L - FA - Niel T. - WK03 - FA After Inst. Cable Glanding, Sealing & Termination
L - FA - Niel T. - WK03 - FA After Inst. Cable Glanding, Sealing & Termination
L - FA - Niel T. - WK03 - FA After Inst. Cable Glanding, Sealing & Termination
2-WI-09-ISSD
E&I 12-18000-0010-339 Modification and extension of the existing GIS NPCC ABSF TP-02 1/4/2023
Focus Assessment was conducted After cable Sealing, glanding, dressing, termination & identification of Instrument cables connected from Relay Panel 007A/B to Digital Fault Recorder
FOCUSED ASSESSMENT AREA / PROCESS
Compliance
Reference
Item No Item Assessed (SAIC,SAES. Sch. Q. . ETC) Finding Root Cause Corrective Action Corrective Action Completion Remarks
YES NO N/A
1 Cable signal segregation inside Relay Panel SAES-J-902 para 14.1.1 √ N/A N/A N/R N/A
3 Checked Terminal Strip assemblies SAES-J-902 para. 15.3.1 √ N/A N/A N/A N/A
4 Cable and core tagging SAES-J-902 para. 16.1.1 & 16.2.1 √ N/A N/A N/A N/A
5 Ensure grounding system for instrumentation SAES-P-902 para 17.1.2 √ N/A N/A N/A N/A
6 Checked as built connection drawing on Panel and JB pocket Schedule Q para. 3.7 √ N/A N/A N/A N/A
Contractor QC: Name:Saseendran Positive Comments / Opportunity for improvement:This assessment found acceptable in accordance with the above mentioned standards and requirements.
8.2-WI-09-ISSD