Material Cost

You might also like

Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 1

Material Quantity

[Foundation to 1st Floor Casting Complete]


Sl Item Description Unit Quantity Rate[approx.] Taka
1 Cement Bag. 700 520 364000
2 Sand (Sylhet) Cft. 1000 52 52000
3 Sand (Local) Cft. 650 24 15600
4 Picket Pcs. 25000 11 275000
5 01 no Bricks Pcs. 6000 11 66000
6 10 mm Dia Rod kg. 3400 89 302600
7 12 mm Dia Rod kg. 280 89 24920
8 16 mm Dia Rod kg. 3700 89 329300
9 20 mm Dia Rod kg. 220 89 19580
Total Amount 1449000