Download as pdf or txt
Download as pdf or txt
You are on page 1of 25

TRENDS IN CONSTRUCTION

CLAIMS & DISPUTES

A Research Perspective Issued by the

Navigant Construction Forum™

James G. Zack, Jr.


Executive Director
Navigant Construction Forum™

December 2012

Construction Forum
CONSTRUCTION

Notice Navigant Construction Forum™


This report was prepared by the Navigant Navigant (NYSE: NCI) established the
Construction Forum™ of Navigant Navigant Construction Forum™ in
Consulting, Inc (“Navigant”). Claims and September 2010. The mission of the
disputes are a constant in the construction Navigant Construction Forum™ is to
industry, regardless of whether the industry be the industry’s resource for thought
is doing well or poorly. The number of leadership and best practices on avoidance
claims seems to have risen during the recent and resolution of construction project
recession despite the downturn (or perhaps disputes globally. Building on lessons
as a result of downturn) in the construction learned in global construction dispute
industry. This research perspective is avoidance and resolution, the Navigant
intended to provide an overview of Construction Forum™ issues papers and
some relatively recent trends related to research perspectives, publishes a quarterly
construction claims and disputes observed e-journal (Insight from Hindsight), makes
by the Navigant Construction Forum™. presentations and offers in-house seminars
Through this insight it is hoped that owners, on the most critical issues related to
design professionals, construction managers, avoidance, mitigation and resolution of
contractors and subcontractors can devise construction disputes.
ways to avoid such issues going forward –
Navigant is a specialized, global expert
thus making projects more successful, and
services firm dedicated to assisting clients
more profitable, for all stakeholders.
in creating and protecting value in the face
Presented herein are provided with the of critical business risks and opportunities.
understanding that they are general in Through senior level engagement with
nature, do not relate to any specific project clients, Navigant professionals combine
or matter and do not necessarily reflect technical expertise in Disputes and
the official policy or position of Navigant. Investigations, Economics, Financial
Because each project and matter is unique Advisory and Management Consulting,
and professionals may differ in their with business pragmatism in the highly
opinions, the information presented herein regulated Construction, Energy, Financial
should not be construed as being relevant Services and Healthcare industries to
or true for any individual project or matter. support clients in addressing their most
Navigant makes no representations or critical business needs.
warranty, expressed or implied, and is
Navigant is the leading provider of expert
not responsible for the reader’s use of, or
services in the construction and engineering
reliance upon, this research perspective
industries. Navigant’s senior professionals
or for any decisions made based on this
have testified in U.S. Federal and State
publication. No part of this publication may
courts, more than a dozen international
be reproduced or distributed in any form or
arbitration forums including the AAA,
by any means without written permission
DIAC, ICC, SIAC, ICISD, CENAPI, LCIA
from Navigant. Requests for permission to
and PCA, as well as ad hoc tribunals
reproduce content should be directed to
operating under UNCITRAL rules. Through
jim.zack@navigant.com.
lessons learned from Navigant’s forensic
cost/quantum and programme/schedule
analysis of more than 5,000 projects located
in 95 countries around the world, Navigant’s
construction experts work with owners,
contractors, design professionals, providers
of capital and legal counsel to proactively

CONSTRUCTION DECEMBER 2012 2


CONSTRUCTION

manage large capital investments through thus providing even more work for claim
advisory services and to manage the risks consultants than when the industry was
associated with the resolution of claims doing well.
or disputes on those projects, with an
Over the past few years of the current
emphasis on the infrastructure, healthcare
recession the industry has again taken a
and energy industries.
substantial hit economically. The number
of projects declined as did the number of
Purpose of Research Perspective construction companies. However, despite
The Navigant Construction Forum™ this decline (or perhaps as a logical reaction
was recently asked to identify new trends to this adverse impact to the industry) it
in the area of construction claims and appears from the Construction Forum’s
disputes. In response to this request the research that the number of claims has risen.
Forum conducted a survey of Navigant “Claimsmanship” 1 has proliferated in the
senior claims consultants in-house and past few years and appears to be equally
an e-mail survey of a number of external practiced by both owners and contractors,
claims professionals with national and and their representatives. As a direct result,
international claims experience. The the number of claims has likewise grown.
response rate was somewhat over 30% From this growth in claims several trends
as many claims consultants have either have developed, among them:
sensed or observed new or developing
trends in the claims arena. The purpose of »» The value of construction disputes has
this research perspective is to summarize declined in the U.S. (as opposed to the
these new trends in an effort to alert Middle East) but the duration of such
stakeholders in the construction industry disputes has increased;
as to the issues we see coming now and »» Courts and Boards of Contract Appeals
in the relatively near future. Additionally, decisions limiting recovery of damages
the Navigant Construction Forum™ offers in the areas of concurrent delay;
recommendations that should help decrease suspensions of work; time extensions;
the downside risk of these new trends notices and claim filing requirements;
related to construction claims and disputes. calculation of extended home office
overhead costs; proof of differing site
Introduction conditions; and risk transfer in the
design/build environment have all
When I first became involved in become more frequent;
construction claims and disputes on a full
»» Public owners have increased the use of
time basis in the 1970’s I asked a noted
False Claim allegations in response to
claims consultant why he had chosen
claim filings;
claims consulting as a career. The response
was short and pithy – “When construction is »» Contractors are becoming more creative
good, claims are good. When construction in developing new forms of claims; and,
is bad, claims are better!” I did not fully »» Increased use of Alternative Dispute
appreciate the accuracy of this response Remedies (“ADR”) has grown
until the recession in the early 1980’s. significantly in order to avoid costly
The construction industry suffered a arbitration and litigation, resolve issues
severe downturn but the number of and, perhaps, maintain relationships
claims proliferated in an inverse ratio between the parties.

1
“Claimsmanship” is generally defined as the art of practice of making and winning claims by questionable expedients without actually violating
the rules.” See James G. Zack, Jr., “Claimsmanship“: Current Perspective, Journal of Construction Engineering and Management, Vol. 119, No.
3, September, 1993, American Society of Civil Engineers.

CONSTRUCTION DECEMBER 2012 3


CONSTRUCTION

These trends may have been exacerbated Value and Duration of


by what the construction bar refers to
as the “vanishing trial”. In regard to this
Construction Disputes
issue a recent article noted that between It has been reported that globally the value
“…1938 and 2009, there was a decline in of construction disputes has declined in the
the percentage of civil cases going to trial United States and Asia but increased slightly
of over 90%...”The author also noted that in Europe and substantially in the Middle
“…the pace of the decline was accelerating East.4 The average value of the disputes
toward the end of that period…” 2 sampled for this report is set forth below
by region. At the global level, dispute value
In March 2012, Andrew D. Ness, then
declined 8% from 2010 to 2011.
Chair-Elect of the American Bar Association
Forum on the Construction Industry DISPUTE DISPUTE
addressed this issue. As Mr. Ness pointed REGION VALUE – 2011 VALUE - 2010
out, in the U.S. legal system “construction (MILLIONS) (MILLIONS)
law” is derived primarily from case law – UK US$10.2 US$7.5
prior legal decisions.3 Mr. Ness pointed EUROPE US$35.1 US$33.3
out as the construction industry changes MIDDLE EAST US$112.5 US$56.3
and evolves (i.e., project delivery methods,
ASIA US$53.1 US$64.5
Building Information Modeling, Green
US US$10.5 US$64.5
construction, location based scheduling,
etc.) so too must construction law. The GLOBAL
US$32.2 US$35.1
unintended consequence of the vanishing AVERAGE
trial is that construction law stops evolving. This same report, however, also concluded
Mr. Ness quoted the Rt. Hon. Beverly that the time required to resolve disputes
McLachlin, Chief Justice of Canada (whom rose from 9.1 months to 10.6 months. The
he identified as a “recovering construction average length of time (in months) to resolve
lawyer) on this issue as follows: the disputes sampled increased at the global
“All areas of law – construction law level by some 16%, as set forth below:
included – are living, constantly
LENGTH OF LENGTH OF
evolving trees. Some branches sprout REGION DISPUTE – 2011 DISPUTE – 2010
and grow; others crack and need (MONTHS) (MONTHS)
trimming. Thus, the law develops UK 8.7 6.75
and remains responsive to changes
EUROPE 11.7 10
in society. The Construction Law
MIDDLE EAST 9 8.25
tree looks different than it used to. It
may not be dead, but new branches ASIA 12.4 11.4
are not appearing as often as they US 14.4 11.4
once did. And old branches that need GLOBAL
10.6 9.1
pruning are being neglected.” AVERAGE

This research perspective discusses each of


these growing trends, and where possible,
offers ideas for mitigating or avoiding
the negative impacts of such trends in
construction claims and disputes.

2
Robert P. Burns, What Will We Lose If The Trial Vanishes?, Northwestern University School of Law, Public Law and Legal Theory Research
Paper Series No. 11-48, 2011. See also, Marc Galanter and Angela Frozena, ‘A Grin Without A Cat’: Civil Trials in the Federal Courts, 2010 Civil
Litigation Conference, Judicial Conference Advisory Committee on Civil Rules, Durham, N.C., May, 2010.
3
Andrew D. Ness, The Future of Construction Law and Claims, 51st Annual Western Winter Workshop, AACE International, Lake Tahoe, NV, March 2012.
4
Global Construction Disputes 2012: Moving in the Right Direction, EC Harris, London, May 28, 2012.

CONSTRUCTION DECEMBER 2012 4


CONSTRUCTION

MIDDLE NORTH
CAUSE OF CLAIMS ASIA EUROPE UK
EAST AMERICA
Ambiguous requirements 3 1 5
Conflicting party interests 3 3 2
Contract administration issues 1 1 5 1
Failure to resolve time extension & delay damages 1 4 4 4
contemporaneously
Incomplete design 5 2 2 2
Owner caused changes 5 3 4
Unrealistic time of completion 4
Unrealistic risk transfer 2 5 3

By reverse scoring these rankings by of 2011. This survey determined that in


region5 and adding up the scores this report the 2009 – 2011 timeframe there were 65
indicates that these causes of claims can be international contract arbitrations in which
ranked globally in the following order. at least US$1 billion was in controversy.6
The amounts in controversy ranged from
1. Contract administration issues;
US$20 billion to US$1 billion.7 The total
2. Incomplete design and ambiguous value of these 65 disputes was US$174.8
contract requirements; billion with the median value being
3. Failure of the owner and contractor to US$2.73 billion. This global survey indicates
resolve time extensions and delay damages a much higher range of dispute values
at the time they occur on the project; than the earlier cited study. This study also
4. Conflicting party interests; indicates that more international projects,
at least, are going to arbitration than the
5. Unrealistic risk transfer; and,
earlier study seemed to indicate.
6. Unrealistic time of completion.
Like the American Lawyer survey, a recent
This cause of claims listing and ranking offers Navigant Construction Forum™ research
some suggestions regarding claims avoidance perspective also concluded, among other
and resolution which will be discussed at the things, that international construction
end of this research perspective. arbitration is growing rapidly.8 Born and
This report provided a good deal of Miles have reported that case filings with
information on claims value, length of time the International Chamber of Commerce
to resolve disputes and the most common (“ICC”), the American Arbitration
causes of disputes. The methodology Association (“AAA”) and the International
employed in this study limited the projects Center for Dispute Resolution (“ICDR”)
and disputes sampled to those the firm have increased between three and five fold
handled during the 2010 and 2011 period. over the past 25 years.9 A major university
in the UK also documented an 8.5% growth
A more robust survey of claims and among 22 arbitral institutions between 2003
disputes submitted to international and 2007.10
arbitration was published in the summer

5
Where a 1st place gets a 5; 2nd place receives a 4; and so forth.
6
Michael D. Goldhaber, 2011 Arbitration Scorecard, americanlawyer.com/focuseurope, Summer 2011.
7
The “amount in controversy” represented the sum of claims and counterclaims.
8
Trends in International Construction Arbitration, Navigant Construction Forum™, Navigant Consulting, Inc., October 2012.
9
Gary Born and Wendy Miles, Global Trends in International Arbitration, American Lawyer – Focus Europe, August 2006.
10
International Arbitration: Corporate Attitudes and Practices, Queen Mary University of London School of International Arbitration and PriceWaterhouseCoopers, 2008.

CONSTRUCTION DECEMBER 2012 5


CONSTRUCTION

In preparing this research perspective The Navigant Construction Forum™


the Navigant Construction Forum™ concludes that international construction
conducted a survey of Navigant senior projects have larger disputes and are more
claims consultants in-house and an likely to resolve their disputes through
e-mail survey of a number of external arbitration. On the other hand, while the
claims professionals with national and number of claims within the United States
international claims experience. Juxtaposed seems to have increased substantially,
to the earlier cited study, the Forum’s claim values have declined as many more
survey found that in the United States, the small claims are now asserted. Additionally,
numbers of claims filed with project owners fewer claims are going to arbitration or
has increased substantially over the past litigation in the United States and more are
few years. However, like the earlier cited resolved through negotiation and/or various
study, the Forum’s survey determined that forms of ADR. The result of this trend is
(1) the value of the claims filed has fallen that owners and contractors will, more
substantially and (2) fewer claims are being than likely, be left on their own to resolve
prosecuted to arbitration or litigation. disputes without resort to arbitration or
litigation. For those well prepared to take on
Some of the findings of the Forum’s
this challenge dispute resolution costs may
survey follow:
decline and cost recovery or defense will
»» Due to the change in the economy over increase. For those not so well prepared, the
the past few years, and the government outcome will not be nearly as satisfactory.
funding more projects than the private This research perspective should help both
sector, many contractors experienced owners and contractors to become better
with negotiated private contracts bid prepared to face this new challenge.
on and were awarded government
contracts binding them to much stricter Increased Limitations on
contract requirements.
»» Along the same lines, many of the less
Recovery of Damages
than US$1 million claims are filed by Another trend observed by the Navigant
small contractors and subcontractors Construction Forum™ is that it is becoming
who entered the public sector when increasingly difficult for contractors
work in the private sector dried up and to recover on claims in litigation on
had, previously, little or no experience government contracts. Courts seem less
with pursuing claims in the public sector. likely to rule in favor of contractors in a
»» Fewer claims are proceeding to number of areas. Some limitations on
arbitration or litigation as most are contractor claim recovery are set forth below.
settled through negotiation or ADR
processes such as mediation, project
neutrals and private trials.
»» Public works owners seem to be
less willing now to hand off dispute
matters to attorneys and are more
ready to compromise in order to reach
settlements or settle through various
ADR mechanisms.

CONSTRUCTION DECEMBER 2012 6


CONSTRUCTION

Concurrent Delay compensable delay due to overlapping


owner caused delay and thus not subject to
Concurrent delay is defined as“[t]wo or
liquidated damages.14 The argument works
more delays that take place or overlap during
equally well in reverse: when contractors
the same period, either of which occurring
assert owner caused delay owners often
alone would have affected the ultimate
respond with allegations of contractor
completion date.”11 Concurrent delay has
caused delay, alleviating the need to pay for
been a contentious and hotly debated issue
delay damages.
since its creation in 1867.12 One in-depth
article on the issue of concurrent delay It appears, however, that courts have
examined the origins of the doctrine of become more conservative when faced with
concurrent delay. The authors summarized concurrent delay arguments and are less
the history of concurrent delay as follows: likely to simply accept concurrent delay
as a way of resolving delay cases. Courts
“…it is evident that the modern
seem to be placing more of a burden on
doctrine of concurrent delay is
contractors with respect to concurrent delay.
premised not on the equitable
For example, in George Sollitt Construction
resolution of construction delays,
Company v. U.S.15 the Court stated that a
but is instead based on past
contractor has an affirmative obligation to
litigants’ failure or inability to
separate and apportion concurrent delay.
effectively prove their cases and
That is, when a contractor is asserting a
the older courts’ hostility toward
delay claim they must first prove the delay
liquidated damages … Over time,
was caused by an event for which they
these factors merged and evolved
were not responsible; then document the
into the legal doctrine of ‘concurrent
duration of the delay to the critical path or
delay.’After several years, the later
the end date of the project; and then prove
courts stopped delving into the ‘real’
there was no concurrent delay during the
analyses of these early courts, and
same period.16 The Court also stated that
instead rotely applied these early
generally, recovery will be denied when
courts’ resolutions of concurrent
delays are concurrent or intertwined and
delay as a ‘rule’ for resolving all
the contractor has not separated its delays
overlapping construction delays.”13
from those caused by the owner.17 The
The issue is contentious in the main Court also stated that a contractor seeking
because it is frequently used as a “get recovery of compensable delay must “…
out of jail” card. When owners assess disentangle its delay from those allegedly
liquidated damages for late project caused by the government…” and prove
completion, contractors frequently respond that both delays impacted the project’s
with allegations of concurrent delay (i.e., critical path.18 Rulings such as this obviously
overlapping owner and contractor delay increase a contractor’s burden of proof when
periods) asserting that all or a part of arguing for recovery of compensable delay.
the late completion was excusable, non-

11
Recommended Practice No. 10S-90, Cost Engineering Terminology, AACE International, Morgantown, W.V., Rev. December 13, 2011.
12
Stewart v. Keteltas, 36 N.Y. 388, 1867 WL 6457 (1867), 2 Transc. App. 288 (1867).
13
James K. Bidgood, Steven L. Reed and James B. Taylor, Cutting the Knot on Concurrent Delay, Construction Briefings No. 2007-02, Thomson/
West, February, 2008.
14
Levering & Garrigues Co. v. U.S., 73 Ct. Cl. 566, 578 (1932); Schmoll v. U.S., 91 Ct. Cl. 1, 28 (1940); PCL Constr. Servs., Inc. v. U.S., 53 Fed. Cl.
479, 484 (2002), aff’d, 96 Fed. Appx. 672 (Fed. Cir. 2004).
15
64 Fed. Cl. 229, February 23, 2005.
16
William F. Klingensmith, Inc. v. U.S., 731 F. 2d 805, 809 (Fed. Cir. 1984).
17
Blinderman Constr. Co. v. U.S., 695 F. 2d 552, 559 (Fed. Cir. 1982).
18
Mega Const. Co. v. U.S., 29 Fed. Cl. 396, 424 (1993).

CONSTRUCTION DECEMBER 2012 7


CONSTRUCTION

Additionally two significant court cases – the contractually mandated procedure


one a Federal case in 2010 and the other a related to change orders, claims and time
State case in 2011 – seem to have created extensions, it was not necessary for the
new hurdles concerning concurrent delay. Court to review the alleged delay issues
(the concurrent delay argument), regardless
In M. Maropakis Carpentry, Inc. v. U.S.19
of which party was responsible for the late
the Court of Appeals for the Federal
completion. On appeal the Appellate Court
Circuit ruled that the contractor could not
ruled that:
allege or assert concurrent delay against
government imposed liquidated damages “[The] City was entitled to
unless the contractor had filed a certified liquidated damages for [the]
delay claim under the terms of the Contract general contractor’s late
Disputes Act20 and requested and received completion under the construction
the Contracting Officer’s final decision. contract, even if the delays were
In this case, the contractor had written caused by the City’s conduct,
letters to the Contracting Officer but did where the contract required any
not submit and certify a delay claim. Nor extension of time to be obtained
did the contractor request and receive through certain procedures, and
the final decision from the Contracting [the] general contractor did not
Officer. While the Court of Federal Claims use such procedures.” 22
upheld the government imposed liquidated
The Appellate Court ruled in this manner
damages it stated that they had no
despite the fact that the City admitted
jurisdiction to hear the contractor’s claim of
some of the delay for which they assessed
concurrent delay. On appeal to the Court of
liquidated damages was actually City
Appeals for the Federal Circuit, that Court
caused delay.
likewise upheld the liquidated damages
assessment but again denied the contractor After surveying the scene concerning the
the right to argue concurrent delay due to issue of concurrent delay it appears that
their lack of compliance with the Contract courts have increased the contractor’s
Disputes Act. Through two court cases, the burden of proof concerning concurrent
contractor was denied the right to present delay and constructed new hurdles
his defense of concurrent delay due to their concerning the use of concurrent delay as
failure to conform to the strict requirements a defense when owners assess liquidated
of the Contract Disputes Act. damages for late project completion.

In Greg Opinski Construction, Inc. v. City of Owners seeking to enhance their defenses
Oakdale21 a California Court of Appeals against concurrent delay situations can
issued a similar ruling to Maropakis but draw a lesson from these cases. Contractors
relied instead on the terms of the contract need to carefully comply with contract
documents as California does not have a provisions and statutory requirements in
statute analogous to the Federal Contract order to maintain the ability to present
Disputes Act. The Superior Court ruled concurrent delay as a defense against
that since Opinski had not followed liquidated damages.

19
609 F.3d 1323 (Fed. Cir. June 17, 2010).
20
41 U.S.C. § 605.
21
199 Cal. App. 4th 1107 (2011), 132 Cal. Rptr. M3d, 170 Court of Appeal, Fifth District, California (Oct. 6, 2011).
22
Greg Opinski Construction, Inc. v. City of Oakdale, ibid.

CONSTRUCTION DECEMBER 2012 8


CONSTRUCTION

Limitation on Recovery of Suspension Costs The contractor filed several claims for
additional compensation in September,
An owner directed suspension of work
2006 and requested that the Contracting
is typically considered an excusable,
Officer issue a final decision approving or
compensable delay. Unless the terms of the
denying each claim within the 60 day time
contract specifically preclude cost recovery,
limit contained in the Contract Disputes
in most cases the compensation sought
Act. The Contracting Officer neither issued
includes extended field office overhead
a final decision on any of the claims nor
costs as well as extended or unabsorbed
did he notify the contractor when such a
home office overhead costs. In the United
decision would be issued. The contractor
States the Eichleay Formula is the classic
then filed suit in the Court of Federal
way to calculate unabsorbed home office
Claims. The case involved nine distinct
overhead. As such, arguments concerning
claims. However, of interest for this research
suspensions of work typically revolve
perspective is Claim 1 – Unabsorbed Home
around how much delay did the suspension
Office Overhead.
order actually cause and are the extended or
unabsorbed home office overhead damages The contractor sought recovery of their
properly calculated. unabsorbed home office overhead for the
period between December 1, 2000 and
In The Redland Company, Inc. v. U.S.23 the
October 18, 2004 – nearly four years – and
Air Force issued a contract to The Redland
calculated the damages based on the Eichleay
Company to resurface an aircraft parking
Formula. The Court openly acknowledged
area at Homestead Air Reserve Base in
that the Air Force issued the NTP and
Florida in October 2000. On December
suspended all work on the same day. The
1, 2000 the Contracting Officer issued
Court likewise acknowledged that the
the Notice to Proceed (“NTP”) for the
suspension extended until October 18, 2004.
work. The contract required the contractor
to begin work within 14 days of receipt Citing P.J. Dick, Inc. v. Principi,24 Nicon, Inc.
of the NTP. Also on December 1, 2000 v. U.S.25 and Altmayer v. Johnson26 the Court
the Contracting Officer issued an order noted that to establish entitlement to
suspending all work on the project until Eichleay damages a contractor must prove
further notice. The Air Force finally lifted three elements:
the suspension order on October 18,
1. Government caused delay or suspension
2004 (nearly four years later) and directed
of work of an uncertain duration;
that work begin on October 20th and be
completed by December 19, 2004 – a period 2. The delay must have extended the
of 60 days. The Redland Company began original time of performance or that
work as directed but was unable, for a the contractor finished on time but still
variety of reasons, to complete the work incurred unabsorbed overhead costs
until January 11, 2006 – some 449 days because it planned to finish earlier; and,
after the suspension of work order was 3. The government required the contractor
lifted, and far beyond the 60 day period to remain on standby during the period
of completion. The Contracting Officer of suspension, waiting to begin work
granted a time extension through January immediately or on short notice once the
11, 2006, did not assess any liquidated suspension was lifted.
damages but also did not grant any
compensation for the additional time.

23
2011 Ct. Fed. Cl. No. 08-606C (Apr. 7, 2011).
24
324 F.3d 1364, 1370 (Fed. Cir. 2003).
25
331 F.3d 878, 882 (Fed. Cir. 2003).
26
79 F.3d 1129, 1132 (Fed. Cir. 1996).

CONSTRUCTION DECEMBER 2012 9


CONSTRUCTION

With respect to arbitration, the 2006 Queen in Redlands the Court felt that the four
The Federal Circuit in Nicon stressed that year suspension of work was too long to
Eichleay damages are only available when justify the award of overhead costs to the
the government caused delay occurs after contractor. It also appears that Courts
performance has begun, thereby extending may not understand that “work” begins
the period of performance. before the first shovel of dirt is moved.
Providing bonds and insurance; arranging
The Court of Federal Claims analyzed
and finalizing subcontracts and vendor
Redland’s claim and determined while the
agreements; planning the work; preparing
government had issued a suspension order
and submitting the bid breakdown; etc. all
of uncertain duration which extended the
are “work” even though no physical work in
original time of performance, Redland (1)
the field is underway. Additionally, once a
had not started work on the project and (2)
contract is awarded a contractor’s bonding
had not been required by the Contracting
capacity is impaired to the extent of the
Officer to “remain on standby” until the
initial contract value. During the four years
suspension order was removed. Thus,
Redland was suspended, their bond was in
despite a four year delay, the contractor was
full force and effect. If Redland was a small
denied recovery of unabsorbed home office
contractor this bond impairment may have
overhead using the Eichleay Formula and
prevented Redland from bidding on other
was denied the right to recover unabsorbed
projects as they may not have had sufficient
home office overhead using an alternative
bonding capacity to cover new projects.
method of calculation (allowed under
All are real costs incurred by contractors
certain circumstances based on Nicon). The
but the Courts in these cases either did
denial of recovery centered on the fact that
not know how the construction industry
the suspension directive was silent as to
operates or chose to ignore such damages
whether the contractor was to “remain on
to protect the government.
standby” while the work was suspended.
The lesson for contractors – in the event
After P.J. Dick some commentators had
a contracting officer suspends all work
suggested that it would be very difficult
on a project but does not state that the
to establish the “standby” requirement “…
contractor “…must remain on standby
because it is unlikely that a Contracting
ready to resume work promptly upon
Officer will issue a suspension order
direction from the government…” recovery
containing a requirement that the contractor
of unabsorbed home office overhead is
be ready to immediately resume full scale
seriously in doubt. One option is for the
work with no remobilization period.”27 It is
contractor to immediately write back to
more likely to be the case now that Redlands
the contracting office specifically asking is
has zeroed in on the same issue.
they are to “…remain on standby…” If the
Based on these cases, it appears that answer is “yes” then home office overhead
Courts are actively looking for ways to damages may be recoverable. If the answer
limit contractor damage recovery pursuant is “no” then the contractor is alerted to the
to suspension directives. It appears that situation and may seek out other ways to
reduce their damages.

27
Ralph C. Nash and John Cibinic, Postscript: Unabsorbed Overhead and the “Eichleay” Formula, 17 No. 6 Nash & Cibinic Report ¶ 33 (June 2003).

CONSTRUCTION DECEMBER 2012 10


CONSTRUCTION

Restrictions on Time Extensions The author of this article went on to point


out the results of Jackson Construction Co., Inc.
In a recent article published in Insight from
v. United States.30 In discussing the outcome
Hindsight the author commented that –
of this case the author noted that“In denying
“Turning to decisions addressing the claim, the Court’s decision provides a
the merits of delay claims and checklist of what not to do in presenting a
the means to prove them we find claim.”(Underscoring provided.) Among the
that the boards and courts are things Jackson did wrong:
demanding greater specificity in
1. Improperly calculated the home office
proof of delays. Total time claims
overhead amount claimed;
continue to be denied. Lack
of contemporaneous, updated 2. Was unable to prove their intended early
schedules is criticized. Contractor completion;
delays are scrutinized for proof 3. Failed to support the contention of
of government delays. Claims cumulative impact of multiple changes
lacking segregation of contractor beyond merely pointing to a large
and government delays often lead number of change orders; and,
to denial as do analyses based 4. Signed off on all government issued
solely on claims prepared after the change orders without a proper
project is completed.” 28 reservation of rights.
The author pointed to Phillips National, Inc.29 As was pointed out by the author of the
in which the Armed Services Board of referenced article,“In summary, this claim
Contract Appeals held Phillips responsible had no contemporary factual support
for a number of delays on the project for its theories of claim, no support for
because Phillips did not present a schedule government liability, no reservation of
delay analysis of any sort to the Contracting rights on many change orders, no proper
Officer or the Board separating the delays showing of causation and no justification
resulting from the government’s change for using the total cost method of
orders from the delays caused by the calculating damages.”31 It is noted, however,
contractor. The Board noted that “Without one interesting outcome from this decision
a CPM schedule, there was nothing to was the Court’s statement that “…notice
approve and it follows that no bilateral to the government is not a prerequisite to
modification incorporating an approved proving intent to finish early.”
as-built schedule could have been issued.”
As noted in this article, it appears that the In a similar manner the Court in George
Board denied the claim solely on the basis Sollitt Construction Company v. U.S.32
of non-compliance with the contract’s analyzed Federal delay claim case law,
schedule requirements. going back to 1909, to ascertain a checklist
concerning time extensions. The Sollitt
Court came up with the following checklist.

28
Geoffrey T. Keating, Government Contracts – Feast or Famine, Insight from Hindsight, Issue No. 4, Navigant Construction Forum™,
December, 2012, www.navigant.com/NCF.
29
ASBCA No. 53241, 04-01 BCA Para. 32,567.
30
62 Fed. Cl. 84 (2004).
31
Keating, Government Contracts – Feast or Famine.
32
64 Fed. Cl. 229, February 23, 2005.

CONSTRUCTION DECEMBER 2012 11


CONSTRUCTION

»» Compensable Delay ›› The contractor must prove the


›› The government is liable for an amount of home office and field
equitable adjustment when they office overhead directly related to the
cause a delay to the contractor’s government’s delay.
performance. ›› When the parties stipulate to a daily
›› The government’s liability is limited delay cost the contractor must prove
to unreasonable delays under the the extent of the government’s delay
Suspension of Work clause. but is relieved of the obligation of
›› The government’s actions or lack of proving their increased costs.
action must be the sole proximate ›› When multiple delays by one party
cause of the delay. are concurrent with each other, that
›› The burden of proving compensable other party’s delays must be analyzed
delay falls to the contractor as the to ensure that the overall effect of
claimant. these multiple delays is correctly
›› The contractor bears the burden attributed to that party.
of separating and apportioning »» Excusable Delay
concurrent delays. ›› The government has the initial burden
›› The contractor must prove the extent of showing late completion and the
of the government’s delay and its contractor has the burden of showing
increased costs in order to recover. that the delay was excusable.
›› Increased costs of winter construction ›› When the government has
may be recoverable; provided that the caused part of the delay to project
contractor can demonstrate that but completion, liquidated damages are
for the governments delay the work either waived or apportioned.
would have been completed prior to
Some may consider these various decisions
the winter.
harsh and very tough on contractors
›› Increased cost of winter work
attempting to assert delay claims. Others,
must be apportioned if there are
however, believe that these decisions reflect
concurrent delays.
a growing sophistication on the part of the
›› When demonstrating the extent of
judiciary when considering delay claims
the government’s delay the contractor
and the standard by which such claims are
bears the burden of proving critical
measured. Finally, it is also acknowledged
path delays.
that these decisions may reflect a lack of
›› Because the critical path changes over
attention to contract requirements on the
time, critical path schedule updates
part of contractors who fail to file notice,
are needed to analyze delays.
follow contract procedures, or wait until the
›› The contractor bears the burden
end of the project to prepare and submit
of apportioning concurrent critical
delay claims.33
path delays.
›› The contractor may recover wage Contractors should use the guidelines
rate increase costs that would not above as a checklist when considering
have been incurred but for the filing a delay claim. Documentation of each
government’s delay. of the points in these guidelines must be
thoroughly documented or contractors risk
losing their ability to obtain time extensions.

33
Keating, Government Contracts – Feast or Famine.

CONSTRUCTION DECEMBER 2012 12


CONSTRUCTION

Notice and Claim Filing Requirements Finally, this set of contract documents also
states that any claim not in compliance
A recent article published in Construction
with these requirements “…shall be
Lawyer discussed lack of notice as a
conclusively deemed to have been waived
defense against construction claims.34
by Contractor.” (Lest readers conclude
The author noted that “When technical
that this particular set of prerequisites is
and procedural defenses are upheld, they
unique to this particular State, the author of
encourage contract drafters to include more
this research perspective has encountered
of them. Owners and their construction
similar requirements in many contracts
managers devise increasingly complex ways
across the country.)
to channel and limit the claims of their
prime contractors. Prime contractors may This article goes on to discuss enforcement
similarly seek to circumscribe the claims of of notice requirements in State and Federal
their subcontractors.”While notice of claims courts. With respect to enforcement of
is an issue of fairness between owners notice requirement in Federal courts, the
and contractors, the article points out that article notes four general exceptions to
many owners now “…impose lengthy notice requirements, as follows –
and detailed claims notice requirements
1. Written notice was actually provided;36
as preconditions for recovery.”The author
points to one set of contract documents 2. The Contracting Officer had actual or
which requires the following be provided imputed knowledge of the facts giving
within a short time after the initial notice of rise to the claim;
claim.35 3. Notice to the contracting officer would
have been useless;
The contractor is required “at a minimum”
to provide the following – 4. The contracting officer considered the claim
on its merits despite the lack of notice.37
1. Factual statement of claim;
“Unless a contractor is operating
2. Dates concerning the event leading to in a jurisdiction where the
the claim; enforceability of notice provisions
3. Owner and A/E employees is clearly limited, it is important
knowledgeable about the claim; for contractors to understand the
4. Support from contract documents; full literal requirements of their
contractual provisions and either
5. Identification of other supporting
comply fully or negotiate a written
documentation;
agreement as to what form of
6. Details on claim for contract time; notice will satisfy the other party
7. Details on claim for adjustment of under those clauses.”38
contract sum; and,
8. Statement certifying the claim “…under
penalty of perjury…”

34
Douglas S. Oles, Lack of Claim Notice As A Defense To Construction Claims, Construction Lawyer, Winter 2012, American Bar Association.
35
General Conditions for Washington State Facility Construction, www.ga.wa/gov.
36
Hoel-Steffen Constr. Co. v. United States, 456 F. 2d 760, 763 (Ct. Cl. 1972).
37
Appeal of Powers Regulator Co., G.S.B.C.A. No. 4838, 80-2 B.C.A (CCH) ¶ 14,463 (Apr. 30, 1980).
38
Douglas S. Oles, Lack of Claim Notice As A Defense To Construction Claims.

CONSTRUCTION DECEMBER 2012 13


CONSTRUCTION

Extended Home Office Overhead industry under which a contractor


Calculated as a Percentage of Costs normally charges an owner a
percentage of a project’s direct
A 2012 U.S. Court of Appeals case determined
costs to cover its overhead.
that when a contractor’s time of performance
was extended as a result of owner caused … at least some of the project
changes, then any extended home office delays were attributable to extra
overhead cost had to be calculated as a work for which the debtor was
percentage of the direct cost of that work. compensated. (Citation omitted.)
In Redondo Construction Corp. v. Puerto Rico For those delays, extended
Highway and Transportation Authority39 the overhead should have been
contractor was awarded three highway awarded as a percentage of the
construction contracts by the Authority. direct costs associated with the
All three projects encountered differing projects’ change orders and
site conditions and owner caused changes extra work orders. (Citation
resulting in compensable changes and delay. omitted.) ‘It is inappropriate to
Redondo filed claims but before these claims use the Eichleay formula to
could be resolved, went into bankruptcy. The calculate home office overhead
various claims were tried in Bankruptcy Court for contract extensions because
which awarded some $12 million in damages adequate compensation for
to Redondo plus pre-judgment interest. overhead expenses may usually be
calculated more precisely using a
On appeal to the Federal District Court
fixed percentage formula.’”
the damages awarded were affirmed
in all respects. The Authority appealed Some Federal government agencies use
this decision to the First Circuit Court of fixed markup rates in their construction
Appeals. The Appellate Court upheld some contracts – specifically the General
of the lower Court’s findings but focused on Services Administration42 and the Veteran’s
the issue of home office overhead recovery. Administration.43 Many State and local
Citing C.B.C. Enterprises, Inc. v. United government agencies and professional
States40 and Aniero Concrete Co. v. N.Y. C. associations also impose fixed change order
Constr. Auth.41 the Court concluded that: markup rates in their contract documents.44
However, based on the author’s experience,
“When a project’s completion
such percentage of cost markup rates
is delayed due to necessary
rarely, if ever, take into account the cost of
but unanticipated work for
delay arising from owner caused changes.
which the contractor is entitled
Rather, such predetermined percentages are
to compensation, extended
typically the owner’s opinion of what it may
overhead is usually calculated
cost the general contractor to administer
as a percentage of the direct
added work (including the management
costs of the additional work.
of vendors, suppliers and subcontractors
This percentage-of-direct-cost
involved in performing a portion of the
approach comports with standard
added work).
practice in the construction

38
2010 International Arbitration Survey: Choices in International Arbitration, pp. 11 – 16.
39
Litigation Trends Survey Report – Trends in International Arbitration, 2011, page 4.
40
International Arbitration: Corporate Attitudes and Practices, 2008.
41
The Increasing Importance of Arbitration in Trade and Investment in the World – General Trends, Opportunities and Challenges, 2010.
42
See FAR §552.243-71.
43
See FAR §8-7.650-21.
44
Herbert Saunders, Survey of Change Order Markups, Practice Periodical on Structural Design and Construction, American Society of Civil Engineers,
February, 1996.

CONSTRUCTION DECEMBER 2012 14


CONSTRUCTION

As a result the Redondo ruling may deprive line projection.” Citing Sternberger v. United
contractors of the right to recover delay States47 the NDG Court stated that “It is
damages arising from owner directed highly improbable that subsurface soil of
changes that also cause project delay. one type would transition into another type
Contractors performing work under contracts along a straight line projection. We do not
without fixed markups for change order costs accept NDG expert’s opinion in this regard
in the contract should consider adjusting because it is intrinsically unpersuasive.”
their markups when quoting changes which
With respect to NDG’s other claims
involve project delay as they may no longer
the Court focused on the issue of what
be able to collect extended home office
conditions were “indicated” in the contract
overhead costs as separate damages.
documents and concluded that –
Differing Site Conditions - A Change
“A Type I differing site condition
in the Rules?
claim is dependent on what is
The Armed Services Board of Contract ‘indicated’ in the contract. Foster
Appeals (“ASBCA”) recently examined a Type Constr. C.A. and Williams Bros. Co.
I differing site condition (“DSC”) claim in the v. United States, 435 F.2d 873, 881
case of Appeal of NDG Constructors45 which (Ct. Cl. 1970) (“On the one hand,
arose from a contract with the U.S. Army a contract silent on subsurface
Corps of Engineers. The contract involved conditions cannot support a
the construction of a waterline under I-90 changed conditions claim.... On
to service Ellsworth Air Force Base in South the other hand, nothing beyond
Dakota. A portion of this waterline was contract indications need be
to be tunneled under I-90 employing the proven.”). A contractor cannot
bore and jack method. NDG subcontracted be eligible for an equitable
the tunneling portion of the project to BT adjustment for Type 1 changed
Construction, Inc. BT examined the two conditions unless the contract
geotechnical reports issued with the bid indicated what those conditions
documents when preparing their bid to NDG. would supposedly be. P.J. Maffei
The NDG contract included the standard Bldg. Wrecking Corp. v. United
Differing Site Conditions clause from the States, 732 F.2d 913, 916 (Fed.
Federal Acquisition Regulations (“FAR”).46 Cir. 1984); S.T.G. Construction Co.
v. United States, 157 Ct. Cl. 409,
BT encountered subsurface conditions it
414 (1962). Here, the contract
considered materially different than those
documents did not indicate
indicated in the contract documents and filed
where precisely the contractor
notice of DSC to NDG, who provided notice
would encounter Carlile Shale.
to the Contracting Officer. The Contracting
In bidding the project, BTC did
Officer denied NDG’s claim and NDG
not expect to transition from
appealed to the ASBCA. NDG contended that
“Fine Alluvium” to “Carlile Shale”
they encountered a“different soil profile”, soil
or, to use its terminologies, from
with different characteristics and increased
“clay fill material” to “shale rock
soil moisture conditions all of which, they
material” at any specific point but
claimed, were materially different from the
only “at some point.” … And, as
conditions indicated at the time of bidding.
BTC predicted, the soil profile
In part, NDG based their claim on BT’s
indeed changed from clay fill
assumption that the soils would transition
material to shale rock material ‘at
from one type to another along “…a straight
some point.’”

45
ASBCA No. 57328, August 21, 2012.
46
FAR §52.236-2 (April 1984).
47
401 F.2d 1012, 1016 (Ct. Cl. 1968).

CONSTRUCTION DECEMBER 2012 15


CONSTRUCTION

The Court concluded that since the soil Based upon these cases, contractors
conditions did, in fact, transition “at some seeking recovery under the Differing Site
point” then the conditions encountered did Conditions clause –
not differ materially from those “indicated”
1. Are at risk when they draw straight lines
in the contract documents at the time of
between boring in order to calculate soil
bidding. The Board also ruled that with
transition or encounters with differing
respect to the soil conditions the general
types of soils and/or rock;
warnings contained in the geotechnical
report to the effect that “…soils between 2. Are at risk by drawing conclusions
boring locations may vary…”was sufficient or inferences from “silence” (i.e., the
information to alert a contractor to absence of any groundwater information
changing soil conditions. The Board in this from a series of borings may no longer
case also ruled that despite the fact that justify the assumption that there is no
the soil borings were silent on the moisture groundwater to be encountered on the
content of the soils, the contractor was project); and,
solely at risk for drawing any assumptions 3. Information referred to at bid as being
based on the absence of moisture content. “available upon request” may now be
considered as information included in
In the Appeal of Bean Stuyvesant LLC48 the
the contract documents or incorporated
Armed Services Board of Contract Appeals
into the contract documents by
dealt with the issue of what“…physical
reference.
conditions at the site…”were indicated in
the contract documents. In Bean Stuyvesant These two cases taken together increase
the contractor relied upon the geotechnical a contractor’s risk concerning latent
information provided with the bidding site conditions considerably and appear
documents. However, the Invitation to Bid to indicate a lack of understanding by
did not include soils information taken the Boards as to how a contractor uses
from another set of borings at the site. The geotechnical information during bidding.
information from the separate boring was“… They seem to miss the point that the
available upon request…”The contractor did bidders are attempting to turn geotechnical
not request this additional information and did information into means and methods
not see it until the information was produced and costs to be included in their bids. For
by the government at the Board hearings. example, 20 borings on a project showing
no groundwater at excavation depth
The Board ruled against the contractor typically means that the contractor should
on the basis that the conditions not expect to encounter groundwater while
encountered did not differ materially from excavating. How else could a contractor
those indicated based upon “available” possibly interpret the absence of such
information. The Board concluded that “…a an indication? While the absence of data
contractor has a duty to review information such as this has typically been considered
that is made available for inspection.” reasonable and logical when making a
(Underscoring supplied.) bid, it is apparently no longer sufficient to
justify a “material difference” when seeking
recovery for a differing site condition.

48
ASBCA No. 53882, October 5, 2005.

CONSTRUCTION DECEMBER 2012 16


CONSTRUCTION

Risk Transfer Increasing in A very recent Civilian Board of Contract


Government Contracts Appeals (“CBCA”) case related to
construction of a U.S. embassy under a
The concept of equitable risk allocation
design/build contract.49 According to the
has started to unravel in recent years. The
CBCA the design/build contract transferred
equitable adjustment doctrine that has for
all risk under the contract to the design/build
many years, provided avenues of recovery
entity by using clauses such as the following:
for cost and time, are now being modified
by contract drafters. For example, one “The Contractor remains solely
respondent to the Navigant Construction responsible and liable for design
Forum™ survey conducted in support of sufficiency and should not
this research perspective commented that he depend on reports provided by
is seeing more anti-concurrent delay clauses the Government as part of the
in contracts (i.e., contracts that declare contract documents.”
concurrent delay is non-excusable delay).
“Offerors shall not rely on any
This same respondent also commented information provided by the
that he had been asked to review two Government concerning the host
sets of “bridging documents” that were country, such as climatology data
approximately 90% complete design (versus at the site, local laws and customs,
the more typical 30% design). The design/ currency restrictions, taxes, or the
build entities in these cases claim that availability of local labor, etc.”
given this level of design detail done by the
With respect to the infrastructure that
owner’s consultant prior to bidding, the
was supposed to be available to the site
Spearin Doctrine should apply. The owner,
at the outset of construction the Board
as might be expected, asserted that since
commented that while the contract
this is a design/build contract the design/
documents stated the local government
builder is solely responsible for the design
had “…committed to provide utilities …
and the bridging documents were intended
to the site by June 2003”“nothing in these
for general guidance only. Strictly speaking,
statements can be construed as a promise
this is not risk transfer but has the effect of
from the Department of State that these
substantially increasing the design/builder’s
events would occur…”
risk if the owner holds the design/build
entity to the requirements of the bridging The Board decided that design/build
documents as if they were crafted by the contractor had no right to rely on the
design/builder. design documents provided by the
government at time of bidding because
the contract advised bidders “…not to rely
on the drawings, as the drawings are for
the sole purpose of illustrating the design
intent…” Finally, the Board ruled that since
the design/build contractor was “…solely
responsible and liable…” for the design,
they “…should not depend on reports
provided by the Government as part of the
contract documents.” 50

49
Fluor Intercontinental, Inc. v. Department of State, CBCA Nos. 491, et al., March 28, 2012, WL 1144872.
50
This ruling is an interesting juxtaposition to the decision reached in the Appeal of Bean Stuyvesant LLC. In Bean Stuyvesant the contractor was
held liable for “available information” not included or incorporated by reference in the contract documents whereas in Fluor Intercontinental the
design/builder was not allowed to rely on information specifically provided by the government and included in the contract documents.

CONSTRUCTION DECEMBER 2012 17


CONSTRUCTION

Increased Use of False FERA reflects the government’s

Claim Actions growing commitment to


discover and prosecute fraud. In
False claims allegations are becoming much furtherance of that commitment,
more frequent in construction today than Congress began to include
at any time previously. With the increased antifraud measures in statutes,
emphasis on the False Claims Act51 (“FCA”) such as the American Recovery
contractors who certify a claim to the U.S. and Reinvestment Act (the
government are potentially liable to the Stimulus Bill), that create an
government if any portion of a passed independent board to oversee
through subcontractor claim is determined disbursed funds and provide for
to be a false claim. Subsequent to the government audits.”55
Deficit Reduction Act of 200552 some 28
“False claims and charges of fraud are
States have adopted State False Claim Acts
receiving increased emphasis by the federal
and others apparently are contemplating
government. For years, the playing field
doing the same.53 Not only are government
was generally limited to procurement of
agencies more likely to counter contractor
supplies, and defense industry contracts,
claims with allegations of false claims
but recently the clear trend has increased
but the legal profession has also become
prosecution overall and therefore greater
very active in this arena. If one Googles
focus on construction.”56 The author pointed
“whistleblower attorneys” you’ll find some
to Riley Construction Co. v. United States57
2.95 million hits in 0.22 seconds – most of
and Daewoo Engineering and Construction
which advertise firms ready, willing and
Co. Ltd. V. United States58 to help make his
able to assist potential whistleblowers with
point. Riley (a design build contractor)
qui tam lawsuits under the FCA.
included both their claimed costs as well as
Added to this are some recent changes to their architect’s cost on the basis that the
Federal law which broadened the definition architect’s fee was based on a percentage of
of the term “claim” and extended the reach total construction cost. Riley did this without
of the FCA to include subcontractors. One asking the architect, thus the architect
recent paper summarized the impact of the was unaware that they were involved in
Fraud Enforcement Recovery Act of 2009 the claim. When the government found
(“FERA”)54 in the following manner. out about this they counterclaimed with
false claim and fraud allegations against
“FERA expanded the FCA in
Riley. The Court determined that Riley
several additional ways, such as
lacked“intent”when submitting the claim
by eliminating the “presentment”
for the architect’s fee and dismissed the
requirement, adding a “relate
government’s FCA claim. This case serves to
back” provision to circumvent
highlight the government’s intent to seek
statutes of limitations, and
out and prosecute false claims and fraud and
declaring retroactivity for certain
illustrates the risk a contractor assumes when
amendments. The passage of
submitting a claim that is not fully vetted.

51
31 U.S.C. § 3729(a).
52
P.L. 109-171, February 2, 2006.
53
www.whistleblowerslawyerblog.com, “Part 6: States’ Experience With Their Own False Claim Acts”, December 2010.
54
Pub. L. No. 111-21, 123 Stat. 1617.
55
Elspeth England, The Government Upgrades the False Claims Act: Implications for Construction Contracting, Construction Lawyer, Winter,
2012, American Bar Association.
56
Keating, Government Contracts – Feast or Famine.
57
65 Fed. Cl. 264 (2005).
58
73 Fed. Cl. 47 (2006), aff’d 557 F.3d 1332 (Fed. Cir. 2009), cert. denied 130 S.Ct. 490 (2009).

CONSTRUCTION DECEMBER 2012 18


CONSTRUCTION

In Daewoo the contractor submitted not certify the claim nor did the contractor
a certified claim to the government request and receive a final decision from the
in the amount of $64 million that contracting officer. During their appeal to
included approximately $50.6 million in the Court of Appeals for the Federal Circuit
unsubstantiated costs. The contractor the contractor argued that their letters to
apparently assumed that the claim would the contracting officer constituted a valid
be settled via negotiation and did so in claim for a time extension sufficient to give
order to give them some room to negotiate the Court of Federal Claims jurisdiction
with the government. Regardless of the over the matter. As stated by the Court
merits of the initial claim the government of Appeals “Maropakis also argue[d] that
counterclaimed under the Contract even if it was not in technical compliance
Disputes Act and the FCA and entered a with the CDA, the United States had actual
“special plea in fraud” under the Contracts knowledge of the amount and basis of
Dispute Act seeking forfeiture of Daewoo’s Maropakis’ claim and therefore the Court of
entire claim under the provisions of 28 Federal Claims had jurisdiction.”
U.S.C. §2514. When all was said and done
In essence, Maropakis tried to create a
the U.S. Court of Appeals for the Federal
“constructive claim” – a claim derived by
Circuit ruled that Daewoo not only forfeited
inference or implied by operation of law
their entire $64 million claim but also owed
– analogous to a constructive change, a
the government an additional $50 million
constructive suspension or constructive
plus FCA penalties.
notice. Maropakis did this, of course, in
Contractors working on government order to get the Court to hear their case
contracts need to understand the as the Court of Federal Claims ruled that
implications of the FCA and FERA; need they did not have jurisdiction since the
to thoroughly examine and document all contractor had not fully complied with
claimed costs; and must understand the the requirements of the Contract Disputes
legal significance and risk of “certifying” a Act. The Appellate Court focused on the
claim to the government. statutory requirements of the Contract
Disputes Act and chose not to infer the
New Forms of Claims existence of a constructive claim in the
absence of these clear requirements.
Lest readers conclude that current
claimsmanship is exercised solely by All in all, this was an ingenious attempt
owners let’s now look at contractors. Based by a desperate contractor to get around
on the Forum’s survey most contractor their failure to conform to clear statutory
“claimsmanship” seems to result in requirements. The Navigant Construction
assertion of new forms of claims. Some of Forum™ believes that more contractors
those identified are set forth below. will attempt to use the “constructive
knowledge” approach to excuse their own
Constructive Claim non-compliance with contract or statutory
In M. Maropakis Carpentry, Inc. v. U.S.59 requirements concerning claim submittals.
the contractor submitted a number of
letters to the government requesting time
extensions. However, notwithstanding
the requirements of the contract and the
Contract Disputes Act, the contractor did

59
609 F.3d (Fed. Cir. June 17, 2010).

CONSTRUCTION DECEMBER 2012 19


CONSTRUCTION

Underinspection Claim The ASBCA, citing Amigo Building Corp.62


stated that –
The concept of a constructive change to a
contract arising from “improper inspection” “It is well established that the
or “overinspection” is not a new one in government’s right to inspect
construction law.60 Several respondents to work generally does not relieve
the Forum’s survey, however, mentioned a contractor of its obligations to
having experience with claims of perform, nor can the contractor
“underinspection.”Typically, these claims properly rely on government
have been described in one of two ways. In inspection for the discovery and
the first instance, underinspection is alleged correction of any errors.”
as a way to recover additional costs for
Based on this approach the ASBCA
completion of punchlist work at the end of
concluded that –
the project. The theory asserted is that, had
the owner or their representative inspected “It is unfortunate that appellant’s
the contractor’s work properly during the failure to comply with the contract
performance of the work, they would have requirements did not come to
found the work was improperly performed light earlier in the performance
or incomplete and corrected the situation, of its work. However, appellant
thus eliminating the need for punchlist would have us decide that the
work. Since the punchlist work exists this government’s alleged failure
proves allegation of improper inspection to perform an early adequate
and the resulting damages are the cost of inspection shifts the contract
the punchlist work. The second way the performance issues to the
underinspection claim is used is to allow the government’s shoulders. This
contractor to argue wrongful termination for we cannot do. The contract
default due to substandard work. Despite clauses and the relevant law clearly
the number of times the author and others establish that it was appellant’s
heard this type of claim asserted none had legal responsibility to maintain
heard of this claim being litigated. an adequate inspection system
to ensure that its work conformed
The Appeal of Tawazuh Commercial and
to the contract requirements.
Construction Co. Ltd.61 involved construction
The government proved that
of 40 kilometers of road in Afghanistan. The
appellant was in default and
contractor was ultimately terminated for
appellant did not establish that
default due to failure to perform its contract
the default was excusable.”
obligations; failure to provide a remediation
plan as required by the cure notice; and, Tawazuh, like Amigo before it, lost their
failure to perform in accordance with the argument that an owner’s underinspection
contract requirements. The contractor entitled Tawazuh to additional money
asserted, among other defenses, that if and time to repair the substandard work
the Corps of Engineers had performed and/or excused the substandard work
adequate quality inspections throughout and deprived the owner of the right
the project the situation would have been to terminate for default. However, the
corrected earlier and thus prevented the Navigant Construction Forum™ believes it
default termination. is foreseeable that as less experienced, less
skilled contractors undertake to perform
more complex projects this type of claim is
likely to occur with greater frequency.

60
See J.J. Barnes Constr. Co. v. U.S., ASBCA No. 27876, 85-3 B.C.A. (CCH) ¶ 18,503 (1985) and Adams v. United States, 358 F.2d 986 (Ct. Cl. 1966).
61
ASBCA No. 55656, 2011-2 B.C.A. (CCH, ¶ 34,781), June 13, 2011, 2011 ASBCA LEXIS 37.
62
ASBCA No. 54329, 05-2 BCA ¶ 33,047.

CONSTRUCTION DECEMBER 2012 20


CONSTRUCTION

Equipment Productivity Loss While the claim is understandable (due to


its simplicity) and the mathematics of the
Lost labor productivity claims in U.S.
calculation are easy to follow, there is often
construction law are hardly new. Wunderlich
no direct correlation between labor and
Contracting Co. v. United States63 involved a
equipment cost. There is a strong likelihood
request for delay damages and lost labor
that when labor is less productive, that
productivity arising from a contract issued
equipment costs go up. However, increased
in 1950 and completed in 1951. Although
equipment costs are more likely to increase
the Wunderlich joint venture did not prevail
due either to idled equipment or equipment
in this case, their failure to recover was
retained on site longer than anticipated
based on lack of causation – that is, they
resulting in increased equipment rental or
did not establish the nexus between the
ownership costs on the project.
government’s actions and the damages
sought – not because the Court rejected the Despite the flaws inherent in this new
theory of entitlement. type of claim the Navigant Construction
Forum™ believes it will become more
However, the Navigant Construction
common as contractors seek new ways
Forum™ survey revealed that some
to recover losses or less sophisticated
contractors have started to assert
contactors become more involved in claims.
“equipment inefficiency claims.” Such
claims attempt to establish a direct cost “Expanded” General Condition Costs
ratio between labor costs and equipment
Extended general condition costs, frequently
costs using the following formula –
referred to as extended field office overhead
are a well accepted element of damages
Actual Equipment Cost Equipment when a contractor encounters excusable,
=
Total Labor Cost Cost adder compensable delay. The general rules
governing extended field office overhead
What contractors are attempting to show cost recovery are fairly straight forward.
is that for every labor cost dollar expended
1. The contractor must prove they encountered
“$x” dollars was spent on equipment. This
an excusable, compensable event as defined
equipment productivity cost is applied to
by the terms of the contract;
labor productivity claims (whether total
cost, modified total cost, measured mile 2. The contractor must document notice of
calculations, etc.). To calculate this type of delay was provided per the contract;
claim. first the contractor has to calculate 3. The contractor must submit their time
the labor cost added to the base scope cost extension request in accordance with the
and then the added labor cost is multiplied terms of the contract;
by the equipment cost ratio calculated by 4. The contractor must demonstrate that
the formula set forth above.64 the event caused “x” days of delay as
required by the contract and that there
was no concurrent delay; and,
5. The contractor must then document
the daily field office overhead cost after
removing all non-time related field office
overhead costs.

63
351 F.2d 956 (Ct. Cl.1965).
64
It is noted that this claim does not include the cost of small tools and consumables, such cost being added separately to the total claim.

CONSTRUCTION DECEMBER 2012 21


CONSTRUCTION

Assuming the contractor can show all of the In more general terms, this new form
above then they are generally entitled to a of claim creatively “front end loads”
time extension and delay damages (consisting anticipated claim costs. As such, there is
of extended field office overhead and, a distinct possibility that the contractor
perhaps, extended home office overhead). asserting this new form of claim has
walked, inadvertently though it may be,
In response to the Navigant Construction
into a false claim under either the Federal
Forum™ survey a new variant of this claim
or a State statute.
was identified. The“expanded general
conditions”claim is not grounded on The Navigant Construction Forum™
compensable delay. This new form of claim believes that this new claim will likely
is a request for additional cost to add field spread for a while; at least until a Court
resources in order to complete the project ruling concerning the false claim potential
on time. At first blush, this sounds like an is issued. If this claim is found to be a
element of damages arising from either false claim, then it will slowly fade into
directed or constructive acceleration – but no the background as this information gets
acceleration is being alleged by the contractor. around. If it is found not to be a false claim
(along the lines of U.S. ex rel. Alva Bettis v.
After execution of the contract and notice
Odebrecht Contractors of California, Inc.65 )
to proceed, the contractor submits a change
where the Court found that the fraud-in-
order proposal for expanded general
the-inducement theory, on its own, did not
conditions on the basis that the project is
constitute a false claim, then this new form
more complicated; is less fully designed;
of claim may become more common.
has more design busts and flaws; requires
more coordination with third parties; will
have more changes than normal; etc. Any Recommendations
or all of these allegations are then used to Claimsmanship has not declined over
justify the addition of field resources (i.e., the past two decades and is projected
document control, project control, project to continue based upon this review of
engineering staff, superintendents, etc.). current trends. Based on this conclusion,
The problems with this new form of claim the Navigant Construction Forum™ offers
are many – the following recommendations for all
stakeholders in the construction industry.
1. The contractor has not proven
entitlement to any of these allegations For Owners
under the contract; »» Since owners have more opportunity to
2. The contractor has not expended any practice claimsmanship when preparing
additional costs as a result of any of the contract documents, owners need
these allegations; and, to spend more time training their
3. There is not yet any cause and effect own staff concerning the terms and
relationship between any of the conditions of their contracts and in
potential future problems the contractor contract administration. Recall that
anticipates and the cost the contractor is one major international survey showed
presently seeking. that improper contract administration
is, in fact, the most common cause
of disputes.66 With appropriate and
ongoing training, this type of dispute
should be avoidable.

65
393 F.3d 1321 (2005).
65
E.C. Harris, Global Construction Disputes 2012: Moving in the Right Direction.

CONSTRUCTION DECEMBER 2012 22


CONSTRUCTION

»» Since so many claims and disputes arise »» A knee jerk reaction of many
from incomplete, poorly coordinated owners (and their representatives)
or flawed drawings and specifications when faced with a claim or dispute
and from owner issued changes, owners is to automatically go into a self-
are well advised to spend more time in preservation mode. However, experience
planning and design stages of the project demonstrates that if both the owner and
to “get it right” before bidding. If owners the contractor can maintain focus on
make certain that all project stakeholders project success, not party interest, and
have adequate input to the planning seek out solutions to potential problems
and design, then this should sharply when they first occur, then there will
reduce owner issued change orders be fewer claims and disputes later as
during construction, reducing in turn the jointly crafted solutions tend to result in
disputes that stem from such changes. negotiated change order settlements at a
»» Recognizing that no “perfect” set of lower cost.
drawings and specifications exists, »» Owners who are considering crafting
owners seeking to avoid changes and unique risk assignment clauses must
disputes should implement biddability, keep the basic rules of risk transfer
constructability, claims prevention in mind at all times. First, all risk
and operability reviews before belongs to owner unless specifically
issuing bidding documents using an assigned elsewhere in the contract since
independent review team67 in order to the owner has all the benefit of the
find and eliminate errors and mistakes constructed project. Second, when any
and prevent the need for owner issued risk is assigned in a contract that risk
changes during construction. should be assigned to the party best able
»» End of the job claims are complicated, to control risk if the risk event occurs.68
difficult to analyze and tough to resolve. »» Project owners need to spend more
Such claims result from owners refusing time with project delivery scheduling
to settle delay claims until all work is in order to avoid unrealistic scheduling
completed. Owners need to train their requirements at the time of bidding as
staff to focus on timely delay notice inappropriate schedules (either too short
and act aggressively to resolve time or too long) cause claims and disputes.
extension requests and delay damages
at or near the time they occur. Owners
should not discourage contractors from
filing notices of change, delay, etc. but
should encourage them to do so in order
to identify potential claims and disputes
as early as possible and then focus on
issue resolution in a timely manner.

67
An “independent review team” is one made up of experienced construction and operations personnel who were not part of the design team. This
“cold eyes” review is necessary because it is difficult in the extreme for someone to review work they themselves performed.
68
Mitigation of Risk in Construction: Strategies for Reducing Risk and Maximizing Profitability, McGraw Hill Construction, Navigant Consulting &
Pepper Hamilton, LLP, New York, 2011.

CONSTRUCTION DECEMBER 2012 23


CONSTRUCTION

Contractors ›› Are at risk should they not review


information referenced to in bid
»» Contractors must pay more attention
documents as “available upon
to scheduling, notice, and claim filing
request” as this available information
requirements lest they lose their right
may now be considered information
to prosecute such claims and recover
included in the contract documents
time and cost. Contractors need to train
or incorporated by reference.
their own staff in each of these areas
and provide refresher training routinely »» Contractors must remember that they
rather than run the risk of losing their cannot rely upon owner quality control
rights. inspections. Contractors must keep in
mind that owner inspections are solely
»» Contractors working on government
for the benefit of the owner, not the
contracts need to understand the
contractor. Contractors are obligated
implications of the FCA and FERA; need
to conform to all requirements of
to thoroughly examine and document all
the contract and perform their own
claimed costs; and must understand the
inspections.
legal significance and risk of “certifying”
a claim to the government. »» Contractors seeking to be creative with
claims must seek out competent legal
»» Based upon the cases discussed in
advice experienced with construction
this research perspective contractors
law in order to avoid pursuit of a claim
seeking recovery under the Differing Site
that is unwinnable.
Conditions clause –
›› Are at risk when they rely upon »» Contractors trying out a new theory of
straight line interpretations between entitlement on a public works project
borings in order to calculate soil must obtain legal advice from attorneys
transition or encounters with familiar with both Federal and State False
differing types of soils and/or rock; Claims Acts in order to avoid accusations
›› Are at risk by drawing conclusions of false claims from the owner.
or inferences from “silence” (i.e.,
the absence of any groundwater
information from a series of borings
may no longer justify the assumption
that no groundwater will be
encountered on the project); and,

74
International Arbitration: Corporate Attitudes and Practices, 2008, page 5.
75
International Arbitration: Corporate Attitudes and Practices, 2008, pp. 10 - 12.
76
Litigation Trends Survey Report – Trends in International Arbitration, 2011, page 2.

CONSTRUCTION DECEMBER 2012 24


CONSTRUCTION

Conclusion Future Efforts of the Navigant


Construction Forum™
Owners and contractors seeking to practice
claimsmanship need to keep in mind a In 2013, the Navigant Construction
paraphrased version of one of Sir Arthur Forum™ will continue its analysis of
Conan Doyle’s Sherlock Holmes quotations – construction industry issues. The Navigant
Construction Forum™ is in the process of
“What one man can invest,
conducting a survey related to the use and
another can circumvent!”
abuse of Requests for Information (“RFIs”)
At a time when owners and contractors and crafting recommendations on how
say they want to discourage disputes on to handle the problems caused by RFIs in
construction projects and find ways to today’s construction industry.
deliver projects on time, within budget,
Further research will continue to be
safely and with the quality required
performed and published by the Navigant
by the contract, claimsmanship seems
Construction Forum™ as we move forward.
counterproductive and wasteful. The
If any readers of this research perspective
recommendations set forth above should
have ideas on further construction dispute
help stakeholders achieve their stated goals.
related research that would be helpful
to the industry, you are invited to e-mail
suggestions to jim.zack@navigant.com.

©2013 Navigant Consulting, Inc. All rights reserved. 00000877 Navigant Consulting is not a certified public accounting firm and does not provide audit, attest, or public accounting services.
See navigant.com/licensing for a complete listing of private investigator licenses.

CONSTRUCTION DECEMBER 2012 25

You might also like