KAK AYT REC CMS 0003 Installation Work Rev.A00
KAK AYT REC CMS 0003 Installation Work Rev.A00
Rev No :
KAK-AYT-REC-CMS-0003
A00
FOR Date : 27-June-2021
INSTALLATION OF PRE-CAST
Page No : 1 of 7
FOUNDATIONS
Contract No : C&F-45204
INSTALLATION OF PRE-CAST
Page No : 2 of 7
FOUNDATIONS
TABLE OF CONTENTS:
1.0 SCOPE ...................................................................................................................... 03
3.0 REFERENCES.............................................................................................................. 03
INSTALLATION OF PRE-CAST
Page No : 3 of 7
FOUNDATIONS
1. SCOPE
The work covered by this method statement covers delivery, lifting, unloading and installation of
pre-casted foundations required on site.
2. WORK EXTENT
2.1 Installation of Pre-Cast Foundation for Sleepers, Analyzers and Cross Over Support Foundation.
3. REFERENCES
ASTM D6938 - Standard Test Methods for Density of Soil and Soil-Aggregate in-place by
Nuclear Method
ASTM C136-14 - Standard Test Method for Sieve Analysis of Fine and Coarse Aggregates.
ASTM D4318 - Standard Test Methods for Liquid Limit, Plastic Limit and Plasticity Index
of soils
OSHA 29 - OSHA Safety and Health Regulations for Construction
4. WORK EQUIPMENT
5. WORK MATERIALS
INSTALLATION OF PRE-CAST
Page No : 4 of 7
FOUNDATIONS
INSTALLATION OF PRE-CAST
Page No : 5 of 7
FOUNDATIONS
INSTALLATION OF PRE-CAST
Page No : 6 of 7
FOUNDATIONS
7. WORK PROCEDURE
Prior for any lifting activities, all lifting certificates and vehicle entry permits should be made
ready on the site. All lifting equipments such as cranes, boom trucks, are all inspected with
stickers required.
Equipment operators shall have certification and ID for plant access to perform work.
Site shall be barricaded and safety signage to be posted for intended lifting activity.
The lifting radius of cranes shall be barricaded to avoid other persons entering the site
during activity execution.
The site shall be made ready to receive and to be installed. Soil sub-grade compaction
preparation shall be made available before the work.
Lifting operation shall be postponed during high winds and unfavorable weather conditions.
INSTALLATION OF PRE-CAST
Page No : 7 of 7
FOUNDATIONS
8. SAFETY PRECAUTIONS
8.1 Permit to work shall be secured prior to starting any site activity.
8.2 All workers shall comply with the requirements of the approved project safety manual, job
safety analysis and permit conditions.
8.3 All workers shall wear required PPE’s at all times while engaged on the work.
8.4 Hand tools shall be in good working conditions.
8.5 All mechanical/electrical tools used are in good conditions and inspected by SAFETY or
Competent Personnel’s.
8.6 Cranes and boom truck third party certification shall be available with equipments.
8.7 Riggers, flagman and safety officers shall be vigilant to ensure that all lifting activity is performed
in safe manner not to damage any other facilities and plant equipments.
8.8 Crane, boom truck outrigger positions should be provided with wooden or steel pads to avoid
punching through ground, pavements or road.
8.9 Barricades shall be provided with the lifting radius and no personnel will walk or stay below
lifted load or crane boom.
8.10 All lifting accessories such as shackles, slings, chains and lifting beam when used are in good
working condition and inspected by third party.
8.11 Ensure all lifting and rigging activities postponed during presence of heavy winds and
unfavorable weather conditions.