Quezon Cash Req 70%
Quezon Cash Req 70%
MATERIALS:
CHB 6" 5,850.00 pc/s 17.50 /pc 102,375.00
LABOR:
CHB laying 450.00 sqm 140.00 /sqm 63,000.00
EQUIPMENT:
SUBTOTAL 165,375.00
MATERIALS:
LABOR:
Welding Works 1.00 set 55,000.00 /set 55,000.00
EQUIPMENT:
SUBTOTAL 55,000.00
MATERIALS:
Roofing Materials 1.00 set/s 110,000.00 /set 110,000.00
LABOR:
Installation 1.00 set/s 18,000.00 /set 18,000.00
EQUIPMENT:
SUBTOTAL 128,000.00
LABOR:
Painting Labor 1,738.00 sqm 130.00 /sqm 225,940.00
EQUIPMENT:
SUBTOTAL 225,940.00
MATERIALS:
LABOR:
Ceiling Labor 276.00 sqm 120.00 /sqm 33,120.00
EQUIPMENT:
SUBTOTAL 33,120.00
MATERIALS:
LABOR:
Plastering Labor 2,162.00 sqm 120.00 /sqm 259,440.00
EQUIPMENT:
SUBTOTAL 259,440.00
TOTAL 866,875.00
OCM 86,687.50
ADMIN 450,000.00
GRANDTOTAL 1,403,562.50