1. Welding inspection is a critical part of an overall:
Reference: Section 4.1 Welding Inspection (General) ; API may check your understandings of basics.
Remember all activities are part of a program.
2. Welding Inspection includes much more than just the non-destructive examination of the completed
weld. Many other issues are important & they include all of the below except:
Reference: Section 4.1 Welding Inspection (General) ; API may check your understandings of basics. PMI
is not normally part of welding inspection activities.
3. Welding inspection activities can be separated into three stages corresponding to the welding work
process and include all of the following except:
Prior to welding
During welding
During audits after weld inspections
Upon completion of welding
Reference: Section 4.1 ;Inspection; these are main duties of welding inspector (before, during, after
welding).
4. What is the most important stage of welding to assure that welding problems are avoided and changes
and corrections necessary are made?
In the planning and preparation stage before any welding on the job begins
Just immediately before the planned start of welding on a new job
During the welding of initial production joints
Either during welding or immediately after
Reference: Section 4.2 Tasks prior to Welding. Always be proactive and ensure all elements in place
before welding.
5. Prior to welding, a review of drawings, standards, codes, and specifications is done to:
Understand the requirements for the welding and identify any inconsistencies
Ensure that the welder understands the specification and is qualified
Ensure that the drawings meet the specifications
None of these are correct per API 577
https://inspector-training.com/api-577-mock-exam-question/ 3/12
12/24/23, 9:47 AM API 577 Sample Questions | Free Test | Welding Inspection and Metallurgy
Reference: Section 4.2.1 Drawings, Codes& Standards
6. All of the following are Quality Control items to assess prior to welding except?
Dimensions are detailed and any potential for distortion has been addressed
Perform Visual Welding to ensure no rejectable defects are present.
Weld maps identify welding procedure specification (WPS) used for specific weld joints
Welding symbols, weld sizes, weld joint designs, & weld dimensions are clearly specified
7. Inspectors shall review welding procedures (WPS) & qualification records (WPQs) prior to work to
ensure that:
Ref: Sect. 4.2.3.1 Procedures & Qualification Records Note: WPQ shows welder ability to deposit sound
weld while PQR supports the WPS and validate weld design or WPS.
9. Inspectors reviewing welding procedures & qualification records (prior to work) should address all of
the following actions EXCEPT:
Ref: Sect. Sect. 4.2.3.2 4.2.3.2 Procedures/Qual records potential inspector action!
Confirm the NDE procedure(s) from inspection organization are acceptable for the work
Confirm the NDE examiner(s) from inspection organization are capable for the work
Confirm the NDE equipment from inspection organization is acceptable for the work
Confirm the NDE examiner(s) are certified to ASNT SNT TC 1A or ASNT CP 189 or ISO 9712.
https://inspector-training.com/api-577-mock-exam-question/ 4/12
12/24/23, 9:47 AM API 577 Sample Questions | Free Test | Welding Inspection and Metallurgy
Ref: Sect. 4.2.4 ; NDE Information Trick question : NDE examiner shall be qualified as per ASNT SNT TC
1A or ASNT CP 189 or ISO 9712.
11. Inspectors reviewing NDE Information (prior to work) should assess all of the following Quality
Control items except:
12. Inspectors shall check Welding equipment & Instruments prior to work to:
Confirm Welding equipment & Instruments operate properly and are in good condition
Confirm Welding equipment & Instruments operate properly and are calibrated
Confirm Welding equipment & Instruments operate properly
Confirm Welding equipment & Instruments are calibrated
13. Inspectors checking welding equipment & instruments prior to work should assess all of the
following Quality Control items except:
14. Inspectors shall check Heat Treatment & Pressure Testing procedures/ associated equipment prior to
work in order to:
Confirm Heat Treatment & Pressure testing procedures/associated equipment are acceptable
Confirm Heat Treatment & Pressure testing associated equipment is acceptable
Confirm Heat Treatment & Pressure testing procedures are acceptable
confirm heating is adequate after welding.
15. Inspectors checking Heat Treatment & Pressure Testing procedures/associated equipment prior to
work should assess all of the following Quality Control items except:
Heat treatment procedure is available & appropriate & equipment calibrations are current
Pressure testing equipment & gauges calibrated & meet appropriate test requirements
https://inspector-training.com/api-577-mock-exam-question/ 5/12
12/24/23, 9:47 AM API 577 Sample Questions | Free Test | Welding Inspection and Metallurgy
Pressure testing procedures are available and detail the testing requirements
Trained personnel to perform activities have been approved for the work
Ref: Sect. 4.2.6.1 Heat Treat& Press Testing QC Items to Assess! Note: there is no PMI, PWHT and
Pressure Testing Technician Certificate unlike NDT Certifications. These technicians are normally
trained in house.
16. Inspectors shall check all Materials (for welding) prior to work in order to ensure all of the following
except:
Ensure all filler metals, base materials, and backing ring materials are properly identified
Ensure all filler metals, base materials, and backing ring materials are properly marked
Ensure material traceability is maintained as per mandatory API 578 requirements
Ensure PMI is performed (if required) to verify the material composition
17. Inspectors checking Materials prior to work should assess all of the following Quality Control items
except:
Material test certifications are available & items properly marked (incl. back-up rings if used)
Electrode marking/bare wire flag tags/identification on wire spools as-specified
Filler material markings are visible and known to the welding organization
Base metal markings are traceable to a material certification
Ref: Sec. 4.2.7.1 fillet materials need only be traceable and identifiable only.
18. Inspectors checking Materials prior to work should assess all of the following Quality Control items
except:
19. Final tasks upon completion of the weldment and work should include those that assure final weld
quality before placing the weldment in service & they include all of these except:
Document Audit (Perform final audit of Insp dossier to identify inaccuracies/ incomplete info)
Appearance & finish (Verify post-weld acceptance, appearance & finishing of welded joints)
NDE review (Verify NDE is performed at selected locations & review examiner’s findings)
Identify non-conformances and defects and take immediate corrective actions
https://inspector-training.com/api-577-mock-exam-question/ 6/12
12/24/23, 9:47 AM API 577 Sample Questions | Free Test | Welding Inspection and Metallurgy
20. If defects or non-conformances to specification are found by the Inspector, this should be handled
when and in what manner (Identify False statement):
Inspector takes actions on these issues at any time during the welding inspection
Inspector takes actions on these issues after his welding inspections by report issuance
Inspector takes steps to ensure correction of the issues before welding proceeds further
Inspector brings issues to attention of those responsible before welding proceeds further
Note: you should be pro active and don't wait until the end result. Intervene if you see something is not
right otherwise the cost and delay would be much more to rectify the issue at hand.
21. Recording on a data sheet of an indication that exceeds the reject flaw size criteria and needs to be
corrected is .....
Recordable indication
Reportable indication
Notable indication
Removable indication
Reportable indications need to be removed, corrected while recordable indications are those that do not
exceed acceptance criteria but still significant enough to be recorded.
22. A sub –surface terrace and step-like crack with basic orientation parallel to the base metal surface
caused by tensile stresses in thickness direction is called ......
Lamination
Plane-breaking crack
Lamellar tearing
D] Stress corrosion crack
GMAW
SAW
SMAW
FCAW
https://inspector-training.com/api-577-mock-exam-question/ 7/12
12/24/23, 9:47 AM API 577 Sample Questions | Free Test | Welding Inspection and Metallurgy
UT
PT
ET
RT
Within 6” – 24” with angle less than 30° with the surface
Within 6’’-24’’ with angle not less than 30° with surface
Beyond 24’’ with angle less than 30°
Beyond 24’’with angle not less than 30°
2
4
0
infinity
27. In UT examination,
Preheating only
Pre-heating & PWHT
No pre- heating or PWHT
PWHT only
30. Welding process that has very high metal deposition rate is ........
SMAW
https://inspector-training.com/api-577-mock-exam-question/ 8/12
12/24/23, 9:47 AM API 577 Sample Questions | Free Test | Welding Inspection and Metallurgy
GMAW
GTAW
SAW
There are three definite leads to help you understand what type of questions to expect during
examination. These are:
API 577 and it’s cross references (ASME V & ASME IX),
Body of Knowledge or what you are expected to know
Exam Score Report (showing the areas where you are scored against and the number of questions
from each topic).
https://inspector-training.com/api-577-mock-exam-question/ 9/12
12/24/23, 9:47 AM API 577 Sample Questions | Free Test | Welding Inspection and Metallurgy
1. Is the question written clearly?
2. Does the question cover knowledge that is important to a vessel inspector?
These questions then go into a question data-bank as non scored exam questions.
Presently there are over 500 questions in the data-bank and are grouped by topics. For each
examination, there are 80 questions on the exam pulled in specified proportion from various categories.
Only 70 Questions are scored. The remaining 10 are pre-test questions and not marked towards your
score, meaning these pre-test questions do not affect your score whether you have answered them
correctly or incorrectly. API does not tell you which ones these questions are.
API needs to ensure that these questions are not significantly challenged by the candidates and also has
been answered by a reasonable number of people before adding them to their question bank as scored
questions.
Scoring area
Percentage of Questions
ASME V 15%
ASME IX 15%
You are scored for your performance in the following areas during the examination:
Metallurgy
Welding Process, Procedure and Qualifications
Definitions, Acronyms and Symbols
Welding Inspection and NDE Examination
Refinery and Petrochemical Plant Welding Issues
Welding Materials
No Negative Marking
https://inspector-training.com/api-577-mock-exam-question/ 10/12
12/24/23, 9:47 AM API 577 Sample Questions | Free Test | Welding Inspection and Metallurgy
The pass mark is roughly 70% for all the API examinations. No negative marking is applied. Therefore,
make sure that you have answered all the questions. At the end, click the ‘’review all’’ button and peruse
through the list to ensure that you have not skipped any question. You can also check ‘’review
incomplete questions’’ to ensure there is nothing on the list, that is, no question left unanswered.
API 577 Mock Exam Package API 577 Welding Inspection & Metallurgy Online
Training Course
NEXT
API 1169 Sample Questions | Free Prac…
More To Explore
https://inspector-training.com/api-577-mock-exam-question/ 11/12
12/24/23, 9:47 AM API 577 Sample Questions | Free Test | Welding Inspection and Metallurgy
base and filler metals. 2. 𝙌𝙪𝙖𝙡𝙞𝙛𝙮
𝙒𝙚𝙡𝙙𝙚𝙧𝙨 𝙛𝙤𝙧 𝙋𝙞𝙥𝙚 𝙋𝙤𝙨𝙞𝙩𝙞𝙤𝙣𝙨 𝙉𝙚𝙚𝙙𝙚𝙙
Validate Welder Performance
Qualification (WPQ) performed on the
actual pipe welding positions that will
inspector-training.com
WHAT PEOPLE SAY
“
Jason T
API SIRE
I want to use this medium to say thank you to Mos and Ash for
https://inspector-training.com/api-577-mock-exam-question/ 12/12