Professional Documents
Culture Documents
GCS 5000-Guidelines (200809)
GCS 5000-Guidelines (200809)
GCS 5000-Guidelines (200809)
Guidelines for
Substation Constructions
General Electricity
Company Of Libya
Table of Contents
1. Scope 1
2. General 1
2.1. Substation Types (Refer to GDS 5000, clause 2.2) 1
2.1.1. Outdoor AIS 1
2.1.2. Outdoor GIS 1
2.1.3. Outdoor hybrid GIS 1
2.1.4. Outdoor full GIS 1
2.1.5. Indoor GIS 2
2.1.6. Indoor AIS 2
2.1.7. Underground GIS 2
2.2. Review of Required Area 2
2.2.1. Overview 2
2.2.2. Equipment Arrangement 3
2.3. Flowchart for Substation Construction 4
3. Construction Process Management 5
3.1. Making a Master Time Schedule 5
3.1.1. Objectives 5
3.1.2. Process for master time schedule 5
3.1.3. Master time schedule details 6
3.1.4. Approval and submission time for MTS 7
3.2. Construction Management 8
3.2.1. Starting construction 8
3.2.2. Construction management 8
3.2.3. Master time schedule verification 9
3.2.4. Construction verification 9
3.2.5. Measuring work 9
3.2.6. Review on special construction methods 10
3.2.7. Review of applied techniques 10
4. Construction Supervision 11
5. Safety Management 11
5.1. Safety Management Organization 11
5.1.1. Duty 11
ii
5.2. Safety Inspection 12
5.2.1. Kinds of safety inspection 12
5.2.2. Methods of safety inspection 12
5.2.3. Inspection item 13
6. Material control 13
6.1. General 13
6.2. Installation Conditional Material 13
7. Quality management 13
7.1. General 13
7.2. Priority Quality Management 14
8. Environmental Countermeasures 14
8.1. Noise and Vibrations 14
8.2. Water Contamination 14
8.3. Land 15
9. Post-Construction 15
iii
List of Tables
iv
List of Figures
v
Guidelines for Substation Construction
1. Scope
This standard covers construction work for the Libyan power system 66/11kV and
30/11kV substations.
2. General
Based on economic development and rapid increases in power demand, additional
substations are required in Libya. In a power system, substations play an important role. If
a breakdown occurs at the substation, it has a serious effect on the rest of the system.
Therefore power quality should be improved by developing advanced equipment and
managing a stable power system. Improving power quality should start with substation
construction, in accordance with process management and quality management.
Considering construction sites in Libya, it is expected that the land security is not difficult
and civil engineering costs have no great effect on the overall construction cost. However,
a smaller area is better for efficient utilization of national land. Based on this, the required
area of each substation type was compared.
Considering future extensions, required area shall be decided according to the final scale
suggested in the long-term system plan. The required area of each type was calculated
assuming the equipment arrangement as shown in GDS 5100.
As shown above, the outdoor AIS requires more than twice the area of the indoor GIS
(based on the 66 kV substations).
Site Selection
Site Acquisition Stage
Permission
Site Purchase
Procurement
Design and Contract Stage
Detail Design
Contract
Construction
Commissioning
Construction and Completion Stage
Energizing
Completion
Review &
Approval
No
Yes <Reference>
GDS
GES
GCS
Construction
5. Safety management
General safety regulation
plan
5.1 Safety management
Diagrams, roles
organization
5.2 Safety meeting Objectives, period, personnel, meeting details
plan
5.3 Construction safety
Safety plan for each phase
plan
5.4 Safety check plan Types, methods and details for safety check
5.5 Safety facilities Facility name and standards, considering
installation plan construction progress
5.6 Individual safeguards
Proper safeguards for each progress
supply plan
5.7 Manpower and
Manpower and equipment for each phase
equipment plan
5.8 Protection plan Risk management protection plan
5.9Emergency manpower
Additional manpower planning
System
6. Quality assurance
plan
6.1 Quality assurance Quality management policy, the purpose, and
plan and procedure organization system
6.2 Quality control plan Plan and procedure
Start Construction
Construction Management
Review of Construction
Special methods Verification
Measuring
Work
(b) The supervisor shall manage that substation construction is completed with good
quality during the construction period.
A. Each result measured by contractor
B. Review detailed schedules for each phase
C. Verification for each stage
3.2.3. Master time schedule verification
(a) The supervisor has to review construction plans submitted by the contractor.
(b) The supervisor has to review the MTS whenever it’s changed.
(c) Construction detail designs should be drawn clearly in order to ensure construction
safety. The supervisor and contractor shall review selected construction detail designs
according to construction conditions.
(d) Don’t permit construction before detailed reviews of drawings.
Field
Construction Contractor’s
technical Submit
examination Supervisor’s
field Announce
examination
completion check request examination result
NO
Re-construction Acceptance
YES
Next stage
Inception
4. Construction Supervision
An objective of supervision is to obtain and supply high quality, stable power through
acquisitions, construction management, safety management and efficient process
management.
5. Safety Management
The purpose of this standard is to present safety rules and methods. Such standards assist
and protect personnel and the general public during substation construction. Safe
construction methods shall be practiced and maintained at all times and on all phases of
work.
6. Material control
6.1. General
(a) For material storage, it is necessary to secure a warehouse and rent a security guard
resident.
(b) A warehouse shall be the proper site to store, load/unload, and avoid corrosion,
deterioration, flooding and so on.
(c) Materials should be always arranged categorically. The security guard or warehouse
clerk shall take great care to prevent theft and damage.
(d) When moving or managing materials, be careful no to damage or lose materials.
7. Quality management
7.1. General
(a) The supervisor shall check whether the contract document, work plan, instructions,
etc. meet with relevant regulations and strictly conform to quality control for each
step of construction.
(b) When inspecting the construction site, the supervisor shall prepare a construction
quality check sheet and add details according to site conditions.
(c) The supervisor shall receive the inspection and test plan from the contractor. The
supervisor will inspect construction procedures according to approved ITP. If the
inspection results violate standards, the supervisor shall manage non-conformance
quality control procedures and take appropriate action.
(d) The supervisor shall meet quality control conditions for regulations, schedules,
procedures and specifications as issued by client.
8. Environmental Countermeasures
8.1. Noise and Vibrations
(a) Noise and vibration during construction should be limited, based on environmental
standards. Equipment (facilities) is needed to reduce noise and vibration.
(b) If complaints are received, quickly take measures as follows:
A. Use low noise, low vibration techniques and machines
B. Adjust or limit working times
C. Install soundproofing walls and materials which absorb vibration
8.3. Land
(a) The land needed for construction is to be minimized. The scope, area and use of the
land shall be approved by land owners and government officials.
(b) When land is damaged, quickly restore it to its original condition.
9. Post-Construction
(a) When closing down a construction site, workers shall rearrange construction site to
its original condition.
(b) When closing down a site a long time before construction work finishes, take special
care not to leave hazards (which could cause accidents) for future users of the land.
(c) The construction site manager shall check the status of readjustments.
A. Clean and rearrange construction site
B. Restore warehouse and material piling sites to their original condition.
Date Site
All workers
② Safety belt who work on
the tower
Tools and
No Pictures and Spec
Equipment
Torque Wrench
Spanner
Wrench
(one side
type)