Introduction

Thank you for purchasing the product of Saki Corporation.


Before using the product, please read this manual carefully together with the supplied manuals to
ensure the prolonged life with the proper handling and the operation of this system.

Notations used in this manual


Notation Meaning
“DANGER” indicates an imminently hazardous situation which could be threat to life or
cause serious injury.
“WARNING” indicates a potentially hazardous situation which could be threat to life or
cause serious injury.
“CAUTION” indicates a potentially hazardous situation which could result in injury or
equipment (including peripheral) damage.

“NOTE” indicates an advice on operation.

Document Disclaimer

• For easier understanding, some of the figures and photographs included in this manual may be slightly different
from the actual objects depicted.
• For improvement and enhancement purposes, the physical appearance and specifications for the product are
subject to change without notice.
• All brand names and product names contained in this manual are trademarks or registered trademarks of their
respective companies.
• Saki Corporation has copyright of all the contents in this manual. No part of this manual may be reproduced into
any form without prior written consent of Saki Corporation, and be used for improper purposes of the Manual.
©2017 Saki Corporation. All Rights Reserved. Printed in Japan.

Saki Corporation X3-Booster Instruction Manual (Original Instructions)

X3-Booster
Introduction

Precautions for Safety

For the safe usage of the product, the items which should be handled with extra care are shown as indications
and symbols listed below.
Please make sure that you understand them well before start using the product.
This machine is designed to comply with the relevant laws of the EC (European Community) for X-Ray
inspection systems.
The machine provides sufficient protection against common hazards if it is used according to the specified
purpose and function.

Ignoring this indication and the wrong handling is extremely dangerous as it may result
DANGER in death or serious injury.
Ignoring this indication and the wrong handling could be threats to life or cause serious
WARNING injury.
Ignoring this indication and the wrong handling could cause personal injury or property
CAUTION damages.

This symbol indicates the prohibition items.

This symbol indicates actions must be taken.

This symbol indicates that touching the items with this symbol could result in personal
injury.

This symbol indicates the potential danger of electric shock.

This symbol indicates that the items with this symbol could be very hot and touching
may result in burns.
This symbol indicates that the items with this symbol generate strong magnetic force
and could be harmful.

This symbol indicates the location of an X-ray radiation unit.

X3-Booster
Introduction

WARNING
To avoid electric shock or fire, and to ensure safety, do not disassemble, repair, or modify
the machine.
The equipment should not be installed in a place subjected to fumes, steam, high humidity,
or dust particles.
Using the system in an environment in violation of the operating conditions described in the
Manual can cause fire or electric shock.
To avoid damage to the cable, the following actions should never be performed: bending the
cord by force, pulling the cord, or placing it near warm heated equipment.
To avoid electric shock or fire, damaged power supply cords, or loose outlets should not be
used.
To avoid electric shock or fire, the voltages higher or lower than the indicated power supply
voltage should not be used.
To avoid electric shock or fire, power supply cords other than those designated should not
be used.
To avoid system malfunction or unexpected accidents, the mounted cover should never be
opened.
Do not cover up the inlet of this machine. And do not insert a foreign substance.
If the inlet is covered up, an inside will be filled with heat and it could cause fire or failure.
To protect the operator from X-ray radiation, lead panels are installed on the machine.
Do not attempt to remove the lead panels.
If the panels need to be removed, please contact Saki Corporation.
The machine has been designed so the X-ray leakage does not exceed 0.5 μSv/h.
Each person can operate the machine for 2000 hours per year (approximately 40 hours per
week). Do not operate the machine for more than 2000 hours in a year.
(The time is calculated according to dose constraints in public exposure (1 mSv per year)
indicated in the 2007 recommendations of the ICRP.)
The machine generates strong magnetic forces.
All persons who may be affected by strong magnetic forces, such as persons wearing
medical implants (e.g., pace makers), do not put the body into the inspection machine.
Otherwise, devices may malfunction or be broken due to the strong magnetic forces.
Lead is a harmful substance.
Although the lead panels are coated, a customer should handle them with care.
Ensure that the local governmentʼs safety relevant rules, regulations, procedures and laws
applied to the operation of X-ray equipments are observed.
Operation, maintenance, and troubleshooting of the machine should be performed by
trained personnel.

Operate the machine with all covers and doors closed.

If water or foreign substances goes inside the machine, first of all, shut off the power supply;
extract the power supply cord and remove the connection cable from the main machine.
Please consult with Saki Corporation or our representatives.

When discarding the machine, comply with local regulations.

X3-Booster
Introduction

CAUTION
This machine is the Inspection System for Printed Circuit Boards.
Do not put objects other than a PCB on the table as it may result in malfunction.
Do not put the machine on a place with much vibration or shock.
Also, do not put it on an unstable place like a shaky table and a leaning place.
Objects should not be placed on the system.
Objects can damage the system exterior and affect the system’s inspection performance.
Objects can fall off the system and cause accidents.
To avoid system malfunction or accidents, operations not described in the operating
instructions should not be performed.
Any problem caused by action in violation of the above item is not covered by the warranty.
In case of lifting this machine, please support firmly by the equipment sole plate.
There is no intensity which can be equal to carrying in a cover.
Ensure that the floor can bear the weight of the machine (approx. 5200 kg) before installation.
Ensure that the four adjustment feet firmly touch the floor after installation.

If the machine needs to be moved, please contact Saki Corporation or our representatives.

Before undertaking any replacement of parts or maintenance servicing, ensure safety by


performing the following procedures:
• To avoid electric shock or fire, turn off the machine and unplug the power supply cord
from the machine.
• To avoid burns or injury, let the electric components and units cool down sufficiently.
Do not put a hand or any object in the driven section during the machine running.
It may result in personal injury.
To avoid malfunction or accidents, do not touch any system internal structure with the
exception of components described in this manual.
Connect the ground lead (to prevent electric shock in the event of current leakage) of the
power plug to one of the following items.
• Ground terminal of the facility power outlet
• Pipe permitted as the grounded object by waterworks department
With the power supply turned on, please do not move the main machine.
It may result in electric shock or personal injury.

To avoid electric shock, do not touch the power supply cord with a wet hand.

X3-Booster
Introduction

Top View

Side View Rear View

Injury can result if fingers or hands are caught between PCB


entrance and exit shutters or Maintenace door..
1 CAUTION Do not touch the unit when the machine is running.
Be sure to turn off the earth leakage breaker of AXI machine before
servicing the unit.

X3-Booster
Introduction

Operation 1 Product Overview and Features ............................... I-2


Table of Contents 1.1 Product Overview ......................................................................I-2
1.2 Features ....................................................................................I-2
1.2.1 System Structure ................................................................I-2
1.2.2 Improving Tact Time ..........................................................I-2
2 Product Configuration ............................................... I-3
2.1 External View ............................................................................I-3
2.2 Name and Function of Each Unit ..............................................I-4
2.2.1 Product External View ........................................................I-4
2.2.2 Internal View.......................................................................I-6
3 Mechanism ................................................................ I-8
3.1 Shutter Mechanism ...................................................................I-8
3.2 Auto Width Adjust Rail Mechanism ...........................................I-8
3.3 Safty Devices ............................................................................I-9
4 Operation ................................................................. I-10
4.1 Emergency Stop ......................................................................I-10
4.1.1 Emergency Stop Switch ...................................................I-10
4.1.2 Releasing Emergency Stop ..............................................I-11
4.2 System Activation ....................................................................I-12
4.3 System Shutdown ...................................................................I-12
4.4 Basic Operation .......................................................................I-12
4.4.1 Touchscreen.....................................................................I-12
4.4.2 How to Open Maintenace Door ........................................I-13
5 Operation Procedure ............................................... I-14
5.1 Basic Operation of BF-X3 Connected X3-Booster ..................I-14
5.1.1 Separation of Capturing Processing and Inspection Processing ...I-14
5.1.2 Stop X-Ray Tube Shutter Operation During Auto Inspection ...I-14
5.1.3 Reading Barcode..............................................................I-15
5.2 Auto Inspection Procedure ......................................................I-16
5.2.1 Auto Inspection Start Procedure ......................................I-16
5.2.2 Auto Inspection Stop Procedure.......................................I-16
5.2.3 Error Occurrence and Recovery Procedure .....................I-16
Maintenance 1 Troubleshooting .......................................................II-2
Table of Contents 1.1 Error/Warning Message ...........................................................II-2

X3-Booster
Introduction

Installation / 1 Machine Installation ...............................................III-2


Customer Support 1.1 Tools Required in the Installation Process ..............................III-2
Table of Contents 1.2 Unpacking and Installing the Machine .....................................III-3
1.2.1 Items to be Verified at Unpacking ....................................III-3
1.2.2 Space for Maintenance Door Opening .............................III-3
2 Maintenance and Service .......................................III-4
2.1 Maintenance and Service ........................................................III-4
2.1.1 After Sales Service ...........................................................III-4
2.1.2 Product Warranty .............................................................III-4
2.1.3 Maintenance Check Service.............................................III-4
2.1.4 Others...............................................................................III-4
2.2 Customer Support Contacts ....................................................III-5
3 Terms and Conditions for Technical Service .........III-6

X3-Booster
Operation

Operation

X3-Booster

I-1
Operation

1 Product Overview and Features


1.1 Product Overview
This machine features the tact time improvement conveyor unit connectable to Saki’s X-Ray inspection
machine, such as BF-X3.

1.2 Features

1.2.1 System Structure


• Connect X3-Booster to the forward and backward of BF-X3, all control is performed from the X-Ray
inspection machine and it operates as one machine.
• This machine is not equipped with an X-Ray irradiation device. Even if it is connected to BF-X3,
this machine is designed to comply with the relevant laws of the EC (European Community) for
X-Ray inspection systems.

1.2.2 Improving Tact Time


• When production by BF-X3 alone, the opening and closing of the X-Ray tube shutter was necessary
at the time of loading and unloading the PCBs, the loss time occurred.
But X3-Booster is connected, because of using both loading / unloading shutter and internal
shutters to loading and unloading of PCBs, able to loading and unloading even during X-Ray
irradiation. And pCT inspection can be executed at the time of loading and unloading the PCBs,
productivity can be improved.

X3-Booster

I-2
Operation

2 Product Configuration
2.1 External View

(2250 mm)
840 mm
317 mm
797 mm 797 mm

Top View

(2308 mm)
1127 mm

(3394 mm)

Front View Side View

Rear View
Figure 2-1 External View

X3-Booster

I-3
Operation

2.2 Name and Function of Each Unit


This section describes the name and function of each unit.

2.2.1 Product External View


Here illustrates and describes the external view of the machine and the function of each unit.

㻹㻯㻜㻝

㻸㼁㻜㻟

㻿㼃㻞㻞
Front Side
㻹㻯㻜㻞
(Close)

㻹㻯㻜㻝

㻸㼁㻜㻟

㻿㼃㻞㻞

㻹㻯㻜㻞 Front Side


(Open)

Figure 2-2 Product External View


X3-Booster

I-4
Operation

No. Name Function


When need to maintenace the units, access from this door.
MC01 Maintenance Door Normally locked.
It is necessary to unlock to open this door.
Load and unload the PCBs from this shutter.
MC02 PCB Load / Unload Shutter
A shutter is for prevent from exposure to X-Rays.
Indicates the locked state of the maintenance door by lamp lighting.
LU03 Door Lock Status Lamp
When maintenance door is locked, lamp is lighting.
When the machine needs emergency stop, push this switch to stop
inspection at once.
SW22 Emergency Stop Switch EMERGENCY STOP indicates the emergency stop switch.
The emergency stop switch is interlocked with the BF-X3 and when
pressed, BF-X3 also enters an emergency stop condition.

Table 2-1 Name and Function of Each Unit (Product External View)

X3-Booster

I-5
Operation

2.2.2 Internal View


Here illustrates and describes the position and function of each unit of the internal machine.

SN50
MT12

MT14

MT13 SN48 SN49


Conveyor Assembly

SM03
PB01 DM03
PB01-1 SM02

SI01 DM02

SI02 SM01

SI03 DM01

DO01 SR03

SO01 SR02

SR01 SN50

TB24 SN49

CB36 SW26

CB37 TB26

TB25 Electrical Components CB38

SW23

SW47-2

SW47-1

SW24

SW26-2

SW26-1

SW25

SN46

CY16

Front Side

PCB Entrance and Exit Details


Figure 2-3 Internal View
X3-Booster

I-6
Operation

No. Name Function


Shuts off the circuit when excessive current flows.
CB36 Circuit Breaker
The current rating is 3 [A]. [SJEC1C019]
Shuts off the circuit when excessive current flows.
CB37 Circuit Breaker
The current rating is 10 [A]. [SJEC1C022]
Shuts off the circuit when excessive current flows.
CB38 Circuit Breaker
The current rating is 10 [A]. [SJEC1C017]
CY16 Shutter Cylinder Cylinder which brings the shutter up/down. [SJAS2A060]
PB01 Power Link Bus Controller Sub PLC modules. [SJEC1R017]
PB01-1 Splitter Modules to distribute 24V. [SJEC1R026]
SI01
Input modules for safety circuits.
SI02 Safety Circuit Digital Input
[SJEC1R028]
SI03
SO01 Safety Circuit Digital Output Output modules for safety circuits. [SJEC1R031]
DO01 Digital Output Output modules. [SJEC1R024]
DM01
Dummy modules.
DM02 Dummy
[SJEC1R034]
DM03
SM01 Driver modules for the PCB conveyor motor and width adjustment
SM02 Stepping Motor Driver motor.
SM03 [SJEC1R030]
SR01
Relays for the safety circuit.
SR02 Safety Relay
[SJEC1R027]
SR03
TB24
TB25 Terminal Block Connection parts for wiring.
TB26
SN46 Shutter Sensor The sensor that detect when the shutter is opened. [SJSS1R001]
Shutter Pinching Prevention The sensor that detect when the shutter is pinched.
SN47-1/2
Sensor (1:Transmitter 2:Receiver) [SJ34EH008]
The sensor that detect loading (when the flow direction is left to
Left Side Sensor/Sensor right)/unloading (when the flow direction is right to left) of a PCB.
SN49
Amplifier Sensor Amplifier : [SJ34EH002]
Fiber Sensor : [SJSS5K006]
The sensor that detect loading (when the flow direction is right to
Right Side Sensor/Sensor left)/unloading (when the flow direction is left to right) of a PCB.
SN50
Amplifier Sensor Amplifier : [SJ34EH003]
Fiber Sensor : [SJSS5K006]
The switch to detect the maintenance door opening/closing.
SW23 Maintenance Door Switch When the maintenance door is closed, the interlock activates.
[SJEC1S054]
The switch to detect the maintenance door opening/closing.
Maintenance Door Switch
SW24 When the maintenance door is closed, the interlock activates.
(Interlock)
[SJ34EH009]
The sensor that detect when the shutter is physically closed.
SW25 Shutter Switch
When close the shutter, the interlock will operate. [SJ34EH007]
The sensor that detect whether a hand or an object is caught in the
inlet and outlet of PCB.
SW26 Area Sensor
Sensor Amplifier : [SJ34EH001]
Fiber Sensor : [SJ00PE277]

Table 2-2 Name and Function of Each Unit (Internal View)

X3-Booster

I-7
Operation

3 Mechanism
3.1 Shutter Mechanism
This section illustrates and describes the positions of X-Ray exposure prevention shutter of BF-X3 and X3-Booster.
Each shutters are controlled optimally to tact time becomes the shortest during production operation.
To prevent X-Ray exposure, the left and right units of inner shutter (L or R) and the loading (unloading) shutter are
controlled either one is always closed.

X-Ray Tube

X-Ray Tube Shutter

Inner Shutter L Inner Shutter R

Loading Shutter Unloading Shutter


(Unloading) (Loading)

Display on
Touchscreen

Figure 3-1 Shutter Mechanism

3.2 Auto Width Adjust Rail Mechanism


The X3-Booster conveyor is equipped auto width adjustment rail mechanism, and it works in conjunction with the
conveyor of BF-X3.
When performing automatic width adjustment, it is necessary that no PCBs remain inside of BF-X3 and X3-Booster.
If automatic width adjustment is performed while the PCB remains, an error message is displayed and stops.
Impossible to change the width only for the X3-Booster conveyor. Always three conveyors
synchronization adjustment.

Figure 3-2 Auto Width Adjust Rail Mechanism


X3-Booster

I-8
Operation

3.3 Safty Devices


X3-Booster has the following three safety devices equipped.
No. Item Description
Cuts off the energization of all motors of the conveyor when the BF-X3 is
judged to be abnormal.
1 Mechanism Safety Device
Every units that the BF-X3 displays an error message is the target.
e.g., When opening the upper door, the motors of the conveyor turns off.
Safety device that instructs the BF-X3 not to generate X-Rays when the
2 X-Ray Safety Device
loading / unloading shutter or maintenance door is open.
In conjunction with the emergency stop switch of the BF-X3, perform the
following operation.
3 Emergency Stop Switch
[1] Stop processing X3-Booster, stop processing and 1 and 2 above
[2] Cuts off power source of loading / unloading shutter of X3-Booster

Table 3-1 Safty Devices

X3-Booster

I-9
Operation

4 Operation
4.1 Emergency Stop
The emergency stop switches on the X3-Booster, perform same as BF-X3.

4.1.1 Emergency Stop Switch


The machine has emergency stop switches for safety, especially to prevent injury at the operating
area or material damage.
Emergency stop switch locate on the top of each unit.
When the front door is opened, the machine does the emergency stop.

Push the emergency stop switch in case that the machine is in an emergency situation.
The dialog shown in Figure 4-2 appears. Beep tones sound and the motor stops immediately.
X-ray radiation and system operation will be suspended.

Emergency Stop Switch Touchscreen Emergency Stop Switch Emergency Stop Switch

Rear View

M E R GE Release
E

N
CY

Emergency Stop Switch

Reset Switch

Push
Emergency Stop Switch

Figure 4-1 Reset Switch and Emergency Stop Switch

Figure 4-2 Emergency Stop Mode

X3-Booster

I-10
Operation

4.1.2 Releasing Emergency Stop


Step1: Turn the emergency stop switch to the direction indicated in Figure 4-1 (clockwise) to
release the emergency stop switch.

Step2: Push the reset switch. Beep tones stop.

Step3: Click OK in the dialog shown in Figure 4-2.

Step4: The dialog shown below appears on the touchscreen. Press Lock.

Figure 4-3 Releasing Emergency Stop 1

Step5: The dialog shown below appears. Press Start to initialize the system.

Figure 4-4 Releasing Emergency Stop 2

X3-Booster

I-11
Operation

4.2 System Activation


Starts up in conjunction with activation of BF-X3. For details, refer to BF-X3 Instruction Manual.

4.3 System Shutdown


Shuts down in conjunction with shutdown of BF-X3. For details, refer to BF-X3 Instruction Manual.

4.4 Basic Operation


All operations are performed from Touchscreen of BF-X3.

4.4.1 Touchscreen
Here describes the Touchscreen items related to X3-Booster.

Figure 4-5 Touchscreen

Item Description
Indicates the presence of PCBs inside BF-X3 and X3-Booster.

BF-X3
Left Side Right Side
X3-Booster X3-Booster

Figure 4-6 Display on Touchscreen


Icon changes with status.
PCB exist No PCB Unknown

Displays the shutter state of the BF-X3 and X3-Booster.


For detail location, refer to 3.1 Shutter Mechanism.

Shutter Closed Shutter Opened

Displays the status of X-Ray irradiation.

Irradiable During irradiation Irradiation impossible

Displays the status of communication establishment with BF2 inspection software.

Communicating Not communicating

Table 4-1 Touchscreen

X3-Booster

I-12
Operation

4.4.2 How to Open Maintenace Door


The maintenance door is normally locked. When opening / closing, necessary to perform the unlocking
operation.
Step1: Press Unlock on the Touchscreen

Figure 4-7 Unlock

Step2: Grasp the Maintenance Door handle and open.

Handle

Figure 4-8 Maintenance Door

X3-Booster

I-13
Operation

5 Operation Procedure
5.1 Basic Operation of BF-X3 Connected X3-Booster

5.1.1 Separation of Capturing Processing and Inspection Processing


Only the BF-X3 inspection operation was shown in Figure 5-1, and a delay occurred in processing.
When X3-Booster is connected, it shown in Figure 5-2, the processing schedule is changed and it is
speeded up.

Load Unlo
Capture
pCT Inspection

Figure 5-1 Inspection Schedule (BF-X3 Only)

Load Unload Load Unload Loa


Capture Capture
pCT Inspection

Figure 5-2 Inspection Schedule (BF-X3 Connected X3-Booster)

5.1.2 Stop X-Ray Tube Shutter Operation During Auto Inspection


Opening and closing of the X-Ray Tube Shutter as described below was required in the BF-X3 stand
alone inspection.
When X3-Booster is connected, use conventional loading and unloading shutters as inner shutters
and deactivate the X-Ray Tube Shutter, it is possible to load and unload PCBs during X-Ray irradiation.

BF-X3 Only Loading (Shutter Open > Loading PCB > Shutter Close)
Unloading (Shutter Open > Unloading PCB > Shutter Close)
X3-Booster Connected Loading (Loading procedure only)
Unloading (Unloading procedure only

Figure 5-3 BF-X3 Only

Figure 5-4 X3-Booster Coonected

X3-Booster

I-14
Operation

5.1.3 Reading Barcode


When X3-Booster is connected, the tact time will be controlled to be the shortest.
The correspondence with the barcode reader will cause a time lag occured from reading to processing
as shown below.
The inspection result of the bar code that is read becomes the timing (the position of the orange
arrow) taken out from the exit conveyor and is output after 4 time lags.
The inspection result of the barcode is fixed at the timing (the position of the blue arrow) of unload
from X3-Booster (Unloading Unit). Output barcode timing is after four PCBs.

Barcode X3-Booster BF-X3 X3-Booster


Barcode Reader Conveyor (loading Unit) (Unloading Unit)

PCB Barcode

PCB Direction

Scan (effectiveCode) 002 001


Inspect (manageCode) 001

㻺㼑㼣
Barcode Que 004
003
002
001 Removed
㻻㼘㼐

Figure 5-5 Reading Barcode

In case of misalignment of barcode, such as breakage of PCB (transport errors and etc...),
Necessary to remove the all PCBs in the BF-X3 and X3-Booster and re-inspection.

X3-Booster

I-15
Operation

5.2 Auto Inspection Procedure


This section describes how to operate the X-Ray inspection. For details of BF2 inspection software operation,
refer to BF-X3 Instruction Manual and AXI Programming Manual.

5.2.1 Auto Inspection Start Procedure


Step1: Check that no PCBs remain inside of X3-Booster and barcode conveyor.

Step2: Click Start button on the BF2 inspection software to start auto inspection.

Step3: Automatically adjust the conveyor rail width at only for the first time.

Step4: When the conveyor rail width adjustment is completed, the PCB is loaded into the barcode
conveyor and auto inspection is started.

5.2.2 Auto Inspection Stop Procedure


Step1: Check that no PCBs remain inside of BF-X3 and X3-Booster.

The inspection of the last PCB may not be completed.

Step2: Click Stop button on the BF2 inspection software.

5.2.3 Error Occurrence and Recovery Procedure


If a transport error occurs, BF-X3 moves to STOP mode and the auto inspection is interrupted.
At this time, there may be some discrepancies in barcode management.
If an error occurs, remove all PCBs in the BF-X3 and X3-Booster and resume production.

Step1: Follow the error message and correct the cause of the error.

Step2: Remove all PCBs in the BF-X3 and X3-Booster.

Step3: Follow the 5.2.1 Auto Inspection Start Procedure and resume production.

X3-Booster

I-16
Maintenance

Maintenance

X3-Booster

II-1
Maintenance

1 Troubleshooting
This chapter describes actions need to be taken if the machine fails to operate properly or messages/
warnings are displayed on the software window.

1.1 Error/Warning Message


This section describes error/warning messages and recovery methods.
Error and warning messages are displayed if the software cannot make judgements and human intervention
is required when selecting the inspection data or starting/quitting the inspection software.
In the table below, the contents of error, warning messages, and the action needs to be taken are listed.
Before checking and executing these items, the following two points must be observed.

• No PCBs remain inside of BF-X3 and X3-Booster.


• The all doors and external covers are closed.

No. Error/Warning Message Description and Recovery Method


Maintenance door of X3-Booster is not locked.
If the maintenance door of X3-Booster can not lock or open, the
4 Door is not Locked
message will be displayed. Close the maintenance door and
restart.
The shutter pinch damage prevention function is activated at the
20 C1C2Crash guard detection previous or next of the X3-Booster.
Remove the pinched objects and restart.
Even if BF-X3's conveyor and X3-Booster's conveyor operated for
more than specified time, BF-X3 could not move to the next
317 Timeout of Conveyer move motion.
This error occurs when stuck due to the PCB or objects.
Remove the cause and restart.
The entrance shutter does not completed within the specified time.
320 Timeout of Entrance shutter move This error occurs when air pressure is low or damage of shutter.
Check the aire pressure or shutter.
The exit shutter does not completed within the specified time.
321 Timeout of Exit shutter move This error occurs when air pressure is low or damage of shutter.
Check the aire pressure or shutter.
Communication with the PC has been interrupted for at least the
specified time.
347 Timeout of PC Heart Beat. This error occurs when PC is hunged up.
Restart the BF2 inspection software.
When this error occurs, X-Ray is forcibly turned OFF for safety.

Table 1-1 Error/Warning Messages and Recovery Methods

X3-Booster

II-2
Installation / Customer Support

Installation / Customer Support

Installation/Customer Support

X3-Booster

III-1
Installation / Customer Support

1 Machine Installation
This chapter describes installation procedures.
Please contact Saki corporation for installation and relocation.
Since it is a device handling X-Rays, proper work is necessary.

Check that the outlet FG terminal at the factory equipment is properly grounded at the installation.

Check that time and time zone are set correctly when activating the PC.

1.1 Tools Required in the Installation Process


These are commonly used tools that should be on hand for installation.
These tools will also be required during machine maintenance or adjustment.

Item Usage Purpose and Description

Hex Wrench
For attaching and detaching external covers,
attaching internal parts, and performing adjustments.
N 2
No.2

Phillips Screw
Driver N 1
No.1

Precision
For attaching internal parts and adjusting sensors.
Screw Driver

Monkey For rotating the leveling pad located underneath of


Wrench the machine, as adjusting the level of the machine.

Bubble Leveler For checking the levelness of the machine.


m/1m (4SEC)
1DIV=0.02mm

OFF ON DATA RANGE DC/AC

POWER ࣮ HOLD ࣮

DCAC DCAC
V Ω 200mA 12A

Electrical Tester V
MAX DC1000V
MAX AC750V
For checking I/O signals and voltages.
Ω
200mA 12A
COM (FUSED 0.5A) (UNFUSED)
MAX 250V MAX 200mA MAX 12A

Table 1-1 Tools Required in the Installation Process

X3-Booster

III-2
Installation / Customer Support

1.2 Unpacking and Installing the Machine

1.2.1 Items to be Verified at Unpacking


Most of accessories are packed inside of the machine or already connected to the machine.
The signal tower is connected but not assembled to the machine. Assemble it after unpacking.
Before starting installation, check the items.
If any damaged or missing items are found, please contact Saki Corporation.

No. Item Qty


1 Conveyor Units (Entrance and Exit Units) 1 each
2 This Manual 1
3 Work Conveyor Belt (Spare) [SJMC6B066] 4

Table 1-2 Items to be Verified at Unpacking

1.2.2 Space for Maintenance Door Opening


For the maintenance of the X3-Booster, secure the space for maintenance door opening and for
accessing the electrical components.
200 mm

200 mm

52 mm
Top View Side View

Figure 1-1 Space for Maintenance Door Opening

X3-Booster

III-3
Installation / Customer Support

2 Maintenance and Service


2.1 Maintenance and Service
If some adjustment or technical support becomes necessary, replacement parts are required, or technical
questions arise, please contact Saki Corporation. In such case, please check the situation in detail including
when and how it occurred and state the following items.
• Model Name
• Serial Number
• Condition in Detail
• Date of Purchase

2.1.1 After Sales Service


Installation
Saki service representatives carry out installation at delivery.
Transportation of the product or changing the site of the product after the delivery will be charged.
Be sure to contact us in order to avoid troubles caused by the transportation.

Repairs
Saki Corporation can provide repair services at customer site. Our representatives or Saki
Corporation’s service representatives will visit customer’s factory to provide repair services on site.

2.1.2 Product Warranty


We provide the guarantee of this product according to the specification sheet.
Notwithstanding the warranty period, there might be cases that we cannot provide the maintenance
service or provide with charges, for example in case of aging of consumable parts, resale of this
product, any trouble caused by unauthorized alter, force major, or other reasons not attributable to
us.
Please refer to and confirm the specification sheet for the details.
2.1.3 Maintenance Check Service
To ensure the safe operation of this product, additional maintenance check services are provided.
For further inquiries, please contact Saki Corporation.

2.1.4 Others
Property Rights of the Replacement Parts
The old parts replaced by the repair and necessary for the investigation become our property, so
please be forewarned.

Holding Period of the Maintenance Parts


Basically, replacement parts (required to maintain product function) will be kept in stock for at least 5
years after termination of production. Please note that the product may not be repaired even during
this period, depending on the malfunctioning parts due to a shortage of those parts.
Depending on the nature of the required repairs, it may still be possible to repair your product even
after this period. Please contact our representatives or Saki Corporation.

X3-Booster

III-4
Installation / Customer Support

2.2 Customer Support Contacts

Company Name Saki Corporation


Address Ogawa Building, 4-14-7, Nakanobu, Shinagawa-Ku, Tokyo 142-0053, Japan
URL http://www.sakicorp.com/
Inquiry about the products +81-(0)3-5788-6286
Phone
Inquiry about the technical service +81-(0)3-5788-6287

X3-Booster

III-5
Installation / Customer Support

3 Terms and Conditions for Technical Service


Article 1 (Purpose) (4) To acknowledge that there is a possibility that the Remote Monitoring is (10) to insert the service key which unlocks the interlock of the Product
This terms and conditions (hereinafter “Terms and Conditions” ) is to not be able to use due to the situation of the Product, the system option (hereinafter “Service Key” ) at the time of being provided the Remote
stipulate the agreement between Customer and SAKI about the services to connected to the Product, or the internet connection, Monitoring, and
maintain normal action and operation of the objective equipment and its (5) To manage the information which is sent from SAKI by an e-mail to use (11) to have any third party make activities defined in each previous
system option which Saki Corporation or its related company (hereinafter the Monitoring System (hereinafter “Login Information” ) under its own paragraph.
“SAKI” ) sales (hereinafter “Product” ).Customer may use the Product only responsibility, and Article 17 (Indemnities)
in case agrees with this Terms and Conditions. (6) To use the Monitoring System under its own responsibility, and to If the events defined in following each paragraph should occur, SAKI shall
Article 2 (Definition) indemnify and hold SAKI and its related companies harmless from and be released from the duty of providing the Service and compensating any
The definition of each service menus which SAKI provides are as below; against all claims, losses, liabilities or obligations arising as a result of damages occurring on Customer by each event, or any and all other duties.
(1) Hardware Periodical Maintenance such use/ inoperative of the Monitoring System, lose of data due to (1) In the event that Customer should make the prohibited activities defined
Service in relation to periodical check for the objective hardware of the computer virus, and any other damage occurred including (3), (4), and in the previous Article,
Product (hereinafter “Objective Hardware” ) written on the Individual (5) of this Article above. (2) In the event that the installation condition of the Product defined in the
Contract. (7) SAKI may introduce antivirus software based on the Customer’ s Article 11 should not be met,
(2) Software Periodical Maintenance request. In case Customer uses any antivirus software, Customer shall (3) Trouble, damage etc, caused by the change of installation site or
Service in relation to periodical check for the software of the Product use and maintain any antivirus software and the Product which antivirus removal of the Product after its delivery,
(including the Fare-paying Software of (8) of this Article, hereinafter software is installed under its own liability and SAKI shall not have any (4) Trouble, damage etc, caused to consumable parts of the Project,
“Objective Software” ). obligation to guarantee certain and collect operation of such antivirus (5) Trouble, damage, etc, caused by or related to any device other than the
(3) On-call Service software and the Product which antivirus software is installed. Product,
Service in relation to a survey, checkup, and maintenance of the Product Article 7 (Charge for Maintenance Service) (6) Trouble, damage, etc, caused by stolen or loss,
or the system option connected to the Product which is not included in The terms of the payment from Customer to SAKI shall be stipulated in the (7) In the event that Customer should decompose or repair the Product or
the (1) and (2) above and provided over a phone. Individual Contract. replace the parts thereof without permission from SAKI,
(4) On-line Service 2. The charge for the Service shall not refund for any reason whatsoever. (8) Trouble, damage etc, caused by use or inoperative of the Product,
Service in relation to a survey, checkup, and maintenance of the Product 3. SAKI may change the charge of the Service considering the market (9) Trouble, damage etc, caused by using the Objective Software together
or the system option connected to the Product which is not included in situation, economic situation, commodity price and the like. with any other software,
the (1) and (2) above and provided by monitoring or remote controlling Article 8 (Customer Expense) (10) Trouble, damage, etc, caused by computer virus,
the Product, the system option connected to the Product, other Customer shall burden the costs as below other than the charge stipulated (11) Trouble, damage etc, caused by making change or update of the
electronic devices and the like (hereinafter “Connection Media” ) through in the preceding Article. BIOS, drivers, or OS without a confirmation by SAKI,
the system which SAKI indicates (hereinafter “Remote System” ) to (1) electricity and water rates (12) Trouble, damage etc, caused by operation in any environment other
show how to use the Product or the system option connected to the (2) cost occurred related to any communication device (including phone, the than the recommended environment of the Product,
Product (hereinafter “Remote Monitoring” ). Connection Media, and the like), and an internet connection (13) In case any and all data which the Objective Software outputs are lost,
(5) On-site Service (3) parts price (excluding the selling of (9)Service Parts of Article 2 ) and the (14) In the event that Customer should commit any breach of instructions
Service in relation to a survey, checkup, and maintenance of the Product its transportation cost for use and for handling of the Product defined by SAKI,
or the system option connected to the Product which is not included in Article 9 (Title of Exchanged parts) (15) In the event of force major such as fire, earthquake, lightning strike,
the (1) and (2) above and provided by visiting the Instillation site of the The title of the faulty parts which are exchanged through the Periodical wind and flood damage, gas damage, salt damage, and other act of
Product and the system option connected to the Product when SAKI Maintenance and the Technical Support shall belong to SAKI. providence, war, armed conflict, etc occurs,
assumes the trouble is not able to be solved only with (3) and (4) above. Article 10 (Reconsignment) (16) Trouble, damage, etc, caused on the Product by the events which are
(6) Training SAKI may consign all or a part of the Service to any third party with other than the events defined in each previous paragraph and not for
The service in relation to give explanation, instruction, and teach how to notification to Customer. reasons attributable to SAKI, and
use the Product or the system option connected to the Product through Article 11 (Maintenance of Installation Condition) (17) In the event any defect is found or any trouble or damage occurs after
the Remote Monitoring, teaching video (DVD), or at the place where Customer shall always adjust and maintain the installation condition of the the term or termination of the period stipulated in the Individual Contract.
SAKI indicates. Product to meet the condition defined in instructions for handling (e.g. Article 18 (Data Save)
(7) Inspection Data Support power sources, temperature, humidity, vibrations, magnetisms, saltiness, Customer shall acknowledge that inspection data or other data may be lost
The service in relation to a support to make the inspection data of the grounding conditions, etc.). by a certain trouble or damage, and shall try to save data at new creation
Product through the Remote Monitoring, or at the place where SAKI Article 12 (Objective Software) and every updating under its responsibility. SAKI shall not be liable for the
indicates. Customer may use the Objective Software only for the appropriate use of responsibility about such loss of data.
(8) Fare-paying Software the Objective Hardware and this License of use of the Objective Software Article 19 (Cancellation of Agreement)
Selling of the fare-paying software which SAKI provides. shall be non-exclusive and non-assignable license. In case the other party corresponds to one of the following each paragraph,
(9) Service Parts 2. The Copyright of the Objective Software and any output made through either party may have the right to immediately cancel the Individual
Selling of the service parts which SAKI provides. the Objective Software shall be owned by SAKI, and Customer shall not Contract without requiring any notice regardless of the preceding article;
2. The service (1) and (2) above shall be referred to as “Periodical be granted the Copyright nor other rights. Saki shall not provide any (1) In case the other party breaches one of the paragraphs stipulated in this
Maintenance” and the service (3), (4), and (5) above shall be referred to guarantee that the Objective Software does not infringe any third parties’ terms and condition and does not correct the breach in spite of the notice
as “Technical Support” and the service from (1) to (9) above shall be right including but not limited to the copyright and the like. defining the reasonable period
referred to as “Service” in this Terms and Conditions. 3. SAKI may modify specifications or contents, and alter distribution method (2) In case the other party is subjected to punishment for revoking or
3. The details, such as contents of the Periodical Maintenance, charge and of Objective Software without making any prior notice to and without suspending business by the supervisory authorities
so on, shall be stipulated separately by SAKI. obtaining agreement with Customer. This terms and condition shall also (3) In case the other party suspends payment, or is subjected to
4. Individual service menu which SAKI provides to Customer shall be be applicable to the software produced by modifying specifications or punishment for dishonor of the clearinghouse
stipulated in the individual contract which is completed by the fact that contents and altering distribution method of the Objective Software. (4) In case the other party is subjected to attachment, provisional
Customer issues an order to SAKI in a manner predefined by SAKI and 4. In case trouble, damage etc, are caused by updating, adding of function attachment, provisional disposition, compulsory execution, and the like
SAKI accepts the order (hereinafter “Individual Contract” ). and the like to the Objective Software by SAKI, SAKI shall restore it by any third parties
5. Customer shall agree that (a) providing the Periodical Maintenance and before updating, adding of function and the like. Next action after the (5) In case the other party offers or makes a procedure for bankruptcy,
the Technical Support does not guarantee prompt response from SAKI, restoration shall be decided through mutual consultation between company liquidation, special liquidation, civil rehabilitation or corporate
entire operation of the Product, or entire recovery of troubles, and (b) the Customer and SAKI. reorganization, or any grounds causing these events arise
inspection data which is made thorough (6) Training and (7) Inspection Article 13 (Cooperation) (6) In case the other party passes a resolution for dissolution, or institutes a
Data Support above does not guarantee the accuracy of the inspection Customer shall agree following terms to be provided the Service smoothly significant change in the other management structures, and
and its improvement. by SAKI. (7) In case Customer relocate the Product more than 50 km from the
Article 3 (Periodical Maintenance) (1) to do the maintenance which is stipulated to be done by Customer in the Installation site in the Individual Contract.
In case Customer purchases the Periodical Maintenance in the Individual appendix 2. In case the Agreements is cancelled according to the preceding article,
Contract, SAKI shall visit Customer once per 6 months to provide the (2) to keep the log book of the Product and disclose the log book when either party may make a claim for damages incurred thereby against the
Periodical Maintenance during the term as written in the Individual Contract. SAKI requires other party.
One visit shall 8 hours at the maximum and its schedule shall be informed (3) to try its best effort to organize the circumstances so that SAKI is able to 3. In case the Individual Contract is canceled or expired for any reasons,
by SAKI to Customer one month before and decided through mutual access the Product and other external network freely during SAKI’ s Article 12, Article 14, Article 15, Article 16, Article 17, Article 20, Article
consultation between Customer and SAKI. performance of the Service 21, Article 22, Article 23, and Article 24 shall survive and be still valid.
Article 4 (Reception time and service time for On-call Service and On-line Service) (4) to try its best effort to assign Customer’ s employee who is familiar with Article 20 (Maintenance of Confidentiality)
The reception time and service time for the On-call Service and On-line the Product as the window person for the Service and Customer shall not disclose or leak any SAKI’ s trade or technical secrets
Service shall be as below. However, in case of Saturday, Sunday, national (5) (in case the Product is X-ray product) to recognize the Product shall which are knowable in relation to the Product, Individual Contract, or this
holiday or other date which SAKI indicates as holiday, SAKI shall not have checked periodically by the qualified person according to the legal Terms and Conditions to any third party during and after the period of the
provide the On-call Service. standard and cooperate with its check Individual Contract.
Reception time: From Monday to Friday AM 9:00 to PM 5:00 (time of Article 14 (Information) Article 21 (Liability)
the place where SAKI(who provide the Service)’ s office is located) SAKI may collect, use, process, store, and utilize the information which In any case, the maximum amount which SAKI burdens shall not exceed
Service time: From Monday to Friday AM 9:00 to PM 5:00 (time of the SAKI obtains from Customer through the execution of the Service according the purchase price of the Product which causes the damage.
place where SAKI(who provide the Service)’ s office is located) to the Privacy Policy to improve and enhance SAKI’ s Product including the 2. SAKI shall not burden any liability of trouble and damage caused on an
2. In case Customer requests SAKI to provide the On-call Service or Service. object other than the Product, indirect damage such as manufacturing
On-line Service at the time other than the date and time of preceding Article 15 (Beta Service) loss, and the like.
section, this request shall be assumed as the request received in the SAKI may make available a “beta” version of the Service (hereinafter “Beta 3. Except for the extent that by statute liability may not lawfully be excluded,
next working day by SAKI, and SAKI shall provide the On-call Service or Service” ) for evaluation and feedback by third parties. In case Customer the whole liability which SAKI shall incur related to the Individual Contract
On-line Service in the time stipulated in the preceding section of the next requests the Beta Service, Customer shall agree with the following terms; and the Product shall be what is written specifically in this Terms and
working day. However, in case SAKI judges the degree of importance (1) Not to use the Beta Service for the purpose other than the evaluation Conditions. SAKI, directly and indirectly, shall not be liable for any other
and urgency is high, SAKI may provide the On-call Service or On-line and feedback, matters against Customer.
Service at the time other than the preceding section with the additional (2) To agree that Beta Service may contain bugs, errors, and other Article 22 (Jurisdiction)
charge as stipulated in the appendix. problems, use the Beta Service with the care of a good manager, and not As to any legal dispute arising with respect to the Individual Contract and
Article 5 (Reception time and service time for On-site Service) to claim the damages which are occurred due to the Beta Service against this Terms and Conditions, the Tokyo District Court shall be designated as
The reception time and service time for the On-site Service shall be as SAKI, an exclusive agreement jurisdictional court of the first trial.
below. The fee for the On-site Service is as stipulated in the appendix. (3) Not to use the Beta Service for illegal purpose, or other purpose which Article 23 (Consultation and Resolution)
However, in case of Saturday, Sunday, national holiday or other date which would cause trouble or other damage against a third party’ s Matters arising any questions relating to this Terms and Conditions and the
SAKI indicates as holiday, SAKI shall not provide the On-site Service. tangible/intangible property, and Individual Contract and matters not provided for in this Terms and
Reception time: From Monday to Friday AM 9:00 to PM 5:00 (time of (4) To provide all of the data and feedback of test and evaluation of the Conditions and the Individual Contract shall be resolved through mutual
the place where SAKI(who provide the Service)’ s office is located) Beta Service to SAKI for free of charge. consultation between Customer and SAKI.
Service time: From Monday to Friday AM 9:00 to PM 5:00 (time of the Article 16 (Prohibited Activities) Article 24 (Jurisdiction)
place where SAKI(who provide the Service)’ s office is located) Customer shall not make any activities defined in following each paragraph. As to any legal dispute arising with respect to this This Terms and
2. In case SAKI judges the degree of importance and urgency of a trouble is (1) to alter the Objective Hardware Conditions and the Individual Contract, the Tokyo District Court shall be
high, SAKI may provide the On-site Service at the date and time other (2) to repair, alter, or decompose the Objective Hardware or replace the designated as an exclusive agreement jurisdictional court of the first trial.
than the date and time of preceding section with the additional charge as parts thereof unjustly Article 25 (Entire Agreement)
stipulated in the appendix. In case SAKI provides the On-site Service on (3) to rent, lease, or transfer the Objective Hardware to any third party This Terms and Conditions supersedes and cancels any and all previous
the several time blocks stipulated in the appendix, only the highest without permission from SAKI agreements, contracts or understandings between the parties relating to the
Accommodation fee and Allowance shall be applied. (4) to copy or alter a part or all of the Objective Software Product, the Service and expresses the complete and final agreement of
Article 6 (Remote Monitoring) (5) to use the Objective Software outside the scope of the license defined in the parties in respect thereof.
Customer shall agree the following terms to be provided the Remote Clause 1 of Article 12 Article 26 (Severability)
Monitoring; (6) to install and use the Objective Software in other products which is out
(1) To follow all the terms of service and other rules which the third party In any provision or any portion of any provision of this Terms and
of this Terms and Conditions Conditions shall be held to be void or unenforceable, the remaining
who provides the Remote System stipulates, (7) to rent, lease, transfer or re-license the Objective Software to any third
(2) To prepare the Connection Media and an internet connection which are provisions of this Terms and Conditions and the remaining portion of any
party without permission from SAKI provision held void or enforceable in part shall continue in full force and
necessary for the Remote Monitoring by its own cost and responsibility, (8) to try to analyze, change the source code of the Objective Software and
(3) To acknowledge that there is a possibility that any wrong function and effect.
the like by reverse engineer, disassemble or decompile and the like a
wrong operation screen which is different from Customer’ s intention part or all of the Objective Software January 1st, 2016
might be activated or shown due to the Remote Monitoring, (9) to make software and derivation similar to the Objective Software; Saki Corporation

X3-Booster