Professional Documents
Culture Documents
ABB AMS 800SF Generator Installation Manual
ABB AMS 800SF Generator Installation Manual
Chapter 1 - Introduction
1.1 General information.................................................................................................... 4
1.2 Safety .......................................................................................................................... 4
1.3 Site conditions............................................................................................................. 4
1.4 Prerequisites................................................................................................................ 5
1.5 Contraindications ........................................................................................................ 5
1.6 Manual system and related documents ....................................................................... 6
Chapter 3 - Alignment
3.1 Preparations for generator installation...................................................................... 20
3.2 Rough levelling of generator after erection .............................................................. 21
3.2.1 Rough alignment...................................................................................... 21
3.3 Grouting .................................................................................................................... 21
3.4 Correction for thermal expansion ............................................................................. 22
3.5 Final alignment and inspection ................................................................................. 22
3BSY 200016-EYZ i
Synchronous generator, type AMS
Table of Contents
Chapter 5 - Commissioning
5.1 Check of mechanical installation.............................................................................. 26
5.2 Check of electrical installation ................................................................................. 27
5.3 Electrical checks ....................................................................................................... 28
5.3.1 Start interlocking...................................................................................... 32
5.4 Checks during running of the generator ................................................................... 33
5.4.1 Normal vibration levels ........................................................................... 33
5.4.1.1 Bearing housings ...............................................................33
5.4.1.2 Structural vibrations ..........................................................34
5.4.1.3 Shaft vibrations .................................................................34
5.4.2 Temperature levels................................................................................... 34
5.5 Check list .................................................................................................................. 35
5.5.1 Page 1....................................................................................................... 36
5.5.2 Page 2....................................................................................................... 37
5.5.3 Page 3....................................................................................................... 38
Chapter 6 - Operation
6.1 Start up procedure..................................................................................................... 39
6.2 Continuous supervision............................................................................................. 39
6.3 Shut down procedures............................................................................................... 40
6.4 Alarm during operation............................................................................................. 40
Chapter 7 - Maintenance
7.1 Preventive maintenance ............................................................................................ 43
7.2 Before all maintenance work .................................................................................... 43
7.3 Recommended maintenance program....................................................................... 44
7.3.1 Generator ................................................................................................. 45
7.3.2 Stator........................................................................................................ 46
7.3.3 Stator terminal.......................................................................................... 47
7.3.4 Rotor ........................................................................................................ 48
7.3.5 Bearings ................................................................................................... 50
7.3.6 PMG (Permanent magnetic generator) .................................................... 51
7.3.7 Exciter and Rectifier ............................................................................... 52
Skeleton No. 3BSM005469, Rev. - EN -
3BSY 200016-EYZ ii
Synchronous generator, type AMS
Table of Contents
Chapter 1 Introduction
1.2 Safety
The machine is manufactured and intended for use only as described by this manual.
Modification, alteration, or lack of maintenance as described in the manual, may
adversely affect the safety and efficacy of this machine. The manufacturer is not
responsible for malfunctions that comprise machinesafety as a result of alteration, use of
non ABB replacements parts, neglect or misuse.
Replacements parts may vary from those shown in this manual. Should you have questions on
those parts please contact ABB AB, Machines.
The actual apperarance of the machine may vary from the illustration in this manual.
Should pre-owned ABB equipment be purchased and reconditioned, the equipment should not
be used until testing and analysis demonstrate that the equipment meets the original or upgraded
specifications.
The use of solvents as cleaning agents and the use of lubricants can involve health and/or safety
hazards. The recommended precautions and procedures of the manufacturer should be followed.
1.4 Prerequisites
The operator must:
• be proficient in the application of the machine and electricity.
• be thoroughly trained in the skills and have the knowledge required to operate this
machine.
• be thoroughly familiar with the contents of this manual and other operator´s manuals that
deals with the machine and accessory devices that may be used with this machine.
• be fully qualified and trained in the operation of this machine and able to distinguish
normal from aberrant device behaviour.
• never reset an alarm or trip until the reason for the alarm/trip has been located and
necessary remedy has been made to make a safe restart of the machine.
1.5 Contraindications
The machine is not designed, sold or intended for any use except as indicated above.
Furthermore, it is not intended to be used outside of the machine specifications or limitations.
The machine must be in good working order.
Skeleton No. 3BSM005470, Rev. B EN -
Technical Specification
Circuit Diagrams
Anchoring point
Figure 2-1
Anchor points during transport on lorry. Beware of area that is dotted in accordance with Figure
2-1 on page 8.
Skeleton No. 3BSM005471, Rev. D EN -
Anchor point
Figure 2-2
Anchor points during transport on lorry or by vessel, located on both sides of the crate.
Skeleton No. 3BSM005471, Rev. D EN -
0.86xB
60o
Figure 2-3
2.1.6 Unpacking
Place the generator so that it is out of the way of any other goods handling and on a flat,
Skeleton No. 3BSM005471, Rev. D EN -
vibration-free surface.
Remove top and sides of the wooden crate.
When the crating has been removed a check should be made to see that the generator is not
damaged and that all accessories are included. Tick off the accessories on the packing list which
is enclosed. Report immediately to the supplier if there is any damage, suspected damage or if
accessories are missing.
Lifting must be performed with great care and using steel cables long enough to assure the angle
requirements shown in Figure 2-4 on page 11. (Otherwise there will be risk of damaging the
upper sheet metal housing).
60o
0.86xL
L
Figure 2-4
Skeleton No. 3BSM005471, Rev. D EN -
When lifting the cooler top only use lifting lugs according to Figure 2-5 on page 12, the other
lifting lugs are not designed to lift the complete cooling top.
If the cooler top is delivered in separate parts, assemble the parts according to the cooler
supplier’s drawings and manuals included in the binder “Users Manual”.
NOTE: Centre of gravity is moved towards the “fan side”. Compensate by using different
length on the lifting lugs.
Figure 2-5
Skeleton No. 3BSM005471, Rev. D EN -
Figure 2-6 on page 13 shows an example how the main terminal box should be lifted. As an
option a smaller box could be included in the scope of supply, instead of as shown in Figure 2-6
on page 13. Then it will just be supplied with two lifting loops on top.
Not included
Figure 2-6
with a tarpaulin on the top extending at least 1 meter out from the crate to avoid direct rain
on the crate.
• The crate should be kept dry, protected from rain and moisture.
Before commissioning the following items should be carried out:
• Visual external inspection of bearings and entering shaft
• Check insulation resistance in accordance with section 5.3
The vertical positioning of the generator is made with hydraulic jacks (optional equipment)
placed as shown in Figure 2-7 on page 17 and Figure 2-8 on page 18.
ABB AB, Machines´s delivery includes shims with 0.5 and 1 mm thickness, placed as shown in
Figure 2-9 on page 18. Shims needed with other thicknesses are to be provided by the customer.
Bracket plates, (optional equipment) with adjusting screws for horizontal positioning of the
generator are placed at each corners, as shown in Figure 2-7 on page 17.
The bracket plate is to be placed against the foundation edge and the bracket is to be tied down
by using an expansion bolt or welding.
Hydraulic jack
CL
Vertical adjustment
screw, if included
Bracket with
adj. screw
Figure 2-7
Skeleton No. 3BSM005471, Rev. D EN -
Elect. machine
max. 79 mm
Foundation
Figure 2-8
Footplate,
machine
Shims
Footplate in foundation
Figure 2-9
Skeleton No. 3BSM005471, Rev. D EN -
Figure 2-10
Skeleton No. 3BSM005471, Rev. D EN -
Chapter 3 Alignment
Introduction
Good planning and preparation result in fast, simple and correct installation. Safe running
conditions with maximum of accessibility are assured.
Figure 3-1.
A simple lever is needed for turning the rotor. While turning the rotor, oil must be continuously
poured into the funnels at both end of the generator.
Skeleton No. 3BSM005472, Rev. A EN -
• If the generator is to be erected outdoors, sun and rain protection must be provided to
eliminate measuring errors.
NOTE: When the surroundings are neither heated nor dry, heating equipment must be
provided.
Axially
Lift the generator onto the foundation plates as close to the actual position as possible.
The rotor is placed in the magnetic neutral position when the dimension A is fulfilled. Read the
correct distance in the inspection and test record, included in the binder “Users Manual”,
“Magnetic neutral position” (Dimension A). There is also a sign on the bearing house.
NOTE: It is important that the rotor is “IN” the magnetic neutral position when the
generator is in operation.
3.3 Grouting
When the generator has been properly aligned, its base elements are attached to the foundation
by grouting. Use only non-shrinking concrete for grouting to ensure proper adhesion between
the base frame and grouting. Make sure that the grouting fills properly the whole space around
and under the base element. Do not use a vibrator in order to avoid any disturbance in the
alignment.
After the grouting has set (cured), adjust vertically to the final elevation by putting shims
between the base frame and the base element. Check also the other alignments of the generator
and adjust, if necessary.
Non-shrink grout is recommended for the best results. For shaping and grouting, the
manufacturers instructions to be followed.
Skeleton No. 3BSM005472, Rev. A EN -
Radial misalignment Δr
Gap (angular displacement) Δb
Axial displacement Δa
Figure 3-2.
The tolerances given by the coupling manufacturers must not be used in deciding how accurate
the alignment should be because these tolerances indicate what the coupling can accept.
Excessive tolerances will give rise to vibrations, bearing damage etc. and therefore should
tolerances as narrow as recommended above be aimed at.
Finally check the axial distance between the two coupling halves.
Skeleton No. 3BSM005472, Rev. A EN -
Air to air
If the cooler housing is delivered separately the following action needs to be taken:
If the cooler top is delivered in separate parts, assemble the parts according to the cooler
supplier’s drawings and manuals included in the binder “Users Manual”.
1. Remove the transport roof on the generator.
NOTE: Mount the cooler hood to the generator according to instructions and drawings
included in the binder “Users Manual”.
5. Mount the earth strip between the motor housing and cooler top.
6. Mount the hydraulic hose (purge system), with cutting ring and nut, connecting the pipe
from the relief valve with the pipe from the purge unit.
The return pipes should have an incline of 40-50 mm/m in order to guarantee trouble-free oil
circulation. The oil pipes should be designed so that they do not obstruct service and
maintenance. The pipes should be designed so that no stress is applied to the flanges on the
generator.
For required oil flow and pressure see outline drawing. The oil pipes should be carefully flushed
before they are connected to the generator.
To be able to transport the machine the main terminal box for the high voltage connection is
delivered separately and must be fitted at site.
The terminal should be supported so that no stress is applied to the generator.
1. Remove the protection cover fitted over the generator bushings.
2. Level the main terminal box so that no stresses will be induced to the generator bushings
when they are connected to the busbars in the main terminal box.
3. The joint between the main terminal box and the generator should be tightened according
to instruction 3BSM 001263R0001, included in the binder “Users manual”.
4. Before the high voltage cables are connected to the main terminal box the insulation
resistance (megged) should be checked. Check both the generator insulation resistance
(stator winding resistance) and the insulation resistance of the main terminal box
according to instruction in Section 5.3.
5. Tighten the connection of the purging pipes fitted to the main terminal box. Mount the
metal hose and sealing (purge system) between the main terminal box and the cooler top.
For terminal box location and content see outline drawing (included in binder “Users manual”).
Connections should be made according to circuit diagram.
NOTE: Space heaters in exciter and stator should be connected as soon as possible after
unpacking. If the permanent supply is not available a temporary supply should be
connected.
Chapter 5 Commissioning
On the commissioning personnel lies a great responsibility for a safe and trouble free operation
of the generator during its lifetime.
Commissioning should only be made by qualified personal.
The following are tests and checks on the generator that are recommended by the manufacturer.
If other tests are to be performed, the manufaturer should be consulted.
Bearing insulation
• “Megging” of bearings should be performed before the generator is coupled to the
turbine. See section 5.3 on page 28.
Other checks
• Open the generator at both ends and check that no loose parts are present inside the
generator. Check that no parts have come loose during transportation and that the air-gap is
free.
• If possible, turn the rotor and make sure that the rotor turns freely and that no abnormal
sound can be heard. See section 3.1 on page 20.
• Check the airgap between the exciter stator and rotor, see the test record “Air gap
measurement” (included in binder “Users manual”).
2. Personnel with pace maker should not be working in the vicinity of the PMG.
• Check the air gap between the PMG stator and rotor, see the test record “Air gap
measurement” (included in binder “Users manual”).
NOTE: The lubrication system must be commissioned and running before the rotor is
turned.
• Check the assembly of the main terminal box and cooling system.
• Check pressure and flow for oil and cooling system according to outline drawing (included
in binder “Users manual”).
All connections of control equipment are to be checked and the function tested.
A bearing insulation check should be carried out before the generator is connected to the
turbine.
Remove the earth cable located on the bearing on the drive end side. Megger the shaft to ground
using no more than 500 Volt DC. See Figure 5-1 on page 28 and Figure 5-2 on page 29.
Figure 5-1
Skeleton No. 3BSM005474, Rev. C EN -
Figure 5-2
Insulation resistance is acceptable if the megger value is more than 1 Mohm.
Skeleton No. 3BSM005474, Rev. C EN -
Conversion factor, k
100
50
10
0.5
(0.25)-
0.1
0.05
o
-10 0 10 20 30 40 50 60 70 80 90 100 ( C)
Winding temperature
14 32 50 68 86 104 122 140 158 176 194 212 (oF) when meggering
R = Megger-value at a specific temperature
R40 = Equivalent insulation resistance at 40oC
R40 = k x R Example:
R = 30 MΩ measured at 20oC
k = 0.25
R40 = 0.25x30=7.5 MΩ
Recommended minimum insulation resistance at 40oC must exceed the following value
Skeleton No. 3BSM005474, Rev. C EN -
Megging should be performed in the terminal box and from the synchronizing circuit breaker
(when the high voltage cables has been connected).
If the insulation resistance is low when measuring from the synchronizing circuit breaker,
disconnect high voltage cables and perform the megging direct on the terminals in the terminal
box.
A 5000 Volt DC megger should be used. Reading should be made after 1 minute.
NOTE: For all meggering or HV-tests on rotor see also page 6 in the manual for Telemetry
Unit (ground jumper to be open) included in the binder “Users Manual”.
Meggering should be performed at the exciter rotor connection to the main rotor.
A 500 V DC megger should be used. Reading should be made after 1 minute.
NOTE: If 1000V DC megger is used the rectifier has to be short circuit before measuring.
1 2 3 Time (Days)
Figure 5-3
During the drying process it is important that the temperature does not increase too rapidly and
that the final temperature is not too high. The temperature increase may not exceed 5 oC per
hour and the final temperature may not exceed 100 oC. The temperature must be watched
carefully throughout the drying process and the insulation resistance measured at intervals.
When a steady value for the insulation resistance has been achieved, the winding is dry.
If the lubricating or cooling systems are provided with pressure or flow monitors, should these
also be included in the start interlocking systems.
A counter for the number of start up and a duty time meter should be included in the equipment.
Vertical/horizontal Axial
mm/s in/sec micron mills mm/s in/sec micron mills
rms rms p-p p-p rms rms p-p p-p
Testroom
1.8 0.07 32.4 1.3 2.3 0.9 41.4 1.63
(typical)
Alarm 4.5 0.18 81.0 3.2 7.0 0.28 126.0 5.0
Trip 8.0 0.31 144.1 5.7 15.0 0.59 270.1 10.6
Table 5-1: Acceptable vibration levels for bearing housings. The values are valid for all speeds.
(Measured frequency range 10-1000 Hz)
Skeleton No. 3BSM005474, Rev. C EN -
Vertical/horizontal Axial
mm/s in/sec micron mills mm/s in/sec micron mills
rms rms p-p p-p rms rms p-p p-p
Testroom
4.5 0.18 81.0 3.2 4.5 0.18 81.0 3.2
(typical)
Alarm 7.0 0.28 126.0 5.0 11.0 0.43 198.1 7.8
Trip 15.0 0.59 270.1 10.6 20.0 0.79 360.1 14.2
Table 5-2: Acceptable vibration levels for supporting structures. The values are valid for all
speeds. (Measured frequency range 10-1000 Hz)
Vertical/horizontal
mm/s in/sec micron mills
rms rms p-p p-p
Testroom
- - 50.8 2.0
(typical)
Alarm - - 76.2 3.0
Trip - - 101.6 4.0
Table 5-3: Acceptable vibration levels for shaft vibrations. The values are valid for all speeds.
5.5.1 Page 1
Customer: Name and company of responsible commissioning engineer:
Site name:
Serial number:
Order number: Date:
Generator data
Output: kVA Power factor: Voltage: V
Frequency: Hz Speed: r/min Current: A
Excitation: V A Oil quality:
Skeleton No. 3BSM005474, Rev. C EN -
5.5.2 Page 2
Customer: Name and company of responsible commissioning engineer:
Site name:
Serial number:
Order number: Date:
5.5.3 Page 3
Customer: Name and company of responsible commissioning engineer:
Site name:
Serial number:
Order number: Date:
Chapter 6 Operation
Chapter 7 Maintenance
Preparation for Open inspection covers. Open inspection covers. Disassembly PMG stator. Open bearings.
inspection Open bearings. Removal rotor
and exciter.
Instrument/ Megger, stator. Megger, stator Megger, stator.
Tools Megger, rotor. Megger, rotor Megger, rotor.
Fibre-optic or video Rotor removal equipment.
borescope. Torque wrench.
Oscilloscope/Test Oscilloscope/Test
equipment. equipment.
Parts/ Bearing shell, Acc. to L1 and suggestion Acc. to L2 and suggestion Acc. to L3 and suggestion
Spare parts Brushes, from inspection L1. from inspection L1 and from inspection L1, L2
Shaft seals, Silicon tape. L2. and L3.
Airlock filter (bearing), Rectifier kit. Rotor kit.
Control pulse unit, Bearing kit.
Thyristors, Diodes. Gaskets.
Other order specific
parts.
Expected Approx. 1 day. Approx. 2 days. Approx. 5 days. Approx. 10 days.
downtime
Interval 10 20 30 40 50 60 70 80
Hours x 1000
Program L1 L2 L1 L3 L1 L2 L1 L4
Timing of the inspection and overhauls are largely determined by the number of operating hours, the mode of operation and
the number of starts of the generator. Local condition has to be considered.
The maintenance intervals shall be co-ordinated for the generator, in a suitable way.
Skeleton No. 3BSM005476, Rev. A EN -
7.3.1 Generator
Location L1 L2 L3 L4 Activity Approved
General cross-
section AMS
machine (actual
design acc. to
outline included in
binder “Users
Manual”).
Inspection covers
on both ND- and
D-end sides.
Skeleton No. 3BSM005476, Rev. A EN -
Figure 7-1
7.3.2 Stator
Location L1 L2 L3 L4 Activity Approved
Air cover
Stator coils
Bracing rope
Skeleton No. 3BSM005476, Rev. A EN -
Figure 7-2
7.3.4 Rotor
Location L1 L2 L3 L4 Activity Approved
Figure 7-3
Fan
Balancing weights
Pole bolts
Pole shoes
Figure 7-4
Skeleton No. 3BSM005476, Rev. A EN -
7.3.5 Bearings
Location L1 L2 L3 L4 Activity Approved
Bearing shell
Baffle or
Skeleton No. 3BSM005476, Rev. A EN -
Tightening cover
Figure 7-5
PMG stator
PMG rotor
Permanent magnets
Skeleton No. 3BSM005476, Rev. A EN -
Figure 7-6
Exciter stator
Exciter rotor
Rectifier
Figure 7-7
The test is carried out by applying an AC-voltage over the entire field winding and measuring
the current and the voltage drop across the total winding as well as each single coil, see figure
7-8.
The applied voltage should be 230 V or 400 V 50 Hz / 208 V or 480 V 60 Hz depending on the
rated frequency of the machine.
+ ΔU1
The voltage over a single coil (ΔU) should
ΔU
Skeleton No. 3BSM005476, Rev. A EN -
U
ΔU
ΔU4
3
-
Figure 7-8
Supply
Exciter
voltage osc side
Uac
Skeleton No. 3BSM005476, Rev. A EN -
≈ 600 Ω
+
Figure 7-9
• Increase the voltage and check with an oscilloscope the triggering voltage level of the
firing unit and the thyristors as shown in figure 7-10 chart 2 and 3.
• Decrease the voltage to a level under the firing units trigger level, see figure 7-10 chart 1
and measure over each diode separately. A shorted diode will show zero (0) volt on the
oscilloscope.
Ûac
3. Û > Triggering voltage level Ûac > UT
UT
Ûac
Figure 7-10
Skeleton No. 3BSM005476, Rev. A EN -
NOTE: Before altering the firing level, write down the original connections for firing
level, thyristors, etc.
Thyristor B Thyristor A
K K-G K K-G +
150V
225V
300V
450V
600V
750V
900V
1.1kV
1.3kV
1.5kV
x Drawing number
Seriel number
x
Figure 7-11
Skeleton No. 3BSM005476, Rev. A EN -
7.5.3 Lubrication
The generators are provided with sleeve bearings with an almost unlimited service life provided
that the lubrication functions continuously and that the oil is changed at suitable intervals.
Temperature
To enable the bearing temperature to stabilize at a normal level, the correct amount or flow of
oil is required. The normal bearing temperature is 65 - 85 oC.
Oil qualities
Unless otherwise stated on ABB AB, Machines drawing “Outline synchronous generator”
included in the binder “Users Manual”, the bearings are designed for any of the following oil
qualities:
Mobil: D. T. E. 26
Optimol: Ultra 5045
Shell: Tellus Oil 68
Texaco: Rando Oil HD C 68
Check with
Unsuitable oil Change oil
ABB AB,
quality Machines´s quality
recommendation
Damaged shaft
Repair the seals
seals
Oil leaks
Too high oil
flow Correct oil flow
Incorrect
Problem in oil
inclination of
flow return
the return pipe?
Check that
bearing under pressure
is well below
surrounding
outside the
bearing housing
Faulty
Faulty sensor
instrument
Cooling air
temperature to
high
High winding and/or
air temperature
Dirty or plugged Clean the
filter/airduct filter/airduct
Overload
8.1 General
The manufacturing process of the machine is carried out in accordance with the Environmental
Management System ISO 14001.
This instruction concerns the disposal and recycling of Large AC-machines. The machines are
designed in a way that it is easy to separate the different components and types of material from
eachother, making it esier to recycle.
NOTE: The methods are described in a very general way. All instructions are to be
performed by personnel which is trained and skilled for the procedure.
Dismantling the machine is done by simply separating all the components of the machine. Since
the machine mainly is assembled with screws and nuts, it is rather simple to carry out the
dismantling. When the machine has been dismantled into its different components, the different
components has to be separated and grouped together dependent upon the different types of
material.
• Foot plates
• Encapsulation
• Side plates
• Roof
8.3.7 Aluminium
The following components are separated into one group for aluminium:
• Coil supports of the rotor
• Heat sinks for thyristors and diodes in the exciter.
8.3.8 Copper
Copper is mostly integrated in the actual components and require some effort in order to be
separated. There exist some special tools for making the separation but normally wedges, large
hammers, gas burners and manpower is used.
The following components are separated into one group for copper:
• Stator coils
The copper is integrated in the stator and is glued to the stator by use of an impregnation
resin. Thereafter the copper in the stator is surrounded by several mm of micabased
insulation. The separation of copper from the insulation is done by the method granulation,
which is used by larger recycling companies. The granulation method cuts the copper into
pieces and the copper is then separated from the insulation by a mechanical process. This
can also be done by manpower using hammer and wedges. The amount of copper in the
stator is large.
• Stator connection
The copper is integrated within the stator winding. It may be cut off and separated from its
insulation by granulation or by manpower.
• Rotor coils in the machines rotor
This is clean copper mixed together with layers of insulation. It may be separated from the
rotor by loosening the pole bolts of the rotor body and by removing the coil supports. This
copper is of high quality and value, and the amout is large. The copper from the rotor coils
is to be kept separate from all insulated copper.
• Rotor connections in the machines rotor
This is cable copper that may be separated from the rotor by a gas burner combined with
manpower.
It might come off easier if first heating up the rotor until the epoxy resin within the rotor
shaft is carbonised.
Skeleton No. 3BSM005478, Rev. A EN -
It might come of easier if first heating up the stator until the impregnation resin is
carbonized.
• Rotor coils in the exciter rotor
This is enammelded copper that is glued together by impregnation resin. It may be
separated from the exciter by manpower or using special equipment.
It might come of easier if first heating up the rotor until the impregnation resin is
carbonised.
NOTE: Make sure the power plant is adapted for this kind of fuel and have the proper
types of filter etc. in order to prevent gases and dust to enter the environment.
Contents
6DIHW\
1.1 General safety instructions ............................................ 3
&KDQJHRIGLRGHVDQGWK\ULVWRUV
2.1 Dismantling of diode and thyristor ................................ 4
2.2 Assembling of diode and thyristor................................. 7
2.3 Change of control pulse unit........................................ 10
2.4 Recommended tightening torque for bolts ...................11
6\QFKURQRXVPDFKLQH
127,&(
The information in this document is subject to change without notice and should not be construed as a commitment by ABB.
ABB assumes no responsibility for any errors that may appear in this document.
In no event shall ABB be liable for direct, indirect, special, incidental or consequential damages of any kind arising from the use
of this document, nor shall ABB be liable for incidential or consequential damages arising from the use of any software or
hardware described in this document.
This document and parts thereof must not be reproduced or copied without ABB’s written permission, and the contents thereof
must not be imparted to a third party nor be used for any unauthorized purpose.
3BSM 005449 ii
6\QFKURQRXVPDFKLQH
6DIHW\
6DIHW\
*HQHUDOVDIHW\LQVWUXFWLRQV
The procedures described in this manual are only to be performed by trained personnel
authorized by the user.
The manufacturer is not responsible for malfunctions that comprise safety as a result of
alteration, use of non ABB replacement parts, neglect or misuse.
Replacement parts may vary from those shown in this manual. Should you have questions on
those parts please contact ABB Automation Technologies AB.
The actual appearance of the machine may vary from the illustration in this manual.
Should pre-owned ABB equipment be purchased and reconditioned, the equipment should not
be used until testing and analysis demonstrate that the equipment meet the original or upgraded
specifications.
The use of solvents as cleaning agents and the use of lubricants can involve health and/or safety
hazards. The recommended precautions and procedures of the manufacturers should be
followed.
3BSM 005449, Rev. B EN -
3BSM 005449 3
6\QFKURQRXVPDFKLQH
&KDQJHRIGLRGHVDQGWK\ULVWRUV
&KDQJHRIGLRGHVDQGWK\ULVWRUV
:$51,1*'LRGHIDXOW
,IDIDXOW\GLRGHRUWK\ULVWRUWKHUHFRPPHQGDWLRQLVWRUHSODFHDOOGLRGHVWK\ULVWRUVDQG
FRQWUROSXOVHXQLW
:$51,1*0DJQHWLFIRUFH
7KHUHDUHYHU\VWURQJPDJQHWLFIRUFHVEHWZHHQWKH30*URWRUDQGVWDWRU
1. Be extremely careful when removing the PMG stator frame. There are very strong
magnetism to avoid, and prevent damage to components due to magnetic forces.
2. Remove your own wrist watch, credit cards and digital equipment before working around
those strong magnetic forces.
3. Personnel with pace maker should not be working in the vecinity of the PMG.
'LVPDQWOLQJRIGLRGHDQGWK\ULVWRU
When dismantling of thyristor: Disconnect the cable from the control pulse unit. Observe the
connection of the cable to the control pulse unit. The new thyristor should have same connection
during assembly procedure.
Loosen the assembly brack from the connection bar and remove the two plastic plugs (one on
each screw). See Figure 2-1 on page 4 and Figure 2-2 on page 5.
3BSM 005449, Rev. B EN -
'LRG
)LJXUH
3BSM 005449 4
6\QFKURQRXVPDFKLQH
&KDQJHRIGLRGHVDQGWK\ULVWRUV
$06
)LJXUH
Open the spring lock as shown in Figure 2-3 on page 5 and Figure 2-4 on page 6 at the assembly
bracket by using a screw driver.
)LJXUH
3BSM 005449, Rev. B EN -
3BSM 005449 5
6\QFKURQRXVPDFKLQH
&KDQJHRIGLRGHVDQGWK\ULVWRUV
6SULQJORFN
$06
)LJXUH
Loosen the hex. head socket cap bolts while pushing out the spring lock. Loosen the bracket so
much that the diode/thyristor can be removed. See Figure 2-5 on page 6.
'LRGH
)LJXUH
3BSM 005449, Rev. B EN -
3BSM 005449 6
6\QFKURQRXVPDFKLQH
&KDQJHRIGLRGHVDQGWK\ULVWRUV
Observe and write down the direction of the black arrow on the front of the diode/thyristor. The
replacement diode/thyristor must point in the same direction during assembly procedure, see
Figure 2-6 on page 7.
$06
)LJXUH
$VVHPEOLQJRIGLRGHDQGWK\ULVWRU
7K\ULVWRU
Thyristor connections (wires) must be soldered as shown in Figure 2-7 on page 7 to ensure safe
operating conditions.
3BSM 005449, Rev. B EN -
$06
)LJXUH
Put a protective sleeve over the cable and a pin in the end of the cable. Connect the cable to the
control pulse unit at same place as before.
3BSM 005449 7
6\QFKURQRXVPDFKLQH
&KDQJHRIGLRGHVDQGWK\ULVWRUV
'LRGHDQG7K\ULVWRU
Clean the contact surface between the diode/thyristor and the assembly bracket, and the contact
surface between the diode/thyristor and the heat sink with a piece of cloth damped in
ACETONE. See Figure 2-8 on page 8.
&OHDQWKHFRQWDFW
VXIDFHV
'LRGH
)LJXUH
Clean the contact surfaces of the new diode/thyristor by using steel wool and a cloth damped
with ACETONE. See Figure 2-9 on page 8 and Figure 2-10 on page 9.
$06
)LJXUH
3BSM 005449, Rev. B EN -
3BSM 005449 8
6\QFKURQRXVPDFKLQH
&KDQJHRIGLRGHVDQGWK\ULVWRUV
$06
)LJXUH
Apply a thin coat of Silicon grease to both sides (contact areas) of the diode/thyristor.
Place the diode/thyristor back between the heat sink and the mounting bracket.
Rotate the diode so that the arrow marking of the diode/thyristor is visible at the front . Check
that the black arrow on the diode/thyristor points in the same direction as the one that was
removed earlier. See Figure 2-11 on page 9.
'LRGH
)LJXUH
Be careful that both guide pins (roll pins) are in place before tightening bolts.
Tighten the screws carefully one at the time so that the mounting bracket applies an even
pressure to the diode.
A spring is attached on the mounting bracket which snaps in place when the right torque is
3BSM 005449, Rev. B EN -
reached (note that in the dismantling mode, the screw driver was used to remove this spring to
permit loosening of the screws). Use a “dentists mirror” (a mirror with a handle) behind the
spring to check that the spring has snapped in place. Check with the mirror that there is no
3BSM 005449 9
6\QFKURQRXVPDFKLQH
&KDQJHRIGLRGHVDQGWK\ULVWRUV
visible gap between the spring and the mounting bracket body. The spring must be in place
before the assembly is completed. See Figure 2-12 on page 10.
$06
)LJXUH
Replace the plastic plugs.
&KDQJHRIFRQWUROSXOVHXQLW
Disconnect the thyristor cables.
Loosen the two bolts which attaching the control pulse unit to the exciter hub, see Figure 2-13
on page 10.
/RRVHQ
3BSM 005449, Rev. B EN -
$06
)LJXUH
2EVHUYHWKHFRQQHFWLRQRIWKHFRQWUROSXOVHXQLWWKHQHZFRQWUROSXOVHXQLWVKRXOGKDYH
WKHVDPHFRQQHFWLRQ
3BSM 005449 10
6\QFKURQRXVPDFKLQH
&KDQJHRIGLRGHVDQGWK\ULVWRUV
5HFRPPHQGHGWLJKWHQLQJWRUTXHIRUEROWV
Recommended tightening torque for bolts property class 8.8, slightly coated with oil.
127( 'RQRWXVH0RO\EGHQXPGLVXOSKLGH³0RO\FRWH´
3BSM 005449 11
3BSM 005449
2003-01-15
Service & repair Synchronous machine
Dismantling and assembly of the rotor
earth fault detection system and the
PMG-stator
Document No.:3BSM901594
Contents
1 - Safety
1.1 General safety instructions................................ 3
NOTICE
The information in this document is subject to change without notice and should not be construed as a commitment by ABB.
ABB assumes no responsibility for any errors that may appear in this document.
In no event shall ABB be liable for direct, indirect, special, incidental or consequential damages of any nature or kind arising
from the use of this document, nor shall ABB be liable for incidental or consequential damages arising from use of any software
or hardware described in this document.
This document and parts thereof must not be reproduced or copied without ABB’s written permission, and the contents thereof
must not be imparted to a third party nor be used for any unauthorized purpose.
3BSM901594 ii
Synchronous machine
Safety
1 Safety
3BSM901594 3
Synchronous machine
Dismantling and assembly of the rotor earth fault detection system and PMG-stator
Cable tray
Figure 2-1
3BSM901594, Rev. - EN
3BSM901594 4
Synchronous machine
Dismantling and assembly of the rotor earth fault detection system and PMG-stator
Remove the rotor earth fault antenna in accordance with Figure 2-2 on page 5. Be careful not to
damage the rotor earth fault unit. If needed loosen the cable (from the junction box) to be able to
remove the antenna safely.
Cover drum
Figure 2-2
Loosen the bolts and remove both halves of the internal PMG protective cover plates. See
Figure 2-3 on page 5.
Keyphasor
Figure 2-3
3BSM901594, Rev. - EN
3BSM901594 5
Synchronous machine
Dismantling and assembly of the rotor earth fault detection system and PMG-stator
Dismantling the PMG cover drum and then lift the cover drum away, by using a crane. Be
careful during the disassembly and when the cover drum is lifted away, in order not to damage
the keyphasor.
AMS.-66
Figure 2-4
Place a sheet of stiff paper or plastic in the airgap (around PMG rotor), as shown in Figure 2-5
on page 6.
Stiff paper
3BSM901594, Rev. - EN
AMS-24
Figure 2-5
3BSM901594 6
Synchronous machine
Dismantling and assembly of the rotor earth fault detection system and PMG-stator
Attach lifting chains to the PMG stator frame, remove the bolts and the guide pins. See Figure
2-6 on page 7.
Guide pin
Figure 2-6
Lift the PMG stator frame, carefully with the crane, axially away from the generator.
Note and take care of the guide pinsmotor.
NOTE: There are very strong magnetic forces between the PMG rotor and stator. Be
extremely careful when moving the PMG stator frame to avoid damage to
components due to magnetic forces. Remove your own wrist watch, credit cards
and digital equipment before working around those strong magnetic forces.
3BSM901594, Rev. - EN
3BSM901594 7
Synchronous machine
Dismantling and assembly of the rotor earth fault detection system and PMG-stator
Now you are ready for changing diodes or thyristors as described in document “Replacement of
diodes and thyristors”, Figure 2-7 on page 8
AMS-33
Figure 2-7
3BSM901594, Rev. - EN
3BSM901594 8
Synchronous machine
Dismantling and assembly of the rotor earth fault detection system and PMG-stator
Before assembling the stator, make a simple protection sleeve of stiff paper or plastic.
Lift the PMG-stator with a crane and move carfully over the paper sleeve. See Figure 2-8 on
page 9.
Protection sleeve
AMS-24
Figure 2-8
Be sure that the guide pins fit into the holes in the exciter stator .
3BSM901594, Rev. - EN
While the stator is suspended, insert all the bolts including washers and tightening the lightly.
3BSM901594 9
Synchronous machine
Dismantling and assembly of the rotor earth fault detection system and PMG-stator
Check the air gap between rotor and stator, see Figure 2-9 on page 10.§
AMS-51
Figure 2-9
The air gap between rotor and stator is approx. 2.0 mm.
Adjust the air gap with the two adjusting bolts, which are placed on the stator frames lower feet
according to Figure 2-10 on page 10
Adjusting bolt
AMS-52
Figure 2-10
3BSM901594, Rev. - EN
3BSM901594 10
Synchronous machine
Dismantling and assembly of the rotor earth fault detection system and PMG-stator
When an acceptable air gap is obtained, tighten the bolts, see Figure 2-11 on page 11, place
feeler guages between the stator and rotor with the desired thickness at 9 o’clock, 3 o’clock and
12 o’clock position to check that the air gap is still correct.
Guide pin
Figure 2-11
Remove the feeler guages. Check the air gap with a feeler in a final check around the periphery.
The air gap (tolerance) must not exceed 0.25mm.
If the tolerance between 3 and 9 o’clock or between 6 and 12 o’clock exceeds 0.25 mm the
bolts must be loosened and carefully retightened. The periphery must be rechecked with
feeler guages until the required tolerance is obtained. After the tolerance is reached,
redrill the guide pin holes.
Insert the cylindrical guide pins in the frames feet, see Figure 2-12 on page 11.
AMS-53
Figure 2-12
3BSM901594, Rev. - EN
3BSM901594 11
Synchronous machine
Dismantling and assembly of the rotor earth fault detection system and PMG-stator
Connect the wires from the PMG stator to the terminal as shown in Figure 2-13 on page 12.
AMS-66
Figure 2-13
Remove the protection sleeve from the magnets.
Assemble the PMG cover drum.
3BSM901594 12
Synchronous machine
Dismantling and assembly of the rotor earth fault detection system and PMG-stator
Bolt size M8 M 10 M 12
Bolt size M 16 M 20 M 24 M 30
3BSM901594 13
3BSM901594
2008-02-18
Service & Repair 6\QFKURQRXVPDFKLQH
Dismantling and assembly of exciter
stator
Document No.:3BSM 005448
Contents
6DIHW\
1.1 General safety instructions .........................3
'LVPDQWOLQJDQGDVVHPEO\RIWKHH[FLWHU
VWDWRU
2.1 Dismantling of the exciter stator.................4
2.2 Assembly of exciter stator ..........................9
2.3 Recommended tightening
torque for bolts..........................................10
6\QFKURQRXVJHQHUDWRUW\SH*%$
127,&(
The information in this document is subject to change without notice and should not be construed as a commitment by ABB.
ABB assumes no responsibility for any errors that may appear in this document.
In no event shall ABB be liable for direct, indirect, special, incidental or consequential damages of any kind arising from the use
of this document, nor shall ABB be liable for incidential or consequential damages arising from the use of any software or
hardware described in this document.
This document and parts thereof must not be reproduced or copied without ABB’s written permission, and the contents thereof
must not be imparted to a third party nor be used for any unauthorized purpose.
6DIHW\
*HQHUDOVDIHW\LQVWUXFWLRQV
The procedures described in this manual are only to be performed by trained personnel
authorized by the user.
The manufacturer is not responsible for malfunctions that comprise safety as a result of
alteration, use of non ABB replacement parts, neglect or misuse.
Replacement parts may vary from those shown in this manual. Should you have questions on
those parts please contact ABB Automation Technologies AB.
The actual appearance of the machine may vary from the illustration in this manual.
Should pre-owned ABB equipment be purchased and reconditioned, the equipment should not
be used until testing and analysis demonstrate that the equipment meet the original or upgraded
specifications.
The use of solvents as cleaning agents and the use of lubricants can involve health and/or safety
hazards. The recommended precautions and procedures of the manufacturers should be
followed.
3BSM 005448, Rev B EN -
3BSM 005448 3
6\QFKURQRXVPDFKLQH
'LVPDQWOLQJDQGDVVHPEO\RIWKHH[FLWHUVWDWRU
'LVPDQWOLQJDQGDVVHPEO\RIWKHH[FLWHUVWDWRU
'LVPDQWOLQJRIWKHH[FLWHUVWDWRU
:$51,1*5,6.RISHUVRQDOLQMXU\
%HIRUHGLVPDQWOLQJWKHIROORZLQJPXVWEHGRQH
1. The machine must be completely stopped, dead, diconnected and grounded before
dismatling the exciter stator.
Remove all external cables from the junction boxes on exciter stator housing. Loosen the bolts
which attache the exciter stator housing, see Figure 2-1 on page 4.
/RRVHQWKHEROWV
$06
)LJXUH
3BSM 005448, Rev B EN -
3BSM 005448 4
6\QFKURQRXVPDFKLQH
'LVPDQWOLQJDQGDVVHPEO\RIWKHH[FLWHUVWDWRU
:$51,1*+HDY\OLIW
7KHH[FLWHUVWDWRUKRXVLQJLVDKHDY\XQLW
1. Use lifting equipment that is appropriate for the load, see TBA for weight.
Lift carefully away the exciter stator housing, see Figure 2-2 on page 5.
$06
)LJXUH
3BSM 005448, Rev B EN -
3BSM 005448 5
6\QFKURQRXVPDFKLQH
'LVPDQWOLQJDQGDVVHPEO\RIWKHH[FLWHUVWDWRU
Remove the bolts of the inner cover plates between generator housing and the exciter stator, see
Figure 2-3 on page 6.
$06
)LJXUH
Remove the four bolts (two on each side) which attached the exciter stator, according to Figure
2-4 on page 6 and Figure 2-5 on page 7.
$06
)LJXUH
3BSM 005448, Rev B EN -
3BSM 005448 6
6\QFKURQRXVPDFKLQH
'LVPDQWOLQJDQGDVVHPEO\RIWKHH[FLWHUVWDWRU
$06
)LJXUH
Remove the bolts and the guide pins from the exciter stator footplates, see Figure 2-6 on page 7.
5HPRYHEROWVDQGJXLGHSLQV
$06
)LJXUH
3BSM 005448, Rev B EN -
3BSM 005448 7
6\QFKURQRXVPDFKLQH
'LVPDQWOLQJDQGDVVHPEO\RIWKHH[FLWHUVWDWRU
Remove the space heater before lifting away the exciter stator, to be sure not to destroy the
space heater.
:$51,1*+HDY\OLIW
7KHH[FLWHUVWDWRULVDYHU\KHDY\XQLW
1. Use lifting equipment that is appropriate for the load, see TBA for weight.
Attach lifting chains to the fore and rear exciter stator flange, see Figure 2-7 on page 8, and
carefully lift the unit away to not damage the exciter rotor.
$06
)LJXUH
Each set of shims must be held together, marked and stored so that they are returned to the same
side when ressembling the exciter stator.
3BSM 005448, Rev B EN -
3BSM 005448 8
6\QFKURQRXVPDFKLQH
'LVPDQWOLQJDQGDVVHPEO\RIWKHH[FLWHUVWDWRU
$VVHPEO\RIH[FLWHUVWDWRU
Assemble the exciter stator in reverse order as described in section 2.1
Carefully lift the exciter stator and slide the stator axially and very carefully over the exciter
rotor.
Place the same shims under the foot plates of the stator flange and behind the stator flange.
Replace the guide pins and the bolts.
Check the air gap.
Check that the sealing has not been damaged, if necessary replace them.
Assemble the inner cover plates between the machine housing and the exciter stator.
Assemble the exciter stator cover.
Assemble all external cables.
3BSM 005448, Rev. B EN -
3BSM 005448 9
6\QFKURQRXVPDFKLQH
'LVPDQWOLQJDQGDVVHPEO\RIWKHH[FLWHUVWDWRU
5HFRPPHQGHGWLJKWHQLQJWRUTXHIRUEROWV
Recommended tightening torque for bolts property class 8.8, slightly coated with oil.
127( 'RQRWXVH0RO\EGHQXPGLVXOSKLGH³0RO\FRWH´
3BSM 005448 10
3BSM 005448
2003-01-15
Service & Repair 6\QFKURQRXVPDFKLQH
Dismantling and assembly of
bearing
Document No.: 3BSM 005443
Contents
6DIHW\
1.1 General safety instructions .........................3
'LVPDQWOLQJDQGDVVHPEO\RIEHDULQJ
2.1 Dismantling of bearing ...............................4
2.2 Assembly of bearings ...............................12
2.3 Recommended tightening torque for bolts in
bearing ......................................................23
6\QFKURQRXVPDFKLQH
127,&(
The information in this document is subject to change without notice and should not be construed as a commitment by ABB.
ABB assumes no responsibility for any errors that may appear in this document.
In no event shall ABB be liable for direct, indirect, special, incidental or consequential damages of any kind arising from the use
of this document, nor shall ABB be liable for incidential or consequential damages arising from the use of any software or
hardware described in this document.
This document and parts thereof must not be reproduced or copied without ABB’s written permission, and the contents thereof
must not be imparted to a third party nor be used for any unauthorized purpose.
3BSM 005443 ii
6\QFKURQRXVPDFKLQH
6DIHW\
6DIHW\
*HQHUDOVDIHW\LQVWUXFWLRQV
The procedures described in this manual are only to be performed by trained personnel
authorized by the user.
The manufacturer is not responsible for malfunctions that comprise safety as a result of
alteration, use of non ABB replacement parts, neglect or misuse.
Replacement parts may vary from those shown in this manual. Should you have questions on
those parts please contact ABB Automation Technologies AB.
The actual appearance of the machine may vary from the illustration in this manual.
Should pre-owned ABB equipment be purchased and reconditioned, the equipment should not
be used until testing and analysis demonstrate that the equipment meet the original or upgraded
specifications.
The use of solvents as cleaning agents and the use of lubricants can involve health and/or safety
hazards. The recommended precautions and procedures of the manufacturers should be
followed.
3BSM 005443, Rev. B EN -
3BSM 005443 3
6\QFKURQRXVPDFKLQH
'LVPDQWOLQJDQGDVVHPEO\RIEHDULQJ
'LVPDQWOLQJDQGDVVHPEO\RIEHDULQJ
'LVPDQWOLQJRIEHDULQJ
:$51,1*5LVNRISHUVRQDOLQMXU\
%HIRUHGLVPDQWOLQJWKHIROORZLQJPXVWEHGRQH
1. The machine must be completely stopped, dead, disconnected and grounded before
dismantling the machine.
Before starting the dismantling of the bearing, rotate the rotor so that the poles are at 90 degrees
to the vertical.
Remove the upper half of the bearing support.
Disconnect the Bentley Nevada cable inside the protective housing on the bearing and remove
the Bentley Nevada probes. Remove the flexible protective tube between the Bentley Nevada
body housing and the generator end plate.
Loosen all cables from the cable brackets.
Loosen the cable from the vibration detector and remove the vibration probes.
If lower half of the bearing shell will be removed from the bearing housing, the temperature
probe has to be dismantled from the bearing housing.
7KHWHPSHUDWXUHSUREHLVDSDUWRIERWKWKHEHDULQJVKHOODQGWKHEHDULQJKRXVLQJ DQG
KDVWREHUHPRYHGLIWKHEHDULQJVKHOOZLOOEHPRYHGIURPLWVSRVLWLRQ
Remove the bolts in the upper half of the bearing housing, see Figure 2-1 on page 4, Figure 2-2
on page 5 and Figure 2-3 on page 6.
3BSM 005443, Rev. B EN -
$06
)LJXUH
3BSM 005443 4
6\QFKURQRXVPDFKLQH
'LVPDQWOLQJDQGDVVHPEO\RIEHDULQJ
7L
7LJKWHQLQJFRYHU
$06
)LJXUH
3BSM 005443, Rev. B EN -
3BSM 005443 5
6\QFKURQRXVPDFKLQH
'LVPDQWOLQJDQGDVVHPEO\RIEHDULQJ
$LUORFNVHDO
$06
)LJXUH
Carefully lift upper half of the bearing housing away. see Figure 2-4 on page 6
$06
)LJXUH
3BSM 005443, Rev. B EN -
3BSM 005443 6
6\QFKURQRXVPDFKLQH
'LVPDQWOLQJDQGDVVHPEO\RIEHDULQJ
Remove the springs on each bearing seal and remove the bearing seal, see Figure 2-5 on page 7.
$06
)LJXUH
Remove the bolts from the upper half of the bearing half and disconnect the earthing cable, see
Figure 2-6 on page 7 and Figure 2-7 on page 8.
$06
)LJXUH
3BSM 005443, Rev. B EN -
3BSM 005443 7
6\QFKURQRXVPDFKLQH
'LVPDQWOLQJDQGDVVHPEO\RIEHDULQJ
(DUWKLQJFDEOH
$06
)LJXUH
Insert lifting eyes and carefully lift the upper bearing half away, see Figure 2-8 on page 8.
$06
)LJXUH
3BSM 005443, Rev. B EN -
3BSM 005443 8
6\QFKURQRXVPDFKLQH
'LVPDQWOLQJDQGDVVHPEO\RIEHDULQJ
Loosen the bolts holding together the oil ring and remove them, (the oil ring is made of brass in
two halves, held together with two bolts and four cylindrical pins) see Figure 2-9 on page 9.
$06
)LJXUH
'LVPDQWOLQJRIWKHORZHUKDOIRIWKHEHDULQJVKHOO
Place a magnetic foot with a dial indicator so that the indicator can measure a vertical
movement (lift) of the rotor as shown in Figure 2-10 on page 9.
3BSM 005443, Rev. B EN -
$06
)LJXUH
Place a hydraulic jack (20 ton lifting capacity) underneath the rotor shaft as shown in Figure
2-11 on page 10 and lift the rotor 0.3-0.4 mm.
3BSM 005443 9
6\QFKURQRXVPDFKLQH
'LVPDQWOLQJDQGDVVHPEO\RIEHDULQJ
:$51,1*&RPSRQHQWGDPDJH
'RQRWOLIWRUORZHUVKDIWPRUHWKDQWKHDERYHVWDWHGWROHUDQFHRWKHUZLVH\RXFDQGDPDJH
WKHEHDULQJDWWKHRWKHUVLGHRIWKHPDFKLQH
$06
)LJXUH
Place two distance element in the air gap between the rotor poles and the stator. Attach a lifting
eye into the lower half of the bearing shell as shown in Figure 2-12 on page 10, and draw the
assembly toward you so that is slides around the journal.
$06
)LJXUH
3BSM 005443, Rev. B EN -
3BSM 005443 10
6\QFKURQRXVPDFKLQH
'LVPDQWOLQJDQGDVVHPEO\RIEHDULQJ
Insert lifting eyes as shown in Figure 2-13 on page 11 and carefully lift lower bearing shell
away.
$06
)LJXUH
Store both halves of the bearing shell in a very clean place. It is strictly forbidden to store metal
chips and other metalic components together with the bearings.
127( 0DNHVXUHWKDWWKHEHDULQJKDOYHVDUHVWRUHGWRJHWKHUDQGWKDWWKH\FDQQRWEH
FRQIXVHGZLWKRWKHUFRPSRQHQWVZKHQERWKEHDULQJ 'HQGDQG1HQG DUHVWRUHG
WRJHWKHU7KHEHDULQJKDOYHVDUHPDUNHGZLWKLGHQWLW\QXPEHUVWRDYRLGLQFRUUHFW
DVVHPEO\ZKLFKFRXOGFDXVHVHULRXVSUREOHPV
127( )RUFKDQJHRIEHDULQJVKHOORUEHDULQJVHDOVUHPRYHRQO\RQHEHDULQJDWDWLPH
'RQRWOLIWRUORZHUWKHURWRUPRUHWKDQPPRWKHUZLVHGDPDJHWRWKH
EHDULQJFDQRFFXURQWKHRWKHUVLGHRIWKHPDFKLQH
127( )RUUHPRYDORIWKHURWRUWDNHDZD\WKHXSSHUSDUWRIERWKEHDULQJKRXVLQJDQG
VKHOOVEHIRUHOLIWLQJWKHURWRUDQGEORFNLQJLWXSE\SODFLQJWKHURWRURQWRZRRGHQ
VKLPVSODFHGLQWKHDLUJDSEHWZHHQVWDWRUDQGURWRU
3BSM 005443, Rev. B EN -
3BSM 005443 11
6\QFKURQRXVPDFKLQH
'LVPDQWOLQJDQGDVVHPEO\RIEHDULQJ
$VVHPEO\RIEHDULQJV
Inspect both the upper and lower bearing shell very carefully for damage, metal chips and
impurities.The inspection is to be made by eye and by using your hand, feeling after damage.
127( ,IERWKEHDULQJVKDYHEHHQUHPRYHGPDNHVXUHWKDWWKHPDWFKLQJEHDULQJVKHOOV
DQGEHDULQJKRXVLQJVZKLFKDUHVWDPSHGZLWKLGHQWLW\QXPEHUVDUHUHDVVHPEOHG
7KHFRPSRQHQWVKDYHEHHQPDFKLQHGWRJHWKHUDQGPXVWEHPDWFKHGIRU
UHDVVHPEO\
&KHFNWKDWWKHEHDULQJKRXVLQJVDUHDEVROXWHO\FOHDQDQGIUHHIURPIRUHLJQPDWWHU
Basically, reassembly is executed in the reverse order as described in section 2.1.
The hydraulic jack is still underneath the rotor shaft as described in section 2.1, Figure 2-11 on
page 10 and use a dial indicator to measure a vertical movement (lift) of the rotor.
Apply a thin coat of oil to components which are to be assembled.
3BSM 005443, Rev. B EN -
3BSM 005443 12
6\QFKURQRXVPDFKLQH
'LVPDQWOLQJDQGDVVHPEO\RIEHDULQJ
Insert three lifting eyes in the lower bearing shell and lift the shell over and onto the rotor shaft.
Remove the two upper lifting eyes. See Figure 2-14 on page 13.
5HPRYH
$06
)LJXUH
Hold onto the upper lifting eye and allow the shell to glide around the journal until the lower
shell is inserted. See Figure 2-15 on page 13 and Figure 2-16 on page 14.
$06
)LJXUH
3BSM 005443, Rev. B EN -
3BSM 005443 13
6\QFKURQRXVPDFKLQH
'LVPDQWOLQJDQGDVVHPEO\RIEHDULQJ
$06
)LJXUH
Lower the rotor shaft carefully into the bearing shell.
Check the distance between the bearing journal and the bearing shell with a feeler guage on
front and rear end of the shell on both sides. The tolerances must be as equal as possible and the
minimum distance between bearing shell and journal must be 0.1 mm. Otherwise the rotor must
be jacked up again. Using a plastic hammer knock slightly at the horizontal joint of the bearing
shell to adjust the spherical position of the bearing. Repeat until an acceptable tolerance is
obtained.
Assemble the oil ring. Apply “Loctite” to the bolts (the oil ring is held together by two bolts and
four cylindrical pins) and tighten. See Figure 2-17 on page 14.
3BSM 005443, Rev. B EN -
$06
)LJXUH
3BSM 005443 14
6\QFKURQRXVPDFKLQH
'LVPDQWOLQJDQGDVVHPEO\RIEHDULQJ
Lift the upper bearing shell into position as shown in Figure 2-18 on page 15.
$06
)LJXUH
Connect the earth cable, se Figure 2-19 on page 15.
(DUWKFDEOH
$06
)LJXUH
3BSM 005443, Rev. B EN -
3BSM 005443 15
6\QFKURQRXVPDFKLQH
'LVPDQWOLQJDQGDVVHPEO\RIEHDULQJ
Insert the bolts and tighten the bolts with a torque wrench. See Figure 2-20 on page 16.
$06
)LJXUH
Assemble the fore and rear bearing seal and the sealing placed inside the tightening cover. See
Figure 2-21 on page 16, Figure 2-24 on page 18 and Figure 2-25 on page 18.
5HDUEHDULQJVHDO
)RUHEHDULQJVHDO
$06
)LJXUH
3BSM 005443, Rev. B EN -
3BSM 005443 16
6\QFKURQRXVPDFKLQH
'LVPDQWOLQJDQGDVVHPEO\RIEHDULQJ
&$87,218VHRIVHDOLQJFRPSRXQG
)ROORZWKHVDIHW\SUHFDXWLRQVDQGSURFHGXUHVRIWKHPDQXIDFWXUHU
Apply a thin coat of “Curil-T” sealing compound in the slot for the bearing seal, according to
Figure 2-22 on page 17.
)LJXU
Apply a thin coat of “Curil-T” sealing compound on the bearing seal, according to Figure 2-23
on page 17.
)LJXU
3BSM 005443, Rev. B EN -
3BSM 005443 17
6\QFKURQRXVPDFKLQH
'LVPDQWOLQJDQGDVVHPEO\RIEHDULQJ
6HDOLQJLQWKHWLJKWHQLQJFRYHU
$06
)LJXUH
$06
)LJXUH
The fore and rear bearing seal must be assemblied so that the axial oil drain hole is located at the
6 o’clock position, turned into the bearing and the radial guide pin (roll pin) fits into the upper
half of the bearing housing at the 12 o’clock position (the guide pin prevent rotation of the
bearing seal).
3BSM 005443, Rev. B EN -
3BSM 005443 18
6\QFKURQRXVPDFKLQH
'LVPDQWOLQJDQGDVVHPEO\RIEHDULQJ
A guide pin is placed on the upper half of the sealing (inside the tightening cover) which should
fit with the slot in the tightening cover (the guide pin prevent rotation of the sealing). See Figure
2-26 on page 19.
$06
)LJXUH
Clean the upper part of the bearing housing and apply a thin coat of oil to the spherical bearing
seat.
&$87,218VHRIVHDOLQJFRPSRXQG
)ROORZWKHVDIHW\SUHFDXWLRQVDQGSURFHGXUHVRIWKHPDQXIDFWXUHU
Clean the horizontal joint of the upper bearing housing carefully and apply a thin coat of
“Curil-T” sealing compound.
3BSM 005443, Rev. B EN -
3BSM 005443 19
6\QFKURQRXVPDFKLQH
'LVPDQWOLQJDQGDVVHPEO\RIEHDULQJ
Lift the upper bearing half into place as shown in Figure 2-27 on page 20.
6HDOLQJFRPSRXQG
$06
)LJXUH
Tighten the bolts with a torque wrench, see Figure 2-28 on page 20, Figure 2-29 on page 21,
and Figure 2-30 on page 21.
$06
)LJXUH
3BSM 005443, Rev. B EN -
3BSM 005443 20
6\QFKURQRXVPDFKLQH
'LVPDQWOLQJDQGDVVHPEO\RIEHDULQJ
$06
)LJXUH
Check the radiall clearance between the shaft and the sealing in the airlock cover. The distance
between the shaft and the sealing must be at 12 o´clock 0.55 mm and at 6 o´clock 0.35 and at 3
and 9 o´clock as equal as possible. Rechecked with a feeler guage until required distance is
obtained.
$LUORFNFRYHU
$06
)LJXUH
3BSM 005443, Rev. B EN -
3BSM 005443 21
6\QFKURQRXVPDFKLQH
'LVPDQWOLQJDQGDVVHPEO\RIEHDULQJ
Check the bearing insulation by megging as shown in Figure 2-31 on page 22 and Figure 2-32
on page 22. Connect the earth cable after megging.
$06
)LJXU
&RQQHFWWKHHDUWK
FDEOHDIWHUPHJJLQJ
$06
)LJXU
The insulation resistance is acceptable if the value is higher then 1 Mohm.
3BSM 005443, Rev. B EN -
3BSM 005443 22
6\QFKURQRXVPDFKLQH
'LVPDQWOLQJDQGDVVHPEO\RIEHDULQJ
5HFRPPHQGHGWLJKWHQLQJWRUTXHIRUEROWVLQEHDULQJ
Recommended tightening torque for bolts, slightly coated with oil.
127( 'RQRWXVH0RO\EGHQXPGLVXOSKLGH³0RO\FRWH´
3BSM 005443 23
3BSM 005443
2001-09-13
Service & Repair Synchronous machine
Instruction for removal of
rotor on site
(AMS 710, 800, 900)
Document No.: 3BSM 009019
Contents
1 - Safety
1.1 General safety instructions ......................... 3
NOTICE
The information in this document is subject to change without notice and should not be construed as a commitment by ABB
Industrial Systems AB. ABB Industrial Systems AB assumes no responsibility for any errors that may appear in this document.
In no event shall ABB be liable for direct, indirect, special, incidental or consequential damages of any kind arising from the use
of this document, nor shall ABB be liable for incidential or consequential damages arising from the use of any software or
hardware described in this document.
This document and parts thereof must not be reproduced or copied without ABB Industrial Systems AB’s written permission,
and the contents thereof must not be imparted to a third party nor be used for any unauthorized purpose.
3BSM 009019 ii
Synchronous machine
Safety
1 Safety
3BSM 009019 3
Synchronous machine
Rotor removal
Preparations
Remove the cooler top, covers, bearings, main rotor and perform level 4 inspection.
Dismantling, assembling and inspections including measurements in accordance with the order
specific manual for the machine.
3BSM 009019, Rev. A EN -
3BSM 009019 4
Synchronous machine
Rotor removal
Sliding plate D
Sliding support plate
Front support
Sliding plate ND
Figure 2-1
3. Ensure before start of work that the machine is disconnected from the high voltage net and
that the circuit breaker is locked in the open position so it not accidentally (or otherwise)
3BSM 009019 5
Synchronous machine
Rotor removal
can be closed during work and measurements. Ensure that the machine is grounded. See
users manual, Chapter 5.
4. Before use inspect the installed lifting equipment and ensure that all lifting equipments
have current test certificates.
5. Disconnect the machine shaft from all the driven object. The rotor pole position should be
3, 6, 9 and 12 o’clock.
6. Remove the inspection covers on ND- and D-side. Remove the cooler top by the crane.
7. (If PMG), remove the PMG stator by the truck and in accordance with the manual.
8. Remove the exciter stator by the truck and in accordance with the manual.
9. Remove the pipes for oil, temperature probes etc from the bearing in accordance with the
manual.
10. Assembly the draw plate to the shaft end on ND-end.
11. Erect the mobile/overhead crane on the ND-end side for lifting and removing of the rotor.
See Figure 2-2 on page 6.
Front support
Figure 2-2
12. Dismantle the upper half of the ND- and D-end bearing in accordance with the manual.
13. Place the lift jack underneath the shaft on D-end side.
14. Lift the rotor about 5 mm.
15. Dismantle the lower part of the ND-end bearing and the end shield.
3BSM 009019, Rev. A EN -
16. Mount the front support of the sliding tool on the ND-end of the machine housing.
3BSM 009019 6
Synchronous machine
Rotor removal
Figure 2-3
17. Place the sliding support plate into the air gap between the rotor and stator. Extreme care
should be taken when inserting the tool not to damage the stator core and winding. See
Figure 2-2 on page 6 and Figure 2-3 on page 7.
18. Bolt the sliding support plate to the front support.
19. Place the two sliding plates into the air gap, one at ND-end and one at D-end.
Figure 2-4
20. Apply the towing equipment on D-end and ND-end, use tackle blocks/chain hoists
(optional equipment) and slings (optional equipment). See Figure 2-4 on page 7.
D-end - shall be mounted somewhere on the gearbox/steam turbine, on a hook in the
wall or something else and around the shaft end, and shall be used as
counterstay to prevent to much movement during the removal of the rotor.
ND-end - shall be mounted on a hook in the wall or somewhere else and to the draw plate
mounted on the shaft, and shall be used to draw the rotor out of the stator.
3BSM 009019, Rev. A EN -
21. Remove the lower half of the D-end bearing and end shield in accordance with the manual.
3BSM 009019 7
Synchronous machine
Rotor removal
22. Lower the rotor so that it rests on the sliding tool. See Figure 2-5 on page 8.
Figure 2-5
23. Remove the lift jack on D-end side.
24. Gently pull the rotor towards to the ND-side and at same time loose on D-side until the
centre of the rotor is well outside the machine housing.
25. Support underneath the shaft on the ND-end by hard wood. See Figure 2-6 on page 8.
Figure 2-6
3BSM 009019, Rev. A EN -
3BSM 009019 8
Synchronous machine
Rotor removal
26. Move the slings to be around the rotor body and move carefully towards the ND-side. Be
sure that the rotor is in balance before moving so the rotor not will destroy the stator coil
ends. Move until the rotor is free to lift away. See Figure 2-7 on page 9
Figure 2-7
27. Dismantle the towing equipment.
28. Lay down the rotor on the cradle. See Figure 2-8 on page 9.
Cradle
Figure 2-8
29. Perform the inspection Level 4 in accordance with the manual.
3BSM 009019, Rev. A EN -
3BSM 009019 9
Synchronous machine
Rotor removal
Store the rotor on solid supports and high enough so that the exciter not will be destroyed.
Protect the rotor with a tapaulin.
Store both halves of the bearing shells in a very clean place- It is strictly forbidden to store
metal chips and other metallic compontent together with the bearings.
Make sure that the bearing halves are stored toghether and that they cannot be confused
with other components when both bearings (D-side and ND-side) are store together. The
bearing halves are marked with identity numers to avoid incorrect assembly which could
cause serious problems.
3BSM 009019, Rev. A EN -
3BSM 009019 10
Synchronous machine
Rotor removal
Figure 2-9
6. Put a support underneath the shaft on the ND-end by hard wood.
7. Move the slings from the rotor body to the shaft end (ND-side) according to Figure 2-10
on page 11.
Towing eqiupment
Towing eqiupment
Figure 2-10
8. Apply the towing equipment on D-end and ND-end, use tackle blocks/chain hoists
3BSM 009019, Rev. A EN -
(optional equipment) and slings (optional equipment). See Figure 2-10 on page 11.
D-end - shall be mounted somewhere on the gearbox/steam turbine, on a hook in the
3BSM 009019 11
Synchronous machine
Rotor removal
wall or something else and around the shaft end, and shall be used to draw the
rotor into the stator.
ND-end - shall be mounted on a hook in the wall or somewhere else and to the draw plate
mounted on the shaft, and shall be used as counterstay to prevent to much
movement during assembling of the rotor.
9. Gently pull the rotor towards to the D-side and at same time loose on ND-end until the
rotor is in place in the stator in same position as before dismantling.
10. Place a lift jack underneath the shaft on D-end side. Figure 2-11 on page 12
Figure 2-11
11. Lift the rotor, on D-end, about 0.5mm with the lifting jack.
12. Assembly the lower half of the D-end bearing and end shield in accordance with the
manual.
13. Remove the towing equipments.
14. Remove the two sliding plates from the air gap.
15. Loosen the bolts for the sliding support plate from the front support.
16. Remove the sliding support plate.
17. Reassembly the lower part of the ND-end bearing and the end shield.
18. Lower the rotor down into the bearing.
19. Remove the lifting jack from D-side.
20. Remove the lifting slings.
21. Reassembly the upperhalf of the ND-end and D-end bearing accordance with the user’s
manual.
22. Reassembly the pipes for oil, temperature probes, etc from the bearing in accordings with
the user’s manual.
23. Reassembly the exciter stator by the truck and in accordance with the manual.
24. (If PMG) Reassembly the PMG stator by the truck in accordance with the manual.
25. Reassembly the inspection covers on ND-side and D-side.
26. Reassembly the cooler top.
27. Connect the machine shaft to the driven/driving object.
28. Clean and clear site working area of all tools and equipment.
3BSM 009019, Rev. A EN -
3BSM 009019 12
Synchronous machine
Rotor removal
Bolt size M8 M 10 M 12
Bolt size M 16 M 20 M 24 M 30
3BSM 009019 13
3BSM 009019
2005-06-01