Professional Documents
Culture Documents
CP05-03-MMC-MST-ELE-0030 REV.00 Testing & Commissioning For Lighting Control System
CP05-03-MMC-MST-ELE-0030 REV.00 Testing & Commissioning For Lighting Control System
SN Description
All review comments noted vide PT-CP05-TCMS-33 | 00 dated 13.06.23 have been closed in the revised
1
document.
The revised CP05-03-MMC-MST-MEC-00026 REV.00 Method statement for Testing and Commissioning of
2
Firefighting Pumps, has been reviewed and is accepted for onward submission to the Engineer.
Page 1 of 1
Document Review
SN Description
Reword for clarity, '4. Lower the setting the of pressure switch to prv the end pump from starting' - item
1 4, 5.2 Starting Up For Electric Pump (Pg. 8/16)
Page 1 of 1
DIFC CP-05 Office DOCUMENT NUMBER
Building-Main METHOD STATEMENT
CP05-03-MMC-MST-MEC-0026
Works Package FOR TESTING AND
COMMISSIONING OF FIRE
Project, Dubai, UAE Revision 00
FIGHTING PUMPS
Issue Date 10-06-2023 Page 1 of 24
METHOD STATEMENT
FOR TESTING AND COMMISSIONING OF
FIRE FIGHTING PUMPS
DIFC CP-05 Office DOCUMENT NUMBER
Building-Main METHOD STATEMENT
CP05-03-MMC-MST-MEC-0026
Works Package FOR TESTING AND
COMMISSIONING OF FIRE
Project, Dubai, UAE Revision 00
FIGHTING PUMPS
Issue Date 10-06-2023 Page 2 of 24
CONTENTS
4) RESPONSIBILITIES
4.1 PROJECT MANAGER
4.2 MECHANICAL SENIOR ENGINEER
4.3 MECHANICAL SITE ENGINEER
4.4 MECHANICAL SUPERVISOR
4.5 QA/QC ENGINEER
4.6 SAFETY ENGINEER
5) PROCEDURE / METHOD TO BE EMPLOYED
9) RISK ASSESSMENT
10) ATTACHMENTS
1.2 PURPOSE
The purpose of the documents is to ensure that quality control objectives are
maintained and accurate records are established for all testing and commissioning-
related activities.
1.3 OBJECTIVE
The objective is to ensure that the testing & commissioning plan is executed,
controlled, and documented strictly in compliance with the contract drawings and
specifications.
2.2 DEFINITIONS
• MAIN CONSULTANT means M/S LACASA Architects & Engineering Consultants
• MAIN CONTRACTOR means Ali & Sons Contracting L.L.C
• MEP SUB-CONTRACTOR means MENASCO Mechanical Contracting. LLC.
All work will be undertaken in full accordance with safety procedures specified in the
contractor’s HSE Plan.
Prior to commencing any activity, the labor force shall receive a toolbox on the project
site as per safety regulations.
The general safety guidelines are given below:
1. Ensure the work area is safe & clean.
2. All employees shall adopt safe working practices.
3. Safety equipment (for example, hard hats, safety shoes, coveralls, gloves, goggles, and
face masks as applicable) is to be worn at all times.
4. When working at a high level, the appropriate safety harness shall be used and secured
whilst working-extra care shall be taken whilst using tools at a high level to prevent
dropping.
DIFC CP-05 Office DOCUMENT NUMBER
Building-Main METHOD STATEMENT
CP05-03-MMC-MST-MEC-0026
Works Package FOR TESTING AND
COMMISSIONING OF FIRE
Project, Dubai, UAE Revision 00
FIGHTING PUMPS
Issue Date 10-06-2023 Page 4 of 24
5. Ensure sufficient lighting is available during all stages of testing and commissioning.
6. Report all accidents no matter how small to the safety officer on duty.
7. Ensure any electrical isolation permit is obtained if required, for the testing and
commissioning activities.
4.0 RESPONSIBILITIES (Sub-Contractor)
Mechanical site engineer coordinates all site activities required for the testing and
commissioning as per specification, manufacture datasheet, and approved drawing.
He should ensure to:
• Obtain a work permit if required.
• Coordinate and explain the work to be carried out to the supervisors.
• Coordination with the safety engineer to ensure that the works are carried out in a
safe working atmosphere.
• Coordination with the QC engineer for tests to be carried out and initiate IR for the
inspection of the finished works.
DIFC CP-05 Office DOCUMENT NUMBER
Building-Main METHOD STATEMENT
CP05-03-MMC-MST-MEC-0026
Works Package FOR TESTING AND
COMMISSIONING OF FIRE
Project, Dubai, UAE Revision 00
FIGHTING PUMPS
Issue Date 10-06-2023 Page 5 of 24
Below is a step-wise guide for conducting the testing and commissioning of the firefighting
pump set i.e. electric pump/jockey pump and diesel pumps.
Before starting the commissioning or testing make sure the below requirements are met:
1. Visual inspection of pump assembly to check for no visible sign of cracks, damages,
rust, etc, if any problem do not start the pump until the supplier is aware of the problem.
2. Ensure that all mechanical and electrical installations are as per the approved drawing.
3. Pumps assembly base securely anchored with foundation bolts in the concrete
floor, and theassembly base should be grouted sufficiently to absorb any vibration.
4. Pump assembly base is smooth leveled and aligned with all connecting piping.
6. Pump is installed in the proper direction of flow in relation to the system and the
suction and discharge are connected correctly and are supported with a rigid stand
independent of the pump assembly.
10. Check valve is installed in the discharge line and is the in proper direction
Open the system valve and turn all isolating valves to the fully open
position Set pressure switches to the following setting valves:
All fire pump stop pressure = fire pump shut off pressure + minimum suction pressure
Jockey pump start pressure = stop pressure – 10 PSI
Electric pump start pressure = jockey start pressure – 5 PSI
Diesel pump start pressure = electric pump start pressure – 10 PSI
Use 10 PSI for each additional pump
The final pressures should not exceed the pressure rating of the system
Place all switches for all control panels in the auto mode
In case of any pressure drop in the line due to the hose reel, fire hose, sprinkler opening or
any small leak in the lines, if the pressure reaches the cut-in pressure point for the jockey
pump it will start automatically and stop automatically at cut-off pressure. If the jockey
pump couldn’t maintain the pressure in the system and pressure drop to the cut-in
pressure of the duty pump it will start automatically and stop manually or automatically
after 10 minutes if the pressure reaches the cutoff point. In case of electric supply failure
or mechanical failure of the electric pump, then the diesel engine pump will start
DIFC CP-05 Office DOCUMENT NUMBER
Building-Main METHOD STATEMENT
CP05-03-MMC-MST-MEC-0026
Works Package FOR TESTING AND
COMMISSIONING OF FIRE
Project, Dubai, UAE Revision 00
FIGHTING PUMPS
Issue Date 10-06-2023 Page 10 of 24
automatically when the pressure in the system will reach to cut in pressure of the standby
pump and it should stop manually from the control panel after assuring there is no
requirement of a fire pump to keep running or automatically after 30 minutes if the pressure
reaches to the cutoff point.
5.7.2 Manual Mode Operation
In case of emergency, the pumps can run in manual mode function for the jockey pump by
placing the selector switch in “hand mode”, the electric pump by depressing the “start”
push button, and the diesel pump can start either from the control panel or engine itself by
putting selector switch in “Manual” mode and depressing “crank push button” for a few
second (i.e. for 34 seconds only just to reach firing condition of the engine) or from the
engine instrument panel. All pumps should stop manually if run in manual mode by
returning the switch to the OFF position and depressing the stop push button.
additional risk to the general public or people associated with this project. Where
vehicles are offloaded from public areas, the activity shall be supervised and a
dedicated offloading/storage area shall be provided.
• Plant Equipment - All plant equipment associated with this activity shall be inspected
prior to the works commencing and at regular periods during the works to ensure
that all required certification is current and that the plant equipment is maintained in
a safe and suitable working manner.
• Lighting - always, appropriate and suitable lighting shall be provided to ensure the
works can be undertaken in a safe and competent manner.
• Housekeeping - At all times, M/s MENASCO supervision shall monitor the work
area, so as to reduce, as far as reasonably practical the storage of rubbish, waste
materials, and debris in the workplace. All waste materials generated during the
curse of the shift/day shall be removed from the workplace to a suitable waste
segregation area.
• Working at height - When required, and working above 1.8m and a potential fall
could arise all appropriate measures shall be enforced to ensure that operatives are
afforded a safe and proper temporary working platform. Materials will be stacked in
a safe and secure manner. Scaffolds shall be erected by competent operatives to
an agreed design. Scaffolds shall be inspected before use and at regular periods
thereafter (every 7 days).
• All lifting activities using lifting equipment and accessories must only be carried out
by third-party trained personnel, such as crane operators and riggers
(slinger/signaler). A lifting Plan and Procedure shall be developed, for both common
and critical lifting activities and in place before any work shall commence.
• Any injury/illness sustained whilst at work must be reported immediately and treated
by a trained first aider or HSE Officer. Incident escalation reporting procedure shall
be always followed.
• HSE violation in any HSE procedures whether a project or legal requirement will
result in black points being issued, as per Subcontractor Agreement, and personnel
removed from the site, if necessary.
• COVID-19 precautionary measures shall be communicated to the workforce and all
personnel under our control, including but not limited to social distancing, wearing
of face masks, regular hand washing and disinfecting of work areas, reporting
outbreaks or positive cases, as per ASC Emergency Escalation procedure, etc
DIFC CP-05 Office DOCUMENT NUMBER
Building-Main METHOD STATEMENT
CP05-03-MMC-MST-MEC-0026
Works Package FOR TESTING AND
COMMISSIONING OF FIRE
Project, Dubai, UAE Revision 00
FIGHTING PUMPS
Issue Date 10-06-2023 Page 13 of 24
• Legal and Technical Guidelines to be always followed, including but not limited to:
• Dubai Municipality (DM) – Code of Construction Safety Practice.
• Dubai Development Authority HSE regulations
• Administrative Decision NO. (68) Of 2010 Issue Implementing By-Law of the Roads
and Transport Authority.
• Ministry of Labor and Social Affairs Federal Law No. 8 (1980).
• Ministry of Labor and Social Affairs Ministerial Order No. 32 (1982)
• Federal Law No. 8 Ministerial Order No. 32 (1982) Regarding Determination of Ways
and Means to Protect Employees Against Occupational Hazards
• Ministerial Order No. 37/2 (1982) Regarding the Requirements Standards of Medical
Care to be Provided by the Employer for His Employees
• Ministerial Decision No. 557 of 2008, for the Executive Order of the Federal Law
No.37 of 2006 Concerning Private Security Companies.
10.0 ATTACHMENTS
• Pre-commissioning Check List.
• Testing & Commissioning Check List.
• Risk Assessment.
DIFC CP-05 OFFICE
BUILDING
INSPECTION CHECKLIST
CHECKED BY:
8 Check all the valves in the pump room are monitor by FACP.
Check the diesel tank is fixed properly as per approval and
9
filled.
Ensure there is no leak from the Tank & Bund Wall
10
constructed and fill point installed as per requirement.
Name
Designation
Signature/Date
CP-05 BUILDING
DIFC
INSPECTION CHECKLIST
Commissioning Checklist of Firefighting Pumps
Floor/Location: Date:
Area:
CHECKED BY:
CONSULTA
S/N ACTIVITIES / ITEMS TO BE INSPECTED MMC ASC REM
NT
1.3 Switch on the Breaker of Jockey Panel and check the Panel
indicators are ON
1.5 Set the Cut OFF Pressure of Jockey pump at 175 PSI
1.6 Switch on the Jockey pump and check for Motor Rotation
Drain the water from at any point of the Network and test
1.7 whether the cut in and cut OFF pressure is happening as
per above mentioned pressure set points.
1.8 Once the pressure setting found satisfactory switch off the
Jockey pump.
2.6 Set the Cut OFF Pressure of electrical pump at 175 PSI
Switch on the Electrical pump and check for Motor
2.7 Rotation as per manufacture recommendation.
Run the pump for 5 minutes and monitor for any smoke or
2.8 sounds coming from pump or motor especially its coupler.
Open only the delivery valve of Electrical Pump and put all
2.9 other valve in closed position to test the performance of
fire pump.
Slowly Open the First valve in front side of Flow meter and
2.10 allow the water to flow through Flow meter.
2.11 Let the Second valve after Flow switch be in fully closed
position.
CP-05 BUILDING
DIFC
2.12 Check the Pressure in Panel at full load and make sure Flow
switch at 0% Flow.
Make sure that pressure should not be generated more
2.13 than 140% of the rated head.
2.14 Record the Flow and Pressure
2.15 Slowly open the Second valve after Flow switch and set the
flow at 50%
2.16 Check the pressure in Electrical Panel at 50% Flow
2.17 Make sure we are getting the project Designed rated head
at 50% Flow
2.18 Record the Flow and Pressure
2.19 Slowly open the Second valve after Flow switch and set the
flow at 100 %
2.20 Check the pressure in Electrical Panel at 100% Flow
2.21 Make sure we are getting the project Designed rated head
at 100% Flow
2.22 Record the Flow and Pressure
2.23 Slowly open the Second valve after Flow switch and set the
flow at 150 %
2.24 Check the pressure in Electrical Panel at 150% Flow
2.25 Make sure we are getting not less than 65% of the project
Designed rated head at
150% Flow
2.26 Record the Flow and Pressure
Close all the Valves and run the pump for 10 minutes and
2.27 make sure that pump is shutting off automatically if there
is any pressure drop.
If the Performance test of Electrical Pump found to be
2.28 satisfactory as per Project requirement, switch off the
Electrical Panel.
Commissioning Procedure for Diesel Pump
3
Check the pump is completely primed.
3.1
Make sure that Suction Valve are in open position.
3.2
Switch on the Breaker of Diesel Panel and check the Panel
3.3 indicators are ON
3.4 Set the Cut in Pressure of Diesel pump at 125 PSI
Run the pump for 5 minutes and monitor for any smoke or
3.5 sounds coming from pump or Engine especially its coupler.
Check the flow of cooling water and make sure the 1" PRV
3.6 is set properly
Open only the delivery valve of Diesel Pump and put all
3.7 other valve in closed position
to test the performance of fire pump.
Slowly Open the First valve in front side of Flow meter and
3.8 allow the water to flow through Flow meter.
3.9 Let the Second valve after Flow switch be in fully closed
position.
3.10 Check the Pressure in Panel at full load and make sure Flow
switch at 0% Flow.
Make sure that pressure should not be generated more
3.11 than 140% of the rated head.
3.12 Record the Flow and Pressure.
CP-05 BUILDING
DIFC
3.13 Slowly open the Second valve after Flow switch and set the
flow at 50 %
3.14 Check the pressure in Diesel Panel at 50% Flow
3.15 Make sure we are getting the project Designed rated head
at 50% Flow
3.16 Record the Flow and Pressure
3.17 Slowly open the Second valve after Flow switch and set the
flow at 100 %
3.18 Check the pressure in Diesel Panel at 100% Flow
3.19 Make sure we are getting the project Designed rated head
at 100% Flow
3.20 Record the Flow and Pressure
3.21 Slowly open the Second valve after Flow switch and set the
flow at 150 %
3.22 Check the pressure in Diesel Panel at 150% Flow
3.23 Make sure we are getting not less than 65% of the project
Designed rated head at
150% Flow
3.24 Record the Flow and Pressure
Close all the Valves and run the pump for 30 minutes and
3.25 make sure that pump is shutting off automatically “ or to
be set as manual shut off “
If the Performance test of Diesel Pump found to be
3.26 satisfactory as per Project requirement, switch off the
Diesel Panel.
Area:
PUMP
MAKE
SERIAL NO.
IMP. NO.
RPM
GPM
PSI / BAR
SHUT OFF PSI
DRIVER
MAKE
SERIAL NO.
RPM
HP/KW
FLA
VOLTS AC//DC
PHASE
FREQUENCY
CONTROLLER
MAKE
MODEL
SERIAL NO.
Area:
Area:
Area:
REMARKS
PUMP CUT IN CUT OUT RPT
JOCKEY
ELECTRIC
DIESEL
Severity
Likelihood 1 2 3 4 5
Certain 5 5 10 15 20 25
Very Likely 4 4 8 12 16 20
Likely 3 3 6 9 12 15
SMay Happen 2 2 4 6 8 10
Unlikely 1 1 2 3 4 5
Trivial Risk - No further improvements necessary provided control measures are maintained
Adequately Controlled Risk - Risk is tolerable when control measures identified are implemented
Moderately controlled Risk - Further risk reduction measures should be considered
Intolerable Risk - Seek specialist advice/ support
Aravi Ashok Designation Proj, HSE Manager Date: 25th February 2023 Signature:
Salman Abu Assali Designation Project Manager Date: 25th February 2023 Signature:
MENASCO MECHANICAL CONTRACTING L.L.C. Page 2 of 24
(DIFC – 05 BUILDING LINK BRIDGE MAIN WORKS)
(RISK ASSESSMENT)
Risk Rating Residual ALARP
Effects/ With No Risk Demonst
Sr. (T/A/M/ I) rated
Job Step Hazards Consequences Controls Recommended Control Measures &
Mitigations (Y/N) Action By
Likelihood
Likelihood
(Refer To Risk
(T/A/M/I)
(T/A/M/I)
(The potential to cause harm (Health, (The harm which could
Outcome
(Sequence of
Outcome
Severity
Severity
Injury, Property damage, environment Assessment
working possibly occur).
etc.)) Procedure, PP
activities) 729-RAP)
01 Access to work Unfamiliarity to the site Minor injury 2 3 6 All personnel to undergo site HSE induction 1 3 3 Compliance to
area Unauthorized parking Major Injury before accessing the site for the first time. DM, COP- CHP
Unauthorized access to Property / asset The Ali & Sons Contracting Project HSE Plan 2- 2.1, 2.3
site or taken shortcut damage shall be strictly complied with by all M/s Y
Slip, trip and fall All work shall be carried out in accordance to Senior Project
Obstructed the walkway all applicable UAE Laws and Regulations, DM Engineer
Likelihood
Likelihood
(Refer To Risk
(T/A/M/I)
(T/A/M/I)
(The potential to cause harm (Health, (The harm which could
Outcome
(Sequence of
Outcome
Severity
Severity
Injury, Property damage, environment Assessment
working possibly occur).
etc.)) Procedure, PP
activities) 729-RAP)
Likelihood
Likelihood
(Refer To Risk
(T/A/M/I)
(T/A/M/I)
(The potential to cause harm (Health, (The harm which could
Outcome
(Sequence of
Outcome
Severity
Severity
Injury, Property damage, environment Assessment
working possibly occur).
etc.)) Procedure, PP
activities) 729-RAP)
Visual check and Electrical Hazards Electric shock, All operatives must undergo ASC HSE
Operational
02
Check of Mechanical Hazard electrical fires. 2 3 6 induction prior to start the task at site 1 3 3
Firefighting Moving Machinery Risk: Contact Method statement and risk assessment
pumps
High-Pressure Hazards with live should be briefed to all operative prior to Commissioning
Slips, Trips, and Falls electrical Work activities. Engineer
Chemical Exposure components, Permit to work system to be strictly followed.
Noise and Vibration damaged wiring. Follow electrical safety standards and codes. Project Manager
Hazardous Environments Entanglement, Use appropriate circuit breakers, fuses, and
crush injuries, protective devices. Construction
lacerations. The working area will be pre-inspected for the Manager
Risk: Contact readiness for the start of the installation
with moving works. Senior Project
parts (e.g., Prepare tools/equipment and materials for Engineer
impellers, Y
testing & commissioning.
motors). Main contractor clearance to proceed for the Site Engineer
Injury from high- testing & commissioning has been received.
pressure water, Trained personnel are to be deployed for HSE Officer
cuts, bruises. firefighting pumps testing and commissioning
Risk: Skin work. Supervisors
irritation, burns, Ensure power is disconnected before
and respiratory conducting visual checks, and use insulated Foreman
issues. tools
Risk: Hearing Keep body parts clear of moving parts, use operators
damage, hand- lockout/tag out procedures when necessary,
arm vibration and provide machine guarding to prevent
syndrome. contact with rotating components.
MENASCO MECHANICAL CONTRACTING L.L.C. Page 5 of 24
(DIFC – 05 BUILDING LINK BRIDGE MAIN WORKS)
(RISK ASSESSMENT)
Risk Rating Residual ALARP
Effects/ With No Risk Demonst
Sr. (T/A/M/ I) rated
Job Step Hazards Consequences Controls Recommended Control Measures &
Mitigations (Y/N) Action By
Likelihood
Likelihood
(Refer To Risk
(T/A/M/I)
(T/A/M/I)
(The potential to cause harm (Health, (The harm which could
Outcome
(Sequence of
Outcome
Severity
Severity
Injury, Property damage, environment Assessment
working possibly occur).
etc.)) Procedure, PP
activities) 729-RAP)
elevated areas.
Use hearing protection in noisy areas, conduct
regular vibration assessments, and implement
measures to reduce noise levels and vibration
exposure.
Ensure proper ventilation in pump rooms,
conduct air quality monitoring, and follow
procedures for working in confined spaces.
Handle flammable materials with caution and
follow safety protocols
Wear appropriate PPE such as gloves,
goggles, and respirators.
MENASCO MECHANICAL CONTRACTING L.L.C. Page 6 of 24
(DIFC – 05 BUILDING LINK BRIDGE MAIN WORKS)
(RISK ASSESSMENT)
Risk Rating Residual ALARP
Effects/ With No Risk Demonst
Sr. (T/A/M/ I) rated
Job Step Hazards Consequences Controls Recommended Control Measures &
Mitigations (Y/N) Action By
Likelihood
Likelihood
(Refer To Risk
(T/A/M/I)
(T/A/M/I)
(The potential to cause harm (Health, (The harm which could
Outcome
(Sequence of
Outcome
Severity
Severity
Injury, Property damage, environment Assessment
working possibly occur).
etc.)) Procedure, PP
activities) 729-RAP)
Preparation of Obstruction of access in test Minor Injury Obtain the work permit
Major Injury
03 test instruments, location 2 3 6 Follow the safe operating procedures which is 1 3 3
Electrocution
Materials,
Uncertified or damaged test Property or identified in the MSRA
Manpower, for
equipment meters Asset damaged TBT & Training to be communicated with the Commissioning
testing and
ccommissioning Inexperience or inadequate operatives by the foreman or supervisor Engineer
of firefighting
training of workers involved regarding the hazard, risk and control
pumps
Poor illumination measures for FF Pumps Project Manager
Likelihood
Likelihood
(Refer To Risk
(T/A/M/I)
(T/A/M/I)
(The potential to cause harm (Health, (The harm which could
Outcome
(Sequence of
Outcome
Severity
Severity
Injury, Property damage, environment Assessment
working possibly occur).
etc.)) Procedure, PP
activities) 729-RAP)
Testing and Electrical Hazards Electric shock, MSRA to be briefed to all concerned persons
prior to starting the work at site
04 Commissioning Mechanical Hazard electrical fires. 3 3 9 1 3 3
of firefighting
Moving Machinery Risk: Contact Permit to be obtained prior to start of testing
pumps and commissioning of firefighting pumps.
High-Pressure Hazards with live
Slips, Trips, and Falls electrical Experienced and trained personnel to be used
for testing and commissioning of firefighting
Chemical Exposure components,
pumps.
Noise and Vibration damaged wiring.
Commissioning Engineer to supervise and
Hazardous Environments Entanglement,
monitor the commissioning activity.
crush injuries,
Check the panel and ensure the isolators are
lacerations.
in off position
Commissionin
Risk: Contact
with moving Ensure that the discharge valves and drain g Engineer
valves are closed.
parts (e.g., HSE Officer
Injury from high- Check isolation valve and suction valves and Operatives
ensure there is no leak in the system
pressure water,
cuts, bruises. Ensure no leak while running the pump and
pressurize the discharge header.
Risk: Skin
Testing and commissioning area to be
irritation, burns,
excluded or zone off from unauthorized entry
and respiratory during testing phase.
issues.
Proper signage’s and access control to be put
Risk: Hearing in place during testing period.
damage, hand-
Ensure o test the pumps for emergency
arm vibration operation.
syndrome.
Ensure to start each pump 6 times from the
Auto Sources and run for (5-10) Mines.
MENASCO MECHANICAL CONTRACTING L.L.C. Page 8 of 24
(DIFC – 05 BUILDING LINK BRIDGE MAIN WORKS)
(RISK ASSESSMENT)
Risk Rating Residual ALARP
Effects/ With No Risk Demonst
Sr. (T/A/M/ I) rated
Job Step Hazards Consequences Controls Recommended Control Measures &
Mitigations (Y/N) Action By
Likelihood
Likelihood
(Refer To Risk
(T/A/M/I)
(T/A/M/I)
(The potential to cause harm (Health, (The harm which could
Outcome
(Sequence of
Outcome
Severity
Severity
Injury, Property damage, environment Assessment
working possibly occur).
etc.)) Procedure, PP
activities) 729-RAP)
Startup & Electrical Hazards Minor Injury MSRA to be briefed to all concerned persons
testing of fire
05 water pumps Mechanical Hazard Major injury 3 3 9 prior to starting the work at site 1 3 3
Moving Machinery Property or Permit to Work to be obtained prior to activity.
Jockey Pump High-Pressure Hazards asset Ensure that only competent and experience
Slips, Trips, and Falls damage personnel should be assigned for the
Chemical Exposure firefighting testing and commissioning.
Noise and Vibration Carry out pre check and ensure the availability of
Hazardous Environments power
Ensure selector switch should be turn to hand
mode for a moment
Commissionin
Ensure isolator is switch on
g Engineer
Cut in pressure must be lesser than cut out
HSE Officer
pressure
Y Supervisor
Pay adequate attention on cut in and cut out
Foreman
running pressure
Operatives
Selector switch must be in auto mode
Double check & ensure the cut in and cut out
pressure are set properly
Ensure the pump room is properly tidy and
arranged from object on the floor and cleaned
from slippery agency.
Ensure after completion of the test to disconnect
the isolators and close the valves.
Appropriate PPE shall be used (Hard Hat, Safety
Shoe, Coverall, Hand Gloves, Protective
Glasses, Dust Mask). Suitable PPE as per activity
requirement
MENASCO MECHANICAL CONTRACTING L.L.C. Page 9 of 24
(DIFC – 05 BUILDING LINK BRIDGE MAIN WORKS)
(RISK ASSESSMENT)
Risk Rating Residual ALARP
Effects/ With No Risk Demonst
Sr. (T/A/M/ I) rated
Job Step Hazards Consequences Controls Recommended Control Measures &
Mitigations (Y/N) Action By
Likelihood
Likelihood
(Refer To Risk
(T/A/M/I)
(T/A/M/I)
(The potential to cause harm (Health, (The harm which could
Outcome
(Sequence of
Outcome
Severity
Severity
Injury, Property damage, environment Assessment
working possibly occur).
etc.)) Procedure, PP
activities) 729-RAP)
Electric Pump Electrical Hazards Minor Injury Permit to Work to be obtained prior to activity.
06 Mechanical Hazard Major injury 3 3 9 MSRA to be briefed to all concerned persons prior 1 3 3
(Duty Pumps)
Moving Machinery Property or to starting the work at site
High-Pressure Hazards asset Ensure that only competent and experience
Slips, Trips, and Falls damage personnel should be assigned for the
Chemical Exposure firefighting testing and commissioning.
Noise and Vibration Ensure isolator is switch on Carry out pre check
Hazardous Environments and ensure the availability of power
Ensure the Voltages must be properly display on
the panel.
Commissionin
Carry out pre check and ensure the availability of
g Engineer
power.
HSE Officer
Electric pump (duty pump) cut in should be min 15
Y Supervisor
psi less than jockey pump cut in pressure.
Foreman
Pay adequate attention on cut in and cut out
Operatives
running pressure
Check and ensure that the pump start and run for
10 Mines. Then stop automatically.
Ensure to start pump 6 times from the Auto
Sources and run for (5-10) Mines.
Ensure to start pump 6 times from Manual
sources and run for (5-10) Mines.
Appropriate PPE shall be used (Hard Hat, Safety
Shoe, Coverall, Hand Gloves, Protectives
Glasses, Dust Mask). Suitable PPE as per activity
requirement.
MENASCO MECHANICAL CONTRACTING L.L.C. Page 10 of 24
(DIFC – 05 BUILDING LINK BRIDGE MAIN WORKS)
(RISK ASSESSMENT)
Risk Rating Residual ALARP
Effects/ With No Risk Demonst
Sr. (T/A/M/ I) rated
Job Step Hazards Consequences Controls Recommended Control Measures &
Mitigations (Y/N) Action By
Likelihood
Likelihood
(Refer To Risk
(T/A/M/I)
(T/A/M/I)
(The potential to cause harm (Health, (The harm which could
Outcome
(Sequence of
Outcome
Severity
Severity
Injury, Property damage, environment Assessment
working possibly occur).
etc.)) Procedure, PP
activities) 729-RAP)
Diesel pump Electrical Hazards Minor Injury Permit to Work to be obtained prior to activity
(Standby pump)
07 Mechanical Hazard Major injury MSRA to be briefed to all concerned persons
Moving Machinery Property or prior to starting the work at site
High-Pressure Hazards asset Ensure that only competent and experience
Slips, Trips, and Falls damage personnel should be assigned for the
Chemical Exposure firefighting testing and commissioning
Noise and Vibration Operative must be trained for Electrical Safety
Hazardous Environments prior their task.
Check and note the RPM, water temperature, oil
pressure is in the engine controller gauge,
Commissionin
take necessary readings like flow, etc.
g Engineer
Check and adjust the gland cooling water as per
HSE Officer
the requirement and make sure that the
3 3 9 1 3 3 Y Supervisor
gland is not overheating.
Foreman
Check & Ensure that AC power Availability
Operatives
Check & ensure the engines cooling water flow is
ok and properly drain.
Check & adjust the gland cooling water as per
the requirement and make sure that the
gland is not overheating.
Ensure an adjustment of the PRV (Pressure
Relief Valve) to the max shut off pressure
of the pump
Put in the switch selector in auto mode or by
manually pressing the stop button from
the engine.
Set the cut in, cut out pressure on the main
MENASCO MECHANICAL CONTRACTING L.L.C. Page 11 of 24
(DIFC – 05 BUILDING LINK BRIDGE MAIN WORKS)
(RISK ASSESSMENT)
Risk Rating Residual ALARP
Effects/ With No Risk Demonst
Sr. (T/A/M/ I) rated
Job Step Hazards Consequences Controls Recommended Control Measures &
Mitigations (Y/N) Action By
Likelihood
Likelihood
(Refer To Risk
(T/A/M/I)
(T/A/M/I)
(The potential to cause harm (Health, (The harm which could
Outcome
(Sequence of
Outcome
Severity
Severity
Injury, Property damage, environment Assessment
working possibly occur).
etc.)) Procedure, PP
activities) 729-RAP)
Used of Lack of prior planning Minor Injury The Ali & Sons Contracting Project HSE
08 temporary Failure to installed the system Major Injury Plan shall be strictly complied with by all
power supply as per the approved SLD Property All works shall be regularly monitored and
and Electrical Shock Hazard damaged supervised by M/s MENASCO site team to
Project Manager
Extension leads. Overloading Hazard: ensure full compliance
Trip and Fall Hazard: MENASCO shall provide adequate
Construction
Fire Hazard: resources, as appropriate to ensure safe
Manager
Defective tools and Equipment execution of work scope.
Likelihood
Likelihood
(Refer To Risk
(T/A/M/I)
(T/A/M/I)
(The potential to cause harm (Health, (The harm which could
Outcome
(Sequence of
Outcome
Severity
Severity
Injury, Property damage, environment Assessment
working possibly occur).
etc.)) Procedure, PP
activities) 729-RAP)
Likelihood
Likelihood
(Refer To Risk
(T/A/M/I)
(T/A/M/I)
(The potential to cause harm (Health, (The harm which could
Outcome
(Sequence of
Outcome
Severity
Severity
Injury, Property damage, environment Assessment
working possibly occur).
etc.)) Procedure, PP
activities) 729-RAP)
Use of Materials Moving parts or accidental Ali & Sons HSE Policies and Procedures shall
09 Hand tools and contact with the device. Pinching or be followed by Menasco team prior to start of DM - Code of
portable power Risk of water leakage or spills, crushing injuries, the Activity. construction
electrical shock if the device has cuts, or electrical Permit to Work to be obtained prior to activity. Safety
electrical components, or injury shock if the Menasco to comply with Local Authority Practices
from accidental contact. device has regulations and DDA HSE requirements. CHAPTER 14
electrical MSRA to be communicated with the HandandPowe
Risk of injury from tools or objects
Operated Tools
inside the toolbox, or manual components. operatives by the foreman or supervisor.
Hot Work Permit to be obtained prior to start 182
handling injuries. Slips, trips,
of cutting or grinding activities (If applicable).
electrical shock,
Risk of electrical shock or injury Operator must be trained for Safe Handling of Project Manager
or injuries from
from improper use or contact with Power Tools.
water contact.
Construction
live electrical components.
Use power tools with both hands never use
Electrical shock 3 3 9
1 3 3 Y
single hand. Manager
Using defective power tools. or injuries from
Maintain cable management and use cable
Used of un-inspected power contact with live
Senior Project
stand.
tools. wires
Engineer
Never modify the power tools maintenance
Untrained Workers using Power Minor injury
Repairing must be done only by a competent
tools Personal injury Site Engineer
person.
Failure to use correct PPE Property/asset
Do not use any damage power tool and worn
Improper handling/storage damage HSE Officer
out cable wires.
Misuse of tools
Grinding/Cutting handle to be available
Excess pressure on tools Supervisors
always prior to use at site
Flying fragments Foreman
Poor/lack of supervision T & C Engrs
Tripping
MENASCO MECHANICAL CONTRACTING L.L.C. Page 14 of 24
(DIFC – 05 BUILDING LINK BRIDGE MAIN WORKS)
(RISK ASSESSMENT)
Risk Rating Residual ALARP
Effects/ With No Risk Demonst
Sr. (T/A/M/ I) rated
Job Step Hazards Consequences Controls Recommended Control Measures &
Mitigations (Y/N) Action By
Likelihood
Likelihood
(Refer To Risk
(T/A/M/I)
(T/A/M/I)
(The potential to cause harm (Health, (The harm which could
Outcome
(Sequence of
Outcome
Severity
Severity
Injury, Property damage, environment Assessment
working possibly occur).
etc.)) Procedure, PP
activities) 729-RAP)
.
MENASCO MECHANICAL CONTRACTING L.L.C. Page 15 of 24
(DIFC – 05 BUILDING LINK BRIDGE MAIN WORKS)
(RISK ASSESSMENT)
Risk Rating Residual ALARP
Effects/ With No Risk Demonst
Sr. (T/A/M/ I) rated
Job Step Hazards Consequences Controls Recommended Control Measures &
Mitigations (Y/N) Action By
Likelihood
Likelihood
(Refer To Risk
(T/A/M/I)
(T/A/M/I)
(The potential to cause harm (Health, (The harm which could
Outcome
(Sequence of
Outcome
Severity
Severity
Injury, Property damage, environment Assessment
working possibly occur).
etc.)) Procedure, PP
activities) 729-RAP)
Likelihood
Likelihood
(Refer To Risk
(T/A/M/I)
(T/A/M/I)
(The potential to cause harm (Health, (The harm which could
Outcome
(Sequence of
Outcome
Severity
Severity
Injury, Property damage, environment Assessment
working possibly occur).
etc.)) Procedure, PP
activities) 729-RAP)
Work at Height - Falling of men and materials from Major Injuries The Ali & Sons Contracting Project HSE Plan DM –
10 Using Scaffold, shall be strictly complied with by all Compliance
height Minor Injury
A-Type ladder / All works shall be regularly monitored and CHAPTER 8
Presence of overhead services Fatality
Podium Ladders supervised by M/s MENASCO site team Scaffolding
Incompetent workers Property damaged to ensure full compliance Safety
MENASCO shall provide adequate resources, 101CHAPTER
Lack of supervision
as appropriate to ensure safe execution of work 4Personal
Improper use of work platform
scope. Protective
Unauthorized access to the All work shall be carried out in accordance to all Equipment 44
applicable UAE Laws and Regulations, DM
equipment
Regulations and MMC Project HSE Management Project
Untrained operator
System. Manager
Unfavourableclimatic conditions MSRA to be communicated with the operatives
3 3 9
1 3 3 Y
by the foreman or supervisor. Construction
Unbalancing of work platform
Permit For work at height on scaffolding to be Manager
Caught-in between
available and approved from concerned team prior
Working under direct sun light to start of work. Senior Project
Pre-Task briefing or TBT to be carried out by Engineer
Dust
foreman or supervisor prior to start of work
Noise
communicating hazard and control measures to its Site Engineer
Slippery surface due to leak of oil workers.
Only Competent scaffolder which is 3rd party HSE Officer
certified to erect mobile Aluminum scaffolding and
platform. Supervisors
Operative Working at height must be trained for
Safe Work at height. Foreman
MENASCO MECHANICAL CONTRACTING L.L.C. Page 17 of 24
(DIFC – 05 BUILDING LINK BRIDGE MAIN WORKS)
(RISK ASSESSMENT)
Risk Rating Residual ALARP
Effects/ With No Risk Demonst
Sr. (T/A/M/ I) rated
Job Step Hazards Consequences Controls Recommended Control Measures &
Mitigations (Y/N) Action By
Likelihood
Likelihood
(Refer To Risk
(T/A/M/I)
(T/A/M/I)
(The potential to cause harm (Health, (The harm which could
Outcome
(Sequence of
Outcome
Severity
Severity
Injury, Property damage, environment Assessment
working possibly occur).
etc.)) Procedure, PP
activities) 729-RAP)
Likelihood
Likelihood
(Refer To Risk
(T/A/M/I)
(T/A/M/I)
(The potential to cause harm (Health, (The harm which could
Outcome
(Sequence of
Outcome
Severity
Severity
Injury, Property damage, environment Assessment
working possibly occur).
etc.)) Procedure, PP
activities) 729-RAP)
Working in hot Heat Stress and Heat-related Major Injuries The midday break regulation from DM to be
11 whether Illnesses, Risk: Prolonged
Minor Injury
ensures that outdoor work activities are
exposure to high temperatures suspended during the hottest part of the day
Fines
(Midday Break can lead to heat stress, heat when temperatures are typically at their peak.
Rule between exhaustion, or even heatstroke. Property damaged This allows workers to rest, hydrate, and seek
June 15th To Dehydration: Working in
hot shade during the most intense heat
Project Manager
September environments can lead to Risk Assessment and Planning:
15th ) excessive fluid loss through Working in heat Training and Awareness shall
Construction
sweating, increasing the risk of be provided
Manager
dehydration Encourage workers to drink plenty of water
Sunburn and Skin Damage risk and fluids before, during, and after work to
Senior Project
of skin cancer. prevent dehydration.
Engineer
All ailments due to excessive Schedule frequent rest breaks in shaded or
4
3 12 1 3 3 Y
heat, like cramps, burns, air-conditioned areas to allow workers to cool Site Engineer
headache, dehydration, etc. down and recover from heat exposure.
Plan work activities to minimize exposure HSE Officer
during the hottest parts of the day, such as
scheduling physically demanding tasks in the Supervisors
cooler morning or late afternoon hours Foreman
Ventilation and Airflow
Implement a system for monitoring workers' T & C Engross
health and well-being, including regular
checks for signs of heat-related illnesses
Provision of cool drinking water
Proper cotton clothing
Change in work schedule, wherever possible.
MENASCO MECHANICAL CONTRACTING L.L.C. Page 19 of 24
(DIFC – 05 BUILDING LINK BRIDGE MAIN WORKS)
(RISK ASSESSMENT)
Risk Rating Residual ALARP
Effects/ With No Risk Demonst
Sr. (T/A/M/ I) rated
Job Step Hazards Consequences Controls Recommended Control Measures &
Mitigations (Y/N) Action By
Likelihood
Likelihood
(Refer To Risk
(T/A/M/I)
(T/A/M/I)
(The potential to cause harm (Health, (The harm which could
Outcome
(Sequence of
Outcome
Severity
Severity
Injury, Property damage, environment Assessment
working possibly occur).
etc.)) Procedure, PP
activities) 729-RAP)
Likelihood
Likelihood
(Refer To Risk
(T/A/M/I)
(T/A/M/I)
(The potential to cause harm (Health, (The harm which could
Outcome
(Sequence of
Outcome
Severity
Severity
Injury, Property damage, environment Assessment
working possibly occur).
etc.)) Procedure, PP
activities) 729-RAP)
Likelihood
Likelihood
(Refer To Risk
(T/A/M/I)
(T/A/M/I)
(The potential to cause harm (Health, (The harm which could
Outcome
(Sequence of
Outcome
Severity
Severity
Injury, Property damage, environment Assessment
working possibly occur).
etc.)) Procedure, PP
activities) 729-RAP)
General Obstructed emergency route Minor Injury MSRA should communicate to workers prior to
13 Emergency Lack of emergency rescue team First Aid case commencement of work.
Situations Lack of emergency rescue kit Medical treatment Operatives must be trained of safe and proper
Lack of training to Emergency case use of hand tools.
responder Fines All tools provided must be assessed to ensure
Incompetent emergency responders Property damage that they are fit for purpose, they fit for the Project Manager
Improper or lack of illumination Lack of training to environment in which they are to be used and they
are in good condition. Construction
Improper or lack of ventilation Emergency responder
Manager
Emergency Response Plan
Incompetent
emergency responders Emergency Communication: Senior Project
Improper or lack of Evacuation Procedures Engineer
site.
Emergency vehicle to be available for ERT TEAM
Contact: No # 0543057866
MENASCO MECHANICAL CONTRACTING L.L.C. Page 22 of 24
(DIFC – 05 BUILDING LINK BRIDGE MAIN WORKS)
(RISK ASSESSMENT)
Risk Rating Residual ALARP
Effects/ With No Risk Demonst
Sr. (T/A/M/ I) rated
Job Step Hazards Consequences Controls Recommended Control Measures &
Mitigations (Y/N) Action By
Likelihood
Likelihood
(Refer To Risk
(T/A/M/I)
(T/A/M/I)
(The potential to cause harm (Health, (The harm which could
Outcome
(Sequence of
Outcome
Severity
Severity
Injury, Property damage, environment Assessment
working possibly occur).
etc.)) Procedure, PP
activities) 729-RAP)
14 Housekeeping Slips, Trips, and Falls: Improper Major Injuries Workers must be trained and aware and comply
at workplace disposal of waste can create with the housekeeping plan on the site.
Minor Injury
after the task obstacles and clutter, increasing TBT on housekeeping to be given to all.
Fire
the risk of slips, trips, and falls Removal of all waste from work after the
Project
Contamination and Exposure: Property damaged completion of activity.
Manager
Fire and Combustible Materials: Where possible, packaging materials shall be
Improper disposal and storage of removed from the site the earliest opportunity in
Construction
flammable or combustible order to reduce the fire load.
Manager
materials can increase the risk of Materials to be stacked and stored properly.
fire Signage and Labelling:
Senior
Health Hazards: Inadequate Establish a regular waste removal schedule to
Project
disposal of waste can create an prevent accumulation. Dispose of waste in a
3 2 6 1 2 2 Y Engineer
unhygienic environment, leading timely manner and ensure that waste collection
to health hazards services or processes are in place.
Site Engineer
Conduct routine inspections of waste storage
areas and disposal practices to identify any
HSE Officer
potential hazards, leaks, or improper waste
handling. Promptly address any issues or
Supervisors
deficiencies found during Effective planning for
Foreman
proper materials arrangement and maintain
T & C Engross
housekeeping at site on daily basis
Specific training to be provided to the working
parties for housekeeping.
MENASCO MECHANICAL CONTRACTING L.L.C. Page 23 of 24
(DIFC – 05 BUILDING LINK BRIDGE MAIN WORKS)
(RISK ASSESSMENT)
Risk Rating Residual ALARP
Effects/ With No Risk Demonst
Sr. (T/A/M/ I) rated
Job Step Hazards Consequences Controls Recommended Control Measures &
Mitigations (Y/N) Action By
Likelihood
Likelihood
(Refer To Risk
(T/A/M/I)
(T/A/M/I)
(The potential to cause harm (Health, (The harm which could
Outcome
(Sequence of
Outcome
Severity
Severity
Injury, Property damage, environment Assessment
working possibly occur).
etc.)) Procedure, PP
activities) 729-RAP)
Note: If any new scenarios emerge that are not covered by this risk assessment, site management should be contacted immediately, and the task should not be completed until a specific risk
assessment has been completed, issued, and understood.