Professional Documents
Culture Documents
01 Dive Plan
01 Dive Plan
No : FRM/Project Code/DP-001
Rev : 00
Date : 14.07.2016
Page : 1/3
DIVE PLAN
Contingency Planning Use of secondary equipments , 10” Air lift and 150 Mtr spare Broco
Team Size 1 Super
9 Men sat team
(Manning Level)
2 Sat Supv
5 Deck crew
2 LSS
2 ALST
24 Knts wind
Vessel Limitations 6 ft wave height Max
4 mtr aside to the Air lift Operations on port side
Hot work permit , Underwater TBI by Super and C/O after the complete broco “Manufacturers”
standard compliances .
Crane load to be tackled by tag line , Underwater and surface , 2 Attach points .
PTW Limitations Tag lines to be tied with minor weights/Small shackles for the weightage underwater and surface.
Pressure test certificates for the Air Hoses to be in place.
Rigging certificates
Doc.No : FRM/Project Code/DP-001
Rev : 00
Date : 14.07.2016
Page : 2/3
DIVE PLAN
GENERAL
This Dive Plane is a Guideline to the proposed work / tasks to be undertaken during a single twelve
(24) hour period and as such is intended to ensure continuity and safe responsibility of the intended
work scope.
However changes to this dive plan may arise without notice due to operational circumstances. Any
changes made for operational reasons must be noted in the Dive Log, with the heading: “Operational
Change to Dive Plan No.”
All major or significant deviations from the Dive Plan will be subject to a Job Safety Analysis
All Personnel associated with the intended work scope are required to familiarise themselves with the
project procedures
SAFETY POINTS
SUBSEA ACTIVITY
1. GVI On the offshore & Shore parted trunk lines . 250 metres each side . Record the and log the
data.
2. Connecting the 15T wire sling on the leaning pipe . and secondary wire as well . TBC for the
location on leaning P/L.
3. Start the air lift on the TDP , 3 metre away on the offshore side .
4. Make 2 m x 2 m x 1 m ditch area with 6” Air lift for the Hot cut .
5. Water Jet on the concrete section , 0.5 mtr concrete to be taken off and wire mesh to be cut off.
6. Bitumistik removal on 3’O – 4’O clock position.
7. Attach crane
8. Start the Hot cut from 3’O – 6’O clock pos. Relocate towards 6’O – 9’O pos by changing the other
side.
9. Once the half clock pos is cut , relocate diver on the top half shell for the cut.
10. With continuation on cutting , on end diver to leave 1 mm spot and move away from the area .
11. Launch ROV for the monitoring the load
12. Take load on crane and once the spot attach is clear , lift the piece 2 mtr from sea bed , and
Doc.No : FRM/Project Code/DP-001
Rev : 00
Date : 14.07.2016
Page : 3/3
DIVE PLAN
move the vessel 50 mtr away from 32” & 4” line. TBC upon on site situation.
13. Rest the piece on sea bottom and deploy diver on site to connect the secondary sling on the
crane for horizontal lift .
14. Connect tag lines on both ends.
15. Recover Pipe line piece on surface with ROV monitoring till -30 Msw .
Equipment List