PROJECT TITLE:

OWNER/S:
LOCATION:

BILL OF MATERIALS
COMPUTATION SHEET
Materials And Estimated
Item To Be Quantities Required
Calculations
Estimated Cement Sand Gravel
(bags) (m 3) (m 3)

Footings For F-1


Rectangular Side Footing for Square Column
Column Conc. volume per footing = ( 0.9 × 0.9× 0.30 )=0.243 m3
Conc. volume for 12 footings = 2.916 m 3
Plus : 10 % allowance for wastage = 0.2916 m 3
Total volume of footings = 3.2076 m 3

Under 50 kg cement, using Class AA concrete mixture:


3.2076 × 9.50=30 .472 ; say
3.2076 × 0.50=1.6038 ; say
3.2076 ×1.00=3.2076 ; say

F-2
Center Footing for Square Column
Conc. volume per footing = ( 0.75 × 0.75× 0.25 )=0.141m3
Conc. volume for 13 footings = 1.828 m 3
Plus : 10 % allowance for wastage = 0.183 m 3
Total volume of footings = 2.0109 m 3

Under 50 kg cement, using Class AA concrete mixture:


2.0109 ×9.50=27.313 ; say
2.0109 ×0.50=1.9509 ; say
2.0109 ×1.00=3.9018 ; say
Rectangular C1
Columns Square Column from Foundation to Roof Slab
Conc. volume per column = 0.3 × 0.3× 17.9=1.611m 3
Conc. volume for 12 columns = 19.332 m 3
Plus : 5 % allowance for wastage = 0.9666 m 3
Total Volume for Columns = 20.2986 m3

Under 50 kg cement, using Class A concrete mixture:


20.2986 ×7.00=142.090 ; say
20.2986 × 0.50=10.1493 ; say
20.2986 ×1.00=20.2986 ; say

C2
Square Column from Foundation to Roof Slab
Conc. volume per column = 0.30 × 0.30× 17.9=1.1188 m3
Conc. volume for 13 columns = 14.5437 m3
Plus : 5 % allowance for wastage = 0.72718 m3
Total Volume for Columns = 15.2709 m3

Under 50 kg cement, using Class A concrete mixture:


15.2709 ×7.00=106.897 ; say
15.2709 ×0.50=7.6355 ; say
15.2709 ×1.00=15.2709 ; say

Reinforced FTB
Concrete Footing Tie Beam
Beams Total Length of FTB = 78.825 m
Conc. volume of beams = 0.30 × 0.15× 78.825=3.547 m3
Plus : 10 % allowance for wastage = 0.3547 m 3
Total Volume for Beam = 3.9018 m 3

Under 50 kg cement, using Class A concrete mixture:


3.9018 ×7.00=27.313 ; say
3.9018 ×0.50=1.9509 ; say
3.9018 ×1.00=3.9018 ; say

2B1
Second Floor Concrete Beam
Total Length of 2B1 =109.775 m
Conc. volume of beams = 0.30 × 0.30× 109.775=9.880 m3
Plus : 5 % allowance for wastage = 0.9880 m 3
Total Volume for Beam = 10.8677 m3

Under 50 kg cement, using Class A concrete mixture:


10.8677 ×7.00=76.074 ; say
10.8677 × 0.50=5.4339 ; say
10.8677 ×1.00=10.868 ; say

3B1
Third Floor Concrete Beam
Total Length of 3B1 =109.775 m
Conc. volume of beams = 0.30 × 0.30× 109.775=9.880 m3
Plus : 5 % allowance for wastage = 0.9880 m 3
Total Volume for Beam = 10.8677 m3

Under 50 kg cement, using Class A concrete mixture:


10.8677 ×7.00=76.074 ; say
10.8677 × 0.50=5.4339 ; say
10.8677 ×1.00=10.868 ; say

4B1
Fourth Floor Concrete Beam
Total Length of 4B1 =109.775 m
Conc. volume of beams = 0.30 × 0.30× 109.775=9.880 m3
Plus : 5 % allowance for wastage = 0.9880 m 3
Total Volume for Beam = 10.8677 m3

Under 50 kg cement, using Class A concrete mixture:


10.8677 ×7.00=76.074 ; say
10.8677 × 0.50=5.4339 ; say
10.8677 ×1.00=10.868 ; say

5B1
Fifth Floor Concrete Beam
Total Length of 5B1 =109.775 m
Conc. volume of beams = 0.30 × 0.30× 109.775=9.880 m3
Plus : 5 % allowance for wastage = 0.9880 m 3
Total Volume for Beam = 10.8677 m3

Under 50 kg cement, using Class A concrete mixture:


10.8677 ×7.00=76.074 ; say
10.8677 × 0.50=5.4339 ; say
10.8677 ×1.00=10.868 ; say

UDB1
Roof Beam
Total Length of UDB1 = 109.775 m
Conc. volume of beams = 0.30 × 0.20× 109.775=6.587 m3
Plus : 5 % allowance for wastage = 0.6587 m 3
Total Volume for Beam = 7.2452 m 3

Under 50 kg cement, using Class A concrete mixture:


7.2452 ×7.00=50.716 ; say
7.2452 ×0.50=3.6225 ; say
7.2452 ×1.00=7.2452 ; say

Concrete Slab on Ground


Slab Area of conc. Slab on Ground =8.2 ×14.20=116.44m 2
Less : Column and Wall Area = 17.473 m 2
Total Area of Concrete Slab = 98.6975 m2
Conc. volume of slab = 98.6975 × 0.10=9.8698 m3
Plus : 10% allowance for wastage = 0.98698 m3
Total volume of Concrete =10.8567 m3

Under 50 kg cement, using Class B concrete mixture:


10.8567 ×6.00=65.140 ; say
10.8567 × 0.50=5.42836 ; say
10.8567 ×1.00=10.857 ; say

S1
Second Floor Two-way Slab
9.50
Area of conc. Slab =8.2 ×14.20=116.44 m 2
Less : Column, Wall and Stairwell Area = 32.933 m 2
Total Area of Concrete Slab = 83.5075 m2
Conc. volume of slab = 83.5075 × 0.15=12.526125 m3
Plus : 10% allowance for wastage = 1.2526 m 3
Total volume of Concrete =13.7787 m3

Under 50 kg cement, using Class B concrete mixture:


13.7787 ×6.00=82.672 ; say
13.7787 × 0.50=6.88937 ; say
13.7787 ×1.00=13.7787 ; say

S2
Third Floor Two-way Slab 11.50
Area of conc. Slab =8.2 ×14.20=116.44 m 2
Less : Column, Wall and Stairwell Area = 32.933 m 2
Total Area of Concrete Slab = 83.5075 m2
Conc. volume of slab = 83.5075 × 0.15=12.526125 m3
Plus : 10% allowance for wastage = 1.2526 m 3
Total volume of Concrete =13.7787 m3

Under 50 kg cement, using Class B concrete mixture:


13.7787 ×6.00=82.672 ; say
13.7787 × 0.50=6.88937 ; say
13.7787 ×1.00=13.7787 ; say
9.50
S3
Fourth Floor Two-way Slab
Area of conc. Slab =8.2 ×14.20=116.44 m 2
Less : Column, Wall and Stairwell Area = 32.933 m 2
Total Area of Concrete Slab = 83.5075 m2
Conc. volume of slab = 83.5075 × 0.15=12.526125 m3
Plus : 10% allowance for wastage = 1.2526 m 3
Total volume of Concrete =13.7787 m3

Under 50 kg cement, using Class B concrete mixture:


13.7787 ×6.00=82.672 ; say
13.7787 × 0.50=6.88937 ; say
13.7787 ×1.00=13.7787 ; say

S4
Fifth Floor Two-way Slab
Area of conc. Slab =8.2 ×14.20=116.44 m 2
Less : Column, Wall and Stairwell Area = 32.933 m 2
Total Area of Concrete Slab = 83.5075 m2
Conc. volume of slab = 83.5075 × 0.15=12.526125 m3
Plus : 10% allowance for wastage = 1.2526 m 3
Total volume of Concrete =13.7787 m3

Under 50 kg cement, using Class B concrete mixture:


13.7787 ×6.00=82.672 ; say
13.7787 × 0.50=6.88937 ; say
13.7787 ×1.00=13.7787 ; say

S5
Fifth Floor One Way Roof Slab
Area of conc. Roof Slab =10.2 ×14.20=116.44 m2
Less : Column, Wall and Stairwell Area = 32.933 m 2
Total Area of Concrete Slab = 132.3075
Conc. volume of slab = 132.3075 ×0.10=13.23075 m3
Plus : 10% allowance for wastage = 1.323075 m 3
Total volume of Concrete =14.553825 m 3

Under 50 kg cement, using Class B concrete mixture:


14.5538 ×6.00=87.323 ; say
14.5538 ×0.50=7.27691 ; say
14.5538 ×1.00=14.5538 ; say

Stair Stair Details


23 Steps with Landing

Rise = 188 mm Landing


Run = 300 mm Width = 2110 mm
Width = 1000 mm Length = 20 00 mm
Thickness of Stairs = 150 mm Thickness = 1 00 mm

Using Special Formulas and Calculations


Conc. volume of stairs = 2.11m 3
Plus : 5% allowance for wastage = 0.10 m3
Total volume of Concrete = 2.21 m3

Under 50 kg cement, using Class A concrete mixture:


2.21 ×7.00=15.52 ; say
2.21 ×0.50=1.11 ; say 2.50
2.21 ×1.00=2.21 ; say

TOTALS 517 39.50 74.00


PROJECT TITLE: As-Built of Plan Two-Storey Residential House
OWNER/S: June and Maritess Raynes
LOCATION: Lot 6, Blk. 24, Rose Hip St., Arbor Towne, Valenzuela City

BILL OF MATERIALS
COMPUTATION SHEET
Materials And
Item to be Estimated Quantities
Calculations Required
Estimated
10mm Ø 12mm Ø 16mm Ø
steel bar steel bar steel bar

Reinforced F-1
Footing Bars Side Footing Bars for Square Column
For
Rectangular Length of footing bar S = 0.9 m
Column Plus:
Mild Steel Hook Allowance = 9 × 0.016=0.144 m
Allowance per footing bar S = 2 ×0.144=0.288 m
Total Length of footing bar S = 0.90+ 0.288=1.188 m

No. of Bar S per Footing = 6 pieces


Total Length of bar S per footing =6 ×1.188=7.128 m

Total Length of bar S for 12 footings = 12 ×7.128=85.536 m

Length of footing bar S = 0.9 m


Plus:
Mild Steel Hook Allowance = 9 × 0.016=0.144 m
Allowance per footing bar S = 2 ×0.144=0.288 m
Total Length of footing bar S = 0.90+ 0.288=1.188 m

No. of Bar S per Footing = 6 pieces


Total Length of bar S per footing =6 ×1.188=7.128 m

Total Length of bar S for 12 footings = 12 ×7.128=85.536 m

Total Length of Side Footing Bars


85.536+ 85.536=171.072
No. of Bars required:
171.072
=28.512 14 pcs
6
; say

F-2
Center Footing Bars for Square Column

Length of footing bar S = 0.75 m

Plus:
Mild Steel Hook Allowance = 9 × 0.016=0.144 m
Allowance per footing bar S = 2 ×0.144=0.288 m
Total Length of footing bar S = 0.75+ 0.288=1.038 m

No. of bar S per footing = 5 pieces


Total Length of bar S per footing = 5 ×1.038=5.19 m

Total Length of bar S for 13 footings = 13 ×5.19=62.28 m

Length of footing bar S = 0.75 m


Plus:
Mild Steel Hook Allowance = 9 × 0.016=0.144 m
Allowance per footing bar S = 2 ×0.144=0.288 m
Total Length of footing bar S = 0.75+ 0.288=1.038 m

No. of bar S per footing = 5 pieces


Total Length of bar S per footing = 5 ×1.038=5.19 m

Total Length of bar S for 13 footings = 13 ×5.19=62.28 m

Total Length of Center Footing Bars


62.28+62.28=124.56 m

No. of Bars required:


124.56 48 pcs
=20.760
6
; say

C1
Reinforced Square Column from Second Floor to Roof Slab
Bars for
Rectangular Length of vertical bar = 17.90 m
Column Plus:
Mild Steel Bend Allowance = 5 ×0.016=0.08 m
Allowance per vertical bar = 0.08 m
Total Length of vertical bar = 17.90+0.08=17.98 m

No. of vertical bar per column = 8 pieces


Total Length of vertical bar per column = 8 ×17.98=143.84 m

No. of Square Column = 12 sets


Length of vertical bar for 12 columns = 12 ×143.84=1726.08 m

No. of Bars required:


1726.08
=287.680
6
; say
89 pcs

C2
Square Column from Second Floor to Roof Slab

Length of vertical bar = 17.90 m


Plus:
Mild Steel Bend Allowance = 5 ×0.016=0.08 m
Allowance per vertical bar = 0.08 m
Total Length of vertical bar = 17.90+0.08=17.98 m

No. of vertical bar per column = 8 pieces


Total Length of vertical bar per column = 8 ×17.98=143.84 m

No. of Square Column = 13 sets


Length of vertical bar for 13 columns = 13 ×143.84=1869.92 m

No. of Bars required:


1869.92
=311.653
6
; say
Column Ties / Lateral Ties
All Column Ties per set should be spaced, 4 @ 0.05 m; 4 @ 0.10 m;
Rest @ 0.20 m O.C.

Length of column tie = 0.3+ 0.3+0.3+0.3=1.20 m


Plus: 51 pcs
Mild Steel Hook Allowance = 9 × 0.010=0.09 m
Allowance per column tie = 2 ×0.09=0.18 m
Total Length of column tie= 1.20+0.18=1.38 m

For C1
Square Column from Foundation to Second Floor Beam

No. of column tie per column = 1074 pieces


Total Length of column ties per column =
1074 × 1.38=1482.12 m

No. of Square Column = 12 sets


Total Length of Column Ties = 12 ×1482.12=17785.44 m

No. of Bars required:


17785.44
=2964.240
6
; say

For C1
Square Column from Foundation to Second Floor Beam

No. of column tie per column = 1164 pieces


Total Length of column ties per column = 13 pcs
1164 ×1.18=1372.93 m

No. of Square Column = 13 sets


Total Length of Column Ties = 12 ×1372.93=17848.09 m

No. of Bars required:


17848.09
=2974.682
6
; say

98 pcs

106 pcs

Reinforced FTB
Bars for Footing Tie Beam
Concrete Total Length of FTB = 78.825 m
Beam
No. of horizontal top bar per beam = 2 pieces
No. of horizontal bottom bar per beam = 2 pieces
Length of horizontal bars = 4 ×78.825=315.30 m
Plus:
Mild Steel Bend Allowance = 5 ×0.012=0.06 m
No. of footing tie beam = 40 sets
Length of bend allowance = 315.30 ×2 × 4 ×0.06=19.2 m

Total Length of Footing Tie Beam Bars = 649.8 m

No. of Bars required:


649.80
=108.30
6
41 pcs.
; say

2B1
Second Floor Concrete Beam
Total Length of 2B1 = 109.78 m

No. of horizontal top bar per beam = 3 pieces


No. of horizontal middle bar per beam = 2 pieces
No. of horizontal bottom bar per beam = 3 pieces
Length of horizontal bars = 8 ×109.78=878.2 m
Plus:
Mild Steel Bend Allowance = 5 ×0.016=0.08 m
No. of 2B1 beam = 40 sets
Length of bend allowance = 40 × 2× 8 ×0.08=51.20 m
Total Length of Horizontal Bars = 929.40 m

Length of left and right support bar = 54.888 m


No. of left and right support bar = 2 pieces
Length of left and right support bar = 2 ×54.888=109.78 m
Plus:
Mild Steel Bend Allowance = 5 ×0.016=0.08 m
No. of 2B1 beam = 40 sets
Length of bend allowance = 40 × 2× 4 × 0.08=25.60 m
Total Length of Left and Right Support Bar = 135.375 m

Length of mid-span support bar = 54.888 m


No. of left and right support bar = 2 pieces
Length of mid-span support bar = 2 ×54.888=109.78 m
Plus:
Mild Steel Bend Allowance = 5 ×0.016=0.08 m
No. of 2B1 beam = 40 sets
Length of bend allowance = 40 × 4 × 0.08=12.80 m
Total Length of Mid-span Support Bar = 122.575 m

Total Length of 2B1 Bars = 1187.35 m

No. of Bars required:


1187.35 73 pcs
=197.892
6
; say

3B1
Third Floor Concrete Beam
Total Length of 3B1 = 109.78 m

No. of horizontal top bar per beam = 3 pieces


No. of horizontal middle bar per beam = 2 pieces
No. of horizontal bottom bar per beam = 3 pieces
Length of horizontal bars = 8 ×109.78=878.2 m
Plus:
Mild Steel Bend Allowance = 5 ×0.016=0.08 m
No. of 3B1 beam = 40 sets
Length of bend allowance = 40 × 2× 8 ×0.08=51.20 m
Total Length of Horizontal Bars = 929.40 m

Length of left and right support bar = 54.888 m


No. of left and right support bar = 2 pieces
Length of left and right support bar = 2 ×54.888=109.78 m
Plus:
Mild Steel Bend Allowance = 5 ×0.016=0.08 m
No. of 3B1 beam = 40 sets
Length of bend allowance = 40 × 2× 4 × 0.08=25.60 m
Total Length of Left and Right Support Bar = 135.375 m

Length of mid-span support bar = 54.888 m


No. of left and right support bar = 2 pieces
Length of mid-span support bar = 2 ×54.888=109.78 m
Plus:
Mild Steel Bend Allowance = 5 ×0.016=0.08 m
No. of 3B1 beam = 40 sets
Length of bend allowance = 40 × 4 × 0.08=12.80 m
Total Length of Mid-span Support Bar = 122.575 m

Total Length of 3B1 Bars = 1187.35 m

No. of Bars required:


1187.35
=197.892
6
; say
42 pcs
4B1
Fourth Floor Concrete Beam
Total Length of 4B1 = 109.78 m

No. of horizontal top bar per beam = 3 pieces


No. of horizontal middle bar per beam = 2 pieces
No. of horizontal bottom bar per beam = 3 pieces
Length of horizontal bars = 8 ×109.78=878.2 m
Plus:
Mild Steel Bend Allowance = 5 ×0.016=0.08 m
No. of 4B1 beam = 40 sets
Length of bend allowance = 40 × 2× 8 ×0.08=51.20 m
Total Length of Horizontal Bars = 929.40 m

Length of left and right support bar = 54.888 m


No. of left and right support bar = 2 pieces
Length of left and right support bar = 2 ×54.888=109.78 m
Plus:
Mild Steel Bend Allowance = 5 ×0.016=0.08 m
No. of 4B1 beam = 40 sets
Length of bend allowance = 40 × 2× 4 × 0.08=25.60 m
Total Length of Left and Right Support Bar = 135.375 m

Length of mid-span support bar = 54.888 m


No. of left and right support bar = 2 pieces
Length of mid-span support bar = 2 ×54.888=109.78 m
Plus:
Mild Steel Bend Allowance = 5 ×0.016=0.08 m
No. of 4B1 beam = 40 sets
Length of bend allowance = 40 × 4 × 0.08=12.80 m
Total Length of Mid-span Support Bar = 122.575 m

Total Length of 4B1 Bars = 1187.35 m

No. of Bars required:


1187.35
=197.892
6
; say
5B1
Fifth Floor Concrete Beam 10 pcs
Total Length of 5B1 = 109.78 m

No. of horizontal top bar per beam = 3 pieces


No. of horizontal middle bar per beam = 2 pieces
No. of horizontal bottom bar per beam = 3 pieces
Length of horizontal bars = 8 ×109.78=878.2 m
Plus:
Mild Steel Bend Allowance = 5 ×0.016=0.08 m
No. of 5B1 beam = 40 sets
Length of bend allowance = 40 × 2× 8 ×0.08=51.20 m
Total Length of Horizontal Bars = 929.40 m

Length of left and right support bar = 54.888 m


No. of left and right support bar = 2 pieces
Length of left and right support bar = 2 ×54.888=109.78 m
Plus:
Mild Steel Bend Allowance = 5 ×0.016=0.08 m
No. of 5B1 beam = 40 sets
Length of bend allowance = 40 × 2× 4 × 0.08=25.60 m
Total Length of Left and Right Support Bar = 135.375 m

Length of mid-span support bar = 54.888 m


No. of left and right support bar = 2 pieces
Length of mid-span support bar = 2 ×54.888=109.78 m
Plus:
Mild Steel Bend Allowance = 5 ×0.016=0.08 m
No. of 5B1 beam = 40 sets
Length of bend allowance = 40 × 4 × 0.08=12.80 m
Total Length of Mid-span Support Bar = 122.575 m

Total Length of 5B1 Bars = 1187.35 m

No. of Bars required:


1187.35
=197.892
6
; say
UDB1
Roof Beam
Total Length of UDB1 = 109.78 m 49 pcs

No. of horizontal top bar per beam = 3 pieces


No. of horizontal middle bar per beam = 2 pieces
No. of horizontal bottom bar per beam = 3 pieces
Length of horizontal bars = 8 ×109.78=878.2 m
Plus:
Mild Steel Bend Allowance = 5 ×0.016=0.08 m
No. of UDB1 beam = 40 sets
Length of bend allowance = 40 × 2× 8 ×0.08=51.20 m
Total Length of Horizontal Bars = 929.40 m

Length of left and right support bar = 54.888 m


No. of left and right support bar = 2 pieces
Length of left and right support bar = 2 ×54.888=109.78 m
Plus:
Mild Steel Bend Allowance = 5 ×0.016=0.08 m
No. of UDB1 beam = 40 sets
Length of bend allowance = 40 × 2× 4 × 0.08=25.60 m
Total Length of Left and Right Support Bar = 135.375 m

Length of mid-span support bar = 54.888 m


No. of left and right support bar = 2 pieces
Length of mid-span support bar = 2 ×54.888=109.78 m
Plus:
Mild Steel Bend Allowance = 5 ×0.016=0.08 m
No. of UDB1 beam = 40 sets
Length of bend allowance = 40 × 4 × 0.08=12.80 m
Total Length of Mid-span Support Bar = 122.575 m

Total Length of UDB1 Bars = 1187.35 m

No. of Bars required:


1187.35
=197.892
6
; say

Stirrups / Beam Ties


All Stirrups per set should be spaced, 1 @ 0.05 m; 8 @ 0.10 m; Rest
@ 0.20 m O.C.
32 pcs
Length of stirrups = 0.20+ 0.40+0.20+0.40=1.20 m
Plus:
Mild Steel Hook Allowance = 9 × 0.010=0.09 m
Allowance per column tie = 2 ×0.09=0.18 m
Total Length of column tie = 1.20+0.18=1.38 m

For FTB
Footing Tie Beam

Length of stirrups = 0.30+ 0.15+0.30+0.15=0.90 m

Plus:
Mild Steel Hook Allowance = 9 × 0.010=0.09 m
Allowance per column tie = 2 ×0.09=0.18 m
Total Length of column tie = 0.90+ 0.18=1.08 m

No. of stirrups = 411 pieces


Total Length of Stirrups = 411× 1.08=443.475 m

No. of Bars required:


443.475
=73.9125
6
; say

For 2B1
Second Floor Concrete Beam

No. of stirrups = 575 pieces


Total Length of Stirrups =575×1.38=792.6375 m 82 pcs
No. of Bars required:
792.6375
=132.1063
6
; say

For 3B1
Third Floor Concrete Beam

No. of stirrups = 575 pieces


Total Length of Stirrups =575×1.38=792.6375 m 69 pcs

No. of Bars required:


792.6375
=132.1063
6
; say

For 4B1
Fourth Floor Concrete Beam

No. of stirrups = 575 pieces


Total Length of Stirrups =575×1.38=792.6375 m 53 pcs

No. of Bars required:


792.6375
=132.1063
6
; say
For 5B1
Fifth Floor Concrete Beam

No. of stirrups = 575 pieces


Total Length of Stirrups =575×1.38=792.6375 m 14 pcs

No. of Bars required:


792.6375
=132.1063
6
; say

For UDB1
Roof Beam

No. of stirrups = 575 pieces


Total Length of Stirrups = 575 ×1.18=677.7625 m
55 pcs

No. of Bars required:


677.7625
=112.9604
6
; say

44 pcs

Reinforced Slab on Ground


Bars for Area of conc. Slab on Ground =8.20 ×14.20=116.44 m2
Concrete Slab Less : Column and Wall Area = 17.743 m 2
Total Area of Slab on Ground =98.698 m 2

Under 6 m steel bar at 0.25 m spacing distance:


98.698 ×1.627=135.25 ; say
135 pcs
S1
Second Floor Two-way Slab
Area of conc. slab = 8.20 ×14.20=116.44 m2
Less : Beam, Column ad Stairwell Area =32.933 m 2
Total Area of Slab = 83.508 m 2

Under 6 m steel bar at 0.10 m spacing distance:


83.508 × 4.369=364.8443 ; say

S2 317 pcs
Third Floor Two-way Slab
Area of conc. slab = 8.20 ×14.20=116.44 m2
Less : Beam, Column ad Stairwell Area =32.933 m 2
Total Area of Slab = 83.508 m 2

Under 6 m steel bar at 0.10 m spacing distance:


83.508 × 4.369=364.8443 ; say

S3
Fourth Floor Two-way Slab 175 pcs
Area of conc. slab = 8.20 ×14.20=116.44 m2
Less : Beam, Column ad Stairwell Area =32.933 m 2
Total Area of Slab = 83.508 m 2

Under 6 m steel bar at 0.10 m spacing distance:


83.508 × 4.369=364.8443 ; say

S4
Fifth Floor Two-way Slab
Area of conc. slab = 8.20 ×14.20=116.44 m2
Less : Beam, Column ad Stairwell Area =32.933 m 2
Total Area of Slab = 83.508 m 2

Under 6 m steel bar at 0.10 m spacing distance:


83.508 × 4.369=364.8443 ; say

S5
One-way Roof Slab
Area of conc. roof slab = 10.20 ×16.20=103.23 m2
Less : Beam and Column Area ¿ 17.743 m 2
Total Area of Roof Slab = 147.50 m 2

Under 6 m steel bar at 0.20 m spacing distance:


147.50 ×1.980=292.0451 ; say

Reinforced Exterior Wall Footing


Bars on CHB Total Length of Exterior Wall Footing = 44.80 m
Wall Footing
For longitudinal bars at 0.30 m on center:
44.80 × 3=134.40 m long

For transverse bars at 0.30 m on center:

No. of transverse bars = 224 pieces


224 × 0.60=89.60 mlong

No. of Bars required:


134.40+89.60
=37.3333
6
; say 28 pcs.

Interior Wall Footing


Total Length of Interior Wall Footing = 47.60 m

For longitudinal bars at 0.30 m on center:


47.60 × 3=142.80 m long
For transverse bars at 0.30 m on center:

No. of transverse bars = 238 pieces


238 ×0.60=95.20 m long

No. of Bars required:


142.80+95.20
=39.6667
6
; say 9 pcs.

Reinforced Exterior Wall from Footing to Second Floor


Bars on CHB Area of Wall = 44.80 × 4.7=210.56 m 2
Wall Less: Door:¿ 4.62 m2
Window = 21.96 m 2
Net CHB Wall Area = 183.98 m 2

Under vertical reinforcement spaced at 0.60m:


183.98 ×2.13=391.8774 m long

Under horizontal reinforcement at every 3 layers:


183.98 ×2.15=395.557 mlong

No. of Bars required:


391.8774+295.557
=131.2391
6
; say

Exterior Wall from Second Floor to Third Floor


Area of Wall = 39.90 ×2.7=107.73 m2
Less: Window = 21.34 m 2 89 pcs.
Net CHB Wall Area = 86.39 m 2

Under vertical reinforcement spaced at 0.60m:


86.39 ×2.13=184.0107 mlong

Under horizontal reinforcement at every 3 layers:


86.39 ×2.15=185.7385 mlong

No. of Bars required:


184.0107+185.7385
=61.62487
6
; say

Exterior Wall from Third Floor to Fourth Floor


Area of Wall = 44.80 × 2.7=120.96 m2
Less: Window = 24.94 m 2
Net CHB Wall Area = 96.02 m 2
86 pcs.
Under vertical reinforcement spaced at 0.60m:
96.02 ×2.13=204.5226 mlong

Under horizontal reinforcement at every 3 layers:


96.02 ×2.15=206.4430 mlong

No. of Bars required:


204.5226+206.4430
=68.4943
6
; say

Exterior Wall from Fourth Floor to Fifth Floor


Area of Wall = 38.30 ×2.7=103.41 m2
Less: Window = 15.34 m 2
Net CHB Wall Area = 88.07 m 2 35 pcs.

Under vertical reinforcement spaced at 0.60m:


88.07 × 2.13=187.5891 mlong

Under horizontal reinforcement at every 3 layers:


88.07 × 2.15=189.3505 mlong

No. of Bars required:


187.5891+ 189.3505
=62.8233
6
; say

Exterior Wall from Fifth Floor to Roof Beam


Area of Wall = 44.80 × 2.7=120.96 m2
Less: Window = 18.04 m 2
Net CHB Wall Area = 102.92 m 2 90 pcs.

Under vertical reinforcement spaced at 0.60m:


102.92 ×2.13=219.2196 mlong

Under horizontal reinforcement at every 3 layers:


102.92 ×2.15=221.2780 mlong

No. of Bars required:


219.2196+221.2780
=73.4163
6
; say

Interior Wall on First Floor


Area of Wall = 10.49 × 4.75=49.83 m2
Less: Door: 0.60 ×2.10=1.26 m 2
Net CHB Wall Area = 48.57 m2

Under vertical reinforcement spaced at 0.60m:


48.57 × 2.13=103.45 m long

Under horizontal reinforcement at every 3 layers:


48.57 × 2.15=104.42 m long

No. of Bars required:


103.45+104.42
=34.64
6
; say

Interior Wall on Second Floor


Area of Wall = 32.59 × 4.12=134.27 m 2
Less: Door: 3(0.80× 2.10)=5.04 m2
2
2(0.60 × 2.10)=2.52 m
Net CHB Wall Area = 126.71 m 2

Under vertical reinforcement spaced at 0.60m:


126.71 ×2.13=269.89 mlong

Under horizontal reinforcement at every 3 layers:


126.71 ×2.15=272.43 mlong

No. of Bars required:


269.89+272.43
=90.39
6
; say

TOTALS 964 358 421

PROJECT TITLE: As-Built of Plan Two-Storey Residential House


OWNER/S: June and Maritess Raynes
LOCATION: Lot 6, Blk. 24, Rose Hip St., Arbor Towne, Valenzuela City

BILL OF MATERIALS
COMPUTATION SHEET
Materials And Estimated Quantities
Item to be Required
Calculations
Estimated CHB CHB Cement Sand Gravel
150 mm 100 mm (Bags) (m 3 ¿ (m 3 ¿

CHB for Exterior Wall from Footing to Second Floor


Exterior Wall Area of Wall = 33.12 ×4.50=149.04 m 2
Less: Door: 1.40 ×2.10=2.94 m 2
2
0.80 ×2.10=1.68 m
Window: 2 ( 1.96 ×2.50 ) =9.80 m2
2
2 ( 2.10 ×1.70 )=7.14 m
2
1.40 ×0.70=0.98 m
2
1.20 ×0.80=0.96 m
0.60 × 0.60=0.36
Net CHB Wall Area = 125.18 m 2

No. of CHB required: 1565


125.18 ×12.50=1564.75 ; say

Exterior Wall from Second Floor to Roof Beam


Area of Wall = 33.28 × 4.12=137.11m2
Less: Window:6 ( 1.60 ×1.50 )=14.40 m 2
2
2 ( 0.60 ×0.60 )=0.72 m
2
1.00 ×1.50=1.50 m
Net CHB Wall Area = 120.49 m 2
1507
No. of CHB required:
120.49 ×12.50=1506.17 ; say

CHB for Interior Wall on First Floor


Interior Wall Area of Wall = 10.49 × 4.75=49.83 m2
Less: Door: 0.60 ×2.10=1.26 m 2
Net CHB Wall Area = 48.57 m2

No. of CHB required:


607
48.57 × 12.50=607.09 ; say

Interior Wall on Second Floor


Area of Wall = 32.59 × 4.12=134.27 m 2

Less: Door: 3(0.80× 2.10)=5.04 m2


2
2(0.60 × 2.10)=2.52 m
Net CHB Wall Area = 126.71 m 2
1584
No. of CHB required:
126.71 ×12.50=1583.88 ; say

Materials for Exterior Wall Footing


CHB Wall Total Length of Exterior Wall Footing = 33.12 m
Footing
Using the Volume Method of Concrete
Conc. volume of footing =
3
33.12 ×0.60 × 0.20=3.97 m
Plus : 10 % allowance for wastage = 0.40 m3
Total volume of footings =4.37 m3

Under Class A concrete mixture: 31


4.37 × 7.00=30.60 ; say 2.50
4.37 × 0.50=2.18 ; say 4.50
4.37 × 1.00=4.37 ; say

Interior Wall Footing


Total Length of Interior Wall Footing = 10.49 m

Using the Volume Method of Concrete


Conc. volume of footing =
3
10.49 ×0.60 × 0.20=1.26 m
Plus : 10 % allowance for wastage = 0.13 m3
Total volume of footings =1.38 m3
10
Under Class A concrete mixture: 1.00
1.38 ×7.00=9.69 ; say 1.50
1.38 ×0.50=0.69 ; say
1.38 ×1.00=1.38 ; say

Materials for Exterior Wall


Cement Total Area = 125.18+1 20.49=245.67 m2
Mortar
Under Class A mixture for a 150mm CHB: 375
245.67 ×1.526=374.89 ; say 21.00
245.67 × 0.0844=20.73 ; say

Interior Wall
Total Area = 48.57 +126.71=175.28 m 2
92
Under Class B mixture for a 100 mm CHB:
8.00
175.28 ×0.522=91.50 ; say
175.28 ×0.0435=7.62 ; say

Materials for Exterior Wall


Cement Total Area = 118.56 +120.49=239.05
Mortar
Plastering Under 16 mm thick plaster Class A mixture:
239.05 ×.288=68.85 ; say 69
239.05 ×.016=3.82 ; say 4.00

Interior Wall
Total Area = 39.13+126.71=165.84 m 2

Under 16 mm thick plaster Class B mixture:


165.84 × 0.192=31.84 ; say 32
165.84 × 0.016=2.65 ; say 3.00

TOTALS 3072 2191 609 39.50 6.00


PROJECT TITLE:
OWNER/S:
LOCATION:

BILL OF MATERIALS
COMPUTATION SHEET
Materials And Estimated Quantities
Item To Be Required
Calculations
Estimated 6mm THK 12mm THK 2” by 2” 2” by 3”
Plywood Plywood Lumber Lumber

Forms for P=2 ( a+ b ) +0.20


Rectangular P=2 ( 0.42+0.17 ) +0.20
Column P=1.38 m

Area of the Forms = 1.38 ×9.15=12.63 m2


Total Area for 12 columns
2
12.627 ×12=151.524 m 53

No. of Plywood required:

151.524
=52.61
2.88
; say
Under Column using 6mm thick plywood on 2” by
2” wood frame: 1573
53 ×29.67=1572.51 ; say

Forms for P = 2 ( a+b ) +0.10


Beam and P = 2 ( 0.40+0.20 )+ 0.10
Girder P = 1.30

Total Length of Beams = 136.28 m


Total Area of the Beams
2
1.30 ×136.38=177.29 m

No. of Plywood required:

177.29 62
=61.56
2.88
; say

Under Beam using 6 mm thick plywood on 2” by 2”


wood frame: 1554
62 ×25.06=1553.72 ; say

Forms for Total Area of Concrete Slab = 72.63 m 2


Concrete
Slab No. of Plywood required:

72.63
=25.22
2.88
; say 26

Forms for Total Area of Roof Slab = 88.53 m 2


Roof Slab
No. of Plywood required:

88.53
=30.73
2.88 31
; say

Forms for Length of Stair = 9.90 m


Stair Width of Stair = 1.00 m
Area of Forms for Stair
2
9.90 ×1.00=9.90 m

Area of Rise = 0.20 ×1.00=0.20 m 2


Total Area of Rise
2
23 ×0.20=4.60 m
Total Area of Forms for Stair = 14.50 m 2

No. of Plywood required:

14.50
=5.03
2.88
; say 5

Forms for Length of Doors = 6.40 m


Doors and Length of Windows = 23.12 m
Windows Total Length = 29.52 m
Total Area of Forms for Doors and Windows
2
29.52 ×0.20=5.90 m

No. of Plywood required:

5.90
=2.05
2.88
; say 2

Scaffolding Length of Column = 9.15 m


for Column Total Length for 12 columns
9.15 ×12=109.80 m

Under Column using 2” by 3” lumber for vertical


support:
109.80 ×7.00=768.60 ; say 769

Under Column using 2” by 2” lumber for horizontal


support:
109.80 ×21.00=2305.80 ; say 2306

Under Column using 2” by 2” lumber for diagonal


braces:
109.80 ×11.70=1284.66 ; say 1285

Scaffolding Total Length of Beams = 136.28 m


for Beam
and Girder Under Beam using 2” by 3” lumber for vertical
support:
136.28 ×6.00=817.68 ; say 818

Under Beam using 2” by 2” lumber for horizontal


support:
136.28 × 4.70=640.52 ; say 641

Scaffolding Total Area of Concrete Slab = 72.63 m 2


for Concrete
Slab Under Column using 2” by 3” lumber for vertical
support:
72.626 × 9.10=660.90 ; say 661

Scaffolding Total Area of Concrete Slab = 102.80 m 2


for Roof
Slab Under Column using 2” by 3” lumber for vertical
support:
102.80 ×9.10=935.48 ; say 936

TOTALS 115 64 7359 3184

PROJECT TITLE:
OWNER/S:
LOCATION:

BILL OF MATERIALS
COMPUTATION SHEET
Materials And Estimated Quantities
Item To Be Required
Calculations
Estimated 30 by 30cm 30 by 30cm 30 by 60cm Square
Glazed Unglazed Marble Foot Wood
Tiles Tiles Tiles Tiles

Floor Tiles First Floor Tiles


First Floor Area = 90.00 m 2
Less: Exterior Wall Area = 30.92 ×0.15=4.64 m2
Interior Wall Area = 9.89 × 0.10=0.99 m 2
Column Area = 12(0.42 ×0.17)=0.86 m 2
Bathroom Area = 2.05 ×1.42=2.91m2
Stair Area = 3.90 ×2.11=8.23 m2
Kitchen Area = 5.40 ×0.60=3.24 m 2
Nook Area = 2.00 ×0.90=1.80 m 2
Net First Floor Tile Area = 67.34 m2

Under 30 by 60 cm floor tiles:


67.34 × 5.56=374.41
Plus : 10 % allowance for cutting and edging = 37.44 412
Total No. of Tiles = 411.85 ; say

Second Floor Tiles


Second Floor Area = 94.50 m 2
Less: Exterior Wall Area = 33.28 ×0.15=4.99 m2
Interior Wall Area = 28.99 ×0.10=2.90 m2
Column Area = 15(0.42× 0.17)=1.07 m2
Bedroom 1 Area = 3.45 ×3.55=12.25 m2
Bedroom 2 Area = 3.45 ×3.55=12.25 m2
Master’s Bed Area = 3.29 ×6.60=21.71 m2
Stairwell Area = 3.40 ×2.11=7.17 m2
Bathroom Area = 3.45 ×1.40=4.83 m 2
2
3.29 ×2.00=6.58 m
Net Second Floor Tile Area = 20.74 m 2

Under 30 by 60 cm floor tiles:


127
20.74 × 5.56=115.34
Plus : 10 % allowance for cutting and edging = 11.53
Total No. of Tiles = 126.88; say

Bedroom Bedroom 1 Floor Area = 3.45 ×3.55=12.25 m2


Floor Tiles Bedroom 2 Floor Area = 3.45 ×3.55=12.25 m2

Master’s Bed Floor Area = 3.29 ×6.60=21.71 m2


Net Bedroom Floor Area = 46.21 m 2

Net Bedroom Floor Area = 497.21 ft 2


Plus : 5 % allowance for cutting and edging =
2
24.86 ft 523.00
2
Total Bedroom Tile Area = 522.07 ft ; say

Stair Tiles Stair Tread Area = 1.00 ×0.30=0.30 m 2


No. of Steps = 22 Steps
Stair Tread Area for 22 steps = 22 ×0.30=6.60 m2
Stair Landing Area = 2.11×1.00=2.11m 2
Net Stair Tile Area =8.71 m2

Net Stair Tile Area = 93.72 ft 2


Plus : 5 % allowance for cutting and edging = 4.68 ft 2 99.00
Total Stair Tile Area = 98.40 ft 2; say

Kitchen Kitchen Tiles


Tiles Kitchen Area = 5.40 ×0.60=3.24 m 2
Nook Area = 2.00 ×0.90=1.80 m 2
Total Kitchen Tile Area = 5.04 m2

Under 30 by 30 cm floor tiles:


5.04 × 11.11=55.99
Plus : 10 % allowance for cutting and edging = 5.60 62
Total No. of Tiles = 61.59; say

Kitchen Wall Tiles


Kitchen Wall Area = 5.40 ×0.30=1.62 m 2
Total Kitchen Wall Tile Area = 1.62 m2

Under 30 by 30 cm floor tiles:


1.62 ×11.11=18.00
Plus : 10 % allowance for cutting and edging = 1.80 20
Total No. of Tiles = 19.80; say

Bathroom Bathroom Floor Tiles


Tiles Bathroom Floor Area = 2.05 ×1.42=2.91m2
2
3.45 ×1.40=4.83 m
2
3.29 ×2.00=6.58 m
Total Bathroom Floor Tile Area = 14.32 m 2

Under 30 by 30 cm floor tiles:


14.32 ×11.11=159.11
Plus : 10 % allowance for cutting and edging = 15.91 175
Total No. of Tiles = 175.02; say

Bathroom Wall Tiles


Bathroom Wall Area = 6.34 × 1.80=11.41m 2

2
9.10 ×1.80=16.38 m
2
9.98 ×1.80=17.96 m
Total Bathroom Wall Tile Area = 45.76 m2

Under 30 by 30 cm floor tiles:


45.76 × 11.11=508.35 :say
Plus : 10 % allowance for cutting and edging = 50.83 560
Total No. of Tiles = 559.18; say

TOTALS 580 237 539 622.00

BILL OF MATERIALS
COMPUTATION SHEET
Materials And Estimated Quantities
Item to be Required
Calculations
Estimated Cement White Cement Tile Adhesive
(bags) (kg) (bags)

Kitchen Kitchen Area = 5.40 ×0.60=3.24 m 2


Tiles Nook Area = 2.00 ×0.90=1.80 m 2
Kitchen Wall Area = 5.40 ×0.30=1.62 m 2
Total Kitchen Tile Area = 6.66 m2

Under 30 by 30 cm floor tiles:


1
6.66 × 0.086=0.57 ; say 4.00
6.66 × 0.50=3.33 ; say 1
6.66 × 0.11=0.73 ; say

Bathroom Bathroom Floor Area = 2.05 ×1.42=2.91m2


Tiles 3.45 ×1.40=4.83 m
2

2
3.29 ×2.00=6.58 m
Bathroom Wall Area = 6.34 × 1.80=11.41m 2
2
9.10 ×1.80=16.38 m
2
9.98 ×1.80=17.96 m
Total Bathroom Tile Area = 60.08 m 2

Under 30 by 30 cm floor tiles: 6


60.08 ×0.086=5.17 ; say 30.00
60.08 ×0.50=30.04 ; say 7
60.08 ×0.11=6.61 ; say

TOTALS 7 34.00 8

BILL OF MATERIALS
COMPUTATION SHEET
Materials And Estimated Quantities
Item To Be Required
Calculations Polymer Calsomine
Estimated Wood Glue Hardener
Liquid Powder
(gallons) (quarts)
(gallons) (kg)

Floor Tiles First Floor Tiles


First Floor Area = 90.00 m 2
Less: Exterior Wall Area = 30.92 ×0.15=4.64 m2
Interior Wall Area = 9.89 × 0.10=0.99 m 2
Column Area = 12(0.42 ×0.17)=0.86 m 2
Bathroom Area = 2.05 ×1.42=2.91m2
Stair Area = 3.90 ×2.11=8.23 m2
Kitchen Area = 5.40 ×0.60=3.24 m 2
Nook Area = 2.00 ×0.90=1.80 m 2
Net First Floor Area = 67.34 m2
3
Under 30 by 60 cm floor tiles: 2
67.34 × 0.035=2.36 ; say 3
67.34 × 0.030=2.02 ; say
67.34 × 0.045=3.03 ; say

Second Floor Tiles


Second Floor Area = 94.50 m 2
Less: Exterior Wall Area = 33.28 ×0.15=4.99 m2
Interior Wall Area = 28.99 ×0.10=2.90 m2
Column Area = 15(0.42× 0.17)=1.07 m2
Bedroom 1 Area = 3.45 ×3.55=12.25 m2
Bedroom 2 Area = 3.45 ×3.55=12.25 m2
Master’s Bed Area = 3.29 ×6.60=21.71 m2
Stairwell Area = 3.40 ×2.11=7.17 m2
Bathroom Area = 3.45 ×1.40=4.83 m 2
2
3.29 ×2.00=6.58 m
Net Second Floor Area = 20.74 m 2 1
1
Under 30 by 60 cm floor tiles: 1
20.74 × 0.035=0.73 ; say
20.74 × 0.030=0.62 ; say
20.74 × 0.045=0.93 ; say

Bedroom Bedroom 1 Floor Area = 3.45 ×3.55=12.25 m2


Floor Tiles Bedroom 2 Floor Area = 3.45 ×3.55=12.25 m2
Master’s Bed Floor Area = 3.29 ×6.60=21.71 m2
Total Bedroom Floor Area = 46.21 m 2

No. of Wood Glue required: 8


46.21 × 0.165=7.62 ; say

Stair Tiles Stair Tread Area = 1.00 ×0.30=0.30 m 2


No. of Steps = 22 Steps
Stair Tread Area for 22 steps = 22 ×0.30=6.60 m2
Stair Landing Area = 2.11×1.00=2.11m 2
Total Stair Tile Area = 8.71 m2

No. of Wood Glue required: 2


8.71 ×0.165=1.44 ; say

TOTALS 10 4 3 4
PROJECT TITLE:
OWNER/S:
LOCATION:

BILL OF MATERIALS
COMPUTATION SHEET
Materials And Estimated Quantities
Item to be Required
Calculations
Estimated Concrete Primer Acrylic Gloss Concrete
Sealer Latex Paint Neutralizer
(gallons) (gallons) (quarts)

Exterior First Floor Exterior


Paint Surface Perimeter = 38.00 m
Surface Area = 38.00 × 4.30=163.40 m 2
Less: Door: 1.40 ×2.10=2.94 m 2
2
0.80 ×2.10=1.68 m
Window: 2 ( 1.96 ×2.50 ) =9.80 m2
2
2 ( 2.10 ×1.70 )=7.14 m
2
1.40 ×0.70=0.98 m
2
1.20 ×0.80=0.96 m
0.60 × 0.60=0.36
Net Surface Area = 139.54 m 2

Under area coverage of 40 sq. m. per gallon:

For Primer Paint:

139.54 4
=3.49
40
; say

For Final Coating:

139.54 4
=3.49
40
; say

For Concrete Neutralizer:

139.54
=3.49
40

* One quart of neutralizer is mixed with 2-½ gallons


of water
1.50
3.49
=1.40
2.5
; say

Second Floor Exterior


Surface Perimeter = 39.00 m
Surface Area = 39.00 × 4.42=172.38 m 2
Less: Window:6 ( 1.60 ×1.50 )=14.40 m 2
2
2 ( 0.60 ×0.60 )=0.72 m
2
1.00 ×1.50=1.50 m
2
Net Surface Area = 155.76 m

Under area coverage of 40 sq. m. per gallon:

For Primer Paint:


4
155.76
=3.89
40
; say

For Final Coating:


4
155.76
=3.89
40
; say

For Concrete Neutralizer:

155.76
=3.89
40

* One quart of neutralizer is mixed with 2-½ gallons


of water 1.50

3.89
=1.56
2.5
; say

Interior First Floor Interior


Paint Total Surface Perimeter = 60.02 m
Surface Area = 60.02 ×3.85=231.08 m 2
Less: Door: 0.60 ×2.10=1.26 m 2
2
1.40 ×2.10=2.94 m
2
0.80 ×2.10=1.68 m
Window: 2 ( 1.96 ×2.50 ) =9.80 m2
2
2 ( 2.10 ×1.70 )=7.14 m
2
1.40 ×0.70=0.98 m
2
1.20 ×0.80=0.96 m
0.60 × 0.60=0.36
Net Surface Area = 205.96 m 2

Under area coverage of 40 sq. m. per gallon:

For Primer Paint;

205.96 5
=5.15
40
; say

For Final Coating;

5
205.96
=5.15
40
; say

For Concrete Neutralizer;

205.96
=5.15
40

* One quart of neutralizer is mixed with 2-½ gallons


of water
2
5.15
=2.06
2.5
; say

Second Floor Interior


Total Surface Perimeter = 104.43 m
Surface Area = 104.43 × 4.42=461.58 m2
Less: Door: 3(0.80× 2.10)=5.04 m2
2
2(0.60 × 2.10)=2.52 m
Window: 6 ( 1.60 ×1.50 )=14.40 m 2
2
2 ( 0.60 ×0.60 )=0.72 m
2
1.00 ×1.50=1.50 m
Net Surface Area = 437.40 m2

Under area coverage of 40 sq. m. per gallon:


11
For Primer Paint;

437.40
=10.94
40
; say 11
For Final Coating;

437.40
=10.94
40
; say

For Concrete Neutralizer;

437.40
=10.94
40
4.50
* One quart of neutralizer is mixed with 2-½ gallons
of water
10.94
=4.37
2.5
; say

Roof Slab Surface Area = 11.10× 9.30=103.23 m2


Paint 40.80 × 0.10=4.08 m
2

2
29.10 ×0.30=8.73 m
Total Surface Area of Roof Slab = 116.04 m 2

Under area coverage of 40 sq. m. per gallon:

For Primer Paint;

116.04
=2.90
40 3
; say

For Final Coating;

116.04
=2.90 3
40
; say

For Concrete Neutralizer;

116.04
=2.90
40

* One quart of neutralizer is mixed with 2-½ gallons


of water

2.90
=1.16 1.50
2.5
; say

TOTALS 27 27 11

BILL OF MATERIALS
COMPUTATION SHEET
Materials And Estimated Quantities
Item to be Required
Calculations
Estimated Wood Primer
Quick Dry
Paint Thinner
Enamel
(gallons) (gallons)
(gallons)
Ceiling First Floor Ceiling
Paint First Floor Area = 90.00 m 2
Less: Interior Wall Area = 10.49 ×0.10=1.05 m2
Column Area = 12(0.42 ×0.17)=0.86 m 2
Beam Area = 63.60 ×0.20=12.72 m2
Stairwell Area = 2.11×3.40=7.17 m2
Total First Floor Ceiling Area = 68.20 m 2

Under area coverage of 35 sq. m. per gallon:

For Primer Paint;

68.20
=1.95 2
35
; say

For Top Coating;

68.20
=1.95 2
35
; say

Second Floor Ceiling


Second Floor Area = 94.50 m 2
Less: Interior Wall Area = 32.59 ×0.10=2.90 m2
Column Area = 15(0.42× 0.17)=1.07 m2
Beam Area = 73.50 ×0.20=14.70 m2
Total First Floor Ceiling Area = 75.83 m 2

Under area coverage of 35 sq. m. per gallon:

For Primer Paint;


2
75.83
=2.17
35
; say

For Top Coating;


2
75.83
=2.17
35
; say

For Paint Thinner


Total gallons of Paint = 8 gallons
1
Under an average of ½ liter per gallon of paint:
8 × 0.132=1.06 ; say
TOTALS 4 4 1

PROJECT TITLE:
OWNER/S:
LOCATION:
BILL OF MATERIALS
COMPUTATION SHEET
Item to be Estimated
Materials Required
Estimated Quantity
30.00mm2 THHN Copper Wire, 150m 2 boxes

8.0mm2 TW Copper Wire, 150m 1 box

32 mm Ø RSC Pipe 2 boxes

Lighting Outlet 63 pieces

Duplex Convenience Outlet 16 pieces

Refrigerator Outlet 1 piece

Washing Machine Outlet 1 piece

Range Outlet 1 piece

Air Conditioning Unit Outlet 5 pieces

Weather-proof Outlet 2 pieces

Single Pole Switch 2 pieces

Duplex Pole Switch 7 pieces

Triplex Pole Switch 7 pieces

Three-way Switch 2 pieces

Fuse Box 1 piece

Circuit Breaker 15 pieces

Junction Box D.T. 4” x 4” 54 pieces

Utility Box D.T. 2” x 4” 75 pieces

Electrical Tape 25 rolls


PROJECT TITLE:
OWNER/S:
LOCATION:
BILL OF MATERIALS
COMPUTATION SHEET
Item to be Estimated
Materials Required
Estimated Quantity
PVC Pipe 4” Ø, 10 ft

Sanitary Line Length of Pipe:

2.50+1.00+5.00+ 11.50+10.50+1.50+ 1.50+21.00+3.00+2.50+ 2.00=62.00 m∨203.40 ft

No. of Bars required:

203.40
=20.34
10

; say
21 pieces

Sanitary Tee 9 pieces

Elbow 14 pieces

1/8 in. Ø Bend Elbow 14 pieces

1/8 in. Ø Bend Elbow and Wye Combo 2 pieces

Sanitary Wye 15 pieces

Coupling 21 pieces

Clean-out with Plug 10 pieces

Solvent Cement 15 liters

Pipe ¾ in. Ø by 14.00 ft

Water Line Length of Pipe:

1.50+13.00+18.00=32.50 m∨106.62 ft

No. of Bars required:


106.62
=7.62
14
8 pieces
; say
Pipe ½ in. Ø by 14.00 ft

Length of Pipe

0.25+ 0.80+0.60+1.80+ 4.00+10.50+3.00+1.00=21.95 m∨72.00 ft

No. of Bars required:


72.00
=5.14
14

; say 6 pieces

Elbow ¾ in. Ø 3 pieces

Elbow ½ in. Ø 6 pieces

Street Ell 4 pieces

PE Adaptor 1 piece

Tapped Tee ¾ in. Ø 1 piece

Tapped Tee ½ in. Ø 10 pieces

Reducer Ell 3 pieces

Reducer Tee 5 pieces

Nipple 14 pieces

Union 2 pieces

Water Meter 1 piece

Gate Valve 3 pieces

Faucet (Kitchen) 1 piece

Faucet (Bathroom) 5 pieces

Hose Bibb 2 pieces

Concrete Hollow Blocks, 100 × 200 × 400 mm 100 pieces


Septic Tank Concrete Hollow Blocks, 150 × 200 × 400 mm 260 pieces

Steel Reinforcing Bars, Deformed 10 mm Ø 14 pieces

Cement 32 bags

Sand 3.20 cu.m.

Gravel 0.90 cu.m.

PVC Pipe 6 in. Ø, 10 ft


Catch Basin
Length of Pipe

36.00+14.00=50.00 m∨164.04 ft

No. of Bars required:


164.04
=16.40
10

; say 17 pieces

Concrete Hollow Blocks, 100 × 200 × 400 mm 120 pieces

Steel Reinforcing Bars, Deformed10 mm Ø 3 pieces

Cement 15 bags

Sand 0.90 cu.m.

Gravel 1.20 cu.m

Water Closet 3 pieces

Fixtures and
Urinal 2 pieces
Accessories
Lavatory 3 pieces

Kitchen Sink 1 piece

Laundry Tray 1 piece

Soap Holder 3 pieces

Toilet Paper Holder 3 pieces


Towel Holder 2 pieces

Shower Head 2 pieces

Floor Drain 4 pieces

Miscellaneous Teflon Tape 20 rolls

PROJECT TITLE:
OWNER/S:
LOCATION:
BILL OF MATERIALS
COMPUTATION SHEET
Item to be Estimated
Computation
Estimated Quantity

Excavation for F-1


Rectangular Side Footing for Rectangular Column
Footing Excavation volume per footing = 1.10 ×1.30 ×1.20=1.72 m3
No. of Side Footing = 4 sets
3
Total Excavation Volume = 4 ×1.72=6.86 m3 6.90 m

F-2
Center Footing for Rectangular Column
Excavation volume per footing = 2.00 ×1.20 ×1.20=2.88 m3
No. of Side Footing = 8 sets 3
Total Excavation Volume = 8 ×2.88=23.04 m3 23.00 m

Excavation for Exterior Wall Footing


Wall Footing Total Length of Exterior Wall Footing = 33.12 m
3
Total Excavation Volume = 33.12 ×0.60 × 0.80=15.90 m3 15.90 m

Interior Wall Footing


Total Length of Interior Wall Footing = 10.49 m
3
Total Excavation Volume = 10.49 ×0.60 × 0.80=5.04 m3 5.00 m

Excavation for Excavation Volume of Septic Tank


Septic Tank 3 3
3.70 ×1.30 ×1.70=8.18 m 8.20 m

Backfill and F-1


Compaction for Side Footing for Rectangular Column
Rectangular Volume of Excavation = 1.72 m3
Footing Less: Volume of Footing = 1.07 m3
Volume of Column = 0.06 m3
Backfill and Compaction volume per footing = 0.59 m3

No. of Side Footing = 4 sets 3


2.40 m
Total Backfill and Compaction Volume = 4 ×0.59=2.36 m3

F-2
Center Footing for Rectangular Column
Volume of Excavation = 2.88 m3
Less: Volume of Footing = 1.21 m3

Volume of Column = 0.06 m3


Backfill and Compaction volume per footing = 1.61 m3 3
No. of Side Footing = 8 sets 12.90 m
Total Backfill and Compaction Volume = 8 ×1.61=12.88 m3
Backfill and Exterior Wall Footing
Compaction for Total Length of Exterior Wall Footing = 33.12 m
Wall Footing 3
Total Excavation Volume = 33.12 ×0.45 × 0.60=8.94 m3 9.00 m

Interior Wall Footing


Total Length of Interior Wall Footing = 10.49 m
3
Total Excavation Volume = 10.49 ×0.50 × 0.60=3.15 m 3 3.20 m

Gravel Fill Area of Gravel Fill = 83.13 m 2


3
Volume of Gravel = 83.13 × 0.20=16.62 m3 17.00 m

PROJECT TITLE:
OWNER/S:
LOCATION:
BILL OF MATERIALS
COMPUTATION SHEET
Materials And Estimated
Item To Be Quantities Required
Calculations
Estimated 12mm THK 2” by 2”
Plywood Lumber

Ceiling Joist First Floor Ceiling


First Floor Area = 90.00 m 2
Less: Interior Wall Area = 10.49 ×0.10=1.05 m2
Column Area = 12(0.42 ×0.17)=0.86 m 2
Beam Area = 63.60 ×0.20=12.72 m2
Stairwell Area = 2.11×3.40=7.17 m2
Total First Floor Ceiling Area = 68.20 m 2

Under 2” by 2” ceiling joist at 0.40 m by 0.40 m


spacing :
68.20 ×6.379=435.05 ; say 435

Second Floor Ceiling


Second Floor Area = 94.50 m 2
Less: Interior Wall Area = 32.59 ×0.10=2.90 m2
Column Area = 15( 0.42× 0.17)=1.07 m 2
Beam Area = 73.50 ×0.20=14.70 m2
Total First Floor Ceiling Area = 75.83 m 2

Under 2” by 2” ceiling joist at 0.40 m by 0.40 m 484


spacing :
75.83 ×6.379=483.72 ; say

Ceiling First Floor Ceiling


Board First Floor Area = 90.00 m 2
Less: Interior Wall Area = 10.49 ×0.10=1.05 m2
Column Area = 12(0.42 ×0.17)=0.86 m 2
Beam Area = 63.60 ×0.20=12.72 m2
Stairwell Area = 2.11×3.40=7.17 m2
Total First Floor Ceiling Area = 68.20 m 2

No. of Plywood required:

68.20
=23.68 24
2.88
; say

Second Floor Ceiling


Second Floor Area = 94.50 m 2
Less: Interior Wall Area = 32.59 ×0.10=2.90 m2
Column Area = 15(0.42× 0.17)=1.07 m2
Beam Area = 73.50 ×0.20=14.70 m2
Total First Floor Ceiling Area = 75.83 m 2

No. of Plywood required:

75.83
=26.33 27
2.88
; say

TOTALS 51 919