Download as pdf or txt
Download as pdf or txt
You are on page 1of 9

FISHERIES RESEARCH INSTITUTE, COA

Shipyard : PT UNITED SINDO PERKASA WEEKLY REPORT


Job Number : H80069-PR-00
Weather : Sunny, occasionally rain
Reporting Priod : 02nd July to 08th July 2023

ACTIVITIES
PIPING DEPARTMENT

PROGRESS
PROGRESS PIPING H80069-PR-00
FABRICATION INSTALLATION REINSTATEMENT TESTING & FINISHING
Physical Progress
Progress Realization (%) Progress Realization (%) Progress Realization (%) Progress Realization (%)
No. No. Drawing System Total Spool
45% 35% 10% FINAL INSPECTION 10% Total Project Project's
Fit Up Welding Fit Up Welding Fit Up Welding
Inspect. Inspect. Inspect. Hydrotest Finishing Project Realization Realization Last Month Progress This Week
45% 35% 10% 10%
42.91% 41.40% 1.50%
40% 50% 10% 40% 45% 15% 35% 50% 15% 80% 20%
1 P2 Tank Vent and Sounding 76 100% 100% 100% 97% 97% 97% 50% 50% 50% 97% 0% 93.8% 93.8% 0.0%
2 P3 Bilge and Ballast System 132 95% 83% 83% 83% 83% 0% 50% 50% 50% 83% 0% 85.1% 80.0% 5.1%
3 P4 Fireman And Deckwash System 29 72% 72% 72% 72% 72% 0% 50% 50% 50% 72% 0% 70.2% 70.2% 0.0%
4 P5 Fuel Oil System 196 89% 68% 68% 4% 1% 1% 0% 0% 0% 44% 0% 45.8% 43.5% 2.3%
5 P6 SW and FW Cooling System 100 93% 69% 69% 44% 44% 0% 0% 0% 0% 44% 0% 61.7% 61.7% 0.0%
6 P7 Domestic FW and SW System 40 100% 100% 100% 80% 80% 0% 50% 50% 50% 80% 0% 86.0% 86.0% 0.0%
7 P-044 External Deck Scupper Arg. 8 100% 100% 100% 0% 0% 0% 0% 0% 0% 0% 0% 45.0% 45.0% 0.0%
8 P8 Soil and Drain System 75 81% 3% 3% 3% 3% 0% 0% 0% 0% 0% 0% 37.5% 37.5% 0.0%
9 P9 Oily Bilge and Dirty Oil System 64 59% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 26.7% 11.6% 15.1%
10 P10 Engines Exhaust System 13 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0.0% 0.0% 0.0%
11 P12 Quick Closing Valve System 35 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0.0% 0.0% 0.0%
12 P0 Hydraulic System 25 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0.0% 0.0% 0.0%
13 P0 CO2 System 20 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0.0% 0.0% 0.0%
14 VSE/Q858-043 Compressed Air System 65 100% 100% 100% 91% 91% 0% 50% 50% 50% 100% 0% 91.8% 91.8% 0.0%
15 VSE/Q858-030 Lubricating Oil System 20 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0.0% 0.0% 0.0%
898 59% 46% 46% 32% 31% 7% 17% 17% 17% 35% 0%

Resume
Physical Progress :
Progress Present Month = 42,91 %
Progress Previous Month = 41,40 %
Progress This Month = 1,50 % (1st Week on July)

PT United Sindo Perkasa


Jalan Raya Pelabuhan Lama Kabil, Kecamatan Nongsa, Kota Batam – 29467, Kepulauan Riau – Indonesia
+62 778 711750-711753 www.vallianzholdings.com

Co Reg No: 8120013233911


Daily Manpower and Man Hours
DAILY MANPOWER AND MAN HOURS ACTUAL (H80069-PR-00)
Month JUNE (2023) JULY(2023)
Week Week 22 Week 23 Week 24 Week 25 Week 26 Week 27
Day/Date 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8
Fabrication
SPV
Foreman/Asst. 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
M Fitter 9 9 9 9 9 9 3 3 3 3 3 4 4 4 4 4 4 2 3 6 5 5 5 5 5 4 4 4 4 3 4 4 4 4 4 3
A Helper 12 12 12 12 12 8 4 4 4 4 4 5 5 5 5 5 5 2 6 7 7 7 7 7 6 6 6 6 6 4 6 6 6 6 7 6
N Welder/Grinder 4 4 4 4 4 8 3 3 3 3 3 4 4 4 4 4 4 2 4 4 6 5 5 5 3 3 3 3 3 3 3 3 4 3 4 2
P Installation and Testing
A O SPV
W Foreman/Asst. 1 1 1 1 1 1 1 1 1 1 1 2 2 2 2 2 1 2 2 2 2 2 1 1 1 1 1 1 1
C Fitter 9 9 9 9 9 5 6 6 6 6 6 9 9 9 9 7 8 8 7 7 7 7 7 7 7 7 8 9 8 9 9 8 8 8
E
T R Helper 10 10 12 12 12 4 6 7 7 5 5 10 10 10 10 6 13 13 12 13 8 6 6 6 7 7 7 7 9 11 10 8 10 10
Welder/Grinder 3 3 4 4 4 3 3 3 3 3 3 1 2 3 4 2 2 2 3 4 2 2 2 2 2 2 2 2 2 2 2 2 2 2
U 49 49 52 52 52 39 27 28 28 26 26 14 14 36 37 38 39 24 38 43 43 44 37 35 31 29 31 31 0 32 29 0 33 36 36 33 37 33
Total Manpower
A 308 252 204 264 183 208

L Man Hours (Basic) Mon-Fri (7 Hours) 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7


M
Man Hours (Basic) Saturday (5 Hours) 5 5 5 5 5 5
A
N Man Hours (OT) Mon-Fri (15.00 - 17.00) 3.5 3.5 3.5 3.5 3.5 3.5 3.5 3.5 3.5 3.5 3.5 3.5 3.5 3.5 3.5 3.5 3.5 3.5 3.5 3.5 3.5 3.5 3.5 3.5 3.5 3.5 3.5
H
Man Hours (OT) Saturday (13.00 - 15.00) 3.5 3.5 3.5 3.5 3.5 3.5
O
U Man Hours (OT) Sunday (07.00 - 15.00) 14 14 14 14 14
R
514.5 514.5 442 728 546 409.5 283.5 294 294 221 364 147 147 378 388.5 399 331.5 336 399 451.5 451.5 462 388.5 297.5 434 304.5 325.5 325.5 0 336 246.5 0 346.5 378 378 346.5 388.5 280.5
S
Total Man Hours
3242 2776 2155 2786 1972 2118

Total accumulation Manpower on this week (02nd July to 08th July 2023) is 208 and total accumulation Man Hours on 02nd July to 08th
July 2023 is 2118 hours.

Calculated Working Spool


1. Air Vent and Sounding System

DAILY WORKING SPOOL ACTUAL (H80069-PR-00)


Month FEBRUARY (2023) MARCH (2023) APRIL (2023) MAY (2023)
Week Week 8 Week 9 Week 10 Week 11 Week 12 Week 13 Week 14 Week 15 Week 16 Week 17 Week 18 Week 19 Week 20 Week 21 Week 22 Total Spool

Day/Date 19 20 21 22 23 24 25 26 27 28 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
A Fabrication
C Fit up 12 13 10 9 2 8 76
Welding 12 16 4 8 10 4 76
T S Inspection (Fit up) 12 13 10 9 8 76
U P
Inspection (Visual/Welding) 20 14 11 76
O
A O Installation and Testing

L L Fit up 14 5 5 2 6 12 8 2 74
Welding 2 1 2 2 3 1 2 1 2 2 1 74
Inspection (Fit up) 16 3 7 6 74
Inspection (Welding) 19 74

Calculated Working Spool Air Vent and Sounding System :


Fabrication
• Fit up : 76 Spool
• Welding : 76 Spool
• Inspection (Fit up) : 76 Spool
• Inspection (Visual/Welding) : 76 Spool
Installation
• Fit up : 74 Spool
• Welding : 74 Spool
• Inspection (Fit up) : 74 Spool
• Inspection (Visual/Welding) : 74 Spool
Total Spool Air Vent and Sounding System is 76 Spool (By Spool Drawing)

PT United Sindo Perkasa


Jalan Raya Pelabuhan Lama Kabil, Kecamatan Nongsa, Kota Batam – 29467, Kepulauan Riau – Indonesia
+62 778 711750-711753 www.vallianzholdings.com

Co Reg No: 8120013233911


2.Bilge System
DAILY WORKING SPOOL ACTUAL (H80069-PR-00)
Month JUNE (2023) JULY(2023)
Week Week 22 Week 23 Week 24 Week 25 Week 26 Week 27 Week 28 Week 29 Week 30 Total Spool
Day/Date
A 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30
Fabrication
C Fit up 3 2 7 2 1 126

T S Welding 3 2 2 1 110
Inspection (Fit up) 3 2 7 2 126
U P
Inspection (Visual/Welding) 5 2 1 110
O
A O
Installation and Testing
Fit up 105
L L
Welding 105
Inspection (Fit up) 23
Testing (Line Check) 0

Calculated Working Bilge System :


Fabrication
• Fit up : 126 Spool
• Welding : 110 Spool
• Inspection (Fit up) : 126 Spool
• Inspection (Visual/Welding) : 110 Spool
Installation
• Fit up : 105 Spool
• Welding : 105 Spool
• Inspection (Fit up) : 23 Spool
• Testing (Line Check) : 00 Spool

Total Spool Bilge and Ballast System is 132 Spool (By Spool Drawing)
3.Firemain and Deckwash System
DAILY WORKING SPOOL ACTUAL (H80069-PR-00)
Month MARCH (2023) APRIL (2023) JUNE (2023)
Week Week 11 Week 12 Week 13 Week 14 Week 15 Week 16 Week 17 Week 22 Week 23 Week 24 Week 25 Week 26 Total Spool
Day/Date 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
A Fabrication
C Fit up 6 6 4 4 1 21
Welding
T S
Inspection (Fit up) 16 5
4 4 5 4 4 21
21
P
U Inspection (Visual/Welding) 16 5 21
O
A O
Installation and Testing
Fit up 6 4 4 4 1 2 21
L L
Welding 16 3 2 21
Inspection (Fit up) 19 2 21
Testing (Line Check) 0
Calculated Working Firemain and Deckwash System :
Fabrication
• Fit up : 21 Spool
• Welding : 21 Spool
• Inspection (Fit up) : 21 Spool
• Inspection (Visual/Welding) : 21 Spool
Installation
• Fit up : 21 Spool
• Welding : 21 Spool
• Inspection (Fit up) : 21 Spool
• Testing (Line Check) : 00 Spool

Total Spool Firemain and Deckwash System is 29 Spool (By Spool Drawing)

PT United Sindo Perkasa


Jalan Raya Pelabuhan Lama Kabil, Kecamatan Nongsa, Kota Batam – 29467, Kepulauan Riau – Indonesia
+62 778 711750-711753 www.vallianzholdings.com

Co Reg No: 8120013233911


4.Cooling System
DAILY WORKING SPOOL ACTUAL (H80069-PR-00)
Month MAY(2023) JUNE(2023) JULY(2023)
Week Week 18 Week 19 Week 20 Week 21 Week 22 Week 23 Week 24 Week 25 Week 26 Week 27 Total Spool
Day/Date
A 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 31 4 5 6 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8
Fabrication
C Fit up 7 6 6 8 6 4 4 6 6 4 4 4 4 4 2 93

T S
Welding 7 6 6 6 4 6 6 3 6 4 6 2 1 69
Inspection (Fit up) 29 28 18 93
U P
Inspection (Visual/Welding) 14 31 5 10 9 69
O
A O
Installation and Testing
Fit up 7 2 6 7 6 8 8 44
L L
Welding 7 2 6 7 6 8 8 44
Inspection (Fit up) 3 6 4 6 6 8 4 2 2 3 44
Testing (Line Check) 0

Calculated Working Cooling System :


Fabrication
• Fit up : 93 Spool
• Welding : 69 Spool
• Inspection (Fit up) : 93 Spool
• Inspection (Visual/Welding) : 69 Spool
Installation
• Fit up : 44 Spool
• Welding : 44 Spool
• Inspection (Fit up) : 06 Spool
• Testing (Line Check) : 00 Spool

Total Spool Cooling System is 93 Spool (By Spool Drawing)

5.Domestic Fresh Water and Sea Water System


DAILY WORKING SPOOL ACTUAL (H80069-PR-00)
Month MARCH (2023) APRIL (2023)
Week Week 9 Week 10 Week 11 Week 12 Week 13 Week 14 Week 15 Week 16 Week 17 Total Spool
Day/Date
A 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30
Fabrication
C Fit up 6 5 8 6 7 4 4 40

T S
Welding 8 12 16 4 40
Inspection (Fit up) 40 40
U P
Inspection (Visual/Welding) 40 40
O
A O
Installation and Testing
Fit up 12 20 8 40
L L
Welding 0
Inspection (Fit up) 0
Inspection (Welding) 0

Calculated Working Fresh Water and Sea Water System :


Fabrication
• Fit up : 40 Spool
• Welding : 40 Spool
• Inspection (Fit up) : 40 Spool
• Inspection (Visual/Welding) : 40 Spool
Installation
• Fit up : 40 Spool
• Welding : 40 Spool
• Inspection (Fit up) : 00 Spool
• Testing (Line Check) : 00 Spool
*Note : Routing line spool on board vessel.

Total Spool Fresh Water and Sea Water System is 40 Spool (Routing Spool Line on Board Vessel)

PT United Sindo Perkasa


Jalan Raya Pelabuhan Lama Kabil, Kecamatan Nongsa, Kota Batam – 29467, Kepulauan Riau – Indonesia
+62 778 711750-711753 www.vallianzholdings.com

Co Reg No: 8120013233911


6. External Deck Scupper System
DAILY WORKING SPOOL ACTUAL (H80069-PR-00)
Month MAY(2023) JUNE(2023)
Week Week 18 Week 19 Week 20 Week 21 Week 22 Week 23 Week 24 Week 25 Week 26 Total Spool
Day/Date 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
A Fabrication
C Fit up 4 3 1 8
Welding
T S
Inspection (Fit up) 7
3 4 7
7
P
U Inspection (Visual/Welding) 7 7
O
A O
Installation and Testing
Fit up 0
L L
Welding 0
Inspection (Fit up) 0
Inspection (Welding) 0

Calculated Working External Deck Scupper System :


Fabrication
• Fit up : 08 Spool
• Welding : 08 Spool
• Inspection (Fit up) : 08 Spool
• Inspection (Visual/Welding) : 08 Spool
Installation
• Fit up : 00 Spool
• Welding : 00 Spool
• Inspection (Fit up) : 00 Spool
• Inspection (Visual/Welding) : 00 Spool

Total Spool External Deck Scupper System is 08 Spool (By Spool Drawing)

7. Fuel Oil System


DAILY WORKING SPOOL ACTUAL (H80069-PR-00)
Month MAY(2023) JUNE(2023) JULY(2023)
Week Week 20 Week 21 Week 22 Week 23 Week 24 Week 25 Week 26 Week 27 Week 28 Total Spool
Day/Date
A 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
Fabrication
C Fit up 7 8 6 8 8 8 8 8 9 9 9 8 8 8 8 8 8 8 7 6 6 6 4 2 175

T S
Welding 6 8 8 8 5 5 7 8 6 6 8 6 4 6 4 3 4 6 6 6 7 1 2 2 2 134
Inspection (Fit up) 30 32 29 20 35 27 2 175
U P
Inspection (Visual/Welding) 24 26 18 22 32 6 134
O
A O
Installation and Testing
Fit up 0
L L
Welding 0
Inspection (Fit up) 0
Inspection (Welding) 0

Calculated Working Fuel Oil System :


Fabrication
• Fit up : 175 Spool
• Welding : 134 Spool
• Inspection (Fit up) : 175 Spool
• Inspection (Visual/Welding) : 134 Spool
Installation
• Fit up : 00 Spool
• Welding : 00 Spool
• Inspection (Fit up) : 00 Spool
• Testing (Line Check) : 00 Spool

Total Spool Fuel Oil System is 196 Spool (By Spool Drawing)

PT United Sindo Perkasa


Jalan Raya Pelabuhan Lama Kabil, Kecamatan Nongsa, Kota Batam – 29467, Kepulauan Riau – Indonesia
+62 778 711750-711753 www.vallianzholdings.com

Co Reg No: 8120013233911


8. Soil and Drain System
DAILY WORKING SPOOL ACTUAL (H80069-PR-00)
Month MAY(2023) JUNE(2023)
Week Week 18 Week 19 Week 20 Week 21 Week 22 Week 23 Week 24 Week 25 Week 26 Total Spool
Day/Date 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
A Fabrication
C Fit up 3 2 3 3 6 5 6 7 7 7 6 6 61
Welding
T S
Inspection (Fit up) 13 21 27
0
61
P
U Inspection (Visual/Welding) 0
O
A O
Installation and Testing
Fit up 0
L L
Welding 0
Inspection (Fit up) 0
Inspection (Welding) 0

Calculated Working Soil and Drain System :


Fabrication
• Fit up : 61 Spool
• Welding : 00 Spool
• Inspection (Fit up) : 61 Spool
• Inspection (Visual/Welding) : 00 Spool
Installation
• Fit up : 00 Spool
• Welding : 00 Spool
• Inspection (Fit up) : 00 Spool
• Testing (Line Check) : 00 Spool

Total Spool Soil and Drain System is 75 Spool (By Spool Drawing)

9. Compressed Air Piping System


DAILY WORKING SPOOL ACTUAL (H80069-PR-00)
Month MARCH (2023) APRIL (2023) MAY (2023)
Week Week 12 Week 13 Week 14 Week 15 Week 16 Week 17 Week 18 Week 19 Week 20 Total Spool
Day/Date 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
A Fabrication
C Fit up 6 5 6 6 6 4 4 6 6 6 6 2 2 65
Welding
T S
Inspection (Fit up)
8 12 16 4
40
12 13
25
65
65
P
U Inspection (Visual/Welding) 40 25 65
O
A O
Installation and Testing
Fit up 12 20 8 40
L L
Welding 12 20 8 40
Inspection (Fit up) 0
Testing (Line Check) 0

Calculated Working Compressed Air Piping System :


Fabrication
• Fit up : 65 Spool
• Welding : 65 Spool
• Inspection (Fit up) : 65 Spool
• Inspection (Visual/Welding) : 65 Spool
Installation
• Fit up : 40 Spool
• Welding : 40 Spool
• Inspection (Fit up) : 00 Spool
• Testing (Line Check) : 00 Spool

Total Spool Compressed Air Piping System is 65 Spool (Routing Spool Line on Board Vessel)

PT United Sindo Perkasa


Jalan Raya Pelabuhan Lama Kabil, Kecamatan Nongsa, Kota Batam – 29467, Kepulauan Riau – Indonesia
+62 778 711750-711753 www.vallianzholdings.com

Co Reg No: 8120013233911


10. Oily Water System (OWS)
DAILY WORKING SPOOL ACTUAL (H80069-PR-00)
Month JUNE(2023) JULY(2023)
Week Week 22 Week 23 Week 24 Week 25 Week 26 Week 27 Week 28 Week 29 Week 30 Total Spool

Day/Date 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30

A Fabrication
Fit up
C 6 6 6 2 6 6 6 38

Welding 0
T S Inspection (Fit up) 18 20 38
U P
Inspection (Visual/Welding) 0
O
A O Installation and Testing
L L Fit up 0

Welding 0

Inspection (Fit up) 0

Testing (Line Check) 0

Calculated Working Oily Water System :


Fabrication
• Fit up : 38 Spool
• Welding : 00 Spool
• Inspection (Fit up) : 38 Spool
• Inspection (Visual/Welding) : 00 Spool
Installation
• Fit up : 00 Spool
• Welding : 00 Spool
• Inspection (Fit up) : 00 Spool
• Testing (Line Check) : 00 Spool

Total Spool Oily Water System is 65 Spool (By Spool Drawing)

Daily Activity Work Report


Air Vent and Sounding System
Actual Date Remarks/Job Description Foto
• Welding Fabrication Spool Pipe F.O System at
02nd Workshop Area.
July 2023 • Installation Spool Line Cooling System on Board
Vessel.
• Installation Welding Penetration Overboard at
Sonar Room,Bow Thruster and Bosun Store

• Fit up inspection of Fabrication Spool Pipe Cooling


03rd System at Workshop Area (18 Spool)
July 2023 BMD P6 003-06-14/BMD P6 004-07-15/BMD P6
005-08-17/BMD P6 005-08-18/BMD P6 005-09-20
BMD P6 010-15-37/BMD P6 011-16-39/BMD P6
012-17-41/BMD P6 013-18-42/BMD P6 014-19-43
BMD P6 014-19-45/BMD P6 015-20-48/BMD P6
015-21-46/BMD P6 015-21-47/BMD P6 016-22-
50/BMD P6 016-22-51/BMD P6 016-22-52/BMD P6
027-42-94
• Welding Fabrication Spool Pipe F.O System at
Workshop Area.
• Installation Spool Line Cooling System on Board
Vessel.

PT United Sindo Perkasa


Jalan Raya Pelabuhan Lama Kabil, Kecamatan Nongsa, Kota Batam – 29467, Kepulauan Riau – Indonesia
+62 778 711750-711753 www.vallianzholdings.com

Co Reg No: 8120013233911


O4th • Fit up Inspection of Installation Spool Pipe Bilge System
July 2023 at F.O Tank (S)
BMD P3 017-27-65
• Installation Spool Line Cooling System on Board
Vessel.
• Try Fit up Installation Spool Pipe Soil and Drain
System on Board Vessel.
• Fit up Fabrication Spool Pipe Oily Water System
at Workshop Area.

05th • Fit up inspection of Fabrication Spool Pipe Bilge


July 2023 System at Workshop Area (02 Spool)
BMD P3 027-42-107/BMD P3 028-43-110
• Visual Inspection of Installation Spool Pipe Bilge System
at F.O Tank (S)
BMD P3 017-27-65
• Fit up inspection of Fabrication Oily Water System
at Workshop Area (22 Spool)
BMD P9 004-07-22/BMD P9 004-07-23 BMD P9 005-
08-25/BMD P9 005-08-26/BMD P9 005-08-27/BMD
P9 006-09-29/BMD P9 007-10-32/BMD P9 009-13-
43/BMD P9 009-14-44/ BMD P9 009-14-45/BMD P9
009-14-46/BMD P9 009-15-47/BMD P9 009-15-48
BMD P9 009-15-49/BMD P9 010-16-51/BMD P9
010-16-53/BMD P9 010-16-54/BMD P9 010-17-55
BMD P9 010-17-56/BMD P9 010-17-57/BMD P9
010-17-58/BMD P9 010-18-59
• Installation Spool Line Cooling System on Board
Vessel.
• Try Fit up Installation Spool Pipe Soil and Drain
System on Board Vessel.
• Fit up Fabrication Spool Pipe Oily Water System
at Workshop Area.
• Visual Inspection of Installation Penetration MGPS
and Blowdown (P/S)

• Fabrication Welding Spool Pipe F.O System at


06th Workshop Area
July 2023 • Installation Spool Line Cooling System on Board
Vessel.
• Try Fit up Installation Spool Pipe Soil and Drain
System on Board Vessel.
• Fit up Fabrication Spool Pipe Oily Water System
at Workshop Area.

07th • Hydrotest Inspection of Fabrication Fuel Oil System at


July 2023 Workshop Area BMD (38 Spool) – 3,5 Bar
BMD P5 003-10-15/BMD P5 003-09-16/BMD P5
003-08-17/BMD P5 003-06-18/BMD P5 003-06-19
BMD P5 005-13-28/BMD P5 005-14-29/BMD P5
005-14-31/BMD P5 005-15-32/BMD P5 006-17-39
BMD P5 008-21-51/BMD P5 009-25-65/BMD P5
009-26-68/BMD P5 011-30-80/BMD P5 012-32-87
BMD P5 012-32-88/BMD P5 014-35-98/BMD P5
017-41-111/BMD P5 018-43-117/BMD P5 018-43-
118/BMD P5 020-50-133/BMD P5 020-50-134/
BMD P5 023-53-143/BMD P5 023-53-144/BMD P5
024-55-150/BMD P5 025-56-155/BMD P5 025-56-
156/BMD P5 025-56-157/BMD P5 026-57-160/
PT United Sindo Perkasa
Jalan Raya Pelabuhan Lama Kabil, Kecamatan Nongsa, Kota Batam – 29467, Kepulauan Riau – Indonesia
+62 778 711750-711753 www.vallianzholdings.com

Co Reg No: 8120013233911


BMD P5 026-57-161/BMD P5 026-58-163/BMD P5
026-58-164/BMD P5 027-59-168/BMD P5 027-59-
169/BMD P5 031-63-177/BMD P5 031-63-178/
BMD P5 031-64-179/BMD P5 032-65-182
AMD (2 Spool) – 3,5 Bar
AMD P5 001-01-01 / AMD P5 001-02-03
• Fabrication Welding Spool Pipe F.O System at
Workshop Area
• Installation Spool Line Cooling System on Board
Vessel.
• Try Fit up Installation Spool Pipe Soil and Drain
System on Board Vessel.
Fit up Fabrication Spool Pipe Oily Water System
at Workshop Area.

08th • Fit up Inspection of Fabrication Spool Bilge System


July 2023 at Workshop Area (1 Spool)
BMD P3 023-38-97
• Visual Inspection Marking Location Hole Exhaust at
Engine Casing
AMD 001-250-EES/AMD 002-250-EES/AMD 003-
150-EES/AMD 004-150-EES

Weekly Achievement & Next Week Activity

Fit up and Welding Fabrication Spool System


• Fit up Fabrication Spool Pipe Soil and Drain System.
• Fit up Fabrication Spool Pipe Oily Water System.
• Fit up Fabrication Spool Pipe Exhaust System.
• Welding Fabrication Spool Fuel Oil System.

Fit up and Welding Installation Spool System


• Fit up and Welding Installation Overboard Penetration on board vessel.
• Fit up Installation Spool Pipe Bilge System on board vessel
• Fit up Installation Spool Pipe Fresh Water System on board vessel.
• Fit up and Welding Installation Spool Pipe Drain Scupper on board vessel.
• Fit up Installation Spool Pipe Cooling System on board vessel.
• Fit up Installation Spool Pipe Air Compressed Piping System on board vessel.
• Hydrotest Overboard Penetration at Sonar Room, Bowthruster Room and Bosun Store.

Risk/Delay

• There are material not available at main store.

PT United Sindo Perkasa


Jalan Raya Pelabuhan Lama Kabil, Kecamatan Nongsa, Kota Batam – 29467, Kepulauan Riau – Indonesia
+62 778 711750-711753 www.vallianzholdings.com

Co Reg No: 8120013233911

You might also like