Professional Documents
Culture Documents
Lec 1intro Remoteness Mitigation
Lec 1intro Remoteness Mitigation
(LAW549)
DR. NORAZLINA ABDUL AZIZ
Redress for a wrong, to put right, to set
right, to rectify, to retrieve, to put in order, to
straighten out, to resolve, to correct, to
What is repair, to mend.
remedy? A way of solving a problem or ordering
someone to make a payment for harm or
damage they have caused, using a decision
made in a law court.
Compensation
Objective/
Specific relief
Function of
Restitution
Remedy?
Redress a wrong (rather than to punish)
Ability to recognise which
remedy is appropriate
Ability to determine the
The skill that likelihood of success
you have to Ability to seek/choose between
acquire: alternative remedies
Understanding of how to
calculate damages
Statutory/legal rights
Breach of v. Equitable rights
rights under
Contract or
Tort
Judicial v.
Non-judicial
Legal
Damages
Rights
Specific
Equitable
Performance &
Rights
Injunction
Functions
Damages in
Contract
Fundamentals
Basic Principles
• Developed by the common law
Money courts. If breach is proved,
compensation damages will be awarded by the
courts to the aggrieved party.
DAMAGES:
the meaning
Right to the • a remedy for every breach,
innocent party whether the nature of the breach
to claim is serious or not.
1)To compensate the aggrieved party by placing
the aggrieved party as far as money can do it in the
same position as if the contract has been
performed/ if the contract had not been breached.
'restitution in integrum’- restoration to original
condition.
DAMAGES:
the objectives 2)To protect the innocent party’s reliance
interest/loss
Compensatory • not to benefit the Plaintiff .
in nature • See Tan Sri Khoo Teck Puat v Plenitude Holdings.
Types of • Pecuniary
losses • Non- pecuniary
Remoteness
Mitigation
Damages:
Principles of
Principles of Assessment
Assessment Anticipatory
Date
Breach
Taxation
Rule in Hadley v Baxendale
PRINCIPLE OF
• (1854) 9 Exch 341
ASSESSMENT
OF DAMAGE: Remoteness of Damage
Remoteness of
damage
Mitigation of Damage
FACTS:
The claimant, Hadley, owned a mill featuring a broken crankshaft.
Hadley v The claimant engaged Baxendale, the defendant, to transport the
crankshaft to the location at which it would be repaired and then
Baxendale: subsequently transported it back. The defendant then made an
Whether the loss of error causing the crankshaft to be returned to the claimant a week
profits resultant from later than agreed, during which time the claimant’s mill was out of
the mill’s closure was operation. The claimant contended that the defendant had
too remote for the displayed professional negligence and attempted to claim the loss
claimant to be able to of profit resulting from the unexpected week-long closure. The
claim. defendant retorted that such an action was unreasonable as he
had not known that the delayed return of the crankshaft would
necessitate the mill’s closure and thus that the loss of profit failed
to satisfy the test of remoteness.
As Baxendale had not reasonably foreseen the
consequences of delay and Hadley had not
Held: informed him of them, he was not liable for the
mill’s lost profits.
Here, the loss of profits did not fall under the 1st
limb as normally mills would have spare shaft.
Since the Defendant did not know that the
Plaintiffs did not have spare shaft, the losses did
not fall under 2nd limb.
**In this case, the defendant had no means of
knowing that the plaintiff would lose profits if the
Grounds: shipment of the shaft was delayed since this
information (P had no spare shaft) was not
communicated directly to D). Therefore, the loss of
profits was not reasonably contemplated by both
the parties when they made the contract.
Hence, the losses are not recoverable.(too remote)
HADLEY’S IN OUR CONTRACT LAW
Important loss is reasonably viewed to have
1st limb resulted naturally from the
principles:
breach, or
embedded in
s. 74(1) of the
Contracts Act Or which the parties knew, when
1950 2nd limb they made the contract, to be
likely to result from a breach of it
Section 74 Contracts Act 1950 sets out the consequences of a
breach of contract:
(1) when a contract has been broken, the party who suffers by the
breach is entitled to receive, from the party who has broken the
Remoteness of contract, compensation for any loss or damage caused to him
Damages in thereby,
which naturally arose in the usual course of things from the
Malaysia. breach, or which the parties knew, when they made the contract,
to be likely to result from the breach of it.
Imputed Actual
IMPUTED:
1st Limb of
KNOWLEDGE: Hadley
when the
defendant ACTUAL:
knew
2nd Limb of
Hadley
Victoria Laundry (Windsor) Ltd v Newman
Industries Ltd [1949] 2 KB 528
Facts:Victoria Laundry Ltd (VLL) ordered a large boiler from
Hadley : the Newman Industries Ltd (NIL) in contemplation of some lucrative
dyeing contracts. NIL were aware of the nature of VLL’s business,
development and that it was intended for the boiler to be put to use as soon as
possible. The delivery of the boiler was delayed by five months
of it’s principle and VLL claimed for breach of contract.
in other cases.
Held:NIL knew the boiler was required as soon as possible for
business purposes; they must have contemplated the use for
which the boiler was to be put. Damages would be awarded for
losses which could reasonably have been expected to be lost.
Bee Chuan Rubber Factory Sdn Bhd v Loo
Sam Moi [1976]
The plaintiff had entered into a tenancy agreement with the defendant. The
period of the agreement was for three years commencing from 12 October
1974 to 11 October 1977, at the monthly rate of $5928.75. On 11 February
1976, the defendant (tenant) wrote to the plaintiff telling their intention to
repudiate the contract and vacated the premises. However, the
plaintiff refused to accept the letter and continued to claim rental for the
premises.
During this time, there was an offer made to the plaintiff to rent the
premises at $4000 per month but the plaintiff rejected this offer. In April 1977,
the plaintiff succeeded in finding another tenant to rent the premises at the
same rate as that paid by the defendant.
The plaintiff then claimed for damages for the loss of rental from February
1976 until April 1977.
The defendant(tenant) claimed that the plaintiff should only be entitled for
the difference between the original rental and the offered rental as the
plaintiff had failed to mitigate his losses by rejecting the $4000 per month
offer made earlier.
On the other hand, the plaintiff claimed that by virtue of White and Carter
he was not obliged to mitigate unless there was a breach of contract and
further argued that
a breach had not yet occurred until he accepted D’s breach (when he
accepted a new tenant in April 1977)
The court held: by virtue of White and Carter (Councils) Ltd, the
breach occurred when the plaintiff finally accepted the anticipatory
repudiation that was when the plaintiff finally took in a new tenant.
As duty to mitigate losses can only arise if there is a breach of contract,
the plaintiff was under no obligation to mitigate it when the defendant
wrote him a letter of repudiation as there was no breach then.
So, the court allowed the claim for damages for the loss of rental from
February 1976 to April 1977 and ruled that the plaintiff was not obliged
to mitigate as there was no actionable breach and that the plaintiff had
elected to ignore the anticipatory breach.
Ban Chuan Trading Co Sdn Bhd v Ng
Bak Guan [2004]
- CA took a different view and held that the plaintiff should
mitigate his losses even in cases of anticipatory breach. This
is because, by looking at the judgment by Mokhtar Sidin JCA, he
required the plaintiff/tenant to accept the repudiation as soon as
possible and by doing so, it could minimize his losses.
Timing of As a general rule, damages should be assessed as at the date
of breach. - Eikobina (M) Sdn Bhd v Mensa Mercantile (Far
Assessment of East) Pte Ltd [1994]
Damages For foreign currency debts – at the date of judgment
(Miliangos v George Frank (Textiles) Ltd [1976]
In appropriate cases (injustice), losses can be assessed as at
the date of trial – Johnson v Agnew [1980], Tan Ah Chim &
Sons v Ooi BeeTat [1993]