OH of Gas Engine

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 5

Over Hauling of GAS Genset Aug 29, 2019

http://www.eslpk.com
PPL

Project manager
Project dates Sep 2, 2019 - Sep 24, 2019

Completion 0%
Tasks 16
Resources 2
Over Hauling of GAS Genset Aug 29, 2019
2
Tasks
Name Begin date End date
Disconnect the engine and alternator including all power / control cables. 9/2/19 9/3/19
Dismantling / removal of all electrical / instrumentation items like battery connections, starter motor, all type of 9/2/19 9/3/19
sensors & gauges, Harnesses, probes, instrumentation tubing etc.
Dismantling and removal of all piping connections, exhaust connections, cylinder heads, turbochargers, after 9/4/19 9/5/19
cooler,lube oil cooler etc.
Removal of all pistons, liners, connecting rods, connecting rod bearings, etc. 9/6/19 9/7/19
Replacement of connecting rod bearings, connecting rod cap screws, cylinder liners, piston rings, flexible coupling of 9/8/19 9/10/19
generator, main bearings if required after inspection, push rods if required, tappet assemblies if required.
Overhauling / refurbishment of turbochargers with new repair kits. Replacement of turbocharger supply and drain 9/11/19 9/12/19
Lines.
Replace fuel filter, fuel line seals and replace bearings of throttle shaft. 9/13/19 9/14/19
Inspection of crankshaft, camshafts, pistons, connecting rods. 9/15/19 9/15/19
Inspection / replacement of all hose pipes and rectify leakages where required. 9/16/19 9/16/19
Inspection of all piping and rectification of leakages where required. 9/17/19 9/17/19
Inspection / replacement of tappet rollers. Inspection of front gear train backlash. 9/18/19 9/18/19
Restoration / installation of all engine components like liners, pistons, connecting rods, oil pump, oil cooler, after 9/19/19 9/20/19
cooler, intake and exhaust manifolds, all piping connections etc. Ensure proper cleaning of all engine components
before installation
Complete inspection / cleaning of lube oil sump. 9/21/19 9/21/19
Adjustment of tappet, installation of spark plug, ignition coil and tappet covers etc. CONTRACTOR COMPANY 9/22/19 9/22/19
Replacement of Spark plugs, Primary air filters, Secondary air filters, lube oil filters, centrifugal filter paper insert, 9/22/19 9/22/19
crankcase breather element, Lube oil etc.
Inspection / replacement of back-up batteries, coil-on-plug extensions. 9/23/19 9/23/19
Over Hauling of GAS Genset Aug 29, 2019
3
Resources
Name Default role
Liaqat Ali Team Leader
Team 3 Persons undefined
Over Hauling of GAS Genset Aug 29, 2019
4
Gantt Chart
September 2019

Week 36 Week 37 Week 38 Week 39 Week 40


Name Begin date End date 9/1/19 9/8/19 9/15/19 9/22/19 9/29/19

Disconnect the engine and alternator including all power / control cables. 9/2/19 9/3/19
Dismantling / removal of all electrical / instrumentation items like battery connections, starter mot...9/2/19 9/3/19
Dismantling and removal of all piping connections, exhaust connections, cylinder heads, turboch... 9/4/19 9/5/19
Removal of all pistons, liners, connecting rods, connecting rod bearings, etc. 9/6/19 9/7/19
Replacement of connecting rod bearings, connecting rod cap screws, cylinder liners, piston rings, ... 9/8/19 9/10/19
Overhauling / refurbishment of turbochargers with new repair kits. Replacement of turbocharger s...9/11/19 9/12/19
Replace fuel filter, fuel line seals and replace bearings of throttle shaft. 9/13/19 9/14/19
Inspection of crankshaft, camshafts, pistons, connecting rods. 9/15/19 9/15/19
Inspection / replacement of all hose pipes and rectify leakages where required. 9/16/19 9/16/19
Inspection of all piping and rectification of leakages where required. 9/17/19 9/17/19
Inspection / replacement of tappet rollers. Inspection of front gear train backlash. 9/18/19 9/18/19
Restoration / installation of all engine components like liners, pistons, connecting rods, oil pump, ... 9/19/19 9/20/19
Complete inspection / cleaning of lube oil sump. 9/21/19 9/21/19
Adjustment of tappet, installation of spark plug, ignition coil and tappet covers etc. CONTRACTOR...9/22/19 9/22/19
Replacement of Spark plugs, Primary air filters, Secondary air filters, lube oil filters, centrifugal filte...9/22/19 9/22/19
Inspection / replacement of back-up batteries, coil-on-plug extensions. 9/23/19 9/23/19
Over Hauling of GAS Genset Aug 29, 2019
5
Resources Chart
September 2019

Week 36 Week 37 Week 38 Week 39 Week


Name Default role 9/1/19 9/8/19 9/15/19 9/22/19 9/29/19

Liaqat Ali Team Leader 200%

Team 3 Persons undefined 200%

You might also like