FX Fiberglass Scaffold Instruction

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 10

Fiberglass Scaffold

Instruction
Kunming Feixiang Material Technology Co.,
Ltd is a leading company of full insulating FRP
ladders and FRP scaffoldings (platform) in
China, we have more than 20 years of
experience in FRP profile pultrusion and FRP
ladder assembly.
We are ISO 9001, ISO 14001, and ISO 45001
certificated and attend the drafting work of
one ISO standard and several China electric
power industry standards. All of our products
have passed the test of China's national
electricity equipment test center.
Our products include FRP Insulating ladder,
FRP Insulating scaffolding, FRP Insulating
platform lift, FRP Insulating operation pole,
electricity detector, fall protection harness,
and other kinds of electricity station
maintenance products for safety.
Our factory occupies 20000 m2 workshop
and 6000 m2 office area, located in Jinning
Industry Zone of Kunming. About 50 km to
Kunming city, near Kunyu highway, which is
very convenient in transportation.
As the leading company in China's electrical
insulating tool industry, We provide
guaranteed quality, competitive pricing, and
satisfactory after-sales service, wishing to
establish a long-term win-win partnership with
both domestic and foreign customers.
FX Fiberglass Scaffolding

FX FRP scaffolding Products Features of FX Fiberglass scaffolding System


Advantages :
· Manufactured using a tube with an additional circumferential
winding for increased compressive and flexural strength.
• Corrosion Resistant
· Two widths – 850 mm single width and 1350 mm double width.
• Light Weight Width and height can be customized.
• Easy Assembling & Dismantling · High visibility due to vibrant color.
• Narrow width allows easier access · Impact-resistant claws. Ease of brace identification. Buckle
into smaller areas connection, easy and fast operation.

• Range of heights available · Ladders with 320 mm easy climb rung spacing.

• Instant assembly with fold-out · 470 mm frame rung spacing in compliance with Work at Height
frame Regulations.

• Safety features such as locking · Ribbed round tube with good anti-slip effect.
castors included as standard · The maximum platform safe working load is 200 kg. The overall
maximum load is 750 kg.
• Easily folds for transport and
efficient storage · Bottom stabilizers to increase the stability of the platform.
• Non conductive · Equipped with guardrails to improve the safety of working at heights.

• Non sparking · Lock the brake casters.

• Non oxidising · Optional toe guards, effectively prevent people from falling from high
altitudes.
• Clean
· The top layer can be optionally equipped with two platform plates to
• Comfortable to handle in both very increase the working area.
cold and warm climates
· Optionally reinforced support tubes to improve the stability of
scaffolds above 10 m.
· Optional hoisting mechanism tripod to facilitate the transfer of high-
altitude items.

www.fxladder.com 2 ada@fxladder.com / +86 159 3118 6366


FX Fiberglass Scaffolding

Single Width (0.85 m) Scaffolding� Double Width (1.35 m) Scaffolding


(Top Platform Can Set Two Decks )�

www.fxladder.com 3 ada@fxladder.com / +86 159 3118 6366


FX Fiberglass Scaffolding

Component Parts

www.fxladder.com 4 ada@fxladder.com / +86 159 3118 6366


FX Fiberglass Scaffolding

Components List of 850 Width Scaffold

Components List of 1350 Width Scaffold

Notice: Toe board and


hanging frame are optional
parts. If you need them or any
other extra quantity of parts
from the list, please state
when you contact us.

www.fxladder.com 5 ada@fxladder.com / +86 159 3118 6366


FX Fiberglass Scaffolding

Assembly Principles
The manufacturer recommends that two persons are used to build scaffold. Above 4 m
height, it is essential that at least two persons are used. Only climb the scaffold inside.
Always start building with the base frames at the base of the scaffold, and building the Guardrail Part
guardrail frames at the top of the scaffold.

Scaffolds (850 mm width and 1350 mm width):

Extension Part

Base Part

Notice: The Extension Part please refer to the scaffold model schematic.

www.fxladder.com 6 ada@fxladder.com / +86 159 3118 6366


FX Fiberglass Scaffolding

Assembly Procedure
1. Push castor and adjustable leg assemblies 3. Install one side of diagonal brace on the 5. Set the adjustable legs of stabilizer as
into base frame, and lock all castors. first rung of one base frame, and the required to ensure the scaffold vertical
Repeat procedure with two base frames. other side on the third rung of another and level, lock the spring pin clip in
base frame, and lock. Then fit another position.
diagonal brace, and they will cross like the
letter “X”.

2. Fit horizontal braces onto the first and 4. Assemble the platform (trapdoor deck) on 6. Fit extension frame onto the assembled
third vertical rung of base frame with the rung of base frame, and confirm it is frame section and lock the spring pin clip
claws facing outwards, both sides the locked. The position of platform please into place.
same, and make sure they are locked. refer to the scaffold model schematic.

www.fxladder.com 7 ada@fxladder.com / +86 159 3118 6366


FX Fiberglass Scaffolding

Assembly Procedure
7. Install horizontal and diagonal braces, and
ensure that the two diagonal braces on 9. Climb the ladder, and keep body through
the same side between the upper and the protected trapdoor (not stand on the
lower frames are crossed. deck) to set the extension frames and
braces.
Guardrail frames are the top frames of
scaffold. Repeat the previous steps until
the required height of scaffold is reached.

8. Set the ladder on the fixed deck of


platform and lock it to the rung of frame. 11. The scaffold is now complete.
Then fit the upper platform. The trapdoor
of platform between the upper and lower Dismantling Procedure
are in the opposite position.

Please reverse the building sequence if take


down the scaffold. When removing protecting
braces, unlock the claws furthest from the
trapdoor and then return immediately to it.
10. Add optional parts to the guardrail Then unlock the claws at the other ends to
frames, such as the toe board, and remove them from the scaffold.
hanging frame. (If no optional parts,
please ignore this step) Notice: Please always keep your body protected
by braces, frames, and trapdoors when
assembling and dismantling.

www.fxladder.com 8 ada@fxladder.com / +86 159 3118 6366


FX Fiberglass Scaffolding

Safety Instruction Important Notice

• Check that all components are on site, undamaged, and that • Before using, must check to make sure the scaffold is built
they are in functioning correctly. Damaged or incorrect correctly & completely, and that all components are locked.
components should not be used. Never use unstable scaffold.

• Check ground on which scaffold is to be erected and moved is • Scaffold, overall height of which is not over 6 m, can be
capable of supporting the scaffold. moved, only be moved by manual effort, and only from the
base. No person or materials should be on the scaffold during
• Beware of horizontal forces (e.g. power tools) which could
movement.
generate instability. The Maximum horizontal force is 30 kg.
• After every movement, use a spirit level to check that the
• Ensure that the caster brake is on before building up the
scaffold is vertical and level is within 10 mm/m, and set the
scaffold. Ensure all braces and platforms are in correct position
adjustable legs as needed.
and are secured tightly.
• Raising and lowering components, tools, and/or materials by
• If scaffold platform is over 4 m, stabilizers must be installed.
rope should be conducted within the scaffold base. Ensure that
Only use the adjustable to level the scaffold and not to gain
the safe working load of the supporting platform and the
extra height. Adjustable legs should only ever be extended to
scaffold structure is not exceeded.
minimum amount required to level the scaffold.
• Do not use scaffold in strong wind.
• Scaffold must only ever be climbed from the inside and using
the ladders. • The maximum safe working load is 200 kg per platform level,
uniformly distributed up to a maximum of 750 kg per scaffold.
• Do not gain extra height on platform by anything, like boxes
or ladders. • Caution should be exercised when wheeling scaffold over
uneven or sloping ground, paying attention to unlock and lock
• During activities on the scaffold should always wear correct
castors. If stabilizers are fitted, they should be lifted a maximum
personal protective equipment. And never use the scaffold
of 25 mm above the ground, and obstructions should be cleared.
unless the guardrails are fitted.
• Mobile access scaffold are not designed to be lifted or
suspended.

www.fxladder.com 9 ada@fxladder.com / +86 159 3118 6366


FX Fiberglass Scaffolding

Model schematic

2*0.85*6 m Scaffolding� 2*1.35*4 m Scaffolding

www.fxladder.com 10 ada@fxladder.com / +86 159 3118 6366

You might also like