Observation Report 30.09.23
Observation Report 30.09.23
Comment Action
Photo taken
Date
NO
Before After
Comment:
1 Grinder machine without
guarding. 19/09/2023
Action to be taken:
Grinder machine has been
provided guarding.
Comment:
2 Excavated area at STP 27/09/2023
requires barricade and
signages.
Action to be taken:
Excavated area at STP has
been barricade and signages
have been provided
Comment:
3 Excavated area requires
barricade. (Behind MH5D) 20/09/2023
Action to
be taken:
Barricade has been
installed at excavated area
Comment:
4 Water ponding 20/09/2023
inside chemical
drum. Might have
larval breeding.
Action to betaken:
Water ponding
inside chemical
drum has been
cleared.
5 Comment:
Need to carry out 29/09/2023
housekeeping at
CLQ.
Action to be
taken:
CLQ housekeeping
has been carried
out.
6. Comment:
Poor workplace
housekeeping at 21/09/2023
STP.
Action to be
taken:
Debris at
workplace has
been cleared (STP)
7. Comment: 29/09/2023
Debris at concrete
mixer did not
dispose properly.
Action to be
taken:
Debris at concrete
mixer area has
been disposed.
Remarks if any:
Note: Evidence shall be provided in order to close the observation report e.g. photographs including time and date.
(1)