Materials And Estimated
Item To Be Quantities Required
Calculations
Estimated Cement Sand Gravel
(bags) (m 3) (m 3)
F-2
Center Footing for Square Column
Conc. volume per footing = ( 0.75 × 0.75× 0.25 )=0.141m3
Conc. volume for 13 footings = 1.828 m 3
Plus : 10 % allowance for wastage = 0.183 m 3
Total volume of footings = 2.0109 m 3
C2
Square Column from Foundation to Roof Slab
Conc. volume per column = 0.30 × 0.30× 17.9=1.1188 m3
Conc. volume for 13 columns = 14.5437 m3
Plus : 5 % allowance for wastage = 0.72718 m3
Total Volume for Columns = 15.2709 m3
Reinforced FTB
Concrete Footing Tie Beam
Beams Total Length of FTB = 78.825 m
Conc. volume of beams = 0.30 × 0.15× 78.825=3.547 m3
Plus : 10 % allowance for wastage = 0.3547 m 3
Total Volume for Beam = 3.9018 m 3
2B1
Second Floor Concrete Beam
Total Length of 2B1 =109.775 m
Conc. volume of beams = 0.30 × 0.30× 109.775=9.880 m3
Plus : 5 % allowance for wastage = 0.9880 m 3
Total Volume for Beam = 10.8677 m3
3B1
Third Floor Concrete Beam
Total Length of 3B1 =109.775 m
Conc. volume of beams = 0.30 × 0.30× 109.775=9.880 m3
Plus : 5 % allowance for wastage = 0.9880 m 3
Total Volume for Beam = 10.8677 m3
4B1
Fourth Floor Concrete Beam
Total Length of 4B1 =109.775 m
Conc. volume of beams = 0.30 × 0.30× 109.775=9.880 m3
Plus : 5 % allowance for wastage = 0.9880 m 3
Total Volume for Beam = 10.8677 m3
5B1
Fifth Floor Concrete Beam
Total Length of 5B1 =109.775 m
Conc. volume of beams = 0.30 × 0.30× 109.775=9.880 m3
Plus : 5 % allowance for wastage = 0.9880 m 3
Total Volume for Beam = 10.8677 m3
UDB1
Roof Beam
Total Length of UDB1 = 109.775 m
Conc. volume of beams = 0.30 × 0.20× 109.775=6.587 m3
Plus : 5 % allowance for wastage = 0.6587 m 3
Total Volume for Beam = 7.2452 m 3
S1
Second Floor Two-way Slab
9.50
Area of conc. Slab =8.2 ×14.20=116.44 m 2
Less : Column, Wall and Stairwell Area = 32.933 m 2
Total Area of Concrete Slab = 83.5075 m2
Conc. volume of slab = 83.5075 × 0.15=12.526125 m3
Plus : 10% allowance for wastage = 1.2526 m 3
Total volume of Concrete =13.7787 m3
S2
Third Floor Two-way Slab 11.50
Area of conc. Slab =8.2 ×14.20=116.44 m 2
Less : Column, Wall and Stairwell Area = 32.933 m 2
Total Area of Concrete Slab = 83.5075 m2
Conc. volume of slab = 83.5075 × 0.15=12.526125 m3
Plus : 10% allowance for wastage = 1.2526 m 3
Total volume of Concrete =13.7787 m3
S4
Fifth Floor Two-way Slab
Area of conc. Slab =8.2 ×14.20=116.44 m 2
Less : Column, Wall and Stairwell Area = 32.933 m 2
Total Area of Concrete Slab = 83.5075 m2
Conc. volume of slab = 83.5075 × 0.15=12.526125 m3
Plus : 10% allowance for wastage = 1.2526 m 3
Total volume of Concrete =13.7787 m3
S5
Fifth Floor One Way Roof Slab
Area of conc. Roof Slab =10.2 ×14.20=116.44 m2
Less : Column, Wall and Stairwell Area = 32.933 m 2
Total Area of Concrete Slab = 132.3075
Conc. volume of slab = 132.3075 ×0.10=13.23075 m3
Plus : 10% allowance for wastage = 1.323075 m 3
Total volume of Concrete =14.553825 m 3
BILL OF MATERIALS
COMPUTATION SHEET
Materials And
Item to be Estimated Quantities
Calculations Required
Estimated
10mm Ø 12mm Ø 16mm Ø
steel bar steel bar steel bar
Reinforced F-1
Footing Bars Side Footing Bars for Square Column
For
Rectangular Length of footing bar S = 0.9 m
Column Plus:
Mild Steel Hook Allowance = 9 × 0.016=0.144 m
Allowance per footing bar S = 2 ×0.144=0.288 m
Total Length of footing bar S = 0.90+ 0.288=1.188 m
F-2
Center Footing Bars for Square Column
Plus:
Mild Steel Hook Allowance = 9 × 0.016=0.144 m
Allowance per footing bar S = 2 ×0.144=0.288 m
Total Length of footing bar S = 0.75+ 0.288=1.038 m
C1
Reinforced Square Column from Second Floor to Roof Slab
Bars for
Rectangular Length of vertical bar = 17.90 m
Column Plus:
Mild Steel Bend Allowance = 5 ×0.016=0.08 m
Allowance per vertical bar = 0.08 m
Total Length of vertical bar = 17.90+0.08=17.98 m
C2
Square Column from Second Floor to Roof Slab
For C1
Square Column from Foundation to Second Floor Beam
For C1
Square Column from Foundation to Second Floor Beam
98 pcs
106 pcs
Reinforced FTB
Bars for Footing Tie Beam
Concrete Total Length of FTB = 78.825 m
Beam
No. of horizontal top bar per beam = 2 pieces
No. of horizontal bottom bar per beam = 2 pieces
Length of horizontal bars = 4 ×78.825=315.30 m
Plus:
Mild Steel Bend Allowance = 5 ×0.012=0.06 m
No. of footing tie beam = 40 sets
Length of bend allowance = 315.30 ×2 × 4 ×0.06=19.2 m
2B1
Second Floor Concrete Beam
Total Length of 2B1 = 109.78 m
3B1
Third Floor Concrete Beam
Total Length of 3B1 = 109.78 m
For FTB
Footing Tie Beam
Plus:
Mild Steel Hook Allowance = 9 × 0.010=0.09 m
Allowance per column tie = 2 ×0.09=0.18 m
Total Length of column tie = 0.90+ 0.18=1.08 m
For 2B1
Second Floor Concrete Beam
For 3B1
Third Floor Concrete Beam
For 4B1
Fourth Floor Concrete Beam
For UDB1
Roof Beam
44 pcs
S2 317 pcs
Third Floor Two-way Slab
Area of conc. slab = 8.20 ×14.20=116.44 m2
Less : Beam, Column ad Stairwell Area =32.933 m 2
Total Area of Slab = 83.508 m 2
S3
Fourth Floor Two-way Slab 175 pcs
Area of conc. slab = 8.20 ×14.20=116.44 m2
Less : Beam, Column ad Stairwell Area =32.933 m 2
Total Area of Slab = 83.508 m 2
S4
Fifth Floor Two-way Slab
Area of conc. slab = 8.20 ×14.20=116.44 m2
Less : Beam, Column ad Stairwell Area =32.933 m 2
Total Area of Slab = 83.508 m 2
S5
One-way Roof Slab
Area of conc. roof slab = 10.20 ×16.20=103.23 m2
Less : Beam and Column Area ¿ 17.743 m 2
Total Area of Roof Slab = 147.50 m 2
BILL OF MATERIALS
COMPUTATION SHEET
Materials And Estimated Quantities
Item to be Required
Calculations
Estimated CHB CHB Cement Sand Gravel
150 mm 100 mm (Bags) (m 3 ¿ (m 3 ¿
Interior Wall
Total Area = 48.57 +126.71=175.28 m 2
92
Under Class B mixture for a 100 mm CHB:
8.00
175.28 ×0.522=91.50 ; say
175.28 ×0.0435=7.62 ; say
Interior Wall
Total Area = 39.13+126.71=165.84 m 2
BILL OF MATERIALS
COMPUTATION SHEET
Materials And Estimated Quantities
Item To Be Required
Calculations
Estimated 6mm THK 12mm THK 2” by 2” 2” by 3”
Plywood Plywood Lumber Lumber
151.524
=52.61
2.88
; say
Under Column using 6mm thick plywood on 2” by
2” wood frame: 1573
53 ×29.67=1572.51 ; say
177.29 62
=61.56
2.88
; say
72.63
=25.22
2.88
; say 26
88.53
=30.73
2.88 31
; say
14.50
=5.03
2.88
; say 5
5.90
=2.05
2.88
; say 2
PROJECT TITLE:
OWNER/S:
LOCATION:
BILL OF MATERIALS
COMPUTATION SHEET
Materials And Estimated Quantities
Item To Be Required
Calculations
Estimated 30 by 30cm 30 by 30cm 30 by 60cm Square
Glazed Unglazed Marble Foot Wood
Tiles Tiles Tiles Tiles
2
9.10 ×1.80=16.38 m
2
9.98 ×1.80=17.96 m
Total Bathroom Wall Tile Area = 45.76 m2
BILL OF MATERIALS
COMPUTATION SHEET
Materials And Estimated Quantities
Item to be Required
Calculations
Estimated Cement White Cement Tile Adhesive
(bags) (kg) (bags)
2
3.29 ×2.00=6.58 m
Bathroom Wall Area = 6.34 × 1.80=11.41m 2
2
9.10 ×1.80=16.38 m
2
9.98 ×1.80=17.96 m
Total Bathroom Tile Area = 60.08 m 2
TOTALS 7 34.00 8
BILL OF MATERIALS
COMPUTATION SHEET
Materials And Estimated Quantities
Item To Be Required
Calculations Polymer Calsomine
Estimated Wood Glue Hardener
Liquid Powder
(gallons) (quarts)
(gallons) (kg)
TOTALS 10 4 3 4
PROJECT TITLE:
OWNER/S:
LOCATION:
BILL OF MATERIALS
COMPUTATION SHEET
Materials And Estimated Quantities
Item to be Required
Calculations
Estimated Concrete Primer Acrylic Gloss Concrete
Sealer Latex Paint Neutralizer
(gallons) (gallons) (quarts)
139.54 4
=3.49
40
; say
139.54 4
=3.49
40
; say
139.54
=3.49
40
155.76
=3.89
40
3.89
=1.56
2.5
; say
205.96 5
=5.15
40
; say
5
205.96
=5.15
40
; say
205.96
=5.15
40
437.40
=10.94
40
; say 11
For Final Coating;
437.40
=10.94
40
; say
437.40
=10.94
40
4.50
* One quart of neutralizer is mixed with 2-½ gallons
of water
10.94
=4.37
2.5
; say
2
29.10 ×0.30=8.73 m
Total Surface Area of Roof Slab = 116.04 m 2
116.04
=2.90
40 3
; say
116.04
=2.90 3
40
; say
116.04
=2.90
40
2.90
=1.16 1.50
2.5
; say
TOTALS 27 27 11
BILL OF MATERIALS
COMPUTATION SHEET
Materials And Estimated Quantities
Item to be Required
Calculations
Estimated Wood Primer
Quick Dry
Paint Thinner
Enamel
(gallons) (gallons)
(gallons)
Ceiling First Floor Ceiling
Paint First Floor Area = 90.00 m 2
Less: Interior Wall Area = 10.49 ×0.10=1.05 m2
Column Area = 12(0.42 ×0.17)=0.86 m 2
Beam Area = 63.60 ×0.20=12.72 m2
Stairwell Area = 2.11×3.40=7.17 m2
Total First Floor Ceiling Area = 68.20 m 2
68.20
=1.95 2
35
; say
68.20
=1.95 2
35
; say
PROJECT TITLE:
OWNER/S:
LOCATION:
BILL OF MATERIALS
COMPUTATION SHEET
Item to be Estimated
Materials Required
Estimated Quantity
30.00mm2 THHN Copper Wire, 150m 2 boxes
203.40
=20.34
10
; say
21 pieces
Elbow 14 pieces
Coupling 21 pieces
1.50+13.00+18.00=32.50 m∨106.62 ft
Length of Pipe
; say 6 pieces
PE Adaptor 1 piece
Nipple 14 pieces
Union 2 pieces
Cement 32 bags
36.00+14.00=50.00 m∨164.04 ft
; say 17 pieces
Cement 15 bags
Fixtures and
Urinal 2 pieces
Accessories
Lavatory 3 pieces
PROJECT TITLE:
OWNER/S:
LOCATION:
BILL OF MATERIALS
COMPUTATION SHEET
Item to be Estimated
Computation
Estimated Quantity
F-2
Center Footing for Rectangular Column
Excavation volume per footing = 2.00 ×1.20 ×1.20=2.88 m3
No. of Side Footing = 8 sets 3
Total Excavation Volume = 8 ×2.88=23.04 m3 23.00 m
F-2
Center Footing for Rectangular Column
Volume of Excavation = 2.88 m3
Less: Volume of Footing = 1.21 m3
PROJECT TITLE:
OWNER/S:
LOCATION:
BILL OF MATERIALS
COMPUTATION SHEET
Materials And Estimated
Item To Be Quantities Required
Calculations
Estimated 12mm THK 2” by 2”
Plywood Lumber
68.20
=23.68 24
2.88
; say
75.83
=26.33 27
2.88
; say
TOTALS 51 919