PROJECT:
KARACHAGANAK 4th STABILISATION & SWEETENING TRAIN
KPO CONTRACT JOB NO: HOLDS: PAGE NO:
NO: JI-184 NO 1 OF 12
AP/M/06/0441
DOCUMENT TITLE:
TABLE OF CONTENTS
1.0 PURPOSE
2.0 SCOPE
3.0 REFERENCES
4.0 DEFINITIONS
5.0 PROCEDURE
6.0 DOCUMENTATION
7.0 ATTACHMENTS
PROJECT: DOCUMENT NUMBER:
TH
KARACHAGANAK 4 STABILISATION & 4TPFC-400-Q00-0000-00001
SWEETENING TRAIN
DOCUMENT TITLE:
FIELD PROJECT CONTROLS PROCEDURE
KPO CONTRACT NO: REV: DATE: PAGE NO:
AP/M/06/0441 3 15.01.08 3 of 12
1.0 PURPOSE
The purpose of this procedure is to provide guidelines for implementing the Field
Project Control System successfully utilised on other major projects. The Field
Project Control System is to be a fundamental mechanism for the Project
Management Team to identify areas of concern and opportunity, and to initiate
appropriate action for the successful execution of the work.
2.0 SCOPE
2.1 This procedure applies to 4TH TRAIN SIT Karaghagnak 4th Train Construction
Project Management team.
3.0 REFERENCES
4.0 DEFINITIONS
5.0 PROCEDURE
The schedules will at any time reflect the total scope of work, duration and the
logic for the different phases viz.:
- Construction
- Pre commissioning, Commissioning
The Project Level II Schedule together with the Work Breakdown Structure will
form the basis of the Progress Measurement System (PMS).
The WBS on which the entire Construction activities are broken down is as
follows.
The intermediate construction steps along with milestone progress for some of
the major commodities are detailed below. The actual progress of an activity
will be evaluated based on the following work steps:
Piling (Nos.):
Steps Cumulative
Description
(%) (%)
Survey & Mark pile location 5 5
Rebar fabrication 15 20
Boring 60 80
Pouring & Rebar Installation 20 100
Building Construction:
Steps Cumulative
Description
(%) (%)
Pedestals / Columns 35 35
Brick wall / Plastering 34 69
Roof 10 79
Door / windows fixing 1 80
Flooring / Painting / False Ceiling 5 85
MEP works (Including HVAC) 10 95
Finishing works 5 100
Road:
Description Steps Cumulative
(%) (%)
PROJECT: DOCUMENT NUMBER:
TH
KARACHAGANAK 4 STABILISATION & 4TPFC-400-Q00-0000-00001
SWEETENING TRAIN
DOCUMENT TITLE:
FIELD PROJECT CONTROLS PROCEDURE
KPO CONTRACT NO: REV: DATE: PAGE NO:
AP/M/06/0441 3 15.01.08 6 of 12
Paving:
Description Steps Cumulative
(%) (%)
Excavation & Levelling 30 30
Sub base & Base compacting 30 60
Reinforcement 25 85
Shuttering 10 95
Pouring 5 100
Underground Works:
Description Steps Cumulative
(%) (%)
Excavation 30 30
Laying Pipe 55 85
Backfilling 15 100
Tanks
Description Steps Cumulative
(%) (%)
Install bottom plates 15 15
Install shell courses 60 75
Install roof assembly 10 85
Nozzles 5 90
Hydrotest 5 95
Insulation/Painting 5 100
Grouting ( by others) 0 0
Final Alignment: 2nd Centering / 25 100
Coupling after Piping
Shelter Erection:
Description Steps Cumulative
(%) (%)
Installation on foundation 45 45
Welding / Bolt-up 25 70
Alignment 5 75
NDT 5 80
Roofing & Cladding 5 85
Floor Concrete Works / Grouting 5 90
MEP Works 10 100
Piping Prefabrication:
Description Steps Cumulative
(%) (%)
Grinding / Preparation Works 10 10
Fit-up 25 35
Welding 55 90
NDT 5 95
PWHT, If applicable 5 100
Piping Erection:
Description Steps Cumulative
(%) (%)
Stringing 10 10
Fit Up & align 20 30
Welding 50 80
PROJECT: DOCUMENT NUMBER:
TH
KARACHAGANAK 4 STABILISATION & 4TPFC-400-Q00-0000-00001
SWEETENING TRAIN
DOCUMENT TITLE:
FIELD PROJECT CONTROLS PROCEDURE
KPO CONTRACT NO: REV: DATE: PAGE NO:
AP/M/06/0441 3 15.01.08 8 of 12
Supports 5 85
NDT 5 90
Hydro-testing 5 95
Reinstatement/Punch List 5 100
Electrical Works:
Description Steps Cumulative
(%) (%)
Equipment / Panel Installation 40 40
Cabling 40 80
Glanding &Termination at both Ends 20 100
Electrical motors:
Description Steps Cumulative
(%) (%)
Lay Cables 70 70
Meggar / Continuity Test 10 80
Cable glanding & termination 20 100
Painting:
Description Steps Cumulative
(%) (%)
Sandblast & Prime Coat 65 65
Intermediate Coat 15 80
Final Coat 15 95
Touch up painting 5 100
Insulation:
Description Steps Cumulative
(%) (%)
Surface preparation 5 5
Insulation lagging 60 65
Insulation cladding 35 100
Similar milestone break-up for the other major construction activities will be
developed and progress will be measured based on the milestones / physical
progress achieved.
6.0 DOCUMENTATION
4th Train SIT will provide regular and comprehensive reporting to COMPANY to
ensure that an accurate, clear and transparent status of the Project is
communicated effectively.
The reports will highlight all trends that impact the schedule and will include
detailed information of the progress of work, variations, and explanations for
slippage in schedule and the recovery plan as may be required.
The progress curves and histograms will indicate the planned cumulative
percentage progress, forecast progress and the actual cumulative percentage
progress.
There will be a descriptive report section common to all Discipline and Activities
followed by specific reports. However, attachments, tables and curves will be
Discipline specific.
PROJECT: DOCUMENT NUMBER:
TH
KARACHAGANAK 4 STABILISATION & 4TPFC-400-Q00-0000-00001
SWEETENING TRAIN
DOCUMENT TITLE:
FIELD PROJECT CONTROLS PROCEDURE
KPO CONTRACT NO: REV: DATE: PAGE NO:
AP/M/06/0441 3 15.01.08 11 of 12
The Monthly Progress Report cut off date will be last Thursday of the Month.
The Progress report will be submitted in 10 days from the monthly cut-off date.
The Monthly Report shall include the followings:
b) HSE report
c) QA / QC
- Highlights
- Non-conformance status
d) Construction Phase
- A narrative of the months’ events by discipline
- Progress per discipline
f) Project Controls
- Planning narrative
- Updated Level 1, 2 & 3 Schedule bar charts
- Updated progress curve & Table – Discipline wise
-Manpower Histograms
- Cost narrative
- Value of Work Done (VOWD)
- Cost Trend Register
g) Contracts
- Invoicing Register
- Variations Log
7.0 ATTACHMENTS
NONE