KGTL 1

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 1

Karachi Port - Demolition Replacement and Construction Works

Bill Of Quantities and Prices


Estimated Unit Rate Total Amount
Item Description Unit
Quantity (PKR) (PKR)

1 RTG Crane Rail Foundations

Removal of Paving blocks, dismantling & demolition of existing


1.1 m² 60,000 850 51,000,000
lean concrete including disposal of debris at designated places.

Excavation in all kinds of sub surface material upto 1.5 m Depth,


1.2 including dewatering and disposal of surplus/rejected material at m³ 85,800 1,035 88,803,000
designated places.

Providing and laying plain cement concrete Class "C1" in


foundation, floor bed, floor and wherever required using
approved graded broken stone aggregate upto 25mm and
1.3 m³ 26,106 16,143 421,425,284
sand i/c levelling, compacting, curing and form work etc.
complete according to the drawings and instruction of the
Engineer.

Providing and laying, Fair face reinforced cement concrete


Class "A", using approved graded, crushed stone aggregate upto
3/4" and sand i/c formwork, levelling, vibrating, curing etc. in
1.4 m³ 2,494 25,310 63,129,214
floor and wherever required excluding the cost of steel
reinforcement, complete according to the drawings,
specifications and instruction of the Engineer.

Providing and filling Imported earth (Morrum) in under floors or


wherever required in layers not exceeding 9” thick and each
layer to be compacted to 95% of maximum dry density
1.5 determined by modified AASHTO procedure described in ASTM D- m³ 57,200 3,593 205,519,600
1SS7 i/c. Breaking clods, dressing, ramming, watering and
consolidating to full compaction all complete according to
drawing, specification and the instruction of Engineer Incharge.

Precast concrete Heavy Duty Pavers of size 200 x 100 x 80mm


1.6 laid in approved pattern over 50 mm thick sand cushion complete m² 50,074 2,993 149,870,285
in all respects, as shown on drawings and as directed by Engineer.

1.7 Providing and fixing M.S. trench Size: 4'' x 4'' x 2'' x 8mm thick. m 1,164 4,821 5,611,644

Providing and laying at any height steel reinforcement grade 40 or


grade 60 conforming with B.5.4449 having minimum yield
stress of 40,000 psi or 60,000 psi respectively, with and
including the cost of straightening, cutting, bending, binding,
1.8 wastage and such overlaps as are not shown over the drawings, Tonne 262.65 467,000 122,656,373
placing in position of cement concrete (1:2:4) precast spacers,
M.S. Chairs, tying with binding wire including cost of chairs and
binding wire etc. complete according to
drawings,specification and instructions of the Engineer.

C.15 Buildings Construction Works

C.15.1 New KGTL offices m² 900 225,000 202,500,000

C.15.2 Replacement Welfare/Canteen/Workshop m² 600 200,000 120,000,000

C.15.3 Replacement equipment/store area m² 600 200,000 120,000,000

C.15.4 New Mosque m² 400 250,000 100,000,000

New Equipment Area/Workshop (15m x 20m x 6m shed with some


C.15.5 m² 300 210,000 63,000,000
internal offices)

C.15.6 New Concrete Substation ls 1.00 20,000,000 20,000,000

TOTAL CONTRACT PRICE 1,733,515,400

Bill of Quantities Page 1/15