PROJECT INSPECTION PLAN PROJECT NAME LOGO

Doc Ref: XXXXXXXXXXXXXX Rev 01 Page: 1 of 2 Date: xxxxx


Controlling Action if not Inspection / Test
# Activity Acceptance Criteria
Document conforming
Resp. Freq. Verification Records Remarks
Site Eng. QC Cons’t

Part 4: Plastering Works


1.0 Submissions
1.1 Approval of method Signed Masonry MS by PM and approved / accepted by QMS Revise Section Prior to H H R Approved method
statements consultant section 09220/P1 engineer works statement
1.2 Approval of subcontractor authorisation QMS Resubmit Project Prior to H H H QMS submittal /
subcontractors Section 09220 alternative manager works correspondence /
Part 1-CI-1-5-1 Qualification data
1.3 Approval of material Compliance to specifications QMS Resubmit Project Prior to H H H Material test reports
section 09220/P2 alternative manager works
part 2 CI- 2-2

1.4 Approval of mock ups -to provide 1 m long by 1 m wide mock-up of exterior QMS Make Section Prior to H H H
and interior wall and ceiling system section 09220/P1 alternative engineer works
(mock-up may considered as a part of the work) part 1 CI- 1-5-2
2.0 Works
2.1 Procurement Ensure definition of full requirement of specifications Approved MS Reject resolve Materials Prior to H H --------
section 09220 part 2 with supplier / engineer works
CI 2.2 manufacture assigned
find good quality signatory
of resources
2.2 Storing -Deliver cementation materials to site in original package, Approved MS Make good QC Prior to M M M Accepted Location Revised as work
containers or bundles, labelled with manufactures name, section 09220 part 1 engineer works proceeds
product brand name and lot number CI 1.6
-Store materials under cover and dry protected from
weather, direct sunlight ,surface contamination ,aging
corrosion and damage
2.3 Plaster composition Plaster shall be cement-sand mortar Approved MS Make good QC ongoing M M M Test Reports,
 Spatter-dash 450 Kg cement/m33 sand section 09220 part 3 engineer Qualification data
 Interior plaster 250 Kg cement/m3 sand CI 3.4.1
 Exterior plaster 300 Kg cement/m3 sand Egyptian specs-
ministerial degree
no:164
2.4 Execution -Termination of plaster (top beads) UOI Approved MS Make good Site Per plot H H H Work / inspection request
Step 1 -Intersections of masonry and concrete surface : install section 09220 part 3 engineer [Form 4.03]
Dash coat , dots , mesh strip 150 mm on each side of the intersection line CI 3.3.1
bands and section09220
accessories part 2
CI 2.4.2
CI 2.4.3
2.5 Execution Plaster mortar shall be mechanically mixed with the correct Approved MS Make good QC Per plot H H H Work / inspection request
Step 2 proportions. section 09220 part 3 engineer [Form 4.03]
Plaster completion Quantity shall be as sufficient as to be used without being section 09220
delayed for excess time. consultant
acceptance
2.6 Curing Plaster coats shall be kept moistened for 2 days Approved MS Make good QC ongoing M M M
section 09220 engineer
Part 3
CI.3.5.4
2.7 Tools for inspection Spirit level and measure tape and angles

2.8 Tolerance Maximum verification from true flatness ±3mm in 3 m Approved MS


section 09220
Part 3 CI.3.5.9
3.0 Tests
NA
3.1 NA NA NA NA NA NA NA NA NA
PROJECT INSPECTION PLAN PROJECT NAME LOGO
Doc Ref: xxxxx Rev xxxx Page: 2 of 2 Date: xxxxxxxx
Controlling Action if not Inspection / Test
# Activity Acceptance Criteria
Document conforming
Resp. Freq. Verification Records Remarks
Site Eng. QC Cons’t
4.0 Trials (optional)
NA
4.1 NA NA NA NA NA NA NA NA NA

5.0 Alternatives (optional)


NA
5.1 NA NA NA NA NA NA NA NA NA