2 3 13.2 m2 Changing room WC Axis B-C, Axis 5-6


575.64 m2

-4.00 1.7 2.1 -14.28 m2 Twin Bed Room Door size Deduction

-4.00 1.5 2.1 -12.6 m2 Twin Bed Room Door size Deduction

-1.00 1.9 2.1 -3.99 m2 Laundry Room Door size Deduction

-2.00 1.7 2.1 -7.14 m2 Changing Room Door size Deduction

-2.00 1.5 2.1 -6.3 m2 Changing Room Door size Deduction


2
-44.31 m
531.33 m2 Total internal cement-sand plastering First floor

Second Floor Cement-Sand Plastering


EXTERNAL

TIMES L W H Square UNIT DESCRIPTION


2 2.8 3 16.8 m2 Right and Left side

1 47.7 3 143.1 m2 Right elevation Axis A-D

1 43 3 129 m2 Front elevation Axis 1-6

1 27.2 3 81.6 m2 Left elevation Axis A-D

1 43 3 129 m2 Rear elevation Axis 1-6


2
499.5 m

-1.00 6 2.15 -12.9 m2 Right Side Window size Deduction


2
-1.00 5 1.55 -7.75 m ditto as above
2
-1.00 2.4 1.55 -3.72 m ditto as above
2
-1.00 2.5 1.55 -3.875 m ditto as above
2
-4.00 1.3 0.65 -3.38 m Front Side Door size Deduction
2
-1.00 4 2 -8 m ditto as above
2
-2.00 2.5 1.55 -7.75 m ditto as above
-1.00 2.4 1.55 -3.72 m2 Left Side Window size Deduction
-1.00 1.3 0.65 -0.845 m2 ditto as above
2
-3.00 1.3 0.65 -2.535 m Rear Side Window size Deduction
2
-2.00 2.5 1.55 -7.75 m ditto as above
2
-1.00 5 2.5 -12.5 m ditto as above
2
-74.725 m
424.775 m2 Total external cement-sand plastering Second floor

INTERNAL
TIMES L W H Square UNIT DESCRIPTION
3 8.4 3 75.6 m2 Stair Case Axis B-C, Axis 3-4
1 7.8 3 23.4 m2 Waiting Area Axis C-D, Axis 3-4

2 8.1 3 48.6 m2 ditto as above

1 9.4 3 28.2 m2

3 9.4 3 84.6 m2 Suite Room AXIS A-C, Axis 1-3

1 7.2 3 21.6 m2 ditto as above

1 3.3 3 9.9 m2 ditto as above

1 9.6 3 28.8 m2 Single Bed Room Axis C-D, Axis 1-2

1 5.8 3 17.4 m2 Single Bed Room Axis C-D, Axis 1-3

1 3.9 3 11.7 m2 Single Bed Room Axis C-D, Axis 1-4

1 7.5 3 22.5 m2 Store Axis C-D, Axis 2-3

1 9.4 3 28.2 m2 ditto as above

1 5.8 3 17.4 m2 Single Bed Room Axis B-C, Axis 4-5

1 3.9 3 11.7 m2 ditto as above

1 5.8 3 17.4 m2 Single Bed Room Axis B-C, Axis 5-6

1 3.9 3 11.7 m2 ditto as above

1 6.6 3 19.8 m2 ditto as above


1 9.6 3 28.8 m2 Single Bed Room Axis C-D, Axis 4-5

1 5.9 3 17.7 m2 ditto as above

1 3.6 3 10.8 m2 ditto as above

1 9.7 3 29.1 m2 Single Bed Room Axis C-D, Axis 5-6

1 5.9 3 17.7 m2 ditto as above

1 3.6 3 10.8 m2 ditto as above


593.4 m2

-1.00 1.7 2.1 -3.57 Single bed room door size deduction

-2.00 1.7 2.1 -7.14 m2 Suite Room door size deduction AXIS A-C, Axis 1-3

-1.00 1.7 2.1 -3.57 m2 Single Bed door size deduction Room Axis C-D, Axis 1-2

-1.00 1.5 2.1 -3.15 m2 ditto as above

-1.00 1.9 2.1 -3.99 m2 Store door sixe deduction Axis C-D, Axis 2-3

-1.00 1.5 2.1 -3.15 m2 Single Bed Room door size deduction Axis B-C, Axis 4-5

-1.00 1.5 2.1 -3.15 m2 Single Bed Room door size deduction Axis B-C, Axis 5-6

-1.00 1.7 2.1 -3.57 m2 ditto as above

-1.00 1.7 2.1 -3.57 m2 Single Bed Room door size deduction Axis C-D, Axis 4-5

-1.00 1.5 2.1 -3.15 m2 ditto as above


-1.00 1.3 0.65 -0.845 m2 Single Bed Room window size deduction Axis C-D, Axis 4-5

-1.00 1.7 2.1 -3.57 m2 Single Bed Room door size deduction Axis C-D, Axis 5-6

-1.00 1.5 2.1 -3.15 m2 ditto as above

-1.00 1.3 0.65 -0.845 m2 Single Bed Room Window size deduction Axis C-D, Axis 5-6
2
-46.42 m
546.98 m2 Total internal cement-sand plastering Second floor

ROOF Cement-Sand Plastering


TIMES L W H Square UNIT DESCRIPTION
2
1 29.6 1.5 44.4 m Right elevation Axis A-D

1 46 1.5 69 m2 Front elevation Axis 1-6

1 30 1.5 45 m2 Left elevation Axis A-D

1 46 1.5 69 m2 Rear elevation Axis 1-6

1 8.4 3 25.2 m2 Axis B-C, Axis 3-4

1 10.4 3 31.2 m2 Axis C-D, Axis 3-5


283.8 m 2

-2.00 0.95 2.1 -3.99 m2 Door size deduction


-3.99 m 2

279.81 m2 Total internal cement-sand plastering Roof

3509.76 m2 TOTAL CEMENT-SAND PLASTERING


4.2 GYPSUM PLASTERING
TIMES L W H SQUARE UNIT
Ground Floor Gypsum Plastering
Internal
2
1 18.8 3 56.4 m Restaurant Axis B-D

1 20.6 3 61.8 m2 Restaurant, Toilet Axis A-B, Axis 2-3

1 7.9 3 23.7 m2 Restaurant, changing room Axis A-B

1 2.8 3 8.4 m2 Restaurant Axis A-B

1 16.6 3 49.8 m2 Restaurant, changing room Axis A-B

1 28.8 3 86.4 m2 Restaurant, Kitchen Axis A-C

1 28.1 3 84.3 m2 Mini Market Axis C-D, Axis 4-6

1 12.6 3 37.8 m2 Guard Room Axis C-D, Axis 5-6

1 31.6 3 94.8 m2 Water Closet Axis B-C, Axis 4-5

1 13.7 3 41.1 m2 Office Axis B-C, Axis 5-6

1 13.5 3 40.5 m2 Store Axis B-C, Axis 5-6

1 2.8 3 8.4 m2 Water Closet Axis B-C, Axis 4-5

2 8.4 3 50.4 m2 ditto as above


2
643.8 m

-1.00 5 2.1 -10.5 m2 Restaurant Door size Deduction Axis C-D


-1.00 1.9 2.1 -3.99 m2 Restaurant Door size Deduction Axis A-B

-4.00 1.5 2.1 -12.6 m2 Restaurant Door size Deduction Axis A-B. Axis 2-3

-1.00 1.7 2.1 -3.57 m2 Restaurant Door size Deduction Axis A-B. Axis 1-2

-1.00 1.9 2.1 -3.99 m2 Mini Market Door size Deduction Axis C-D. Axis 4-5

-1.00 1.9 2.1 -3.99 m2 Guard Room Door size Deduction Axis C-D, Axis 5-6

-2.00 1.7 2.1 -7.14 m2 water Closet Door size Deduction Axis B-C, Axis 4-5

-1.00 1.9 2.1 -3.99 m2 Office Door size Deduction Axis B-C, Axis 5-6

-1.00 1.7 2.1 -3.57 m2 Store Door size Deduction Axis B-C, Axis 5-6

-4.00 1.5 2.1 -12.6 m2 water Closet Door size Deduction Axis B-C, Axis 4-5
2
-65.94 m
577.86 m2 Total internal gypsum plastering Ground floor

First Floor Gypsum Plastering


INTERNAL
1 8.1 3 24.3 m2 Reception

2 9.4 3 56.4 m2 Twin Bed Room Axis C, Axis 1-3

3 8.4 3 75.6 m2 Twin Bed Room Axis A-C, Axis 2

2 6 3 36 m2 Twin Bed Room Axis A-B, Axis 1-3

1 6.6 3 19.8 m2 Twin Bed Room Axis C-D, Axis 2-3


1 20.2 3 60.6 m2 Twin Bed Room Axis C-D, Axis 1-3

2 8 3 48 m2 Twin Bed Room Axis C-D, Axis 3-5

1 6.6 3 19.8 m2 Twin Bed Room Axis C-D, Axis 4-5

1 19.9 3 59.7 m2 Twin Bed Room Axis C-D, Axis 1-6

2 8.4 3 50.4 m2 Laundry Room Axis B-C, Axis 4-5

1 9.4 3 28.2 m2 ditto as above

1 3.8 3 11.4 m2 changing room Axis B-C, Axis 5-6

1 1.2 3 3.6 m2 ditto as above

2 2.8 3 16.8 m2 ditto as above

1 2.2 3 6.6 m2 ditto as above

2 4.74 3 28.44 m2 ditto as above

1 5.6 3 16.8 m2 ditto as above

2 2.2 3 13.2 m2 Changing room WC Axis B-C, Axis 5-6


2
575.64 m

-4.00 1.7 2.1 -14.28 m2 Twin Bed Room Door size Deduction

-4.00 1.5 2.1 -12.6 m2 Twin Bed Room Door size Deduction

-1.00 1.9 2.1 -3.99 m2 Laundry Room Door size Deduction


-2.00 1.7 2.1 -7.14 m2 Changing Room Door size Deduction

-2.00 1.5 2.1 -6.3 m2 Changing Room Door size Deduction


2
-44.31 m
531.33 m2 Total internal gypsum plastering First floor

Second Floor Gypsum Plastering


INTERNAL
TIMES L W H Square UNIT DESCRIPTION
3 8.4 3 75.6 m2 Stair Case Axis B-C, Axis 3-4

1 7.8 3 23.4 m2 Waiting Area Axis C-D, Axis 3-4

2 8.1 3 48.6 m2 ditto as above

1 9.4 3 28.2 m2

3 9.4 3 84.6 m2 Suite Room AXIS A-C, Axis 1-3

1 7.2 3 21.6 m2 ditto as above

1 3.3 3 9.9 m2 ditto as above

1 9.6 3 28.8 m2 Single Bed Room Axis C-D, Axis 1-2

1 5.8 3 17.4 m2 Single Bed Room Axis C-D, Axis 1-3

1 3.9 3 11.7 m2 Single Bed Room Axis C-D, Axis 1-4

1 7.5 3 22.5 m2 Store Axis C-D, Axis 2-3


1 9.4 3 28.2 m2 ditto as above

1 5.8 3 17.4 m2 Single Bed Room Axis B-C, Axis 4-5

1 3.9 3 11.7 m2 ditto as above

1 5.8 3 17.4 m2 Single Bed Room Axis B-C, Axis 5-6

1 3.9 3 11.7 m2 ditto as above

1 6.6 3 19.8 m2 ditto as above

1 9.6 3 28.8 m2 Single Bed Room Axis C-D, Axis 4-5

1 5.9 3 17.7 m2 ditto as above

1 3.6 3 10.8 m2 ditto as above

1 9.7 3 29.1 m2 Single Bed Room Axis C-D, Axis 5-6

1 5.9 3 17.7 m2 ditto as above

1 3.6 3 10.8 m2 ditto as above


2
593.4 m

-1.00 1.7 2.1 -3.57 Single bed room door size deduction

-2.00 1.7 2.1 -7.14 m2 Suite Room door size deduction AXIS A-C, Axis 1-3

-1.00 1.7 2.1 -3.57 m2 Single Bed door size deduction Room Axis C-D, Axis 1-2

-1.00 1.5 2.1 -3.15 m2 ditto as above


-1.00 1.9 2.1 -3.99 m2 Store door sixe deduction Axis C-D, Axis 2-3

-1.00 1.5 2.1 -3.15 m2 Single Bed Room door size deduction Axis B-C, Axis 4-5

-1.00 1.5 2.1 -3.15 m2 Single Bed Room door size deduction Axis B-C, Axis 5-6

-1.00 1.7 2.1 -3.57 m2 ditto as above

-1.00 1.7 2.1 -3.57 m2 Single Bed Room door size deduction Axis C-D, Axis 4-5

-1.00 1.5 2.1 -3.15 m2 ditto as above

-1.00 1.3 0.65 -0.845 m2 Single Bed Room window size deduction Axis C-D, Axis 4-5

-1.00 1.7 2.1 -3.57 m2 Single Bed Room door size deduction Axis C-D, Axis 5-6

-1.00 1.5 2.1 -3.15 m2 ditto as above

-1.00 1.3 0.65 -0.845 m2 Single Bed Room Window size deduction Axis C-D, Axis 5-6
2
-46.42 m
546.98 m2 Total internal gypsum plastering Secondfloor

Roof Gypsum Plastering


INTERNAL
TIMES L W H Square UNIT DESCRIPTION
2
2 9.9 3 59.4 m
-2.00 0.95 2.1 -3.99 m2
55.41 m2 Total internal gypsum plastering roof

1711.58 m2 TOTAL GYPSUM PLASTERING


TIMES L W H Square UNIT 4.3 PAINTING
Ground Floor PAINTING
EXTERNAL
2
1 27.24 3 81.72 m Right elevation Axis A-D

1 8.9 3 26.7 m2 Front elevation Axis 1-6

1 24.2 3 72.6 m2 Left elevation Axis A-D

1 46 3 138 m2 Rear elevation Axis 1-6


319.02 m2

-1.00 1.9 2.1 -3.99 m2 Right elevation Door size deduction Axis A-B

-3.00 1.3 0.65 -2.535 m2 Right elevation window size deduction Axis A-D

-1.00 2.5 1.5 -3.75 m2 Right elevation window size deduction Axis B-C

-1.00 5 2.1 -10.5 m2 Front elevation Door size deduction Axis 3-4

-1.00 2.3 1 -2.3 m2 Front elevation window size deduction Axis 5-6

-1.00 2.1 2.1 -4.41 m2 Left elevation Door size deduction Axis C-D

-4.00 1.3 0.65 -3.38 m2 Rear elevation window size deduction Axis 2-6

-1.00 2.5 1.5 -3.75 m2 Rear elevation window size deduction Axis 5-6

-2.00 3.6 0.65 -4.68 m2 Rear elevation window size deduction Axis 4-5

-1.00 5 2.5 -12.5 m2 Rear elevation window size deduction Axis 3-4
-1.00 17 2.1 -35.7 m2 Rear elevation Door size deduction Axis 2-3
2
-87.495 m
231.525 m2 Total external Painting Ground floor

INTERNAL
TIMES L W H Square UNIT DESCRIPTION
1 18.8 3 56.4 m2 Restaurant Axis B-D

1 20.6 3 61.8 m2 Restaurant, Toilet Axis A-B, Axis 2-3

1 7.9 3 23.7 m2 Restaurant, changing room Axis A-B

1 2.8 3 8.4 m2 Restaurant Axis A-B

1 16.6 3 49.8 m2 Restaurant, changing room Axis A-B

1 28.8 3 86.4 m2 Restaurant, Kitchen Axis A-C

1 28.1 3 84.3 m2 Mini Market Axis C-D, Axis 4-6

1 12.6 3 37.8 m2 Guard Room Axis C-D, Axis 5-6

1 31.6 3 94.8 m2 Water Closet Axis B-C, Axis 4-5

1 13.7 3 41.1 m2 Office Axis B-C, Axis 5-6

1 13.5 3 40.5 m2 Store Axis B-C, Axis 5-6

1 2.8 3 8.4 m2 Water Closet Axis B-C, Axis 4-5

2 8.4 3 50.4 m2 ditto as above


2
643.8 m
-1.00 5 2.1 -10.5 m2 Restaurant Door size Deduction Axis C-D

-1.00 1.9 2.1 -3.99 m2 Restaurant Door size Deduction Axis A-B

-4.00 1.5 2.1 -12.6 m2 Restaurant Door size Deduction Axis A-B. Axis 2-3

-1.00 1.7 2.1 -3.57 m2 Restaurant Door size Deduction Axis A-B. Axis 1-2

-1.00 1.9 2.1 -3.99 m2 Mini Market Door size Deduction Axis C-D. Axis 4-5

-1.00 1.9 2.1 -3.99 m2 Guard Room Door size Deduction Axis C-D, Axis 5-6

-2.00 1.7 2.1 -7.14 m2 water Closet Door size Deduction Axis B-C, Axis 4-5

-1.00 1.9 2.1 -3.99 m2 Office Door size Deduction Axis B-C, Axis 5-6

-1.00 1.7 2.1 -3.57 m2 Store Door size Deduction Axis B-C, Axis 5-6

-4.00 1.5 2.1 -12.6 m2 water Closet Door size Deduction Axis B-C, Axis 4-5
2
-65.94 m
577.86 m2 Total internal Painting Ground floor

First Floor PAINTING


EXTERNAL
TIMES L W H AREA UNIT DESCRIPTION
2
1 2.8 3.3 9.24 m Left side Axis c, Axis 6

1 27.2 3.3 89.76 m2 Right elevation Axis A-D

1 24.2 3.3 79.86 m2 Front elevation Axis 1-6

1 24.2 3.3 79.86 m2 Left elevation Axis A-D


1 18.8 3.3 62.04 m2 Rear elevation Axis 1-6
2
320.76 m

-1.00 2.4 1.5 -3.6 m2 Right Side Window size Deduction Axis C-D, Axis 1-2

-1.00 1.5 2.1 -3.15 m2 Front Side Door size Deduction Axis D, Axis 1-2

-2.00 1.3 0.65 -1.69 m2 Front Side Window size Deduction Axis D, Axis 2-5

-1.00 1.7 2.1 -3.57 m2 Front Side Door size Deduction Axis D, Axis 5-6

-1.00 4 2 -8 m2 Front Side Window size Deduction Axis D, Axis 3-4

-1.00 2.4 1.5 -3.6 m2 Left Side Window size Deduction Axis C-D, Axis 5-6

-5.00 1.3 0.65 -4.225 m2 Rear Side Window size Deduction Axis A, Axis 1-3 and Axis B , Axis 4-6

-3.00 2.5 1.5 -11.25 m2 Rear Side Window size Deduction Axis B, Axis 3-4 and Axis A , Axis 1-3

-1.00 4 2 -8 m2 Rear Side Window size Deduction Axis B, Axis 3-4


2
-47.085 m
273.675 m2 Total external Painting first floor

INTERNAL

1 8.1 3 24.3 m2 Reception

2 9.4 3 56.4 m2 Twin Bed Room Axis C, Axis 1-3

3 8.4 3 75.6 m2 Twin Bed Room Axis A-C, Axis 2

2 6 3 36 m2 Twin Bed Room Axis A-B, Axis 1-3


1 6.6 3 19.8 m2 Twin Bed Room Axis C-D, Axis 2-3

1 20.2 3 60.6 m2 Twin Bed Room Axis C-D, Axis 1-3

2 8 3 48 m2 Twin Bed Room Axis C-D, Axis 3-5

1 6.6 3 19.8 m2 Twin Bed Room Axis C-D, Axis 4-5

1 19.9 3 59.7 m2 Twin Bed Room Axis C-D, Axis 1-6

2 8.4 3 50.4 m2 Laundry Room Axis B-C, Axis 4-5

1 9.4 3 28.2 m2 ditto as above

1 3.8 3 11.4 m2 changing room Axis B-C, Axis 5-6

1 1.2 3 3.6 m2 ditto as above

2 2.8 3 16.8 m2 ditto as above

1 2.2 3 6.6 m2 ditto as above

2 4.74 3 28.44 m2 ditto as above

1 5.6 3 16.8 m2 ditto as above

2 2.2 3 13.2 m2 Changing room WC Axis B-C, Axis 5-6


2
575.64 m

-4.00 1.7 2.1 -14.28 m2 Twin Bed Room Door size Deduction

-4.00 1.5 2.1 -12.6 m2 Twin Bed Room Door size Deduction
-1.00 1.9 2.1 -3.99 m2 Laundry Room Door size Deduction

-2.00 1.7 2.1 -7.14 m2 Changing Room Door size Deduction

-2.00 1.5 2.1 -6.3 m2 Changing Room Door size Deduction


2
-44.31 m
531.33 m2 Total internal Painting First floor

Second Floor PAINTNG


EXTERNAL

TIMES L W H Square UNIT DESCRIPTION


2
2 2.8 3 16.8 m Right and Left side

1 47.7 3 143.1 m2 Right elevation Axis A-D

1 43 3 129 m2 Front elevation Axis 1-6

1 27.2 3 81.6 m2 Left elevation Axis A-D

1 43 3 129 m2 Rear elevation Axis 1-6


2
499.5 m

-1.00 6 2.15 -12.9 m2 Right Side Window size Deduction


2
-1.00 5 1.55 -7.75 m ditto as above
-1.00 2.4 1.55 -3.72 m2 ditto as above
-1.00 2.5 1.55 -3.875 m2 ditto as above
2
-4.00 1.3 0.65 -3.38 m Front Side Door size Deduction
2
-1.00 4 2 -8 m ditto as above
2
-2.00 2.5 1.55 -7.75 m ditto as above
2
-1.00 2.4 1.55 -3.72 m Left Side Window size Deduction
-1.00 1.3 0.65 -0.845 m2 ditto as above
2
-3.00 1.3 0.65 -2.535 m Rear Side Window size Deduction
2
-2.00 2.5 1.55 -7.75 m ditto as above
2
-1.00 5 2.5 -12.5 m ditto as above
2
-74.725 m
424.775 m2 Total external Painting Second floor

INTERNAL
TIMES L W H Square UNIT DESCRIPTION
3 8.4 3 75.6 m2 Stair Case Axis B-C, Axis 3-4

1 7.8 3 23.4 m2 Waiting Area Axis C-D, Axis 3-4

2 8.1 3 48.6 m2 ditto as above

1 9.4 3 28.2 m2

3 9.4 3 84.6 m2 Suite Room AXIS A-C, Axis 1-3

1 7.2 3 21.6 m2 ditto as above

1 3.3 3 9.9 m2 ditto as above

1 9.6 3 28.8 m2 Single Bed Room Axis C-D, Axis 1-2

1 5.8 3 17.4 m2 Single Bed Room Axis C-D, Axis 1-3

1 3.9 3 11.7 m2 Single Bed Room Axis C-D, Axis 1-4

1 7.5 3 22.5 m2 Store Axis C-D, Axis 2-3

1 9.4 3 28.2 m2 ditto as above


1 5.8 3 17.4 m2 Single Bed Room Axis B-C, Axis 4-5

1 3.9 3 11.7 m2 ditto as above

1 5.8 3 17.4 m2 Single Bed Room Axis B-C, Axis 5-6

1 3.9 3 11.7 m2 ditto as above

1 6.6 3 19.8 m2 ditto as above

1 9.6 3 28.8 m2 Single Bed Room Axis C-D, Axis 4-5

1 5.9 3 17.7 m2 ditto as above

1 3.6 3 10.8 m2 ditto as above

1 9.7 3 29.1 m2 Single Bed Room Axis C-D, Axis 5-6

1 5.9 3 17.7 m2 ditto as above

1 3.6 3 10.8 m2 ditto as above


2
593.4 m

-1.00 1.7 2.1 -3.57 Single bed room door size deduction

-2.00 1.7 2.1 -7.14 m2 Suite Room door size deduction AXIS A-C, Axis 1-3

-1.00 1.7 2.1 -3.57 m2 Single Bed door size deduction Room Axis C-D, Axis 1-2

-1.00 1.5 2.1 -3.15 m2 ditto as above

-1.00 1.9 2.1 -3.99 m2 Store door sixe deduction Axis C-D, Axis 2-3
-1.00 1.5 2.1 -3.15 m2 Single Bed Room door size deduction Axis B-C, Axis 4-5

-1.00 1.5 2.1 -3.15 m2 Single Bed Room door size deduction Axis B-C, Axis 5-6

-1.00 1.7 2.1 -3.57 m2 ditto as above

-1.00 1.7 2.1 -3.57 m2 Single Bed Room door size deduction Axis C-D, Axis 4-5

-1.00 1.5 2.1 -3.15 m2 ditto as above

-1.00 1.3 0.65 -0.845 m2 Single Bed Room window size deduction Axis C-D, Axis 4-5

-1.00 1.7 2.1 -3.57 m2 Single Bed Room door size deduction Axis C-D, Axis 5-6

-1.00 1.5 2.1 -3.15 m2 ditto as above

-1.00 1.3 0.65 -0.845 m2 Single Bed Room Window size deduction Axis C-D, Axis 5-6
2
-46.42 m
546.98 m2 Total internal Painting Second floor

ROOF PAINTING
TIMES L W H Square UNIT DESCRIPTION
2
1 29.6 1.5 44.4 m Right elevation Axis A-D

1 46 1.5 69 m2 Front elevation Axis 1-6

1 30 1.5 45 m2 Left elevation Axis A-D

1 46 1.5 69 m2 Rear elevation Axis 1-6

1 8.4 3 25.2 m2 Axis B-C, Axis 3-4


1 10.4 3 31.2 m2 Axis C-D, Axis 3-5
283.8 m2

-2.00 0.95 2.1 -3.99 m2 Door size deduction


-3.99 m2

279.81 m2 Total Painting Roof

2334.63 m2 TOTAL PAINTING

Times L (m) W (m) H Square Unit 4.4 CEILING FINISH


Ceiling Cement-Sand Plastering Work Ground Floor
1 4.8 4.3 20.64 m2 Along Axis-1 and Axis-2 (A-B)

1 4.8 4.3 20.64 m2 Along Axis-1 and Axis-2 (B-C)

1 4.8 5.3 25.44 m2 Along Axis-1 and Axis-2 (C-D)

1 4.8 4.3 20.64 m2 Along Axis-2 and Axis-3 (A-B)

1 4.8 4.3 20.64 m2 Along Axis-2 and Axis-3 (B-C)

1 4.8 5.3 25.44 m2 Along Axis-2 and Axis-3 (C-D)

1 2.8 4.3 12.04 m2 Along Axis-3 and Axis-4 (B-C)

1 2.8 5.3 14.84 m2 Along Axis-3 and Axis-4 (C-D)

1 4.8 4.3 20.64 m2 Along Axis-4 and Axis-5 (B-C)

1 4.8 5.3 25.44 m2 Along Axis-4 and Axis-5 (C-D)

1 4.8 4.3 20.64 m2 Along Axis-5 and Axis-6 (B-C)


1 4.8 5.3 25.44 m2 Along Axis-5 and Axis-6 (C-D)

1 0.9 37.8 34.02 m2 35cm Beam Plastering

1 0.9 31.2 28.08 m2 35cm Beam Plastering

1 0.9 65.8 59.22 m2 35cm Beam Plastering

1 0.9 8.1 7.29 m2 35cm Beam Plastering


381.09 m 2
Total Cement Sand Plastering

Ceiling Gypsum Plastering Work Ground Floor


Times L (m) W (m) Square Unit Description
2
1 4.8 4.3 20.64 m Along Axis-1 and Axis-2 (A-B)

1 4.8 4.3 20.64 m2 Along Axis-1 and Axis-2 (B-C)

1 4.8 5.3 25.44 m2 Along Axis-1 and Axis-2 (C-D)

1 4.8 4.3 20.64 m2 Along Axis-2 and Axis-3 (A-B)

1 4.8 4.3 20.64 m2 Along Axis-2 and Axis-3 (B-C)

1 4.8 5.3 25.44 m2 Along Axis-2 and Axis-3 (C-D)

1 2.8 4.3 12.04 m2 Along Axis-3 and Axis-4 (B-C)

1 2.8 5.3 14.84 m2 Along Axis-3 and Axis-4 (C-D)

1 4.8 4.3 20.64 m2 Along Axis-4 and Axis-5 (B-C)

1 4.8 5.3 25.44 m2 Along Axis-4 and Axis-5 (C-D)


1 4.8 4.3 20.64 m2 Along Axis-5 and Axis-6 (B-C)

1 4.8 5.3 25.44 m2 Along Axis-5 and Axis-6 (C-D)

1 0.9 37.8 34.02 m2 35cm Beam Plastering

1 0.9 31.2 28.08 m2 35cm Beam Plastering

1 0.9 65.8 59.22 m2 35cm Beam Plastering

1 0.9 8.1 7.29 m2 35cm Beam Plastering


381.09 m 2
Total Gypsum Plastering

Ceiling Cement-Sand Plastering Work First Floor


Times L (m) W (m) Square Unit Description
2
1 4.8 4.3 20.64 m Along Axis-1 and Axis-2 (A-B)

1 4.8 4.3 20.64 m2 Along Axis-1 and Axis-2 (B-C)

1 4.8 5.3 25.44 m2 Along Axis-1 and Axis-2 (C-D)

1 4.8 4.3 20.64 m2 Along Axis-2 and Axis-3 (A-B)

1 4.8 4.3 20.64 m2 Along Axis-2 and Axis-3 (B-C)

1 4.8 5.3 25.44 m2 Along Axis-2 and Axis-3 (C-D)

1 2.8 4.3 12.04 m2 Along Axis-3 and Axis-4 (B-C)

1 2.8 5.3 14.84 m2 Along Axis-3 and Axis-4 (C-D)


1 4.8 4.3 20.64 m2 Along Axis-4 and Axis-5 (B-C)

1 4.8 5.3 25.44 m2 Along Axis-4 and Axis-5 (C-D)

1 4.8 4.3 20.64 m2 Along Axis-5 and Axis-6 (B-C)

1 4.8 5.3 25.44 m2 Along Axis-5 and Axis-6 (C-D)

1 0.9 37.8 34.02 m2 35cm Beam Plastering

1 0.9 31.2 28.08 m2 35cm Beam Plastering

1 0.9 65.8 59.22 m2 35cm Beam Plastering

1 0.9 8.1 7.29 m2 35cm Beam Plastering


381.09 m2
Total Cement Sand Plastering

Ceiling Gypsum Plastering Work First Floor


Times L (m) W (m) Square Unit Description
1 4.8 4.3 20.64 m2 Along Axis-1 and Axis-2 (A-B)

1 4.8 4.3 20.64 m2 Along Axis-1 and Axis-2 (B-C)

1 4.8 5.3 25.44 m2 Along Axis-1 and Axis-2 (C-D)

1 4.8 4.3 20.64 m2 Along Axis-2 and Axis-3 (A-B)

1 4.8 4.3 20.64 m2 Along Axis-2 and Axis-3 (B-C)

1 4.8 5.3 25.44 m2 Along Axis-2 and Axis-3 (C-D)

1 2.8 4.3 12.04 m2 Along Axis-3 and Axis-4 (B-C)


1 2.8 5.3 14.84 m2 Along Axis-3 and Axis-4 (C-D)

1 4.8 4.3 20.64 m2 Along Axis-4 and Axis-5 (B-C)

1 4.8 5.3 25.44 m2 Along Axis-4 and Axis-5 (C-D)

1 4.8 4.3 20.64 m2 Along Axis-5 and Axis-6 (B-C)

1 4.8 5.3 25.44 m2 Along Axis-5 and Axis-6 (C-D)

1 0.9 37.8 34.02 m2 35cm Beam Plastering

1 0.9 31.2 28.08 m2 35cm Beam Plastering

1 0.9 65.8 59.22 m2 35cm Beam Plastering

1 0.9 8.1 7.29 m2 35cm Beam Plastering


381.09 m2 Total Gypsum Plastering

Ceiling Cement-Sand Plastering Work Second Floor


Times L (m) W (m) Square Unit Description
2
1 4.8 4.3 20.64 m Along Axis-1 and Axis-2 (A-B)

1 4.8 4.3 20.64 m2 Along Axis-1 and Axis-2 (B-C)

1 4.8 5.3 25.44 m2 Along Axis-1 and Axis-2 (C-D)

1 4.8 4.3 20.64 m2 Along Axis-2 and Axis-3 (A-B)

1 4.8 4.3 20.64 m2 Along Axis-2 and Axis-3 (B-C)

1 4.8 5.3 25.44 m2 Along Axis-2 and Axis-3 (C-D)


1 2.8 4.3 12.04 m2 Along Axis-3 and Axis-4 (B-C)

1 2.8 5.3 14.84 m2 Along Axis-3 and Axis-4 (C-D)

1 4.8 4.3 20.64 m2 Along Axis-4 and Axis-5 (B-C)

1 4.8 5.3 25.44 m2 Along Axis-4 and Axis-5 (C-D)

1 4.8 4.3 20.64 m2 Along Axis-5 and Axis-6 (B-C)

1 4.8 5.3 25.44 m2 Along Axis-5 and Axis-6 (C-D)

1 0.9 37.8 34.02 m2 35cm Beam Plastering

1 0.9 31.2 28.08 m2 35cm Beam Plastering

1 0.9 65.8 59.22 m2 35cm Beam Plastering

1 0.9 8.1 7.29 m2 35cm Beam Plastering


381.09 m 2
Total Cement Sand Plastering

Ceiling Gypsum Plastering Work Second Floor


Times L (m) W (m) Square Unit Description
2
1 4.8 4.3 20.64 m Along Axis-1 and Axis-2 (A-B)

1 4.8 4.3 20.64 m2 Along Axis-1 and Axis-2 (B-C)

1 4.8 5.3 25.44 m2 Along Axis-1 and Axis-2 (C-D)

1 4.8 4.3 20.64 m2 Along Axis-2 and Axis-3 (A-B)

1 4.8 4.3 20.64 m2 Along Axis-2 and Axis-3 (B-C)


1 4.8 5.3 25.44 m2 Along Axis-2 and Axis-3 (C-D)

1 2.8 4.3 12.04 m2 Along Axis-3 and Axis-4 (B-C)

1 2.8 5.3 14.84 m2 Along Axis-3 and Axis-4 (C-D)

1 4.8 4.3 20.64 m2 Along Axis-4 and Axis-5 (B-C)

1 4.8 5.3 25.44 m2 Along Axis-4 and Axis-5 (C-D)

1 4.8 4.3 20.64 m2 Along Axis-5 and Axis-6 (B-C)

1 4.8 5.3 25.44 m2 Along Axis-5 and Axis-6 (C-D)

1 0.9 37.8 34.02 m2 35cm Beam Plastering

1 0.9 31.2 28.08 m2 35cm Beam Plastering

1 0.9 65.8 59.22 m2 35cm Beam Plastering

1 0.9 8.1 7.29 m2 35cm Beam Plastering


381.09 m 2
Total Gypsum Plastering

Ceiling Cement-Sand Plastering Work Roof


Times L (m) W (m) Square Unit Description
1 9.9 2.7 26.73 m 2
Total Cement Sand Plastering

Ceiling Gypsum Plastering Work Roof


Times L (m) W (m) Square Unit Description
1 9.9 2.7 26.73 m 2
Total Gypsum Plastering

1170 m2 TOTAL CEILING CEMENT-SAND PLASTERING


1170 m2 TOTAL CEILING GYPSUM PLASTERING

4.5 CERAMIC TILE FLOOR FINISH


Times L W H Square Unit CERAMIC FLOOR FINISH GROUND FLOOR
1 7.5 10.4 78 m2 Restaurant

1 1.45 1.54 2.233 m2 Cashier

1 2.8 8.1 22.68 m2 Kitchen (Non slippery)

1 4.05 2.8 11.34 m2 Store

2 1.15 2.8 6.44 m2 C.Room

1 2.15 3.85 8.2775 m2 Toilet (Non slippery)

1 2.7 4.3 11.61 m2 stair

1 2.7 5.8 15.66 m2 Entrance

1 7 3.5 24.5 m2 Mini Market

1 2.8 3.5 9.8 m2 Guard Room

1 7.85 1.65 12.9525 m2 Corridor

1 4.85 4.3 20.855 m2 WC (Non slippery)

1 2.4 4.45 10.68 m2 Office

1 2.3 4.45 10.235 m2 Store


245.263 m 2
Total Ceramic Floor Finish Ground Floor
CERAMIC FLOOR FINISH FIRST FLOOR
Times L W Square Unit Description
2 4.93 8.95 88.247 m2 Twin bed room

2 1.83 3 10.98 m2 WC (Non slippery)

1 8 4 32 m2 Twin bed room

1 1.86 4 7.44 m2 WC (Non slippery)

1 8.6 1.15 9.89 m2 Corridor

1 2.7 4.3 11.61 m2 stair

1 3.4 5.6 19.04 m2 Reception

1 8 1.25 10 m2 Corridor

1 7.3 4 29.2 m2 Twin bed room

1 1.85 4 7.4 m2 WC (Non slippery)

1 4.95 4.4 21.78 m2 Laundry (Non slippery)

1 4.85 4.5 21.825 m2 WC and Changing Room (Non slippery)


269.412 m 2
Total Ceramic Floor Finish First Floor

CERAMIC FLOOR FINISH SECOND FLOOR


Times L W Square Unit Description
2
1 9.9 4.3 42.57 m Suite living area, dining and kitchen
1 5.5 4.4 24.2 m2 suite Bed room

1 3.85 4.4 16.94 m2 suite WC (Non slippery)

1 8.6 1.4 12.04 m2 Corridor

1 4.8 3.4 16.32 m2 Single Bed room

1 1.8 2.9 5.22 m2 Single Bed room WC (Non slippery)

1 4.95 3.95 19.5525 m2 store

1 2.7 4.3 11.61 m2 stair

1 2.75 5.6 15.4 m2 Waiting area

2 2.9 4 23.2 m2 Single Bed room

4 1.8 2.8 20.16 m2 Single Bed room WC (Non slippery)

1 8.6 1.3 11.18 m2 Corridor

2 2.9 4.3 24.94 m2 Single Bed room


243.332 m 2
Total Ceramic Floor Finish Second Floor

CERAMIC FLOOR FINISH ROOF


Times L W Square Unit Description
2
1 9.9 14.5 143.55 m Terrace
143.55 m 2
Total Ceramic Floor Finish Second Floor

901.557 m2 TOTAL CERAMIC FLOOR FINISH TILE


141.733 m2 TOTAL CERAMIC FLOOR FINISH TILE (NON SLIPPERY)
759.825 m2 TOTAL CERAMIC FLOOR FINISH TILE SLIPPERY

TIMES L w H SQUARE UNIT 4.6 CERAMIC TILE WALL FINISH


CERAMIC WALL FINISH GROUND FLOOR
2
1 20 1.5 30 m Ceram Wall finish at Kitchen Ground Floor

1 16.15 1.5 24.225 m2 ditto as above but for Toilet on Ground Floor

2 17.31 1.5 51.93 m2 ditto as above but for WC (Male and Female) on Ground Floor
106.155 m 2
Total Ceramic Wall finish on Ground Floor

CERAMIC WALL FINISH FIRST FLOOR


2
2 9.66 3 57.96 m Ceram Wall finish at Twin Bed room WC First Floor

2 11.72 3 70.32 m2 ditto as above

1 5.13 3 15.39 m2 Ceram Wall finish at Laundry First Floor

2 11.88 3 71.28 m2 ditto as above but for WC (Male and Female)


2
214.95 m

-2.00 0.7 2.1 -2.94 m2 Door Size deduction at Twin Bed room WC First Floor

-2.00 0.65 1.8 -2.34 m2 Window Size deduction at Twin Bed room WC First Floor

-2.00 0.7 3 -4.2 m2 Door Size deduction at Twin Bed room WC First Floor

-2.00 0.65 1.8 -2.34 m2 Window Size deduction at Twin Bed room WC First Floor

-1.00 1.2 1.8 -2.16 m2 Window Size deduction at Laundry room First Floor

-1.00 0.65 1.8 -1.17 m2 ditto as above


-2.00 0.7 2.1 -2.94 m2 Door Size deduction at WC (Male and Female) First Floor

-2.00 0.65 1.8 -2.34 m2 Window Size deduction WC (Male and Female) First Floor

-2.00 0.7 3 -4.2 m2 Door Size deduction at WC (Male and Female) First Floor
2
-24.63 m
190.32 m2 Total Ceramic Wall finish on First Floor

CERAMIC WALL FINISH SECOND FLOOR


2
1 16.61 3 49.83 m Ceram Wall finish at Suite Room WC Second Floor

1 8.98 1.5 13.47 m2 ditto as above but for Kitchen

5 9.4 3 141 m2 ditto as above but for WC at single room


2
204.3 m

-1.00 0.65 1.8 -1.17 Window Size deduction at Suite room WC Second Floor

-5.00 0.65 1.8 -5.85 ditto as above but for single Bedroom WC

-1.00 0.7 3 -2.1 Door Size deduction at Suite room WC Second Floor

-5.00 0.7 1.5 -5.25 Ditto as above but for single Bedroom WC
2
-14.37 m
189.93 m2 Total Ceramic Wall finish on Second Floor

486.405 m2 TOTAL CERAMIC WALL TILE

Times L W H Square Unit SKIRTING


GROUND FLOOR SKIRTING (10 cm high)
1 13.7 13.7 m Store
1 22.4 22.4 m Kitchen

1 51.96 51.96 m Restaurant

1 5.9 5.9 m Cashier

1 16.2 16.2 m Changing Room

1 14.4 14.4 m Mini Market

1 12.6 12.6 m Guard Room

1 13.6 13.6 m Store

1 13.6 13.6 m Office


164.36 m

-1.00 0.9 -0.9 m Store Door size deduction

-1.00 0.8 -0.8 m ditto as above

-2.00 0.7 -1.4 m Restaurant Door size deduction

-1.00 0.8 -0.8 m ditto as above

-2.00 0.9 -1.8 m ditto as above

-1.00 1 -1 m ditto as above

-1.00 2 -2 m ditto as above

-1.00 0.9 -0.9 m Kitchen Door size deduction

-1.00 0.8 -0.8 m ditto as above


-2.00 0.7 -1.4 m Changing Room Door size deduction

-1.00 0.9 -0.9 m Mini Market Door size deduction

-1.00 0.9 -0.9 m Guard Room Door size deduction

-1.00 0.8 -0.8 m Store Door size deduction

-1.00 0.9 -0.9 m Office Door size deduction


-15.3 m
149.06 m Total Ground Floor Skirting

FIRST FLOOR SKIRTING (10 cm high)


Times L W H Square Unit Description
2 27.6 55.2 m Twin Bedroom

1 24 24 m ditto as above

1 22.5 22.5 m ditto as above

2 9.5 19 m Changing Room (Male and Female)

1 13.8 13.8 m Laundry


134.5 m

-4.00 0.7 -2.8 m Twin Bedrooms Door Size Deduction

-4.00 0.8 -3.2 m ditto as above

-2.00 0.7 -1.4 m Changing Room (Male and Female) Door size deduction

-2.00 0.8 -1.6 m ditto as above

-1.00 0.9 -0.9 m Laundry Door size deductions


-9.9 m
124.6 m Total First Floor Skirting

SECOND FLOOR SKIRTING (10 cm high)


Times L W H Square Unit Description
1 28.5 28.5 m Suite Room (Living,Dining and Kitchen)

1 20 20 m Suite Room (Bed room)

3 18.45 55.35 m Single Bed rooms

2 14 28 m ditto as above

1 17.75 17.75 m Store


149.6 m

-2.00 0.8 -1.6 m Suite Room (Living,Dining and Kitchen) Door size deduction

-1.00 0.8 -0.8 m Suite Room (Bed room) Door size deduction

-3.00 0.7 -2.1 m Single Bed rooms Door Size deductions

-3.00 0.8 -2.4 m ditto as above

-2.00 0.7 -1.4 m ditto as above

-2.00 0.8 -1.6 m ditto as above

-2.00 1.05 -2.1 m ditto as above

-1.00 0.9 -0.9 m Store door size deductions


-12.9 m
136.7 m Total Second Floor Skirting

ROOF SKIRTING (10 cm high)


1 11.2 11.2
1 2.7 2.7
13.9

-2.00 0.95 -1.9


12 m Total roof Skirting

422.36 m TOTAL SKIRTING

5 Metal Work
5.1Metal work for windows made of aluminium
Times L W H Square Unit A/ 60cm*60cm aluminium frame window on ground floor
13 0.6 1.5 11.7 m²
B/ Ditto but on first floor
7 0.6 1.5 6.3 m²
C/ Ditto but on second floor
10 0.6 0.6 3.6 m²
21.6 m²
D/ 110cm*150cm aluminium frame window on GF
1 1.1 1.5 1.65 m²
E/ 115cm*150cm aluminium frame window on FF
2 1.15 1.5 3.45 m²
F/ Ditto but on second floor
2 1.15 1.5 3.45 m²
6.9 m²
G/ 150cm*150cm aluminium window on FF
1 1.5 1.5 2.25 m²
H/ Ditto but on second floor
1 1.5 1.5 2.25 m²
4.5 m²
I/ 200cm*200cm aluminium frame window on GF,FF and SF
3 2 2 12 m²
J/ 120cm*150cm aluminium frame window on GF
2 1.2 1.5 3.6 m²
K/ 120cm*150cm aluminium frame window on FF
3 1.2 1.5 5.4 m²
L/120cm*150cm aluminium frame window on SF
5 1.2 1.5 9 m²
18
66.45 m² Total metal work for windows made of aluminium

5.2 Metal work for curtain wall made of aluminium


A/ 470cm*300cm aluminium frame curtain wall on GF
3 4.7 3 42.3 m²
B/ 185cm*300cm aluminium frame curtain wall on GF
1 1.85 3 5.55 m²
47.85 m² total metal work for curtain wall made of aluminium

Item Dimension Squar Unit Discription


Length Width Height

5.3 Steel Metal Work for Sliding Door


A/ 85cm*210cm sliding door on FF
1 0.85 2.1 1.785 m²
B/ 70cm*210cm sliding door on FF
1 0.7 2.1 1.47 m²
C/ 100cm*210cm sliding door on SF
2 1 2.1 4.2 m²
D/ 300cm*210cm sliding door on SF
1 3 2.1 6.3 m²
13.755 m² Total metal work for sliding door

5.4 Stair case Steel Metal Work


A/ Ground floor internal staircase handrail
2 3.25 6.5 m
B/ Ditto but on first floor
2 3.25 6.5 m
C/ Ditto but on second floor
2 3.25 6.5 m
19.5 m
D/ GF internal staircase balluster
64 0.9 57.6 m
E/ Ditto but on first floor
64 0.9 57.6 m
F/ Ditto but on second floor
64 0.9 57.6 m
172.8 m
G/ External( outer) staircase handrail
4 2.02 8.08 m
H/ External( outer) staircase balluster
80 0.9 72 m
80.08 m
264.3 m Total length of metal work for staircase

5.5 Balconys' Guadrail Steel Metal work


A/ Guardrail of Balcony1 on first floor front elevation
2 5.3 10.6 m

Item Dimension Squar Unit Discription


Length Width Height
B/ Ditto but Balcony2 on second floor front elevation
2 4.58 9.16 m
C/ Ditto but Balcony 3 on second floor right elevation
1 6.8 6.8 m
D/ Ditto but Balcony 4 on ground floor right elevation
1 5.5 5.5 m
21.46
E/ Balcony 1 Balluster
2 56 112 m
F/ Ditto but for balcony 2
2 44 88 m
G/ Ditto but for balcony 3
1 68 68 m
H/ Ditto but for balcony 4
1 58 58 m
326
347.46 m Total metal work for balcony

Times L(m) W(m) H(m) squaring unit


6. Carpentry and Joinery
6.1 Carpentry
6.1.1 kitchen cabinet
1 22.5 0.6 13.5 m2
6.1.2 closet
5 32.5 0.7 113.75 m2
127.25 m2 Total area of carpentry work.
6.2 Joinery
6.2.1 Doors
6.2.1.1 size 90x210cm
3 Pcs
6.2.1.2 size 70x210cm
17 Pcs
6.2.1.3 size 80x210cm
17 Pcs
37 Pcs Total number of doors

7. Glazing
7.1 2mm thick clear glass
a.same sized window found in the all building
6 10.73 17.02 1095.75 m2
b.same sized window found in the all building
7 4.73 17.02 563.532 m 2

c.same sized window found in the all building


2 5.73 19.73 226.106 m 2
d.same sized window found in the all building
2 19 20.23 768.74 m 2

e.same sized window found in the all building


2 13.42 30.23 811.373 m 2

f.same sized window found in the all building


8 11.05 30.87 2728.91 m 2

g.same sized window found in the all building


4 5.73 19.73 452.212 m 2

h.same sized window found in the all building


3 12.26 16.89 621.214 m 2

i.same sized window found in the all building


2 10.68 10.73 229.193 m 2

j.same sized window found in the all building


2 10 20.23 404.6 m 2

7901.63 m2 Total area of clear glass


7.2 2mm thick Blurred glass
a.
2 5.23 17.02 178.029 m2
b.
8 4.73 16.83 636.847 m 2

c.
5 4.63 17.02 394.013 m 2

1208.89 m2 Total area of blurred glass

8.Waterproof work
8.1 Water Proof for floor area
a. Toilet at Ground Floor
1 2.15 3.58 7.697 m2
b.Wc at ground floor
1 4.85 4.3 20.855 m 2

c. Wc 1st floor
2 1.83 3 10.98 m 2
d. Wc 1st floor
1 1.86 4 7.44 m 2

e.Wc 1st floor


1 1.85 4 7.4 m 2

f. Laundry at 1st Floor


1 4.95 4.4 21.78 m 2

g. suite Wc second Floor


1 3.85 4.4 16.94 m 2

h. single bedroom Wc 2nd Floor


1 1.8 2.9 5.22 m 2

i. single bed room Wc 2nd Floor


4 1.8 2.8 20.16 m 2

h.kitchen area at ground Floor


1 2.8 8.1 22.68 m 2

teracc
1 143.55 m 2

284.702 m2 Total area of water proof for floor area.


8.2 Water proof for wall

a. Kitchen wall water Proof


1 20 1.5 30 m 2

b.laundary
1 5.13 1.5 7.695 m2
c. Wc For Ground Floor
1 16.5 1.5 24.75 m 2

d. ditto wc For Ground Floor Wc Femeal And Men


2 17.31 1.5 51.93 m2
114.375 m2 Total Water Proof On Ground Floor
e. water proof at twin bed room wc 1st floor
2 9.66 1.5 28.9 m2
f. ditto as above
2 11.72 1.5 35.16 m2
g. ditto as above but wc for wc( male and femal)
11.88 1.5 17.82 m 2

81.88 m2
h.door size deduction at twin bed room Wc 1st floor
-2 0.7 2.1 -2.94 m 2

i. window size deduction at twin bed room Wc 1st floor


-2 0.65 1.8 -2.34 m 2

j. door size deduction at twin bed room wc 1st floor


-2 0.7 3 -4.2 m 2

-9.48 m2 total
72.4 m2 Total Water Proof On 1St Floor
k. water Proof Wc For Second Floor
1 16.61 1.5 24.915 m2
l. ditto As Above But For Kitchen
1 8.98 1.5 13.47 m2
m. ditto As Above But For Wc as Single Room
5 9.4 1.5 70.5 m 2

108.885 m2
n. window Size Deduction at Suite room Second Floor
-1 0.65 1.8 -1.17 m2
o. ditto as above but for single bedroom wc
-5 0.65 1.8 -5.85 m 2

p. Door Size Deduction at suite room wc ssecond floor


-1 0.7 3 -2.1 m2
q. ditto as above but for single bedroom wc
-5 0.7 1.5 -5.25 m 2

-14.37 m2
94.515 m2 Total water proof second floor
565.992 m2 Total area of water proof
Reinforcement Bar Schedule
SUB STRUCTURE Total Length of bar based on diameter(m)
Dia Total Length
No of Bar
No of Member
Total No o Dia Dia Dia Dia Dia Dia Dia Dia Dia Remark
Location Shape
(mm) (m) (pcs) (pcs) (m) 6 8 10 12 14 16 20 22 25
FOUNDATION
F1 Both Longtudinal and Transvers 16 2.4 8 2 38.4 38.4
F2 Both Longtudinal and Transvers 16 2.2 7 3 46.2 46.2
F3 Both Longtudinal and Transvers 16 1.9 5 2 19 19
F4 Both Longtudinal and Transvers 16 1.8 5 7 63 63
F5 Both Longtudinal and Transvers 16 1.7 4 7 47.6 47.6

Total Length of Bar(m) 214.2


Unit Weight (kg/m) 0.222 0.395 0.616 0.887 1.25 1.579 2.646 3.3 3.854
Total Weight(Kg) 338.222

Reinforcement Bar Schedule


SUB STRUCTURE Total Length of bar based on diameter(m)
Dia Total Length
No of Bar
No of Member
Total No o Dia Dia Dia Dia Dia Dia Dia Dia Dia Remark
Location Shape
(mm) (m) (pcs) (pcs) (m) 6 8 10 12 14 16 20 22 25
Foundation Column
Base to Ground Floor 14 4.44 8 17 603.84 603.84
Stirrup 10 1.2 15 17 255 255 255
CS-01

Base to Ground Floor 14 4.44 8 4 142.08 142.08


Stirrup 10 1.2 15 4 72 72 72
CS-02

Total Length of Bar(m) 327 1072.92


Unit Weight (kg/m) 0.222 0.395 0.616 0.887 1.25 1.579 2.646 3.3 3.854
Total Weight(Kg) 201.432 1341.15
Reinforcement Bar Schedule
SUB STRUCTURE Total Length of bar based on diameter(m)
Dia Total Length
No of Bar
No of Member
Total No o Dia Dia Dia Dia Dia Dia Dia Dia Dia Remark
Location Shape
(mm) (m) (pcs) (pcs) (m) 6 8 10 12 14 16 20 22 25
GRADE BEAM
Top Bar 1 12 5.02 2 1 10.04 10.04
Top Bar 2 12 8.33 2 1 16.66 16.66
Top Bar 3 12 3.85 2 1 7.7 7.7
Beam CB 1
Bottom Bar 1 16 5.61 2 1 11.22 11.22
Bottom Bar 2 16 5.61 2 1 11.22 11.22

Stirup 10 2.25 58 1 130.5 130.5


Top Bar 1 12 5.02 2 3 30.12 30.12
Top Bar 2 12 8.33 2 3 49.98 49.98
Top Bar 3 12 6.6 2 3 39.6 39.6
Top Bar 4 12 7.3 2 3 43.8 43.8
Top Bar 5 12 8.33 2 3 49.98 49.98
Top Bar 6 12 3.85 2 3 23.1 23.1
Beam CB 2
Bottom Bar 1 16 5.61 2 3 33.66 33.66
Bottom Bar 2 16 5.61 2 3 33.66 33.66
Bottom Bar 3 16 3.62 2 3 21.72 21.72
Bottom Bar 4 16 7.61 2 3 45.66 45.66
Bottom Bar 5 16 5.61 2 3 33.66 33.66

Stirrup 10 2.25 133 3 897.75 897.75


Top Bar 1 12 3.6 2 3 21.6 21.6
Top Bar 2 12 6.65 2 3 39.9 39.9
Top Bar 3 12 7.67 2 3 46.02 46.02
Top Bar 4 12 4.1 2 3 24.6 24.6
Beam CB 3
Bottom Bar 1 16 5.11 2 3 30.66 30.66
Bottom Bar 2 16 5.11 2 3 30.66 30.66
Bottom Bar 3 16 6.11 2 3 36.66 36.66

Stirrup 10 2.25 85 3 573.75 573.75


Top Bar 1 12 3.61 2 3 21.66 21.66
Top Bar 2 12 7.67 2 3 46.02 46.02
Top Bar 3 12 4.1 2 3 24.6 24.6
Beam CB4
Bottom Bar 1 16 5.11 2 3 30.66 30.66
Bottom Bar2 16 3.11 2 3 18.66 18.66

Sirrup 10 2.25 59 1 132.75 132.75

Total Length of Bar(m) 1734.75 539.18 338.1


Unit Weight (kg/m) 0.222 0.395 0.616 0.887 1.25 1.579 2.646 3.3 3.854
Total Weight(Kg) 1068.61 478.253 533.86
Reinforcement Bar Schedule
SUB STRUCTURE Total Length of bar based on diameter(m)
Dia Total Length
No of Bar
No of Member
Total No o Dia Dia Dia Dia Dia Dia Dia Dia Dia Remark
Location Shape
(mm) (m) (pcs) (pcs) (m) 6 8 10 12 14 16 20 22 25
Ground Slab

Longer 8 10.15 28 1 284.2 284.2


Panel 1 AxisA1,2,3 to Axis
Shorter
C1,2,3 8 9.15 31 1 283.65 283.65

Panel 2 AxisC1,2,3 to Axis D1,2,3


Longer 8 10.29 31 1 318.99 318.99
Shorter 8 5.66 17 1 96.22 96.22
Longer 8 13.18 39 1 514.02 514.02
anel 3 Axis B 3,4,5,6 to Axis
Shorter
D 3,4,5,6 8 9.96 30 1 298.8 298.8

Total Length of Bar(m) 1795.88


Unit Weight (kg/m) 0.222 0.395 0.616 0.887 1.25 1.579 2.646 3.3 3.854
Total Weight(Kg) 709.373

Reinforcement Bar Schedule


SUPER STRUCTURE Total Length of bar based on diameter(m)
Dia Total Length
No of Bar
No of Member
Total No o Dia Dia Dia Dia Dia Dia Dia Dia Dia Remark
Location Shape
(mm) (m) (pcs) (pcs) (m) 6 8 10 12 14 16 20 22 25
Column

Ground Floor to First Floor 14 4.24 8 17 576.64 576.64


First Floor to Second Floor 14 4.24 8 17 576.64 576.64
CS-01
Second Floor to Roof Slab 14 5.31 8 17 722.16 722.16
Stirrup 10 1.2 28 17 571.2 571.2

Ground Floor to First Floor 14 4.24 8 4 135.68 135.68


First Floor to Second Floor 14 4.24 8 4 135.68 135.68
Second Floor to Roof Slab 14 4.24 8 4 135.68 135.68
CS-02
Roof Slab to Tanker Slab 14 5.31 8 4 169.92 169.92
Stirrup 10 1.2 39 4 187.2 187.2 187.2

Total Length of Bar(m) 758.4 2452.4


Unit Weight (kg/m) 0.222 0.395 0.616 0.887 1.25 1.579 2.646 3.3 3.854
Total Weight(Kg) 467.174 3065.5
Reinforcement Bar Schedule
SUPER STRUCTURE Total Length of bar based on diameter(m)
Dia Total Length
No of Bar
No of Member
Total No o Dia Dia Dia Dia Dia Dia Dia Dia Dia Remark
Location Shape
(mm) (m) (pcs) (pcs) (m) 6 8 10 12 14 16 20 22 25
Beam
Top Bar 1 12 1.98 2 3 11.88 11.88
Top Bar 2 12 1.84 2 3 11.04 11.04
Top Bar 3 16 4.26 2 3 25.56 25.56
Top Bar 4 12 1.87 2 3 11.22 11.22
Beam CB01
Top Bar 5 12 1.98 2 3 11.88 11.88
Bottom Bar 1 12 5.63 2 3 33.78 33.78
Bottom Bar 2 12 5.63 2 3 33.78 33.78
Stirrup 10 2.25 30 3 202.5 202.5
Top Bar 1 12 2.13 2 6 25.56 25.56
Top Bar 2 22 7.13 2 6 85.56 85.56
Top Bar 3 16 4.77 2 6 57.24 57.24
Top Bar 4 14 4.1 2 6 49.2 49.2
Top Bar 5 22 7.44 2 6 89.28 89.28
Top Bar 6 12 1.88 2 6 22.56 22.56
Beam CB02
Bottom Bar 1 16 5.65 2 6 67.8 67.8
Bottom Bar 2 16 5.65 2 6 67.8 67.8
Bottom Bar 3 12 3.65 2 6 43.8 43.8
Bottom Bar 4 16 5.66 2 6 67.92 67.92
Bottom Bar 5 16 5.61 2 6 67.32 67.32
Stirrup 10 2.25 69 6 931.5 931.5
Top Bar 1 12 2.1 2 3 12.6 12.6
Top Bar 2 12 1.21 2 3 7.26 7.26
Top Bar 3 16 4.28 2 3 25.68 25.68
Top Bar 4 22 7.82 2 3 46.92 46.92
Beam CB03Top Bar 5 14 2.48 2 3 14.88 14.88
Bottom Bar 1 16 5.15 2 3 30.9 30.9
Bottom Bar 2 12 5.17 2 3 31.02 31.02
Bottom Bar 3 20 6.3 2 3 37.8 37.8
Stirrup 10 2.25 45 3 303.75 303.75
Top Bar 1 12 2.26 2 9 40.68 40.68
Top Bar 2 14 4.88 2 9 87.84 87.84
Top Bar 3 14 3.22 2 9 57.96 57.96
Top Bar 4 14 2.18 2 9 39.24 39.24
Top Bar 5 14 1.93 2 9 34.74 34.74
Beam CB04
Top Bar 6 12 2.29 2 9 41.22 41.22
Top Bar 7 14 2.21 2 9 39.78 39.78
Bottom Bar 1 14 5.14 2 9 92.52 92.52
Bottom Bar 2 20 6.3 2 9 113.4 113.4
Stirrup 10 2.25 31 9 627.75 627.75
Top Bar 1 12 2.53 2 9 45.54
Top Bar 2 25 5.2 2 9 93.6
Top Bar 3 16 3.9 2 9 70.2
Beam CB05
Bottom 1 16 5.19 2 9 93.42
Bottom 2 20 7.37 2 9 132.66
Stirrup 10 2.25 59 9 1194.75

Total Length of Bar(m) 2065.5 338.28 416.16 410.22 151.2 221.76


Unit Weight (kg/m) 0.222 0.395 0.616 0.887 1.25 1.579 2.646 3.3 3.854
Total Weight(Kg) 1272.35 300.054 520.2 647.737 400.075 731.808
Reinforcement Bar Schedule
SUPERSTRUCTURE Total Length of bar based on diameter(m)
Dia Total Length
No of Bar
No of Member
Total No o Dia Dia Dia Dia Dia Dia Dia Dia Dia Remark
Location Shape
(mm) (m) (pcs) (pcs) (m) 6 8 10 12 14 16 20 22 25
Top Tie Beam
Top Bar 1 12 2.96 2 2 11.84 11.84
Top Bar 2 12 2.46 2 2 9.84 9.84
Beam CB01
Bottom Bar 12 3.53 2 2 14.12 40.5
Stirrup 10 2.25 9 2 40.5 40.5
Top Bar 1 12 2.09 2 2 8.36 8.36
Top Bar 2 12 1.53 2 2 6.12 6.12
Beam CB02Top Bar 3 12 2.08 2 2 8.32 8.32
Bottom Bar 12 5.03 2 2 20.12 20.12
Stirrup 10 2.25 14 2 63 63

Total Length of Bar(m) 103.5 105.1


Unit Weight (kg/m) 0.222 0.395 0.616 0.887 1.25 1.579 2.646 3.3 3.854
Total Weight(Kg) 63.756 93.2237

Reinforcement Bar Schedule


Location Shape
SUPER STRUCTURE Total Length of bar based on diameter(m)
Stair Case Dia Total Length
No of Bar
No of Member
Total No o Dia Dia Dia Dia Dia Dia Dia Dia Dia Remark
(mm) (m) (pcs) (pcs) (m) 6 8 10 12 14 16 20 22 25

Main Bar 14 5.73 9 6 309.42 309.42


Negative Bar 14 4.6 9 6 248.4 248.4
Waist Slab Distribution Bar 14 3.68 23 6 507.84 507.84
Riser and Tread 14 0.49 10 6 29.4 29.4
Landing 10 1.95 16 3 93.6 93.6
Landing Mini Bar 12 0.198 2 3 1.188 1.188

Total Length of Bar(m) 93.6 1.188 1095.06


Unit Weight (kg/m) 0.222 0.395 0.616 0.887 1.25 1.579 2.646 3.3 3.854
Total Weight(Kg) 57.6576 1.05376 1368.83