Professional Documents
Culture Documents
Ga Qu MS Civ 008
Ga Qu MS Civ 008
Ga Qu MS Civ 008
CONSULTANT CONSULTANT
GALFAR AL MISNAD
GULF CONSULTING
QATAR UNIVERSITY TBM ENGINEERING &
GROUP
CONTRACTING WLL
CONTRACT NUMBER:
A/10/2023
PROJECT TITLE:
DESIGN & BUILD NEW SUBSTATION ALTERNATIVE TO THE EXISTING
SUBSTATION NO.1794 AT QATAR UNIVERSITY
DOCUMENT TITLE:
METHOD STATEMENT FOR CONCRETE DUCT BANK CONSTRUCTION & MANHOLE
CONSTRUCTION (FOR UTILITY TIE-IN)
TABLE OF CONTENTS
NO DESCRIPTION SHEET
1 INTRODUCTION 03
2 PURPOSE 03
3 SCOPE OF WORKS 03
ATTACHMENT
1 RISK ASSESSMENT 07
1. INTRODUCTION
This Method Statement provides Information on the methodology to be followed during the duct bank
and manhole construction activity for the project “Design & Construction Execution of New
Electrical Power Station Alternative of Electrical Power Station No-1794 At Qatar University”.
2. PURPOSE
The purpose of this method statement is to ensure that duct bank & manhole construction and related
activities are executed in accordance with the contract requirements, hazards are analyzed, safety
procedures implemented, all quality assurance / control activities are conducted in a systematic manner,
works inspected and documented.
3. SCOPE OF WORKS
This method statement covers detailed methodology to be adopted in the construction duct bank and
manhole construction for utility tie-in.
5.1 Personnel:
1. Charge hand,
2 . Helpers
3. Labors
4. Operators
5. Engineer
6. HSE Personnel
7. Steel Fixer
8. Carpenter
General
• Permit Requirements: Before commencing any work, all permits as required shall be obtained,
all permits shall be identified and logged on a register.
• Survey work – Implementation of the coordinates at the proposed utility routes and duct bank
locations based on the drawings. & documents.
• TDP - Road crossing duct bank location partially /Fully Traffic diversion prior to the Duct bank
construction.
• Plant & Equipment: All the required plants and equipment will be deployed as required.
• Traffic Management: Traffic arrangements will be made with the assistance of HSE personnel.
• Before commencing the work required permits shall be obtained from the concerned authority.
• Prior to the start of work a traffic diversion plan need to be implemented at the proposed duct
bank location.
• On completion of traffic diversion works and apparatus shall be removed, and land affected
shall be reinstated its original conditions.
• All existing traffic movements will be diverted via the temporary diversion for the duration of
the TDP period.
• After establishment of TDP, the outline of the asphaltic to be removed shall be cut in clean,
straight lines with a power-driven saw to a depth equal to the depth of the existing asphalt before
removing the surfacing.
• Before the start of excavation, the hard/soft landscaping had to be removed, as required.
• The road will be excavated with a front-end loader, backhoe or Excavator, to be required depth.
• The required number of PVC pipes to be installed.
• Reinforcement and shuttering for concrete pouring to be done. Minimum 150mm concrete to
be provided from the PVC pipe to concrete edge.
• For concrete poring ensure Concrete delivered at site within the specified time/interval and
ensure uninterrupted supply of concrete, so as to avoid cold joint.
• At road paving area, the concrete shall be poured up to the bottom level of asphalt (i.e. top level
of base layer).
• The asphalt road to be reinstated with prime coat, binder coat, tack coat and wearing course.
• Hard / Soft landscaping to be reinstated after completion of backfilling and duct bank
construction.
Manhole Construction
• The pit is excavated to its required depth to receive the concrete base for the construction of the
manhole. The base shall be adequate is size to receive the external concrete surround to the
manhole.
• The position of the manhole shall be checked to avoid misalignment of pipes down and up
stream of the manhole.
• Shoring to the pit shall be provided if the pit measured from the top edge is more than 1.5m.
• The required rebar and formwork to be erected and cast the base and allow the concrete to set
for the next day, to complete the chamber wall and slab reinforcement and formwork.
• Before concrete poring ensure the required PVC, pipes are installed at the correct level.
• After concrete curing period remove the inside formwork and provide benching at the bottom
of manhole.
• The surrounding area of manhole to be backfilling layer by layer (150mm thick).
• Above PVC pipe, 200 mm thick dune sand to be laid and settled with water.
8. ATTACHMENTS
• Risk Assessment
• TDP – Proposed Duct Bank Location
1) RISK ASSESSMENT
RISK ASSESSMENT
PROJECT TITLE:
DESIGN & CONSTRUCTION EXECUTION OF NEW ELECTRICAL POWER STATION ALTERNATIVE OF ELECTRICAL POWER STATION NO-1794
DOCUMENT TITLE:
DUCT BANK CONSTRUCTION & MANHOLE CONSTRUCTION FOR UTILITY TIE-IN
4 11-5 Low Risk 4: Major Injury (30>LD>4 days) 3: Probable P: Probability Factor
2 4-1 Negligible 2: Minor Injury (4>LD>1 day) 2: Rare T: Total Points
1
1: No Lost time Injury 1: Very Rare LD: Lost Workdays
Target
Risk E.P
Work Item Risk Foreseen during Work Risk Reduction Measures E.P Responsible
SxP=T
SxP=T person
> Applicable QU- PTW shall be obtained prior to
start of the job
1. Permit to work > Work execution without PTW 4x2=8 >All required supplementary certificates / 2x1=2
Site engineer/
documents to be attached to the PTW and be
Supervisor
available on site.
>Unauthorized entry
>Adequate barricading and proper signage shall be
2. Unauthorized access > Non – familiar with site rules and
4x3=12 provided at the site. 2x1=2 Site engineer/
to work area regulations.
>Ensure adequate barricade around working area Supervisor
> Un-secured area.
>Strictly compliance with procedures of work.
1
RISK ASSESSMENT
>Conduct Safety Toolbox Talk prior start of work.
> All workers to be wearing site applicable PPE.
> Hand tools and equipment to be inspected daily.
> Awareness of personnel on proper manual
handling technique Site charge hand
> Use of mechanical means as necessary
> Finger and Hand Injury > Observed the six point lift technique
>Eye / face injury - Look at the load
> Slip trip and fall - Foot position.
3. Use of Hand Tools 4x2=8 2x1=2
> Back pain - Bend knees / back straight (natural
> Improper Handling
position)
- Test the load / firm grip / head up
- Lift with the legs / load close
- Put down with care
2
RISK ASSESSMENT
> Protect with appropriate supports /sleeves
> Damage to underground services
> Deploy banks man /flagman to control the traffic
> Traffic congestion due to facilities
> Ensure the cutting blade covered by built in
5. Track road / asphalt > Manual handling of the asphalt cutting
shield Site engineer/
road cutting and machine-cut / hit injury 4x3=12 2x2=4
> Spray water to suppress the dust site supervisor
diversion > Accumulation of waste
> Clear accumulate debris on daily basis to avoid
Dust Generation ,falling hazards
slip, trip, fall hazards
PREPARED BY APPROVED BY
Signature : Signature :
5
ATTACHMENT
2) TDP – PROPOSED DUCT BANK LOCATION