L - FA - Niel T. - wk#04 - ICCP Cable Reel Storage & Preservation
L - FA - Niel T. - wk#04 - ICCP Cable Reel Storage & Preservation
2-WI-09-ISSD
E&I 12-18000 UMBILICAL AND ICCP INSTALLATION NPCC ABSF 211 1/12/2023
Storage & Preservation of ICCP Pyramid Anode Sled (Mixed Metal Oxide) assembly with 1C X 70mm sq=400 mtr.length= 06 Set 1.) Anode Sled "A" SI # 95 with cable drum no. 20-3621.2.) Anode Sled "B" SI # 96 with cable drum no. 20-3617.3.) Anode
Sled "C" SI # 98 with cable drum no. 20-3605.4.) Anode Sled "D" SI # 95 with cable drum no. 20-3621.5.) Anode Sled "E" SI # 99 with cable drum no. 20-3605.6.) Anode Sled "F" SI # 100 with cable drum no. 20-3604.
Compliance
Reference
Item No Item Assessed Finding Root Cause Corrective Action Corrective Action Completion Remarks
(SAIC,SAES. Sch. Q. . ETC)
YES NO N/A
Ensure ICCP cable reel are stored to provide easy access for lifting SATIP-P-104-01 /SAEP-385/
1 √ N/R N/R N/R N/R
and moving NFPA 70, NEC 110.3
Cable shall be stored away from open flame, fire, arc welding,
SATIP-P-104-01 /SAEP-385 /
2 brazing, grinding and other sources of high heat or ignition. √ N/R N/R N/R N/R
NFPA 70, NEC 110.3,
SATIP-P-104-01 / SAEP-385/
Check cable ends are sealed (water and dust-proof seals) and
5 NEC, Sec. 110.3 (B), SAES-P- √ N/R N/R N/R N/R
firmly secured
104, Sec. 4.1
Contractor QC: Name:Saeendran Positive Comments / Opportunity for improvement: This assessment carried out was found satisfactory in accordance to the above mentioned SA standards, project quality requirement Schedule Q,
SAMQR, APP-IV, Sec.3 & Sec.5, SAEP-385 & NEC 110.3.
8.2-WI-09-ISSD