KORAPANI IRRIGATION PROJECT

Lat: 21⁰-44’-09”N
Long: 85⁰-02’-33”E

The proposed Karapani Irrigation Project is located near village Barghat in Bonai sub-
division/Lahunipada Block of Sundargarh District. It envisages construction of an earth dam across the
Karapani Nallah, a left tributary of River Brahmani. The catchment area at the proposed site is 121 sqkm
lies entirely in the state of Odisha.

Assembly Constituency:

Cost: Rs.145.15 crore (2012 price level)

Benefit:

Irrigation- 3500 ha ( Lahunipara-1698ha and Bonai-1802ha of Sundargarh District)


Water Supply: Nil
Power Generation: Nil

Total Land Involved in Project (ha)


Type of land Submergence Area Distribution system Total
Forest land 91.355 21.72 113.075
Govt. land 133.158 14.284 147.442
Private land 191.57 27.847 219.417
Total land 416.083 63.851 479.934

Submergence Details:
Fully Submerged Village- 02nos
Partly Submerged Village- 03 nos
Displaced Family- 148 nos (Total Population- (2006 Census)
Affected Family- nos (Total Population- no)

Head Works:
Length of Dam(m): 1312.00 FRL(m) : 190.50
Type: Earth dam with central spillway MWL(m): 190.50
GSC- 3220 ham DSC-49 ham
Distribution System: Length Left Main Canal- 12.00 Km and Right Main Canal- 4.98 Km

 Status of Project Report:- DPR is found to be in order vide CWC lr. no.343 dtd. 10.05.2013.

Status of Statutory Clearances:

Technical Clearance from CWC(MoWR)/State TAC-


Forest Clearance- Stage-I Forest Clearance for 113.075 Ha. has been obtained by MoEF & CC
dated 15th December 2021. Cost for NPV & CATP has been deposited to Forest Deptt.
Permission has been obtained for additional item i.e. site-specific wildlife conservation plan from
DoWR during July 2022.
Environmental Clearance- Conditional Environmental Clearance obtained from SEIAA vide lr.
no. 119 dtd. 21.04.2016 subject to submission of copy of stage-I forest clearance.
R&R Clearance-R&R plan has been submitted to ST & SC Dev., Deptt., GoO by DoWR for
onward transmission to MoTA, GoI.

 Present status: DPR is found to be in order vide CWC lr. no.343 dtd. 10.05.2013.