NIGERIAN PETROLEUM DEVELOPMENT COMPANY LIMITED

PROJECT TITLE:

FRONT END ENGINEERING DESIGN (FEED) FOR THE INSTALLATION OF 2NOS. x


1MW GAS GENERATORS AT OPUAMA FIELD AND ELECTRIFICATION OF 2NOS.
OPUAMA FIELD HOST COMMUNITIES IN OML 40

DOCUMENT TITLE:

MASTER DOCUMENT REGISTER

DOCUMENT NUMBER:

OM40-OPM-PMT-MDR-00001-K01

K01 16.07.20 Issued for Inter-Discipline Check J.DAIRO E.NNALU O.ATTAH


Rev Date Issued Purpose Originator Checker Approver
Company Approval: Contractor:

Date:
Asset Location Discipline Designation Sequence Rev
Document No.
OM40 OPM PMT MDR 00001 K01
MASTER DOCUMENT REGISTER (MDR)

FRONT END ENGINEERING DESIGN (FEED) FOR THE INSTALLATION OF 2NOS. x 1MW GAS GENERATORS AT OPUAMA FIELD AND ELECTRIFICATION OF 2NOS. OPUAMA FIELD HOST COMMUNITIES IN OML 40

INTER-DISCIPLINE CHECK DATE


DOCUMENT NO. OM40-OPM-PMT-MDR-00001-K01 START DATE ISSUED FOR REVIEW (IFR) ISSUED FOR APPROVAL (IFA) ISSUE FOR DESIGN (AFD) Final Handover
(IDC)

Planned Date

Planned Date

Planned Date

Planned Date
Planned date

Planned Date
Revision. No.

Revision. No.

Revision. No.

Revision. No.
Actual Date

Actual Date

Actual Date

Actual Date

Actual Date
No. Issued.

No. Issued.

No. Issued.
Transmittal

Transmittal

Transmittal

Transmittal
No. Issued

No. Issued
TOTAL NO.

Actual Date

Remarks
No.

No.

No.

No.

Forecast
S/No. Company Document Number Document Description

PROJECT MANAGEMENT
1 OM40-OPM-PMT-MDR-00001 Master Documents Register 1 9-Jul-20 15-Jul-20 K01 16-Jul-20 R01 20-Jul-20 A01 22-Jul-20 D01
2 OM40-OPM-PMT-SCD-00001 Project Schedule 1 9-Jul-20 15-Jul-20 K01 16-Jul-20 R01 20-Jul-20 A01 22-Jul-20 D01
3 OM40-OPM-PMT-BOD-00001 Project Design Basis 1 9-Jul-20 16-Jul-20 K01 17-Jul-20 R01 21-Jul-20 A01 23-Jul-20 D01
4 OM40-OPM-PMT-PEP-00001 Project Execution Plan 1 13-Jul-20 16-Jul-20 K01 17-Jul-20 ` R01 21-Jul-20 A01 23-Jul-20 D01
5 OM40-OPM-PMT-RPT-00001 Site Visit Report 1 13-Jul-20 16-Jul-20 K01 17-Jul-20 R01 21-Jul-20 A01 23-Jul-20 D01
PROCESS
6 OM40-OPM-PRS-LST-00001 Legend and Symbology 1 9-Jul-20 12-Jul-20 K01 12-Jul-20 R01 14-Jul-20 A01 14-Jul-20 D01
7 OM40-OPM-PRS-PLS-00001 ESD Philosophy 1 9-Jul-20 15-Jul-20 K01 17-Jul-20 R01 21-Jul-20 A01 23-Jul-20 D01
8 OM40-OPM-PRS-CAL-00001 Process calculation note 1 10-Jul-20 16-Jul-20 K01 18-Jul-20 R01 21-Jul-20 A01 23-Jul-20 D01
9 OM40-OPM-PRS-PFD-00001 Process Flow Diagrams 1 13-Jul-20 23-Jul-20 K01 24-Jul-20 R01 28-Jul-20 A01 30-Jul-20 D01
10 OM40-OPM-PRS-UFD-00001 Utility Flow Diagrams 1 13-Jul-20 23-Jul-20 K01 24-Jul-20 R01 28-Jul-20 A01 30-Jul-20 D01
11 OM40-OPM-PRS-PID-00001 Process and Instrumentation Diagram (P & ID) 1 14-Jul-20 24-Jul-20 K01 25-Jul-20 R01 29-Jul-20 A01 31-Jul-20 D01
12 OM40-OPM-PRS-UID-00001 Utility and Instrumentation Diagram (U & ID) 1 14-Jul-20 24-Jul-20 K01 25-Jul-20 R01 29-Jul-20 A01 31-Jul-20 D01
13 OM40-OPM-PRS-LST-00002 Line List 1 24-Jul-20 26-Jul-20 K01 26-Jul-20 R01 28-Jul-20 A01 30-Jul-20 D01
14 OM40-OPM-PRS-LST-00003 Equipment List 1 24-Jul-20 25-Jul-20 K01 25-Jul-20 R01 27-Jul-20 A01 29-Jul-20 D01
MECHANICAL/PIPING
15 OM40-OPM-MEC-SPT-00001 Equipment Specifications and List 1 23-Jul-20 23-Jul-20 K01 23-Jul-20 R01 27-Jul-20 A01 29-Jul-20 D01
16 OM40-OPM-MEC-DTS-00001 Mechanical Equipment Data Sheets 1 23-Jul-20 23-Jul-20 K01 23-Jul-20 R01 27-Jul-20 A01 29-Jul-20 D01
17 OM40-OPM-PIP-PLT-00001 General Plot Plan 1 20-Jul-20 24-Jul-20 K01 26-Jul-20 R01 28-Jul-20 A01 30-Jul-20 D01
18 OM40-OPM-PIP-KYP-00001 Key Plan 1 24-Jul-20 26-Jul-20 K01 26-Jul-20 R01 28-Jul-20 A01 30-Jul-20 D01
19 OM40-OPM-PIP-PLT-00002 Pipe Support Location Plan 1 3-Aug-20 3-Aug-20 K01 3-Aug-20 R01 6-Aug-20 A01 8-Aug-20 D01
20 OM40-OPM-PIP-SPT-00001 Piping Material Specifications 1 23-Jul-20 24-Jul-20 K01 24-Jul-20 R01 28-Jul-20 A01 30-Jul-20 D01
21 OM40-OPM-PIP-PSU-00001 Pipe Support Detail Drawing 1 3-Aug-20 7-Aug-20 K01 7-Aug-20 R01 9-Aug-20 A01 11-Aug-20 D01
22 OM40-OPM-PIP-MTO-00001 Pipe Support MTO/ Schedule 1 7-Aug-20 10-Aug-20 K01 10-Aug-20 R01 12-Aug-20 A01 14-Aug-20 D01
23 OM40-OPM-PIP-LAY-00001 Piping General Arrangement Drawings 1 24-Jul-20 2-Aug-20 K01 3-Aug-20 R01 7-Aug-20 A01 10-Aug-20 D01
24 OM40-OPM-PIP-MTO-00002 Piping MTO 1 4-Aug-20 9-Aug-20 K01 11-Aug-20 R01 15-Aug-20 A01 17-Aug-20 D01
25 OM40-OPM-PIP-DTS-00001 Valve Data Sheet 1 24-Jul-20 24-Jul-20 K01 24-Jul-20 R01 28-Jul-20 A01 30-Jul-20 D01
ELECTRICAL
25 OM40-OPM-ELE-LST-00001 Legends and Symbols List 1 10-Jul-20 16-Jul-20 K01 16-Jul-20 R01 20-Jul-20 A01 22-Jul-20 D01
26 OM40-OPM-ELE-SPT-00001 Switchgear Specification 1 10-Jul-20 16-Jul-20 K01 17-Jul-20 R01 21-Jul-20 A01 23-Jul-20 D01
27 OM40-OPM-ELE-STD-00001 Overall Single Line Diagram 1 13-Jul-20 18-Jul-20 K01 18-Jul-20 R01 20-Jul-20 A01 22-Jul-20 D01
28 OM40-OPM-ELE-LST-00002 Electrical Load List 1 19-Jul-20 23-Jul-20 K01 23-Jul-20 R01 25-Jul-20 A01 27-Jul-20 D01
29 OM40-OPM-ELE-SPT-00002 Electrical Cable Schedule / Specification 1 9-Jul-20 15-Jul-20 K01 18-Jul-20 R01 22-Jul-20 A01 24-Jul-20 D01
30 OM40-OPM-ELE-LAY-00001 Cable Route Layout 1 20-Jul-20 28-Jul-20 K01 29-Jul-20 R01 2-Aug-20 A01 4-Aug-20 D01
31 OM40-OPM-ELE-LST-00003 Electrical Equipment List 1 24-Jul-20 28-Jul-20 K01 29-Jul-20 R01 2-Aug-20 A01 4-Aug-20 D01
32 OM40-OPM-ELE-MTO-00001 Electrical Material Take-Off 1 23-Jul-20 3-Aug-20 K01 6-Aug-20 R01 10-Aug-20 A01 12-Aug-20 D01
33 OM40-OPM-ELE-LAY-00002 Hazardous Area Classification Layout 1 20-Jul-20 23-Jul-20 K01 24-Jul-20 R01 28-Jul-20 A01 30-Jul-20 D01
34 OM40-OPM-ELE-DTL-00001 Hazardous Area Classification Details 1 20-Jul-20 23-Jul-20 K01 24-Jul-20 R01 28-Jul-20 A01 30-Jul-20 D01
35 OM40-OPM-ELE-LAY-00003 Earthing Layout 1 24-Jul-20 27-Jul-20 K01 28-Jul-20 R01 1-Aug-20 A01 3-Aug-20 D01
36 OM40-OPM-ELE-LAY-00004 Lighting Protection Layout 1 24-Jul-20 27-Jul-20 K01 28-Jul-20 R01 1-Aug-20 A01 3-Aug-20 D01
37 OM40-OPM-ELE-LAY-00005 Perimeter Lighting Layout 1 28-Jul-20 31-Jul-20 K01 1-Aug-20 R01 5-Aug-20 A01 7-Aug-20 D01
38 OM40-OPM-ELE-CAL-00001 Electrical lighting Calculations 1 14-Jul-20 17-Jul-20 K01 18-Jul-20 R01 22-Jul-20 A01 24-Jul-20 D01
39 OM40-OPM-ELE-CAL-00002 Electrical Equipment selection and sizing Calculations 1 21-Jul-20 24-Jul-20 K01 25-Jul-20 R01 29-Jul-20 A01 31-Jul-20 D01
40 OM40-OPM-ELE-DTS-00001 Electrical Equipment Datasheets 1 2-Aug-20 5-Aug-20 K01 5-Aug-20 R01 7-Aug-20 A01 9-Aug-20 D01
41 OM40-OPM-ELE-LAY-00006 Electrical Equipment Layout Drawings 1 6-Aug-20 11-Aug-20 K01 13-Aug-20 R01 17-Aug-20 A01 19-Aug-20 D01
42 OM40-OPM-ELE-CAL-00003 Electrical Cable Sizing and selection 1 13-Jul-20 16-Jul-20 K01 18-Jul-20 R01 22-Jul-20 A01 24-Jul-20 D01
43 OM40-OPM-ELE-SPT-00003 Long Lead Item (Generator) Specification 1 22-Jul-20 25-Jul-20 K01 27-Jul-20 R01 29-Jul-20 A01 31-Jul-20 D01
44 OM40-OPM-ELE-SPT-00004 Long Lead Item (Power Transformer) Specification 1 22-Jul-20 25-Jul-20 K01 28-Jul-20 R01 1-Aug-20 A01 3-Aug-20 D01
45 OM40-OPM-ELE-ALN-00001 Cable Alignment Sheet 1 4-Aug-20 13-Aug-20 K01 15-Aug-20 R01 17-Aug-20 A01 19-Aug-20 D01
46 OM40-OPM-ELE-DTL-00002 Cable Trench Detail 1 5-Aug-20 6-Aug-20 K01 6-Aug-20 R01 8-Aug-20 A01 10-Aug-20 D01
47 OM40-OPM-ELE-RPT-00001 Mechanical Design Report 1 6-Aug-20 8-Aug-20 K01 8-Aug-20 R01 10-Aug-20 A01 12-Aug-20 D01
48 OM40-OPM-ELE-DTL-00003 Cable Crossing Drawing 1 10-Aug-20 15-Aug-20 K01 15-Aug-20 R01 17-Aug-20 A01 19-Aug-20 D01
49 OM40-OPM-ELE-DTL-00004 Typical Cable Marker Details 1 7-Aug-20 10-Aug-20 K01 10-Aug-20 R01 12-Aug-20 A01 14-Aug-20 D01
INSTRUMENTATION/CONTROL
50 OM40-OPM-INS-LST-00001 Instrument Index 1 24-Jul-20 28-Jul-20 K01 28-Jul-20 R01 1-Aug-20 A01 3-Aug-20 D01
51 OM40-OPM-INS-LST-00002 Instrument I/O List 1 24-Jul-20 28-Jul-20 K01 28-Jul-20 R01 1-Aug-20 A01 3-Aug-20 D01
52 OM40-OPM-INS-DTS-00001 Instrument Datasheet 1 24-Jul-20 28-Jul-20 K01 28-Jul-20 R01 1-Aug-20 A01 3-Aug-20 D01
53 OM40-OPM-INS-LAY-00001 Control System Architecture 1 27-Jul-20 31-Jul-20 K01 1-Aug-20 R01 5-Aug-20 A01 7-Aug-20 D01
54 OM40-OPM-INS-SPT-00001 General Instrument Specification 1 20-Jul-20 24-Jul-20 K01 25-Jul-20 R01 29-Jul-20 A01 31-Jul-20 D01
55 OM40-OPM-INS-PLS-00001 Instrument Control Philosphy 1 20-Jul-20 24-Jul-20 K01 25-Jul-20 R01 29-Jul-20 A01 31-Jul-20 D01
56 OM40-OPM-INS-DTL-00001 Instrument Hook-up Drawing 1 27-Jul-20 31-Jul-20 K01 1-Aug-20 R01 3-Aug-20 A01 5-Aug-20 D01
57 OM40-OPM-INS-LAY-00002 Instrument Location Layout 1 27-Jul-20 31-Jul-20 K01 1-Aug-20 R01 5-Aug-20 A01 7-Aug-20 D01
58 OM40-OPM-INS-SCD-00001 Cable Schedule 1 3-Aug-20 7-Aug-20 K01 7-Aug-20 R01 9-Aug-20 A01 11-Aug-20 D01
59 OM40-OPM-INS-LAY-00003 Cable Routing Drawing 1 28-Jul-20 3-Aug-20 K01 4-Aug-20 R01 8-Aug-20 A01 10-Aug-20 D01
60 OM40-OPM-INS-SPT-00002 Fire and Gas Specification 1 27-Jul-20 31-Jul-20 K01 1-Aug-20 R01 5-Aug-20 A01 7-Aug-20 D01
61 OM40-OPM-INS-LST-00003 Alarm and Shutdown Matrix 1 31-Jul-20 2-Aug-20 K01 3-Aug-20 R01 5-Aug-20 A01 7-Aug-20 D01
62 OM40-OPM-INS-MTO-00001 Instrument Material Takeoff 1 24-Jul-20 28-Jul-20 K01 31-Jul-20 R01 4-Aug-20 A01 6-Aug-20 D01
63 OM40-OPM-INS-SPT-00003 Specification for Instrument tubing 1 20-Jul-20 24-Jul-20 K01 27-Jul-20 R01 29-Jul-20 A01 31-Jul-20 D01
64 OM40-OPM-INS-SPT-00004 Specification for tubing tray 1 20-Jul-20 24-Jul-20 K01 28-Jul-20 R01 1-Aug-20 A01 3-Aug-20 D01
65 OM40-OPM-INS-PLS-00002 EDS Philosophy 1 20-Jul-20 24-Jul-20 K01 28-Jul-20 R01 1-Aug-20 A01 3-Aug-20 D01

Page 2 of 3
INTER-DISCIPLINE CHECK DATE
DOCUMENT NO. OM40-OPM-PMT-MDR-00001-K01 START DATE ISSUED FOR REVIEW (IFR) ISSUED FOR APPROVAL (IFA) ISSUE FOR DESIGN (AFD) Final Handover
(IDC)

Planned Date

Planned Date

Planned Date

Planned Date
Planned date

Planned Date
Revision. No.

Revision. No.

Revision. No.

Revision. No.
Actual Date

Actual Date

Actual Date

Actual Date

Actual Date
No. Issued.

No. Issued.

No. Issued.
Transmittal

Transmittal

Transmittal

Transmittal
No. Issued

No. Issued
TOTAL NO.

Actual Date

Remarks
No.

No.

No.

No.

Forecast
S/No. Company Document Number Document Description

STRUCTURAL
66 OM40-OPM-CVS-PLT-00001 Civil Structural Plot Plan 1 20-Jul-20 25-Jul-20 K01 27-Jul-20 R01 31-Jul-20 A01 3-Aug-20 D01
67 OM40-OPM-CVS-LAY-00001 Foundation Layout 1 23-Jul-20 28-Jul-20 K01 30-Jul-20 R01 3-Aug-20 A01 5-Aug-20 D01
68 OM40-OPM-CVS-LAY-00002 Pile Setting Out Drawings 1 29-Jul-20 3-Aug-20 K01 5-Aug-20 R01 8-Aug-20 A01 10-Aug-20 D01
69 OM40-OPM-CVS-SPT-00001 Strutaural Specifications 1 16-Jul-20 21-Jul-20 K01 23-Jul-20 R01 26-Jul-20 A01 28-Jul-20 D01
70 OM40-OPM-CVS-CAL-00001 calculation and Analysis Report 1 30-Jul-20 4-Aug-20 K01 6-Aug-20 R01 10-Aug-20 A01 12-Aug-20 D01

71 OM40-OPM-CVS-SPT-00002 Piling & Foundation requirements and Construction Specifications 1 30-Jul-20 4-Aug-20 K01 6-Aug-20 R01 10-Aug-20 A01 12-Aug-20 D01

72 OM40-OPM-CVS-RPT-00001 Pile Load Selection Analysis Report 1 31-Jul-20 5-Aug-20 K01 7-Aug-20 R01 11-Aug-20 A01 13-Aug-20 D01
73 OM40-OPM-CVS-LST-00001 Quality Control Check List 1 23-Jul-20 28-Jul-20 K01 30-Jul-20 R01 3-Aug-20 A01 5-Aug-20 D01
74 OM40-OPM-CVS-RPT-00002 Geotechnical investigation Report 1 31-Jul-20 5-Aug-20 K01 7-Aug-20 R01 11-Aug-20 A01 13-Aug-20 D01
75 OM40-OPM-CVS-MTO-00001 Materials Take-off 1 5-Aug-20 10-Aug-20 K01 12-Aug-20 R01 16-Aug-20 A01 18-Aug-20 D01
76 OM40-OPM-CVS-PLN-00001 Pile Layour Plan 1 3-Aug-20 8-Aug-20 K01 10-Aug-20 R01 14-Aug-20 A01 15-Aug-20 D01
77 OM40-OPM-CVS-PLN-00002 Piles, Pilecap and Beam Layout and Section 1 3-Aug-20 8-Aug-20 K01 10-Aug-20 R01 14-Aug-20 A01 15-Aug-20 D01
78 OM40-OPM-CVS-DTL-00001 Slab Reinforcement Details 1 12-Aug-20 17-Aug-20 K01 17-Aug-20 R01 19-Aug-20 A01 21-Aug-20 D01
79 OM40-OPM-CVS-DTL-00002 Pile and Pile cap details and Section 1 10-Aug-20 15-Aug-20 K01 17-Aug-20 R01 19-Aug-20 A01 21-Aug-20 D01
80 OM40-OPM-CVS-DTL-00003 Ground Beam Details and Section 1 6-Aug-20 11-Aug-20 K01 13-Aug-20 R01 17-Aug-20 A01 19-Aug-20 D01
81 OM40-OPM-CVS-SCD-00001 Bar Bending Schedule 1 7-Aug-20 12-Aug-20 K01 14-Aug-20 R01 18-Aug-20 A01 20-Aug-20 D01
82 OM40-OPM-CVS-PLN-00003 Generator Platform Plan, elevation and Section 1 8-Aug-20 13-Aug-20 K01 15-Aug-20 R01 17-Aug-20 A01 19-Aug-20 D01
83 OM40-OPM-CVS-PLN-00004 Interconnecting Accessway platform plan and elevation 1 9-Aug-20 14-Aug-20 K01 14-Aug-20 R01 16-Aug-20 A01 18-Aug-20 D01
84 OM40-OPM-CVS-DTL-00004 Transformer and Pole Foundation design 1 7-Aug-20 12-Aug-20 K01 13-Aug-20 R01 15-Aug-20 A01 17-Aug-20 D01
85 OM40-OPM-CVS-PLN-00005 Transformer foundation Plan and Elevation 1 7-Aug-20 12-Aug-20 K01 13-Aug-20 R01 15-Aug-20 A01 17-Aug-20 D01
86 OM40-OPM-CVS-PLN-00006 Fencing and gate Plan and elevation 1 8-Aug-20 13-Aug-20 K01 15-Aug-20 R01 18-Aug-20 A01 20-Aug-20 D01
CATHODIC PROTECTION
87 OM40-OPM-CRN-RPT-00001 Cathodic Protection Calculation Report 1 30-Jul-20 2-Aug-20 K01 2-Aug-20 R01 4-Aug-20 A01 6-Aug-20 D01
88 OM40-OPM-CRN-MTO-00001 Cathodic Protection MTO 1 5-Aug-20 7-Aug-20 K01 7-Aug-20 R01 8-Aug-20 A01 10-Aug-20 D01
89 OM40-OPM-CRN-LAY-00001 Cathodic Protection Layout Drawing 1 3-Aug-20 6-Aug-20 K01 6-Aug-20 R01 8-Aug-20 A01 10-Aug-20 D01
90 OM40-OPM-CRN-DTL-00001 Cathodic Detail Drawing 1 5-Aug-20 8-Aug-20 K01 8-Aug-20 R01 10-Aug-20 A01 12-Aug-20 D01
91 OM40-OPM-CRN-PLS-00001 Corrosion Prevention/ Mitigation Philosophy 1 3-Aug-20 6-Aug-20 K01 6-Aug-20 R01 8-Aug-20 A01 10-Aug-20 D01
92 OM40-OPM-CRN-DTL-00002 Painting Specification 1 20-Jul-20 23-Jul-20 K01 23-Jul-20 R01 25-Jul-20 A01 27-Jul-20 D01
93 OM40-OPM-CRN-DTL-00003 Welding Specification 1 20-Jul-20 23-Jul-20 K01 23-Jul-20 R01 25-Jul-20 A01 27-Jul-20 D01
HEALTH, SAFETY AND ENVIRONMENT
94 OM40-OPM-STY-MTO-00001 Technical Safety Materials Take-Off 1 14-Aug-20 17-Aug-20 K01 17-Aug-20 R01 19-Aug-20 A01 21-Aug-20 D01
95 OM40-OPM-STY-RPT-00001 Fire Water Demand Report 1 28-Jul-20 30-Jul-20 K01 30-Jul-20 R01 31-Jul-20 A01 1-Aug-20 D01
96 OM40-OPM-STY-PLS-00001 Safety Design Philosophy 1 25-Jul-20 27-Jul-20 K01 27-Jul-20 R01 28-Jul-20 A01 30-Jul-20 D01
97 OM40-OPM-STY-LAY-00001 Fire Fighting Equipment Location Layout Drawing 1 27-Jul-20 29-Jul-20 K01 29-Jul-20 R01 31-Jul-20 A01 2-Aug-20 D01
98 OM40-OPM-STY-DTL-00001 Escape Route/Mustering Points Signs Drawing 1 31-Jul-20 3-Aug-20 K01 3-Aug-20 R01 5-Aug-20 A01 7-Aug-20 D01
99 OM40-OPM-STY-DTL-00002 Escape Route/Information Signs Drawing 1 5-Aug-20 8-Aug-20 K01 8-Aug-20 R01 10-Aug-20 A01 12-Aug-20 D01
100 OM40-OPM-STY-DTL-00003 Escape Route/Mandatory Signs Drawing 1 8-Aug-20 10-Aug-20 K01 10-Aug-20 R01 12-Aug-20 A01 14-Aug-20 D01
101 OM40-OPM-STY-DTL-00004 Escape Route/Prohibitive Signs 1 10-Aug-20 12-Aug-20 K01 12-Aug-20 R01 14-Aug-20 A01 16-Aug-20 D01
102 OM40-OPM-STY-DTL-00005 Escape Route/Warning Signs Drawing 1 12-Aug-20 14-Aug-20 K01 14-Aug-20 R01 16-Aug-20 A01 18-Aug-20 D01
TOTAL NO. 103 0 0 0 0 0

NOTES:

COLOUR CODE DISCIPLINE

Piping
Process

Instrument

Mechanical
Electrical
Civil/Structure
Project Management
Cathodic Protection
Health, Safety and Environment