Karachi Port - Demolition Replacement and Construction Works

Bill Of Quantities and Prices

S. NO. ITEM DESCRIPTION UNIT QTY RATE AMOUNT (PKR)

1 Mobilization / Demobilization of equipment,


Office, workshops etc. L.S. 1 5,000,000 5,000,000

Removel of paver blocks, Demolition of lean


concrete and excavation up to +2.75 m kptd and
2
relocation of existing underground utilities Storm
Water Drain, Elecrical conduit, Telephone conduit,
Fire Fighting etc. Sq.M. 1200 13,035 15,641,400
RCC bored cast Piles 1.5m dia with length 30.0 m
including grade 60 steel reinforcement, casing
3 driving, boring, reinforcement fixing and 40 MPA
concrete pouring, Pile head cutting complete.
Permanent steel liner 11.00 and TH=12mm may be
used. No. 96 12,147,330 1,166,143,680

In situ RCC crane rail beam including grade 60 steel


4 reinforcement 40 MPA concrete and forming crane
rail slot, galvanized steel angle, installation of
embedded parts etc. LM 200 583,021 116,604,200

Reconstruction of pavement including sub-base,


5 backfilling and compaction of special granular fill,
lean concrete and fixing of concrete
envicrete paver blocks. Sq.M. 640 62,371 39,917,120

Construction of Test Pile (RCC) of 1.5m dia, 30.0 m


6 length including permanent steel liner, steel driving,
boring, grade 60 steel fixing and 40 MPA concrete
pouring, Pile head cutting complete. Permanent
steel liner 11.00 and TH=12mm may be used. No. 1 12,147,330 12,147,330
Conduct Static Pile Load Test upto 1500t using
7
kentledge loaded with Concrete Blocks. No. 1 11,000,000 11,000,000
SUM: 1,366,453,730
Add 13% S.S.T: 177,638,985
TOTAL AMOUNT: 1,544,092,715