Professional Documents
Culture Documents
K3 Konstruksi - BIM-integrated Management of Occupational Hazards in Building Construction and Maintenance
K3 Konstruksi - BIM-integrated Management of Occupational Hazards in Building Construction and Maintenance
K3 Konstruksi - BIM-integrated Management of Occupational Hazards in Building Construction and Maintenance
Automation in Construction
journal homepage: www.elsevier.com/locate/autcon
a
Department of Construction, School of Technology, University of Extremadura, Avda. de la Universidad s/n, Cáceres, Spain
b
Department of Education, Area of Knowledge in Electronic Technology, University Isabel I, Spain
Keywords: Health and safety in the construction sector are very important issues owing to the high accident rate in the
Building information modelling industry. Recent studies have shown that implementing the building information modelling (BIM) methodology
Health and safety can improve the working conditions at construction sites and during building maintenance. Therefore, the
Occupational risk assessment European Union is promoting the development of projects through BIM. The government of Spain has estab-
lished a roadmap to enforce the development of projects with BIM, and the integration of occupational health
and safety in projects developed with BIM in Spain must comply with the current regulations. This study pro-
poses a methodology—consistent with the requirements stipulated by the Spanish health and safety reg-
ulations—for its integration in the design phase of building projects developed using BIM.
1.1. Accidents and their causes in the construction sector Digital technologies have been entering the construction industry
for several decades. However, their application in occupational health
The rate of work accidents in the construction sector worldwide is and safety (H&S) has been lower than that in other construction fields
among the highest in relation to other industries [1], with approxi- [17]. According to Guo et al. [18], three-dimensional (3D) digital ap-
mately five deaths occurring each working day [2]. Therefore, job plications, such as gaming technologies or virtual reality, have gradu-
safety is vital in the construction industry. However, despite regulatory, ally been introduced [15,19–22], and construction information mod-
governmental, business, and professional effort, there has been no elling (BIM) is one such technology that is being increasingly used in
significant reduction in injuries, illnesses, and deaths occurring at work construction projects [23-25].
in the industry [3,4]. BIM reinforces the benefits of other digital techniques as it adds a
This problem is being extensively analysed by international orga- large amount of parametric information and allows collaborative work
nisations, such as the US Bureau of Labor Statistics and the between the technicians involved in the project [26–28]. These ad-
International Labor Organisation (OIT - acronym in English) [5,6], and vantages are also manifested in visualisation and analysis [29–31],
has been the focus of extensive research [7–11]. Therefore, the OIT has which aids in detecting and controlling occupational hazards and,
been prompted to qualify occupational safety as a major global problem therefore, their prevention according to Malekitabar et al. [32] and
[6]. Martínez-Aires et al. [33] when conducting realistic simulation [34].
A significant number of studies [2,9,12–14] have demonstrated that The integration of H&S into BIM has been partially addressed in
one of the main causes of occupational accidents is the lack of in- previous studies. For example, Getuli et al. [30] focused their research
tegration of occupational health and safety during the design phase. on the information of BIM prevention measure objects, and their re-
There are several reasons for this, including the lack of adequate tools, lationship with other elements and the legal requirements they must
training, and leadership by designers, as indicated by Hallowell et al. meet, but they did not explore methods of conducting such analysis or
and Hongling et al. [15,16]. risk assessment. Sulankivi and Kahkonen [35] followed a general ap-
proach without exploring approaches to such evaluation within the
⁎
Corresponding author.
E-mail address: jpcortes@unex.es (J.P. Cortés-Pérez).
URL: https://www.ui1.es (A. Cortés-Pérez).
https://doi.org/10.1016/j.autcon.2020.103115
Received 19 June 2019; Received in revised form 21 January 2020; Accepted 1 February 2020
Available online 13 February 2020
0926-5805/ © 2020 Elsevier B.V. All rights reserved.
J.P. Cortés-Pérez, et al. Automation in Construction 113 (2020) 103115
methodology. Azhar and Salman [4] studied the development of a four- uBIM guides regulate the use of BIM in these countries [48]. However,
dimensional (4D) safety plan within BIM without establishing the re- these guides do not address the integration of occupational hazards into
quirements for assessing the occupational hazards that will arise during BIM, and only include specific references [49]. The United Kingdom is
construction. Kim et al. [36] focused their study on scaffolding and its the only European country with BIM technology regulation that defines
associated risks, and explored the automation of evaluating scaffolding, the requirements to integrate occupational health and safety in the BIM
but did not analyse the integration of the remaining risks. Ganah and methodology [50]; these regulations address the requirements and
John [34] analysed the application of safety rules and their planning, conceptual framework of work in the Common Data Environment
but did not specify these rules in their evaluation methodology. Shen (CDE) without defining the method for incorporating health and safety
and Marks [37] took a further step in this direction and proposed the information into the BIM.
manual introduction of the risks associated with an element by as-
signing them a colour code based on their severity, but did not complete 1.4. Legal H&S and BIM regulations in Spain
the analysis and reassessment process.
According to Esteban [38], H&S is typically planned independently The Spanish and British H&S regulations were developed from a
of the planning of work in Spain, and Behm [9] and Frijters et al. [12] European standard [51], but they have different characteristics. In
have researched the consequent problems for the management of oc- Spain, two health and safety documents are required (one in the pre-
cupational risk prevention. According to Martínez-Aires et al. [33], the construction project and another during the project construction stage).
BIM methodology allows the simulation of construction, associating the However, in the United Kingdom, only one document is used in both
planning of work with the 3D model, and obtaining a 4D model. stages [52].
The Spanish regulations [53] require everyone involved in the
1.3. H&S in BIM regulations and guidelines construction projects to complete a Health and Safety Survey with very
specific contents. These requirements originate from the regulations set
Internationally, countries with greater development in BIM, such as prior to the approval of the directive [54]. Therefore, they not only
Australia, Canada, the US, and Singapore [39,40], do not have specific differ from British regulations, they also differ from those of any EU
regulations for the integration of H&S in BIM (HSBIM). For example, country. Furthermore, regulations aimed at the mandatory use of BIM
the regulations of Australia [41], Canada [42], or the international ISO methodology in building projects are being developed in Spain [55],
standard [43] do not mention the H&S regulations of the US [44]; they which indicates the transposition of the European directive on public
only refer to the classification of safety elements. procurement [56] and the law [57]. However, there are no government
In New York, advancements have been made in the regulation of regulations or technical documents in Spain that define the require-
HSBIM [45], as its regulations affect the planning and management of ments for HSBIM integration and complying with the requirements of
the 4D phases. However, these advancements did not include methods health and safety regulations [53,58].
of developing the previous risk analysis. Therefore, there is still a need The lack of a methodology defining the H&S information that must
to align traditional methods with BIM to manage risks, as indicated by be introduced into BIM for buildings in Spain, its traceability, and its
Zou et al. [46] and Alomari et al. [47]. management, could lead to problems and difficulties in coordination
In Europe, the countries with the greatest experience in the appli- between design technicians. This could then cause an increase in oc-
cation of BIM are Finland, Norway, Sweden, and Denmark [39,40], and cupational accidents.
2
J.P. Cortés-Pérez, et al. Automation in Construction 113 (2020) 103115
• Budget that quantifies the cost of conducting the health and safety
this, the “H&S” parameter was created and associated with all views of
the model involved with H&S. These will be generated by the Health
study.
and Safety Coordinator (H&SCD) during the design phase.
1.1. Studied BIM
A project navigator was configured using a filter based on the “H&S
parameter” to allow an orderly visualisation of the information re-
BIM can be applied using different modelling, management, and
garding the views of the model, which allows this information to be
planning software. Revit de Autodesk was used to implement H&S in
visible in the plans and views.
the BIM in this study, which has been used in previous studies [37,60].
This research was conducted based on a building with three storeys
above ground level and a basement, the architecture, structure, and 2.2.2. Generation of risk identification parameters
facilities of which have been modelled. The architectural design H&S information can be integrated into BIM based on risks.
3
J.P. Cortés-Pérez, et al. Automation in Construction 113 (2020) 103115
Table 2
Quantitative matrix of risk assessment in the BIM. The evaluated risk rating is in brackets.
Table 3
Actions to be taken according to the risk rating and colour code adopted in the evaluation.
Different risk assessment methodologies have been developed at an Safety Studies must contain detailed preventive measures with graphic
international level that guarantee systematic analysis. The risk identi- information and images.
fication criteria of the National Institute of Occupational Health and
Safety (INSST) are used in this study [62], which is the Spanish tech- 2.2.4. Site planning
nical scientific body that specialises in the analysis and study of occu- H&S is associated with the planning of work to be conducted during
pational health and safety conditions, and are widely understood by the the design phase. For the development of this study, a plan to represent
H&SCD responsible for the development of Health and Safety Studies in those provided by the design team to the H&SCD for the analysis and
Spain. management of risks during the design phase was constructed. From
The INSST methodology defined 32 occupational hazards (Table 1) this planning, execution phases were introduced to the model to allow
to be used to assess the risks of the project in the BIM of the building. each preventive measure to be associated with the corresponding ex-
Thirty-two parameters were defined for the identification of risks in ecution phase.
the project, coded from 1 to 32 for each risk. These parameters are of
the “yes/no” type and are associated with each constructive element of 2.3. H&S risk assessment and information management in the BIM
the model. Therefore, each specific risk generated by the execution of
said element can be activated. 2.3.1. Risk assessment in the BIM
To integrate the risk assessment according to the INSST metho-
2.2.3. BIM object development dology into the BIM, a risk parameter (NRi) was created in each BIM
BIMs are based on the application of BIM objects specific to the object of the model with a value of 1 to 32, according to [62].
modelled discipline [63]. There are fully developed BIM objects for The NRi is the product of the probability and severity of the risk
architecture, structures, and facilities that contain all of the required (Table 2). To obtain the NRis, a probability parameter (Pi) and a se-
constructive information. verity parameter (Gi) associated with the BIM objects of the model were
To allow them to be entered into the BIM, the collective protection also created for each risk, with a value of 1 to 32.
information must be carried out using BIM objects with the technical During the evaluation phase, the H&SCD will identify the risks as-
characteristics established by the H&S standards. These BIM objects are sociated with the construction of each element, marking the yes/no
not fully developed, and many objects do not contain the geometric parameter in the existing risks. Each identified risk will be assessed by
information established by the regulations. To resolve this issue in this assigning the following numerical values to the Pi and Gi: Pi takes a
study, some objects were defined according to their norm, such as value of 1, 2, or 3 for low, medium, or high probability, respectively,
safety nets [64], to indicate that the proposed methodology complies and Gi takes a value of 1, 2, or 3 for slightly harmful, harmful, or ex-
with Article 5 of the regulations [53], which states that Health and tremely harmful, respectively.
4
J.P. Cortés-Pérez, et al. Automation in Construction 113 (2020) 103115
5
J.P. Cortés-Pérez, et al. Automation in Construction 113 (2020) 103115
Fig. 4. a) Generation of probability and severity parameters for the 32 risks. b) Assignment of the risks of the selected element.
a b c
d e
Fig. 5. H&S families created: a) vertical fall protection network, b) guardrail, c) excavation beacon mesh, d) armour protection, and e) hygiene facilities.
3.2. Risk assessment and management should be a priori. After reviewing the risk assessment conducted for the
edge columns, the effectiveness of the corrections can be checked in a
The risk assessment was conducted during the project using the 3D view of NR01 (Fig. 8b).
views and planning tables. In this phase, the H&SCD will assign the Protective measures must be applied to the elements for which the H
probability and severity values for each identified risk. An example of &SCD detects a higher level of risk than tolerable (NR > 2; Table 3) to
the application of the probability and severity values for the risks as- reduce the risk to a level lower than 2. As an example of the application
sociated with ground and first-floor pillars is shown in Figs. 6 a) and b) of this methodology, for risk 01, specifically developed H&S BIM ob-
(“01 People falling between different levels" and “02 People falling on jects, such as protection rails to be added to the edge of the slab and
the same level”. Using the Dynamo script (Fig. 7), these risks were vertical networks for fall prevention, were placed in the model
evaluated to have a risk level (NR) of 2 for the ground-floor pillar. (Fig. 9a). After reassessing this risk, the value of R_NR was 2, indicating
Therefore, both risks (NR01 and NR02) were classified as tolerable that the risk level was then tolerable (Fig. 9b).
[62]. However, for the first-floor pillar, the risk levels of NR01 and Fig. 10a shows the risk assessment phase during which the H&SCD
NR02 were 6, indicating an important risk [62]. incorporates the preventive measures document hosted in the cloud
Fig. 8a presents a 3D view of the structure with risk assessment 01. into the model (Fig. 10b). The safety measures are entered into tables
To generate this view for the management of the H&S model, the colour using the URL parameter for filtering information. Similarly, the H&
filters created according to the proposed code for each risk rating SCD entered the information regarding the personal protection equip-
(Table 2) were applied, which allows a visual review of the levels of risk ment. Fig. 10a shows the IPE URL parameter linked to documents de-
for each element, as well as its components (probability and severity), veloped by the National Institute of Occupational Health and Safety
and the detection of errors. For example, in Fig. 8a, columns are present available on the internet (Fig. 10b), with the model accessing the latest
on the edge of the floor with a different level of risk, when the risk version of the document.
6
J.P. Cortés-Pérez, et al. Automation in Construction 113 (2020) 103115
a b
Fig. 6. Risk assessment of a) a ground floor column and b) first-floor column (highlighted in blue). (For interpretation of the references to colour in this figure legend,
the reader is referred to the web version of this article.)
Fig. 7. Dynamo code for the generation of the NR variable of all risks for the StructuralColumns category.
3.3. Extracting information from the BIM for the Health and Safety Study as that of Melzner et al. [65], where only a conceptual framework was
developed, Shen and Marks [37], who proposed a colour visualisation
The integration of H&S by the H&SCD in the BIM allows the gen- tool for risks, but did not use it in their assessment, or Melzner [66],
eration of the H&S planes in the model itself by linking the plan, ele- who proposed risk assessment during the generation of H&S BIM ob-
vation, and 3D views with the risk colour filters of the parameters to jects, but did not resolve the remaining process information, including
visualise the NR by elements, zones, and so on Fig. 11). The tables were the identification, evaluation, re-evaluation, and application of pro-
also linked to the tables containing the identified risks and their eva- tection and preventive measures within BIM objects.
luation, prevention measures, and their measurement (Fig. 11). Additionally, Fig. 9 shows that 3D visualisation through colour fil-
The parameters of collective and individual protection measures ters can facilitate the identification of risks and perform a more realistic
were obtained from the planning tables of the model were exported to simulation of such risks, as proposed by Ganah and John [34]. Fur-
Excel and loaded into a budget tool. thermore, this proposal allows the reduction of working time from that
of traditional methodology, as indicated by Malekitabar et al. [32], as
the organisation of views and filters allows the quick detection and
4. Discussion
correction of errors. Additionally, the use of visualisation filters and
application of the planning of the work (4D) developed by the designer
These results demonstrate that integrating H&S for a BIM con-
improves the inefficiencies detected by Zhang et al. [2].
struction project progressed from the findings of previous studies, such
7
J.P. Cortés-Pérez, et al. Automation in Construction 113 (2020) 103115
a b
c
Fig. 8. Three-dimensional visualisation of the risk of fallingError! Reference source not found.. a) Incorrect evaluation of the ground floor columns, b) correct
evaluation after a review of the 3D model, and c) filters applied according to the risk rating and colour code in Table 2. (For interpretation of the references to colour
in this figure legend, the reader is referred to the web version of this article.)
Fig. 9. Three-dimensional views for risk assessment 01 “People falling between different levels” (left) and after re-evaluation (right) with the pillars marked in colour
based on the risk.
The proposal of the organisation of both graphic and non-graphic of the execution phases allows the creation of virtual scenarios for the
information and its parameterisation (Figs. 6, 8 and 10) is an ad- training of workers, which, according to Hallowell et al. [15] and
vancement in the direction proposed by Guo et al. [67] for the con- Hongling et al. [16], is one of the causes of accidents during work.
struction phase in which the builder receives a structured model by According to Kassem et al. [41] and Enshassi et al. [68], one of the
facilitating the management of real-time modifications through vir- difficulties faced in the application of BIM methodology is the training
tually identifying the scenario that requires action. The new risks that of technicians. However, the ease of applying the methodology pro-
arise have a pre-established framework for management. Additionally, posed here will aid in resolving this, and would be further improved by
as seen in Fig. 10, when entering the information as consultable para- technicians with an understanding risk assessment methodology [62].
meters, collaborative work in the cloud is possible, and the absence of The standard [50] includes general guidelines for the integration of
such information in the design phase is one of the main causes of ac- H&S in BIM methodology based on the sharing of information through
cidents [9,12,14]. the Common Data Environment (CDE). In this study, progress was made
The generation of the proposed views (Fig. 3) with the sequencing in this direction, as we proposed approaches for introducing the BIM
8
J.P. Cortés-Pérez, et al. Automation in Construction 113 (2020) 103115
a)
b)
Fig. 10. a) Definition of the preventive measures and individual protection through URL, and b) preventive measures and individual protection documents obtained
from the BIM.
itself (Figs. 6, 8, and 10), which is vital for reducing such problems, as and its effectiveness to be fulfilled, as another fundamental requirement
indicated by Martínez-Aires et al. [33]. Additionally, the collaborative of these laws is the automatic generation of the documentation in
work that was proposed through the platform suggests complete in- Health and Safety Studies (Fig. 11).
teroperability with other disciplines, which will allow the model to
reach maturity levels of 2 and 3, as suggested by Kassem [40].
5. Conclusions
Finally, Fig. 4, Fig. 8, and Fig. 9 show that the proposed process
facilitates the management of occupational hazards by identification,
The government of Spain will make it mandatory that the pre-
evaluation, and elimination or minimisation them and the determina-
sentation of building construction projects under its jurisdiction be
tion of means and preventive measures in compliance with regulations
conducted using the BIM methodology. This change in project devel-
[53,58]. Additionally, the results shown in Fig. 4 and Fig. 6 indicate
opment methodology will affect all the technicians involved in the
that the established parameterisation allows the process to be traced
design phase, including H&S technicians. Additionally, H&S in Spain is
9
J.P. Cortés-Pérez, et al. Automation in Construction 113 (2020) 103115
Fig. 11. Plan generated in the BIM with Vitas: 3D, section, and plan views of the collective protections and tables containing their measurements and characteristics.
10
J.P. Cortés-Pérez, et al. Automation in Construction 113 (2020) 103115
11
J.P. Cortés-Pérez, et al. Automation in Construction 113 (2020) 103115
Hazard and Risk Information for Health and Safety, (2018), https://doi.org/10. 1995-24292 (accessed 27 April 2018).
3403/30347710. [59] European Commission, Directive 92/57/EEC, of June 24, 1992, on the im-
[51] European Commission, The implementation of minimum safety and health re- plementation of minimum safety and health requirements at temporary or mobile
quirements at temporary or mobile construction sites, European Commission. 1992 construction sites (eight individual directive within the meaning of article 16 (1) of
(1992) 6–22 https://eur-lex.europa.eu/legal-content/EN/ALL/?uri=celex directive 89/391/EEC), Off. J. Eur. Communities 18 (1992) 1–23 https://eur-lex.
%3A31992L0057 (accessed 7 September 2018). europa.eu/legal-content/EN/ALL/?uri=celex%3A31992L0057 (accessed 8 May
[52] M.D. Martínez-Aires, M.C. Rubio Gámez, A. Gibb, The impact of occupational 2018).
health and safety regulations on prevention through design in construction projects: [60] F. Rodrigues, J. Estrada, F. Antunes, P. Swuste, Safety through design: A BIM-based
perspectives from Spain and the United Kingdom, Work 53 (2016) 181–191, framework, Towards Sustainable Cities in Asia and the Middle East, 2017, pp.
https://doi.org/10.3233/WOR-152148. 112–123, , https://doi.org/10.1007/978-3-319-61645-2_9.
[53] BOE, Royal Decree 1627/97 by Laying Down Minimum Health and Safety [62] INSHT, Technical Guide for the Evaluation and Prevention of Risks Relating to
Provisions in Construction Sites, Boletin Oficial Del Estado, (1997), pp. Construction Works, (2012), p. 143 https://www.insst.es/-/guia-tecnica-para-la-
30875–30886 https://www.boe.es/eli/es/rd/1997/10/24/1627 , Accessed date: evaluacion-y-prevencion-de-los-riesgos-relativos-a-las-obras-de-construccion-ano-
14 July 2018. 2006 , Accessed date: 20 July 2018.
[54] BOE, Royal Decree 555/1986, of February 21, which Establishes the Mandatory [63] ISO 29481-1:2016, Building Information Models - Information Delivery Manual -
Inclusion of a Study of Safety and Health at Work in Building Projects and Public Part 1: Methodology and Format, vol. 2016, (2016) https://www.iso.org/standard/
Works, Boletín Oficial Del Estado, 1986, https://www.boe.es/eli/es/rd/1986/02/ 60553.html (accessed 17 June 2018).
21/555 , Accessed date: 28 March 2019. [64] UNE-EN 1263-1, Temporary works equipment - safety nets - part 1: safety re-
[55] BOE, Law 9/2017, of November 8, on public sector contracts, which transposes the quirements, test methods, https://www.une.org/encuentra-tu-norma/busca-tu-
directives of the European Parliament and of the council 2014/23/EU and 2014/ norma/norma/?c=N0060704, (2018) , Accessed date: 18 June 2018.
24/EU, of February 26, to the Spanish legal system 2014, Boletín Oficial Del Estado [65] J. Melzner, S. Hollermann, S. Kirchner, H.-J. Bargstadt, Model-based construction
(BOE), https://www.boe.es/buscar/act.php?id=BOE-A-2017-12902, (2017) , work analysis considering process-related hazards, Winter Simulations Conference
Accessed date: 23 February 2018. (WSC), IEEE, 2013, pp. 3203–3214, , https://doi.org/10.1109/WSC.2013.6721686.
[56] European Commission, Directive 2014/24/EU of the European Parliament and of [66] J. Melzner, Acquisition and processing of input data for an object - oriented safety
the Council of February 26, 2014 on Public Procurement and Repealing Directive risk simulation in building construction, Proceedings - Winter Simulation
2004/18/EC, 28.3.2014 (2014), pp. 65–242 https://eur-lex.europa.eu/legal- Conference, 2018, pp. 2425–2435, , https://doi.org/10.1109/WSC.2017.8247972.
content/EN/TXT/?uri=celex%3A32014L0024 , Accessed date: 18 April 2018. [67] H. Guo, Y. Yu, M. Skitmore, Visualization technology-based construction safety
[57] BOE, Royal Decree 1515/2018, of December 28, which Creates the Interministerial management: a review, Autom. Constr. 73 (2017) 135–144, https://doi.org/10.
Commission for the Incorporation of the BIM Methodology in Public Procurement, 1016/J.AUTCON.2016.10.004.
Boletín Oficial Del Estado (BOE), 2018, pp. 130033–130064 https://www.boe.es/ [68] A. Enshassi, A. Ayyash, R.M. Choudhry, BIM for construction safety improvement in
buscar/doc.php?id=BOE-A-2019-1368 (accessed 19 April 2018). Gaza strip: awareness, applications and barriers, Int. J. Constr. Manag. 16 (2016)
[58] BOE, Law 31/1995, of November 8, on Occupational Risk Prevention, Boletín 249–265, https://doi.org/10.1080/15623599.2016.1167367.
Oficial Del Estado, 1995, pp. 1–24 https://www.boe.es/buscar/act.php?id=BOE-A-
12