CP05-03-MMC-MST-ELE-0020 REV.01 T&C For Earthing & Lightning Protection System
CP05-03-MMC-MST-ELE-0020 REV.01 T&C For Earthing & Lightning Protection System
CP05-03-MMC-MST-ELE-0020 REV.01 T&C For Earthing & Lightning Protection System
Documents Reference: CP05-03-MMC-MST-MEC-0020 Subject T&C Method of Statement for Earthing & Lightning Protection System– M/s. Menasco
Comment Response
Ref. Status
Date Reviewed by Reviewer comments Response by Contractor Response checked by original reviewer
Method satements shall be recommended/stamped by the approved Comply, The attached Method statement is
1 LACASA
specialist. endorsed by the specialist
SN Description
CP05-03-MMC-MST-ELE-0020 REV.00 Testing & Commissioning for Earthing and Lightning Protection
1
System, has been reviewed and is accepted for further submission.
Page 1 of 1
DIFC CP-05 Office
METHOD STATEMENT DOCUMENT NUMBER
Building-Main
CP05-MMC-MST-ELE-0020
Works Package & FOR TESTING AND
COMMISSIONING OF
Link Bridge Project,
EARTHING AND LIGHTNING Revision 00
Dubai, UAE PROTECTION SYSTEM
Issue Date 01-March-2023 Page 1 of 10
METHOD STATEMENT
FOR TESTING AND COMMISSIONING OF
EARTHING AND LIGHTNING PROTECTION
SYSTEM
CONTENTS
4) RESPONSIBILITIES
4.1 PROJECT MANAGER
4.2 ELECTRICAL SITE ENGINEER
4.3 ELECTRICAL SUPERVISOR
4.4 QA/QC ENGINEER
4.5 SAFETY ENGINEER
5) PROCEDURE / METHOD TO BE EMPLOYED
9) RISK ASSESSMENT
10) ATTACHMENTS
2.2 DEFINITIONS
• MAIN CONSULTANT means M/S LACASA Architects & Engineering Consultants
• MAIN CONTRACTOR means Ali & Sons Contracting L.L.C
• MEP SUB-CONTRACTOR means MENASCO Mechanical Contracting. LLC.
Electrical site engineer coordinates all site activities required for testing and
commissioning activities as per specification, manufacture datasheet and approved
drawing.
He should ensure to:
• Ensure that all the pre-commissioning checks are carried out successfully.
• Earth electrode resistance test is undertaken in accordance with the Fall of Potential
Method (FOP)/ Three pole method.
• Measure ground resistance not less than two full days after last trace of precipitation
and without soil being moistened by any means other than natural drainage or
seepage and without chemical treatment or other artificial means of reducing natural
ground resistance.
• This will involve insertion of 3no test probes, two into the ground to a maximum
depth of 200mm and the third one used as the earth electrode.
• Care must be taken than all three terminals are spaced out equally to obtain the
correct reading and the minimum distance between the spikes to be the depth of the
earth electrode driven in to the ground.
• Once the probes are placed in appropriate places the meter must be set to three
pole test and the readings are to be measured.
• Check the earth resistance values at all the earth pits individually & ensure that the
value is less than 1 ohm.
• If the readings are found to be higher than the required earth resistance value
(1 ohm), the depth of the electrode is increased and the same process is repeated
• Record the data in approved format (refer to attached draft test report) for
submission to consultant engineer.
8 RISK ASSESSMENT
Prior to the commencement of any activities the risk assessment (refer to
attachments) shall be reviewed jointly by the construction and the HSE team to
ensure that all the risks are addressed and the required mitigation measures are in
place and remain fully implemented during operation.
9 ATTACHMENTS
• Checklist for Pre-commissioning and commissioning.
• Risk Assessment.
INSPECTION CHECKLIST
Pre-commissioning Check List for Earthing System
Area/Location: Date:
Verify the location of the earth pits as per approved shop drawings and
3
coordination drawings.
4 Maintain a clear gap of 50mm between top of electrodes and earth pir
cover.
5
Ensure that the top of earth pit cover shall be in level with the finished level
in the area.
6 Check all the enclosures of all electrical switchgears are connected to the
grounding system.
Check and verify tightness of bolted electrical connections of the
7
earthing system.
8
Ensure to connect the earth cables through concealed conduit (from earth
pit side) to the earth bar with clamps as shown in approved shop drawings.
9
Labelling shall be done as per approved material submittal.
11
12
INSPECTION CHECKLIST
Pre-commissioning Check List for Lightning Protection system
3 Verify the location of the earth pits as per approved shop drawings.
Ensure Lightning Protection test point is provided at 500 mm above FFL.
4
8 Check if all exposed metal works on roof are bonded roof grid with copper
tapes.
Check if all down conductors are connected directly to the roof grid in as per
9 drawings
Ensure that the Air Terminal Rod install on the roof as per approved shop
10 drawing.
Check the continuity and resistance of each run of down conductors to the test
11 point using calibrated multi-meter.
Ensure the total resistance of down conductors from roof till ground shall
12
not exceed 0.2 ohm.
Ensure the overall resistance value of lighting protection system is less than 10
13
ohm.
10
11
12
13
14
15
Prepared by
Verified by (CA) Verified by (ASC) Approved by (LACASA)
(TECON/MENASCO)
Name
Designation
Signature
Date
DIFC CP-05 OFFICE
BUILDING MAIN WORKS
CLIENT CONSULTANT MAIN CONTRACTOR MEP CONTRACTOR
TEST REPORT
Down Conductor Resistance test
Date : Instrument Type/Make :
Location/ Room : Serial No : Calibration
:
Floor : Certificate No : Expiry
1 Down Conductor-1
2 Down Conductor-2
3 Down Conductor-3
4 Down Conductor-4
5 Down Conductor-5
6 Down Conductor-6
7 Down Conductor-7
8 Down Conductor-8
9 Down Conductor-9
10 Down Conductor-10
11 Down Conductor-11
12 Down Conductor-12
13 Down Conductor-13
14 Down Conductor-14
15
16
17
18
19
20
Prepared by
Verified by (CA) Verified by (ASC) Approved by (LACASA)
(TECON/MENASCO)
Name
Designation
Signature
Date
MENASCO MECHANICAL CONTRACTING L.L.C.
( DIFC CP - 05 BUILDING LINK BRIDGE MAIN WORKS )
( RISK ASSESSMENT)
Date: 02-05-2023
Reference No
Revision Rev 00
Main Activity: T&C of Earthing and lightning protection
Location: DIFC CP - 05 BUILDING LINK BRIDGE MAIN WORKS
Severity
Likelihood 1 2 3 4 5
Certain 5 5 10 15 20 25
Very Likely 4 4 8 12 16 20
Likely 3 3 6 9 12 15
May Happen 2 2 4 6 8 10
Unlikely 1 1 2 3 4 5
Trivial Risk - No further improvements necessary provided control measures are maintained
Adequately Controlled Risk - Risk is tolerable when control measures identified are implemented
Moderately controlled Risk - Further risk reduction measures should be considered
Intolerable Risk - Seek specialist advice/ support
Aravi Ashok Designation Proj, HSE Manager Date: 06th May 2023 Signature:
Salman Abu Assali Designation Project Manager Date: 06th May 2023 Signature:
s
MENASCO MECHANICAL CONTRACTING L.L.C. Page 2 of 24
(DIFC – 05 BUILDING LINK BRIDGE MAIN WORKS)
(RISK ASSESSMENT)
Risk Rating Residual ALARP
Effects/ With No Risk Demonst
Sr. (T/A/M/ I) rated
Hazards Consequences Controls Recommended Control Measures &
Job Step Action By
(Y/N)
Likelihood
Likelihood
(Refer To Risk Mitigations
(T/A/M/I)
(T/A/M/I)
(The potential to cause harm (The harm which could
Outcome
(Sequence of
Outcome
Severity
Severity
(Health, Injury, Property damage, Assessment
working activities) possibly occur).
environment etc.)) Procedure, PP
729-RAP)
01 Access to work Unfamiliarity to the site Minor injury 3 2 6 The Ali & Sons Contracting Project HSE Plan 1 2 2 Compliance to
area Unauthorized parking Property / asset shall be strictly complied with by all M/s DM, COP- CHP
Unauthorized access to site or damage MENASCO personnel and sub-contractors 2- 2.1, 2.3
taken shortcut Major injury under our control. Y
warning alarm/ warning light All work shall be carried out in accordance to Manager
Slip, trip and fall all applicable UAE Laws and Regulations, DM
Obstructed the walkway /traffic Regulations and MMC Project HSE Senior Project
activity
All material shall be segregated accordingly to Driver & Helper
Likelihood
Likelihood
(Refer To Risk Mitigations
(T/A/M/I)
(T/A/M/I)
(The potential to cause harm (The harm which could
Outcome
(Sequence of
Outcome
Severity
Severity
(Health, Injury, Property damage, Assessment
working activities) possibly occur).
environment etc.)) Procedure, PP
729-RAP)
Likelihood
Likelihood
(Refer To Risk Mitigations
(T/A/M/I)
(T/A/M/I)
(The potential to cause harm (The harm which could
Outcome
(Sequence of
Outcome
Severity
Severity
(Health, Injury, Property damage, Assessment
working activities) possibly occur).
environment etc.)) Procedure, PP
729-RAP)
Likelihood
Likelihood
(Refer To Risk Mitigations
(T/A/M/I)
(T/A/M/I)
(The potential to cause harm (The harm which could
Outcome
(Sequence of
Outcome
Severity
Severity
(Health, Injury, Property damage, Assessment
working activities) possibly occur).
environment etc.)) Procedure, PP
729-RAP)
Likelihood
Likelihood
(Refer To Risk Mitigations
(T/A/M/I)
(T/A/M/I)
(The potential to cause harm (The harm which could
Outcome
(Sequence of
Outcome
Severity
Severity
(Health, Injury, Property damage, Assessment
working activities) possibly occur).
environment etc.)) Procedure, PP
729-RAP)
03 Testing Procedure Untrained operatives. Minor Injuries ASC Policies and Procedures shall be
For Lighting Defect/ damage Major Injuries followed by Menasco team prior to start of the
Protection system tool/equipment. Property / assets Activity.
Lack / poor supervision damage MSRA to be communicated with the
Project Manager
Incompetent/untrained 4 operatives by the foreman or supervisor. 4
Environmental
operatives for T & C 3 3 9 Pre-Task briefing or TBT to be carried out by 1 3 3
Impact Construction
Poor lightening foreman or supervisor prior to start of work
Manager
Trip, slip and fall communicating hazard and control measures
Likelihood
Likelihood
(Refer To Risk Mitigations
(T/A/M/I)
(T/A/M/I)
(The potential to cause harm (The harm which could
Outcome
(Sequence of
Outcome
Severity
Severity
(Health, Injury, Property damage, Assessment
working activities) possibly occur).
environment etc.)) Procedure, PP
729-RAP)
Testing Procedure Incompetent crew Personal Confined space entry PTW should be
04 For Earthing Inadequate access Injuries, obtain from the contractor.
System Inadequate light Property All operatives should be trained and
Project Manager
Lack of communication Damage, certified.
Tools striking due to ill-health, Safe access/ egress should be provided.
Construction
congested work atmosphere. MS& RA will be briefed to employees on
Manager
Heat stress due hot climate their task including safe work procedure
or doing hot work. inside the water Tank prior to start by
Senior Project
Inability to escape. concerned Engineer and supervisor
Engineer
Exclusion zones and signage must be
implemented / maintained around the work
Site Engineer
location.
3 2 6 1 2 2 Y
Ensure that all the pre-commissioning
HSE Officer
checks are carried out successfully.
Earth electrode resistance test is
Supervisors
undertaken in accordance with the Fall of
Potential Method (FOP)/ Three pole
Foreman
method
Measure ground resistance not less than
two full days after last trace of Operators
precipitation and without soil being
moistened by any means other than T & C Engrs
natural drainage or seepage and without
chemical treatment or other artificial
means of reducing natural ground
resistance.
PPE”s to be worn always Such as heavy
duty hand gloves, hard hat, safety shoe,
MENASCO MECHANICAL CONTRACTING L.L.C. Page 8 of 24
(DIFC – 05 BUILDING LINK BRIDGE MAIN WORKS)
(RISK ASSESSMENT)
Risk Rating Residual ALARP
Effects/ With No Risk Demonst
Sr. (T/A/M/ I) rated
Hazards Consequences Controls Recommended Control Measures &
Job Step Action By
(Y/N)
Likelihood
Likelihood
(Refer To Risk Mitigations
(T/A/M/I)
(T/A/M/I)
(The potential to cause harm (The harm which could
Outcome
(Sequence of
Outcome
Severity
Severity
(Health, Injury, Property damage, Assessment
working activities) possibly occur).
environment etc.)) Procedure, PP
729-RAP)
process is repeated
Record the data in approved format (refer
to attached draft test report) for
submission to consultant engineer.
MENASCO MECHANICAL CONTRACTING L.L.C. Page 9 of 24
(DIFC – 05 BUILDING LINK BRIDGE MAIN WORKS)
(RISK ASSESSMENT)
Risk Rating Residual ALARP
Effects/ With No Risk Demonst
Sr. (T/A/M/ I) rated
Hazards Consequences Controls Recommended Control Measures &
Job Step Action By
(Y/N)
Likelihood
Likelihood
(Refer To Risk Mitigations
(T/A/M/I)
(T/A/M/I)
(The potential to cause harm (The harm which could
Outcome
(Sequence of
Outcome
Severity
Severity
(Health, Injury, Property damage, Assessment
working activities) possibly occur).
environment etc.)) Procedure, PP
729-RAP)
Used of temporary Electrocution Minor Injury The Ali & Sons Contracting Project HSE Plan
power supply and
05
Extension leads.
Slip / Trip and falls Major Injury shall be strictly complied with by all
Untrained operative. Property damaged All works shall be regularly monitored and
Use of damage extension leads. supervised by M/s MENASCO site team
Use of damaged equipment's to ensure full compliance
Project Manager
Lack of PPE. MENASCO shall provide adequate resources,
Work In wet areas with damaged as appropriate to ensure safe execution of work
Construction
cable lead or equipment scope.
Manager
All work shall be carried out in accordance to all
applicable UAE Laws and Regulations, DM
Senior Project
Regulations and MMC Project HSE Management
Engineer
System. Obtain the required work permit and
clearance prior to start the task
3 3 9
1 3 3 Y Site Engineer
SOS / MSRA should communicate to workers
prior to commencement of work.
HSE Officer
Pre-Task briefing or TBT to be carried out by
foreman or supervisor prior to start of work
Supervisors
communicating hazard and control measures to
its workers
Foreman
Only competent person can carried out the
electrical task at site
Operators
Inspected and color-coded extension leads to
be used on site.
All electrical tools and equipment's free from
defects and fit to safe use
MENASCO MECHANICAL CONTRACTING L.L.C. Page 10 of 24
(DIFC – 05 BUILDING LINK BRIDGE MAIN WORKS)
(RISK ASSESSMENT)
Risk Rating Residual ALARP
Effects/ With No Risk Demonst
Sr. (T/A/M/ I) rated
Hazards Consequences Controls Recommended Control Measures &
Job Step Action By
(Y/N)
Likelihood
Likelihood
(Refer To Risk Mitigations
(T/A/M/I)
(T/A/M/I)
(The potential to cause harm (The harm which could
Outcome
(Sequence of
Outcome
Severity
Severity
(Health, Injury, Property damage, Assessment
working activities) possibly occur).
environment etc.)) Procedure, PP
729-RAP)
Likelihood
Likelihood
(Refer To Risk Mitigations
(T/A/M/I)
(T/A/M/I)
(The potential to cause harm (The harm which could
Outcome
(Sequence of
Outcome
Severity
Severity
(Health, Injury, Property damage, Assessment
working activities) possibly occur).
environment etc.)) Procedure, PP
729-RAP)
person.
Do not use any damage power tool and worn HSE Officer
Likelihood
Likelihood
(Refer To Risk Mitigations
(T/A/M/I)
(T/A/M/I)
(The potential to cause harm (The harm which could
Outcome
(Sequence of
Outcome
Severity
Severity
(Health, Injury, Property damage, Assessment
working activities) possibly occur).
environment etc.)) Procedure, PP
729-RAP)
.
MENASCO MECHANICAL CONTRACTING L.L.C. Page 13 of 24
(DIFC – 05 BUILDING LINK BRIDGE MAIN WORKS)
(RISK ASSESSMENT)
Risk Rating Residual ALARP
Effects/ With No Risk Demonst
Sr. (T/A/M/ I) rated
Hazards Consequences Controls Recommended Control Measures &
Job Step Action By
(Y/N)
Likelihood
Likelihood
(Refer To Risk Mitigations
(T/A/M/I)
(T/A/M/I)
(The potential to cause harm (The harm which could
Outcome
(Sequence of
Outcome
Severity
Severity
(Health, Injury, Property damage, Assessment
working activities) possibly occur).
environment etc.)) Procedure, PP
729-RAP)
Board (EDB).
insulated.
Likelihood
Likelihood
(Refer To Risk Mitigations
(T/A/M/I)
(T/A/M/I)
(The potential to cause harm (The harm which could
Outcome
(Sequence of
Outcome
Severity
Severity
(Health, Injury, Property damage, Assessment
working activities) possibly occur).
environment etc.)) Procedure, PP
729-RAP)
Use of DSE Untrained worker Eye strain Pre-task, TCRA and TBT to be
07 (computer laptop) Electrocution Spine injury communicated with the operatives by the
equipment Slip, trip and fall Fatigue foreman or Supervisor.
for lightening Lack of PPE Glares Operatives must be trained on safe and
protection system Poor illumination Reflections proper use DSE in Implementing good
Likelihood
Likelihood
(Refer To Risk Mitigations
(T/A/M/I)
(T/A/M/I)
(The potential to cause harm (The harm which could
Outcome
(Sequence of
Outcome
Severity
Severity
(Health, Injury, Property damage, Assessment
working activities) possibly occur).
environment etc.)) Procedure, PP
729-RAP)
Work at Height - Falling of men and materials from Major Injuries The Ali & Sons Contracting Project HSE Plan
08 Using Scaffold, A-
height Minor Injury
shall be strictly complied with by all DM – Compliance
Type ladder / All works shall be regularly monitored and CHAPTER 8
Presence of overhead services Fatality Scaffolding
Podium Ladders supervised by M/s MENASCO site team
Safety
Incompetent workers Property damaged to ensure full compliance 101CHAPTER
MENASCO shall provide adequate resources, 4Personal
Lack of supervision
as appropriate to ensure safe execution of work Protective
Improper use of work platform
scope. All work shall be carried out in Equipment
44Project
Unauthorized access to the accordance to all applicable UAE Laws and
Manager
Regulations, DM Regulations and MMC Project
equipment
HSE Management System. Construction
Untrained operator
MSRA to be communicated with the operatives Manager
Unfavourableclimatic conditions by the foreman or supervisor.
3 3 9
1 3 3
Permit For work at height on scaffolding to be Senior Project
Unbalancing of work platform
available and approved from concerned team prior Engineer
Caught-in between
to start of work. Pre-Task briefing or TBT to be
Working under direct sun light carried out by foreman or supervisor prior to start Site Engineer
of work communicating hazard and control
Dust
measures to its workers. HSE Officer
Noise
Only Competent scaffolder which is 3rd party
Slippery surface due to leak of oil certified to erect mobile Aluminium scaffolding and Supervisors
platform.
Operative Working at height must be trained for Foreman
Safe Work at height.
operators
MENASCO MECHANICAL CONTRACTING L.L.C. Page 16 of 24
(DIFC – 05 BUILDING LINK BRIDGE MAIN WORKS)
(RISK ASSESSMENT)
Risk Rating Residual ALARP
Effects/ With No Risk Demonst
Sr. (T/A/M/ I) rated
Hazards Consequences Controls Recommended Control Measures &
Job Step Action By
(Y/N)
Likelihood
Likelihood
(Refer To Risk Mitigations
(T/A/M/I)
(T/A/M/I)
(The potential to cause harm (The harm which could
Outcome
(Sequence of
Outcome
Severity
Severity
(Health, Injury, Property damage, Assessment
working activities) possibly occur).
environment etc.)) Procedure, PP
729-RAP)
Likelihood
Likelihood
(Refer To Risk Mitigations
(T/A/M/I)
(T/A/M/I)
(The potential to cause harm (The harm which could
Outcome
(Sequence of
Outcome
Severity
Severity
(Health, Injury, Property damage, Assessment
working activities) possibly occur).
environment etc.)) Procedure, PP
729-RAP)
Lack of training to Emergency case Operatives must be trained of safe and proper Construction
Manager
responder Fines use of hand tools.
Improper or lack of illumination Emergency responder environment in which they are to be used and they
Site Engineer
Improper or lack of ventilation Incompetent are in good condition.
3 2 6
.Sharp tools, which cut steel, can cut flesh
1 2 2 Y
emergency responders HSE Officer
without trouble. Hammers, which can drive nails,
Improper or lack of
can squash fingers too. Open-bladed knives, Supervisors
illumination
screwdrivers, and other sharp tools are to be
Improper or lack of Foreman
carried and used so as not to cause injury to the
ventilation
user or others. Operators
Non-ferrous (spark free) tools are to be used in
flammable atmospheres. ERT TEAM
Insulated tools must be used where there is a
possibility of live electrical work
Visual checks must be completed by operatives
on tools prior to their use. They rely on them, as
skilled trade’s persons, to assist them in this by
reporting immediately if something is not suitable
or is broken.
MENASCO MECHANICAL CONTRACTING L.L.C. Page 18 of 24
(DIFC – 05 BUILDING LINK BRIDGE MAIN WORKS)
(RISK ASSESSMENT)
Risk Rating Residual ALARP
Effects/ With No Risk Demonst
Sr. (T/A/M/ I) rated
Hazards Consequences Controls Recommended Control Measures &
Job Step Action By
(Y/N)
Likelihood
Likelihood
(Refer To Risk Mitigations
(T/A/M/I)
(T/A/M/I)
(The potential to cause harm (The harm which could
Outcome
(Sequence of
Outcome
Severity
Severity
(Health, Injury, Property damage, Assessment
working activities) possibly occur).
environment etc.)) Procedure, PP
729-RAP)
Proper ventilation to be provided
Proper and safe access to be provided in work
areas.
Ali & Sons HSE Policies and Procedures shall be
followed by Menasco team prior to start of the
Activity.
Menasco to comply with Local Authority
regulations and HSE requirements
Note: If any new scenarios emerge that are not covered by this risk assessment, site management should be contacted immediately, and the task should not be completed until a specific risk
assessment has been completed, issued, and understood.