Health & Safety MGT Plan - R03-C06C01 Coastal Village Sports & Beach Club Construction
Health & Safety MGT Plan - R03-C06C01 Coastal Village Sports & Beach Club Construction
Document History
Document Approval
Job Title Project Safety Manager Corporate Safety Manager Project Manager
Signature
R03-C07C01 – Construction Phase Health & Safety Management Plan Rev. 00 Page 1 of 66
ABDUL MOHSEN AL TAMIMI CONTRACTING COMPANY
Coastal Village Sports and Beach Club
Construction Health and Safety Management Plan
Revision # 00 Date of issue Oct. 28, 2023
Table of Contents
Section 1: ISO 45001:2018 Certificate...........................................................................................................7
Section 2: BACKGROUND INFORMATION .....................................................................................................8
2.1 PROJECT DESCRIPTION/DURATION............................................................................................................... 8
2.2 ACRONYMS AND ABBREVIATIONS ................................................................................................................ 8
2.3 UNITS............................................................................................................................................................. 9
2.4 SCOPE ............................................................................................................................................................ 9
2.5 PROJECT LOCATION..................................................................................................................................... 11
Section 3: HEALTH & SAFETY POLICY STATEMENT ...................................................................................... 12
Section 4: THREE (3) CORNERSTONE HEALTH & SAFETY PILLARS ................................................................. 13
4.1 Pillar 1 – Ten (10) Senior Leadership Tenets of Safety Culture ................................................................... 13
4.2 Pillar II - Seven Health and Safety Management Philosophies ................................................................... 13
4.3 Pillar III - Ten (10) Life Crucial Health and Safety Rules .............................................................................. 14
Section 5: HEALTH & SAFETY OBJECTIVES/KPI’s.................................................................................................. 15
5.1 Lagging Key Performance Indicators........................................................................................................... 17
5.2 Leading Key Performance Indicators .......................................................................................................... 17
Section 6: COMMUNICATION AND LANGUAGE BARRIERS ........................................................................... 18
Section 7: SUB-CONTRACTOR HEALTH AND SAFETY .................................................................................... 18
7.1 Selection and Appointment ........................................................................................................................ 18
7.1.1 Ongoing Management ......................................................................................................................... 18
7.1.2 Risk Management ................................................................................................................................ 19
7.1.3 Risk Management Plan......................................................................................................................... 19
7.2 Project Risk Register.................................................................................................................................... 20
7.3 Subcontractor Risk Assessment and Method of Statements(Review & Approval Process) ....................... 20
Section 8: MANAGEMENT STRUCTURE, ORGANIZATION CHART, & KEY PERSONNEL RESPONSIBILITIES ........ 20
8.1 RESPONSIBILITIES ........................................................................................................................................ 20
8.1.1 Project Manager Responsibilities......................................................................................................... 20
8.1.2 Construction Manager Responsibilities ............................................................................................... 21
8.1.3 Safety Manager Responsibilities .......................................................................................................... 21
8.1.4 Safety Supervisor/Officer Responsibilities ........................................................................................... 21
8.1.5 Site Engineers/Supervisor / Foreman Responsibilities ........................................................................ 22
8.1.6 Employee Responsibilities.................................................................................................................... 22
R03-C07C01 – Construction Phase Health & Safety Management Plan Rev. 00 Page 2 of 66
ABDUL MOHSEN AL TAMIMI CONTRACTING COMPANY
Coastal Village Sports and Beach Club
Construction Health and Safety Management Plan
Revision # 00 Date of issue Oct. 28, 2023
R03-C07C01 – Construction Phase Health & Safety Management Plan Rev. 00 Page 3 of 66
ABDUL MOHSEN AL TAMIMI CONTRACTING COMPANY
Coastal Village Sports and Beach Club
Construction Health and Safety Management Plan
Revision # 00 Date of issue Oct. 28, 2023
R03-C07C01 – Construction Phase Health & Safety Management Plan Rev. 00 Page 4 of 66
ABDUL MOHSEN AL TAMIMI CONTRACTING COMPANY
Coastal Village Sports and Beach Club
Construction Health and Safety Management Plan
Revision # 00 Date of issue Oct. 28, 2023
R03-C07C01 – Construction Phase Health & Safety Management Plan Rev. 00 Page 5 of 66
ABDUL MOHSEN AL TAMIMI CONTRACTING COMPANY
Coastal Village Sports and Beach Club
Construction Health and Safety Management Plan
Revision # 00 Date of issue Oct. 28, 2023
20.2 Appendix B: Emergency Operation Center .................................................. Error! Bookmark not defined.
20.3 Appendix C: AMT Disciplinary Matrix ....................................................................................................... 56
20.4 Appendix D: Health & Safety Legal Registry.............................................................................................. 59
Section 21: REFERENCE DOCUMENTATIONS ............................................................................................... 65
R03-C07C01 – Construction Phase Health & Safety Management Plan Rev. 00 Page 6 of 66
ABDUL MOHSEN AL TAMIMI CONTRACTING COMPANY
Coastal Village Sports and Beach Club
Construction Health and Safety Management Plan
Revision # 00 Date of issue Oct. 28, 2023
R03-C07C01 – Construction Phase Health & Safety Management Plan Rev. 00 Page 7 of 66
ABDUL MOHSEN AL TAMIMI CONTRACTING COMPANY
Coastal Village Sports and Beach Club
Construction Health and Safety Management Plan
Revision # 00 Date of issue Oct. 28, 2023
R03-C07C01 – Construction Phase Health & Safety Management Plan Rev. 00 Page 8 of 66
ABDUL MOHSEN AL TAMIMI CONTRACTING COMPANY
Coastal Village Sports and Beach Club
Construction Health and Safety Management Plan
Revision # 00 Date of issue Oct. 28, 2023
2.3 UNITS
Unit Expansion
°C Degrees Celsius
A Ampere
dB Decibel
dBA A-Weighted Decibels
kg Kilogram
km Kilometer
km/h Kilometers per Hour
lx Lux
m Meter
mA Milliampere
mm Millimeter
ms Millisecond
V Volt
2.4 SCOPE
AMT will be commencing the work activities works include, but are not limited to, the following:
1) AMT to engineer, supply, construct, install, test, commission, integrate and complete all related
works, where applicable, including all logistical support for shipping and transport to Coastal Village
Sports & Beach Club.
a. Central Sports Club
i. The Central Sports club is the primary indoor sports facility within the COV and
provides. The club consists of the following:
• club house,
• sports hall,
• pool hall,
• tennis kiosk
• sports courts
• sports pitches.
R03-C07C01 – Construction Phase Health & Safety Management Plan Rev. 00 Page 9 of 66
ABDUL MOHSEN AL TAMIMI CONTRACTING COMPANY
Coastal Village Sports and Beach Club
Construction Health and Safety Management Plan
Revision # 00 Date of issue Oct. 28, 2023
• External shade structure attached to the buildings, including all footings, structure,
finishes, and shade fabric.
• All external hard landscape around the above-mentioned buildings as indicated in
the architectural drawings.
• Development of the below ground service connections/sleeves to the swimming
pool plant room and club house foundation to facilitate the future construction of
the swimming pool and swimming pool hall under the optional Priced items.
R03-C07C01 – Construction Phase Health & Safety Management Plan Rev. 00 Page 10 of 66
ABDUL MOHSEN AL TAMIMI CONTRACTING COMPANY
Coastal Village Sports and Beach Club
Construction Health and Safety Management Plan
Revision # 00 Date of issue Oct. 28, 2023
• Squash Courts,
• Shisha Café,
• Golf Simulator & Beach
• Front F&B and associated decking and shades.
R03-C07C01 – Construction Phase Health & Safety Management Plan Rev. 00 Page 11 of 66
ABDUL MOHSEN AL TAMIMI CONTRACTING COMPANY
Coastal Village Sports and Beach Club
Construction Health and Safety Management Plan
Revision # 00 Date of issue Oct. 28, 2023
R03-C07C01 – Construction Phase Health & Safety Management Plan Rev. 00 Page 12 of 66
ABDUL MOHSEN AL TAMIMI CONTRACTING COMPANY
Coastal Village Sports and Beach Club
Construction Health and Safety Management Plan
Revision # 00 Date of issue Oct. 28, 2023
The above tenants will be embedded into health and safety charters for each project, to be signed by those
senior leaders, within each project stakeholder organization, with delegated authority for the respective project.
STEWARDSHIP
Making sure you and everyone in your team goes home safely
We all have the responsibility to ensure best health and safety business practices are
encouraged, supported and followed to ensure at the end of the day, every employee makes
it home safely to their families.
R03-C07C01 – Construction Phase Health & Safety Management Plan Rev. 00 Page 13 of 66
ABDUL MOHSEN AL TAMIMI CONTRACTING COMPANY
Coastal Village Sports and Beach Club
Construction Health and Safety Management Plan
Revision # 00 Date of issue Oct. 28, 2023
REPORT INCIDENTS
All incidents, no matter how minor should be reported immediately to their immediate
supervisor. Reporting incidents including near misses should be encouraged and no one should
feel threatened to report incident.
4.3 Pillar III - Ten (10) Life Crucial Health and Safety Rules
To ensure the protection of the health and wellbeing of all projects related staff is safeguarded, AMT in
partnership with the project-wide stakeholders, Consultants, Sub-contractors shall abide by RSG Ten (10) Life
Crucial Health and Safety Rules with zero deviation, which are as follows:
1) Work at Height – Falls and being struck by a dropped object are among the top causes of workplace injuries
and fatalities in construction.
2) Trucks and Heavy Equipment – The majority of truck and heavy equipment fatalities involved ground
personnel being crushed or run over.
R03-C07C01 – Construction Phase Health & Safety Management Plan Rev. 00 Page 14 of 66
ABDUL MOHSEN AL TAMIMI CONTRACTING COMPANY
Coastal Village Sports and Beach Club
Construction Health and Safety Management Plan
Revision # 00 Date of issue Oct. 28, 2023
3) Light Vehicle Operation – Vehicle fatalities are on the rise and distracted driving is the leading cause.
4) Marine Activity – Marine infrastructure ranks as one of the most hazardous occupations in construction.
Water, waves, weather all pose additional conditions and can change quickly.
6) Trenching and Excavation – Cave-ins can be fatal. A cubic meter of dirt can weigh as much as a small car.
7) Electrical Work – Arc flash can produce temperature equal to the sun’s surface. Don’t risk injury or death.
De-energize equipment before performing work.
8) Hazardous Energy Control – Most incidents occur due to improper energy isolation and inadequate
verification. Always verify that systems are de-energized prior to starting work.
9) Material Handling – Serious injuries can result when materials are stored improperly. Be aware of body
placement and potential movement.
10) Confined Space Entry – Two-thirds of all confirmed space fatalities involve untrained personnel attempting
rescue. Never attempt a rescue without appropriate training and equipment.
All Contractors and their subsequent supply chain will be audited against their adherence and implementation
of RSG’s ‘Ten Life Crucial Health and Safety Principles.’
Health and safety performance indicators of the AMT will be monitored and measured by RSG through the use
of custom H&S dashboards and digital health and safety software systems. A programme-wide performance
monitoring system is a critical tool of the programme controls process to develop, disseminate, and integrate
timely and accurate performance information. It allows for a disciplined approach to analysing and adjudicating
competing operational requirements, communicating a common plan, and enabling overall programme
information flow. It also facilitates accurate predictive analysis for early and decisive corrective actions needed
to deliver a programme which meets the overall vision and objectives.
The collected data and performance appraisals will be used by AMT & RSG to form a database of information
from which all reporting can be produced. This will enable RSG to generate reports and performance dashboards
at various levels of granularity as required – from very specific project performance against a unique target, to
aggregated programme-level performance against a theme or in total.
The information, monitoring data, performance reporting requirements, and templates mentioned in the
following sections will form part of the performance monitoring system, thus they are subject to updating or
amendment once the overall performance monitoring and reporting system is defined.
R03-C07C01 – Construction Phase Health & Safety Management Plan Rev. 00 Page 15 of 66
ABDUL MOHSEN AL TAMIMI CONTRACTING COMPANY
Coastal Village Sports and Beach Club
Construction Health and Safety Management Plan
Revision # 00 Date of issue Oct. 28, 2023
The identified KPIs will allow AMT & RSG to the monitor, support, and target both programme and project
performance. The KPIs may change and be updated as needed by RSG
The identified KPIs will be monitored by AMT & RSG through the reporting mechanisms, audit, and inspections.
The information will be provided to the RSG Senior Management team and the various health and safety
representatives. RSG will use this information for setting priorities and actions for continual improvement:
• AMT shall cooperate with RSG or any of its representatives regarding health and safety audits. AMT
shall acknowledge all audit findings and take all corrective and preventive actions that may be required
to address any nonconformity identified during such audits.
• AMT shall conduct routine health and safety inspections and audits for its ongoing works. Written
records of such inspections and audits shall be maintained by AMT and made available to any
representative of RSG upon request.
• RSG may issue a Stop Work Notice (SWM) to the AMT for any observed cases of serious or imminent
danger associated with their work. On receipt of an SWM, AMT shall refrain from work until such time
as remedial action has been taken to alleviate the serious or imminent danger and to prevent it
reoccurring. AMT shall not claim any variation due to stop work instructions for whatsoever reason.
• AMT shall stop work if any unknown or unplanned conditions occur that give rise to serious or imminent
danger. In such circumstances, AMT shall assess the risks associated with any remedial work required
and revise the method statements and job hazard analysis. The revised method statement and risk
assessment shall be reviewed and approved by AMT’s Health and Safety Manager. RSG shall oversee
the review process and provide comments and recommendations before AMT recommences work.
• RSG will perform periodic health and safety assessments of the project. AMT shall provide timely,
complete and open access to its health and safety processes, files, records and any other related
documentation. AMT shall cooperate with and acknowledge the inspections and take all corrective and
preventive actions that may arise as a result of such inspections. AMT shall close out any SVN
requirements in a timely manner as noted within the notice.
• AMT shall conduct routine health and safety inspections, monitoring and audits for its ongoing works,
and cover all health and safety impacts and risks on the project. Written records of such inspections,
monitoring and audits shall be maintained by AMT and made available to RSG at frequencies defined by
RSG or upon request.
• AMT shall ensure the timely closing out of any issues raised. AMT premises including their messing
facilities, food, etc., shall be inspected and audited on a monthly basis or when deemed necessary and
a report submitted to RSG. These facilities shall be inspected through self-audit and inspection program.
When necessary, RSG will also participate in such audits. AMT shall implement any recommendations
arising out of such inspections.
• AMT shall ensure acceptable health and safety performance of all Sub-contractors, visitors, vendors,
public and other parties that may enter the project.
• Should AMT fail to meet the health and safety performance standards, RSG may take steps in line with
the contract terms and conditions to ensure that the health and safety standards are always maintained
on the project.
• AMT shall develop and implement a culture which shall act as incentives for their teams at all levels, to
make a positive contribution to health and safety performance.
• All the Health & Safety requirements described in this and further documents shall be implemented and
strictly observed in order to achieve the Project Goals that is Project Execution in the best HEALTH &
SAFETY conditions. The proposed HEALTH & SAFETY goals for the Project are the following:
R03-C07C01 – Construction Phase Health & Safety Management Plan Rev. 00 Page 16 of 66
ABDUL MOHSEN AL TAMIMI CONTRACTING COMPANY
Coastal Village Sports and Beach Club
Construction Health and Safety Management Plan
Revision # 00 Date of issue Oct. 28, 2023
R03-C07C01 – Construction Phase Health & Safety Management Plan Rev. 00 Page 17 of 66
ABDUL MOHSEN AL TAMIMI CONTRACTING COMPANY
Coastal Village Sports and Beach Club
Construction Health and Safety Management Plan
Revision # 00 Date of issue Oct. 28, 2023
Those who have responsibility for managing Contractor personnel on site shall be able to communicate in both
written and oral English to a standard appropriate to the tasks being performed. Note that there may be
personnel who are not competent in the English language, and this is permitted provided that AMT can
demonstrate that:
• Such team members are able to give oral instructions and warnings to others.
• Such team members shall receive the required health and safety training / briefing (including any
emergency procedures) before commencing work in a form that they understand.
• Appropriate arrangements are made to ensure that instructions are effectively communicated to and
understood by all team members.
• Particular attention has been given to the communication requirements of safety critical workers.
ensuring a translator is available who is capable of instructing the non-English speaking personnel in
safety and other operational matters.
• Maintaining a reasonable ratio of non-English speaking personnel to each translator at all times
Special provisions for safety critical instructions conveyed by the translator shall be recorded as being received
and clearly understood by each non-English speaking person. Such records shall include those for safety
induction, emergency procedures, safety method statements and safety awareness talks.
R03-C07C01 – Construction Phase Health & Safety Management Plan Rev. 00 Page 18 of 66
ABDUL MOHSEN AL TAMIMI CONTRACTING COMPANY
Coastal Village Sports and Beach Club
Construction Health and Safety Management Plan
Revision # 00 Date of issue Oct. 28, 2023
R03-C07C01 – Construction Phase Health & Safety Management Plan Rev. 00 Page 19 of 66
ABDUL MOHSEN AL TAMIMI CONTRACTING COMPANY
Coastal Village Sports and Beach Club
Construction Health and Safety Management Plan
Revision # 00 Date of issue Oct. 28, 2023
7.3 Subcontractor Risk Assessment and Method of Statements(Review & Approval Process).
An overall project risk and impact management that incorporates all foreseeable hazards and impacts forthe
project as mentioned in 6.11.2 also includes the activities that are generated through the sub-contractors,
vendors or other parties involved on the project.
8.1 RESPONSIBILITIES
HEALTH & SAFETY responsibilities for the project personnel at all organizational levels, also for staff in the head
offices will be established and clearly cascaded through job descriptions roles and responsibility in
responsibilities in accordance with the general requirements of TRS-HS-GEN_0003_Contractor Health and
Safety Requirements Rev_03.
8.1.1 Project Manager Responsibilities
a. Project Manager shall ensure that safety responsibility is not shouldered by the Safety Manager,
Safety Supervisors & Safety Officer alone but as well as with the entire construction Team.
b. Project Manager is responsible for the implementation of the HEALTH & SAFETY plan and ensures
that it is reviewed regularly, kept up to date and used to monitor compliance on its implementation
by the respective site engineer.
c. Shall ensure that all works are carried out as per Red Sea Global Standards and its requirements,
including the appropriate resources need to implement them.
d. Shall ensure conformance to the approved HEALTH & SAFETY Plan and/or this document including
its appendices, Local law and international codes. The objective is to ensure that all Program
Participants use common terminologies, procedures, forms/formats, systems, project management
tools and have the same understanding of the project requirements.
e. Ensure that safety is not compromised at any time to meet other project parameters and
expectations such as those relating to cost and schedules.
f. Make suitable arrangements for regular consultation between construction managers,
superintendents, supervisors, employee representatives and contractor representatives on matters
of health, safety and the environment.
g. Ensure that all incidents involving injury, damage to property or harm to the environment as well as
near misses are reported to the designated Company officers and are thoroughly investigated to
R03-C07C01 – Construction Phase Health & Safety Management Plan Rev. 00 Page 20 of 66
ABDUL MOHSEN AL TAMIMI CONTRACTING COMPANY
Coastal Village Sports and Beach Club
Construction Health and Safety Management Plan
Revision # 00 Date of issue Oct. 28, 2023
identify the causes so that there is no recurrence. It is also a duty to see that any recommended
corrective action should be initiated as soon as possible.
h. Ensure that all critical and hazardous tasks and activities are adequately planned and that
appropriate Job Safety Analysis or other equivalent system for these tasks had been processed,
communicated and discussed with concerned discipline Supervisor/Foreman and his crew.
R03-C07C01 – Construction Phase Health & Safety Management Plan Rev. 00 Page 21 of 66
ABDUL MOHSEN AL TAMIMI CONTRACTING COMPANY
Coastal Village Sports and Beach Club
Construction Health and Safety Management Plan
Revision # 00 Date of issue Oct. 28, 2023
a. Be familiar with and enforce HEALTH & SAFETY rules, regulations, and laws and document all
actions taken to ensure compliance with client and their own Construction Health & Safety
Management Plan.
b. Daily inspections of the Work Site in cooperation with Sub-Contractors according to his work
scope.
c. Organization and performance of daily and weekly inspections as described in his job description.
d. Preparation of indoctrination talks and programs to acquaint new employees with Work Site
hazards, safe work procedures at Work Site, and the behavior expected of them.
e. Reporting the injuries occurring on the Work Site. Immediately visiting the site of serious injuries
or incidents to view evidence, participate in preparing a report and help institute corrective
action.
f. Participate in safety publicity and coordination of safety incentive, recognition, and personal
contact programs.
g. Advising on HS&E regulations, inspections, and activities of government that require compliance
to workforce.
h. Fostering and maintenance of good relations with government and local authority
i. Prepare monthly and weekly safety report as statistics, injury, illness summary, and medical
record form.
j. Ensuring that all heavy equipment operators have current valid Saudi Arabian Government (SAG)
license to operate the equipment.
k. Ensure that all operators have current valid third-party certification.
l. Ensuring emergency plan and evacuation procedures are in place
m. Ensuring that daily safety toolbox meeting was conducted and documented on daily basis.
R03-C07C01 – Construction Phase Health & Safety Management Plan Rev. 00 Page 22 of 66
ABDUL MOHSEN AL TAMIMI CONTRACTING COMPANY
Coastal Village Sports and Beach Club
Construction Health and Safety Management Plan
Revision # 00 Date of issue Oct. 28, 2023
d. Report to their immediate supervisor any situation which they have reason to believe could
present a hazard and which they cannot themselves correct;
e. Report all HEALTH & SAFETY incidents and work-related injuries; and
f. Not intentionally or recklessly interfere with or misuse anything provided at the workplace in the
interest of health, safety, welfare or protection or management of the environment.
g. All workers have the authority and obligation to stop the work and report all unsafe acts /
conditions to their supervisor/foreman or safety representatives.
Every employee is given the right to stop his work, or his co-workers work without fear of reprimand. He shall
report to his supervisor the cause of the stop works and shall only resume upon confirmation that deficiency or
unsafe condition has been corrected, rectified or the hazard has been minimized to a level reasonably
acceptable.
R03-C07C01 – Construction Phase Health & Safety Management Plan Rev. 00 Page 23 of 66
ABDUL MOHSEN AL TAMIMI CONTRACTING COMPANY
Coastal Village Sports and Beach Club
Construction Health and Safety Management Plan
Revision # 00 Date of issue Oct. 28, 2023
appropriate to their assigned tasks. All Contractor employees and Sub-Contractors shall be inducted and
made aware of RSG H&S Administrative Requirements.
• Ensure specialized training is provided to all personnel assigned to working on the Project Site
depending on their tasks and as required by the RSG H&S Administrative Requirements.
• Ensure training materials are prepared by a designated competent trainer and reviewed by the
Employer.
• Provide a dedicated training center, complete with adequate audio-visual equipment and furniture.
Layout and specification to be submitted for review and approval.
• Maintain an updated training matrix in place showing all types of induction and training courses
available, and to which category type of employees these courses will be delivered. A training schedule
shall be in place as well showing the timing/period during which the training courses will be given to
required staff.
• Maintain a training register stating the topic of training or induction conducted, attendees’ details, dates
of presentations, and trainer details. The register shall be kept up to date at the worksite office to ensure
that all staff on the work Site has had the proper trainings and induction.
• All organizations shall provide appropriate health and safety training to staff from non- operational
functions and departments within the organization to avoid any impact to onsite activity.
• RSG requires that everybody engaged on their construction sites is able to demonstrate they have the
necessary health and safety knowledge and skills.
• Employees designated as competent persons have the required training certificates (e.g., third party,
recognized training institution, supplier).
AMT shall ensure that their CPHSP details their arrangements for making sure that all personnel and Sub-
contractor’s employees are trained and competent to undertake their work in accordance with the required
standards.
AMT shall maintain all training records and make it available for inspection by any representative of RSG upon
request. AMT shall conduct training and awareness programs including but not limited to:
• Project-specific Health and Safety induction
• General awareness training
• Skills training
Third-party training approved by RSG, and formal training conducted by training professionals or agencies.
AMT shall develop and implement a full training plan (training matrix) for all staff and workforce. The training
plan shall demonstrate continual improvement and workforce awareness and shall be extended to the Sub-
contractors, as applicable.
R03-C07C01 – Construction Phase Health & Safety Management Plan Rev. 00 Page 24 of 66
ABDUL MOHSEN AL TAMIMI CONTRACTING COMPANY
Coastal Village Sports and Beach Club
Construction Health and Safety Management Plan
Revision # 00 Date of issue Oct. 28, 2023
AMT shall ensure that the training topics provided to employees are based on a number of factors, such as but
not limited to:
• Trends in monthly statistics
• Objectives that have been set
• Recurring issues on site
• Accident/accidents on site
AMT shall ensure that the courses designed to meet the needs of specific operatives involved in specialized
trades including their roles and responsibilities are provided through training. Specialist training include but not
limited to:
• Safe entry into confined spaces
• Marine operations
• Lifting operations
• Scaffolding/false work
• Temporary works
• Abrasive wheels
• Woodworking machinery
• Excavation support equipment
• First aid
• Defibrillator training
• Fire marshal
• Accident investigation
AMT shall:
• Create local employment opportunities as per legal requirements.
• Ensure non-discrimination in hiring and promotion practices.
• Promote life-long learning and on-the-job training.
• Facilitate training opportunities for employees with a view on improving skill levels.
• Provide training in appropriate languages based on the demographics of the workers.
AMT shall retain records of all training provided throughout the Project duration. Such records shall include, as
a minimum:
R03-C07C01 – Construction Phase Health & Safety Management Plan Rev. 00 Page 25 of 66
ABDUL MOHSEN AL TAMIMI CONTRACTING COMPANY
Coastal Village Sports and Beach Club
Construction Health and Safety Management Plan
Revision # 00 Date of issue Oct. 28, 2023
AMT shall conduct a self-audit of their worksite and Health and Safety Management System, and continually
evaluate the level of their compliance with the health and safety standards, regulatory requirements, trends,
results of previous inspections, management visits, incident management, review of corrective action trends
and progress on health and safety goals.
AMT shall conduct the following inspections and audits as a minimum:
• Site safety inspections on a daily, weekly and monthly basis
• Site welfare inspections on a daily, weekly and monthly basis
• Site safety tour with RSG or the appointed Consultant and Contractor’s Senior Management on a weekly
basis.
• Site welfare audits on a quarterly basis
• Third-party audit on Health and Safety Management System on an annual basis
• Other inspections and audits at intervals deemed necessary by RSG.
• Daily visual inspections (e.g., equipment, ladders, tools, harnesses, etc.)
• Daily Site tours and observations
• Monthly inspections (can be conducted jointly or combined with RSG representative in accordance with
AMT’s inspection schedule where needed)
• Monthly Site performance assessments or topic-based audits
• Annual inspections/audits (mobile cranes, forklifts, mobile elevating work platforms)
• ISO 45001 Management System Audits (as required by the internal Contractor certification
requirements)
Auditing shall be performed with the use of standards and specific checklists agreed with RSG.
AMT shall provide RSG with their self-audit report and the associated inspection/close-out reports. The audit
report shall define the corrective actions needed depending on nonconformities and deviations highlighted
during the inspection of the project. Deficiencies identified during the audit shall be reviewed and analyzed to
determine potential shortfalls in the Health and Safety Management System and to develop appropriate
corrective actions to continuously improve the health and safety performance of the project.
R03-C07C01 – Construction Phase Health & Safety Management Plan Rev. 00 Page 26 of 66
ABDUL MOHSEN AL TAMIMI CONTRACTING COMPANY
Coastal Village Sports and Beach Club
Construction Health and Safety Management Plan
Revision # 00 Date of issue Oct. 28, 2023
Observation Trend Analysis Observation raised online reporting Monthly Online reporting system
system are analyzed to identify trends
(Aconex)
H&S Observation Tours Physical inspections of site H&S standards Daily Online reporting system
H&S Inspections Physical inspections of site H&S One Per week minimum Online reporting system
standards.
Undertaken by AMT H&S Manager
H&S Audits Audit review of procedural compliance. As per Schedule Online reporting system
Undertaken by H&S Manager.
H&S Management Audits Audit review of procedural compliance. As per Schedule Online reporting system
Undertaken by H&S Manager.
H&S Management Audits Audit review of procedural compliance. As per Schedule Online reporting system
Undertaken by H&S Manager.
H&S ISO 45001 Management Management System Audit As per Schedule Online reporting system
System Audits
H&S Leadership Tours Physical inspection of site H&S standards Weekly Online reporting system
undertaken by AMT Senior Leadership
Team and Project Leadership Teams
Behavioral Observations Observations are analyzed to identify the Monthly Online reporting system
behavioral evident trends
Coordinated H&S Reviews The RSG H&S Manager and contractor’s Monthly Online reporting system
H&S Manager undertake a combined,
coordinated review of H&S standards and
compliance on the project
Monthly Assessment League League table illustrating current H&S Monthly Online reporting system
Table ratings of contractors based on previous
month’s performance
The review shall include, but not be limited to, where appropriate, an evaluation of and/or changes to:
• Health and Safety Policy
• Construction Phase Health and Safety Plan
• Forms and templates
• Objectives and targets
• Action plans
• Follow-up actions from previous meetings
• Health and safety system suitability and development
• Audit results and close-out actions
• Preventive and corrective actions
• Regulatory changes
• Continual improvement measures
• Performance measures
• Major procedure and risk review changes
• Lessons learned.
R03-C07C01 – Construction Phase Health & Safety Management Plan Rev. 00 Page 27 of 66
ABDUL MOHSEN AL TAMIMI CONTRACTING COMPANY
Coastal Village Sports and Beach Club
Construction Health and Safety Management Plan
Revision # 00 Date of issue Oct. 28, 2023
11.1 Requirements
All H&S incidents (hereafter referred to as “incidents”) will be reported.
• RSG will not retaliate against personnel for reporting an incident.
• The actual and potential severity of all incidents will be determined.
• Response activities will be managed based upon incident severity.
• Each RSG facility/project/program shall maintain a contact list for purposes of incident notification and
communication.
• Incidents will be reported externally as required by law and/or contract.
• All incidents will be entered into RSG H&S online data system for necessary reporting process and record
keeping.
• An investigation will be conducted as soon as reasonably practical following an incident.
• An incident Alerts will be developed and used to communicate significant incidents across the
organization.
• Incident data will be tracked and analyzed to measure and improve performance.
• Compliance with regulatory reporting requirement.
R03-C07C01 – Construction Phase Health & Safety Management Plan Rev. 00 Page 28 of 66
ABDUL MOHSEN AL TAMIMI CONTRACTING COMPANY
Coastal Village Sports and Beach Club
Construction Health and Safety Management Plan
Revision # 00 Date of issue Oct. 28, 2023
R03-C07C01 – Construction Phase Health & Safety Management Plan Rev. 00 Page 29 of 66
ABDUL MOHSEN AL TAMIMI CONTRACTING COMPANY
Coastal Village Sports and Beach Club
Construction Health and Safety Management Plan
Revision # 00 Date of issue Oct. 28, 2023
R03-C07C01 – Construction Phase Health & Safety Management Plan Rev. 00 Page 30 of 66
ABDUL MOHSEN AL TAMIMI CONTRACTING COMPANY
Coastal Village Sports and Beach Club
Construction Health and Safety Management Plan
Revision # 00 Date of issue Oct. 28, 2023
R03-C07C01 – Construction Phase Health & Safety Management Plan Rev. 00 Page 31 of 66
ABDUL MOHSEN AL TAMIMI CONTRACTING COMPANY
Coastal Village Sports and Beach Club
Construction Health and Safety Management Plan
Revision # 00 Date of issue Oct. 28, 2023
the incident, personal medical information, disciplinary actions, contractor details names/logos, etc. will
be omitted.
This guidance has been produced to assist Contractors in providing site management staff with a satisfactory
standard of safe work method statements which clearly identifies the key health and safety arrangements to be
implemented onsite in respect to the safety risks associated with their site operations/tasks.
• It identifies 14 ‘key’ items which shall be utilized by AMT when formulating their Health and Safety
method statements for submission to the “Employer’s Representative”. Note: The 14 items identified
do not form an exhaustive list in respect to health and safety items for Contractor consideration.
• The key elements of this guidance (items 1 – 14 as shown in Table 1) serve as the benchmark for our
site management staff when they are reviewing the health and safety content of AMTs’ health and
safety method statements.
• The key objectives of this guidance are to promote, and encourage our Contractors to provide a concise,
but comprehensible method statement which focuses specifically on the key health and safety issues
associated with their operations.
R03-C07C01 – Construction Phase Health & Safety Management Plan Rev. 00 Page 32 of 66
ABDUL MOHSEN AL TAMIMI CONTRACTING COMPANY
Coastal Village Sports and Beach Club
Construction Health and Safety Management Plan
Revision # 00 Date of issue Oct. 28, 2023
R03-C07C01 – Construction Phase Health & Safety Management Plan Rev. 00 Page 33 of 66
ABDUL MOHSEN AL TAMIMI CONTRACTING COMPANY
Coastal Village Sports and Beach Club
Construction Health and Safety Management Plan
Revision # 00 Date of issue Oct. 28, 2023
14.1.2 Responsibilities
AMT HEALTH & SAFETY Supervisor
1. Advise projects and discipline leaders on health safety and risks and environmental impacts in
accident and emergency situations.
2. Provide at least one 10-unit first aid kit/cabinet.
3. Ensure compliance with Saudi Government Law and Al Tamimi HEALTH & SAFETY Management
Plan.
4. Cooperate with Human Resources to arrange and manage training in emergency response.
5. Ensure all office risk assessments are carried out and are up to date.
6. Keep up to date on fire legislation.
7. Responsible for weekly audit for the availability of first aid medicine, date expired and audit the
records of injury and the expiration of medicine.
8. Ensure medical staff are on duty and available during all work times.
AMT shall provide adequate first aid provisions including competent designated first aid trained personnel based
on the number and distribution of employees, as a minimum, one (1) per fifty (50) employees. All personsshall
have reasonably rapid access to first aid. If employees are dispersed over a wide area, then AMT shall provide
adequate first aid cover for all locations.
• First aiders should be certified as a Basic Life Support (1-day course).
• First aiders should be equipped with an approved first aid kit.
• First aiders should have received appropriate training recognized by the Ministry of Health (MOH) in
KSA.
• First aiders shall undertake a refresher course every year and re-certification after every 3 years.
R03-C07C01 – Construction Phase Health & Safety Management Plan Rev. 00 Page 34 of 66
ABDUL MOHSEN AL TAMIMI CONTRACTING COMPANY
Coastal Village Sports and Beach Club
Construction Health and Safety Management Plan
Revision # 00 Date of issue Oct. 28, 2023
• The site nurse shall work under clinical supervision of a nominated medical director.
• The site nurse may only use medications in accordance with documented nurse standing orders that
have been approved by the supervising medical doctor.
• The site nurse may not issue prescription drugs except under the direct instruction of the supervising
medical doctor.
R03-C07C01 – Construction Phase Health & Safety Management Plan Rev. 00 Page 35 of 66
ABDUL MOHSEN AL TAMIMI CONTRACTING COMPANY
Coastal Village Sports and Beach Club
Construction Health and Safety Management Plan
Revision # 00 Date of issue Oct. 28, 2023
14.2.1 Welfare
• Health and hygiene facilities shall be provided in accordance with normal procedures for construction
sites; adequate chemical toilets shall be provided and maintained at agreed locations adjacent to the
job site. The chemical toilets will be checked twice one day to ensure that they are clean and usable.
• A system will be established to distribute potable water to the workforce in a safe and sanitary fashion
and quality of potable water shall be monitored and records kept.
• Filters and containers shall be regularly maintained and cleaned to prevent the spread of disease or
infection.
• Work and ancillary facility areas will be cleared of all rubbish, garbage, etc. daily to avoid the occurrence
of unsanitary and unhygienic conditions.
• Al-Tamimi site offices and facilities will be cleaned and maintained daily to ensure compliance with
standards.
• Adequately shaded rest areas shall be provided with sufficient room for all personnel.
Any area with ambient noise levels exceeding 90 dB shall be classified as a noise hazard area. Engineering
controls shall be used whenever possible to reduce this noise. Work areas near sensitive receptors (school,
hospital, clinic, and mosque) shall limit work hours and or equipment.
R03-C07C01 – Construction Phase Health & Safety Management Plan Rev. 00 Page 36 of 66
ABDUL MOHSEN AL TAMIMI CONTRACTING COMPANY
Coastal Village Sports and Beach Club
Construction Health and Safety Management Plan
Revision # 00 Date of issue Oct. 28, 2023
AMT shall ensure that sanitary conveniences are adequately ventilated, lit and kept clean and in an orderly
condition, and available for the duration of the project. Separate facilities containing sanitary conveniences shall
be provided for men and women. Toilet facilities should be carefully sited/screened to avoid offending
neighbors and to ensure the workers’ privacy.
R03-C07C01 – Construction Phase Health & Safety Management Plan Rev. 00 Page 37 of 66
ABDUL MOHSEN AL TAMIMI CONTRACTING COMPANY
Coastal Village Sports and Beach Club
Construction Health and Safety Management Plan
Revision # 00 Date of issue Oct. 28, 2023
For every additional 100 personnel onsite, four additional toilets and wash basins are required. For every
additional 100 personnel onsite, two additional urinals are required.
R03-C07C01 – Construction Phase Health & Safety Management Plan Rev. 00 Page 38 of 66
ABDUL MOHSEN AL TAMIMI CONTRACTING COMPANY
Coastal Village Sports and Beach Club
Construction Health and Safety Management Plan
Revision # 00 Date of issue Oct. 28, 2023
For maintenance work or for project work of short duration it may not be feasible to provide the level of welfare
facility described in this section. In such circumstances the level of welfare for washing, toilets and break areas
shall be, as a minimum, hygienic with running water and portable toilets in good condition and cleaned regularly.
AMT shall install water filters, chlorinators and disinfection units and ensure that water storage tanks are
cleaned and maintained regularly. Water quality tests of storage tanks and delivery pipework shall be carried
out in accordance with all applicable standards, legislation and regulations by third party accredited
laboratories, before first use of the tank and then at regular intervals. Suggested frequency is every three
months, but specific to be determined by Risk Assessment and included in the welfare plan.
R03-C07C01 – Construction Phase Health & Safety Management Plan Rev. 00 Page 39 of 66
ABDUL MOHSEN AL TAMIMI CONTRACTING COMPANY
Coastal Village Sports and Beach Club
Construction Health and Safety Management Plan
Revision # 00 Date of issue Oct. 28, 2023
• Fixed drinking water stations shall be provided, as a guide, at a ratio of one station per 50 persons as a
guide.
R03-C07C01 – Construction Phase Health & Safety Management Plan Rev. 00 Page 40 of 66
ABDUL MOHSEN AL TAMIMI CONTRACTING COMPANY
Coastal Village Sports and Beach Club
Construction Health and Safety Management Plan
Revision # 00 Date of issue Oct. 28, 2023
• Prior to removal from the premises, garbage and other refuse shall be stored in a way that makes it
inaccessible to insects, rodents and other vermin.
• Transportation
• AMT shall provide workers at AMT expense transportation to and from the project site and to other
events and services, including medical care, as required.
AMT shall bear the cost of insuring, testing and payment of applicable taxes and registration, repairing and
maintaining the vehicles and for all other running expenses of the vehicle used to transport worker to and from
the project site.
All busses shall be equipped with the following safety requirements and ensure the regulatory compliances:
• Surrounded by suitable lighting to identify its dimensions
• Visibly display the name of AMT on the outside including contact details
• Each seat to be fitted with functional seatbelts and handgrips
• Equipped with air-conditioning
• Equipped with at least six (6) hammers to break the window glass in case of emergency
• Equipped with a fully stocked first aid kit with contents regularly checked and inspected
• Equipped with suitable fire extinguishers regularly checked and inspected
• Equipped with emergency windows indicted with signed
• Smoking is prohibited inside all vehicles
All vehicles shall pass an annual inspection as required by the competent authority. All vehicles shall be driven
by a competent driver holding a KSA driver license for the appropriate category of vehicle and possess current
basic first aid training.
This element does not address the hazards of exposure to exhaust by-products from diesel engines, or materials
designated as waste or emissions from waste. These hazards are regulated by other standards. Further, this
element does not apply to the following substances:
• Agricultural products or vegetable seed treated with pesticides
• Articles not modified (whole components, such as screws to be plated)
• Biological hazards (first aid waste)
• Consumer products (e.g., “white-out,” spray paint)
• Consumer products used at work where exposure is no more than consumer use (spray paint used only
as much and as long as a person would at home)
• Cosmetics
• Drugs in retail packaging and in packaging designed for personal consumption
• Dust, if not hazardous
• Food and food ingredients
• Hazardous wastes
• Personal food consumed at work
R03-C07C01 – Construction Phase Health & Safety Management Plan Rev. 00 Page 41 of 66
ABDUL MOHSEN AL TAMIMI CONTRACTING COMPANY
Coastal Village Sports and Beach Club
Construction Health and Safety Management Plan
Revision # 00 Date of issue Oct. 28, 2023
• Pesticides
• Radiation
• Retail food or alcohol
• Tobacco or tobacco products
• Wood or wood products (unless treated and/or sawed or cut, creating dust)
If a current hazardous substance inventory is not available, the designated person will conduct a complete
physical inventory at the beginning of the project, and quarterly thereafter, of all products (liquids, solids,
powders, pastes, gases).
AMT COSHH Coordinator records each product and forwards copies of all completed inventory sheets for
current and future products to the "Employer's Representative" for review, and maintains the sheets on file
until completion of the project.
AMT shall conduct the inventory using a wall-to-wall system for collecting all products for inclusion on the list.
Foremen assist the designated person by submitting a list of hazardous substances used by their employees.
Review process flow diagrams, if necessary. Unless all materials are included in this list, some hazardous
substances might be overlooked.
Include products in small quantities or in small containers. Small quantities of materials are frequently more
hazardous than larger quantities because of the risk of being overlooked and their potential hazards thus being
disregarded.
• Include compressed gases, paints, epoxies, glues, waterproofing and mixtures.
• Do not include exclusion materials identified in this guideline above.
• Include the approximate quantities (e.g., liters, kilograms, gallons, pounds) for each product that will be
on site at any given time.
• Attach a site map to the inventory showing where inventoried hazardous substances are stored.
• Include a list of all products from the inventory at the front of the SDS binder as an index for locating an
SDS. The list shall include the SDS number assigned for location in the binder, the product name,
manufacturer, and status of the SDS on file. The list shall also include any common name that employees
use for the product.
Each COSHH coordinator shall ensure their respective employer has undertaken a Control of Substances
Hazardous to Health (COSHH) assessment for all hazardous substances used and/or created by work activities.
R03-C07C01 – Construction Phase Health & Safety Management Plan Rev. 00 Page 42 of 66
ABDUL MOHSEN AL TAMIMI CONTRACTING COMPANY
Coastal Village Sports and Beach Club
Construction Health and Safety Management Plan
Revision # 00 Date of issue Oct. 28, 2023
copy of this request in the project file. If a project employee has a telephone conversation with a
manufacturer or supplier, he shall record the conversation as a dated memo and include at the memo
in the project file.
• Personnel purchasing or receiving products: Submit SDSs to the COSHH Coordinator.
• H&S Representative: Review each SDS to ensure that all information is provided. The names of
substances listed on the SDS shall be the same as those printed on container labels and on the hazardous
substance inventory. The SDS shall be specific to the substances provided by suppliers rather than
representative or generic.
16.3 Labelling
The project COSHH plan defines the method for labelling each container of hazardous material on the project.
The plan designates an employee responsible for labelling all containers as detailed below.
Review all containers of products on the hazardous substance inventory to ensure that the containers are
properly labelled. If a container is not properly labeled, obtain a label from the supplier or create one from the
information on the SDS. Local safety equipment vendors may supply labels.
If hazardous materials are received at the project without proper labels, set them aside; do not distribute them
for use until they are properly labeled. If an unlabeled container is found in the workplace, test and label it
accordingly or dispose of it properly.
R03-C07C01 – Construction Phase Health & Safety Management Plan Rev. 00 Page 43 of 66
ABDUL MOHSEN AL TAMIMI CONTRACTING COMPANY
Coastal Village Sports and Beach Club
Construction Health and Safety Management Plan
Revision # 00 Date of issue Oct. 28, 2023
• For non-English speaking employees, information written on labels shall be provided in an indigenous
language.
• Containers of mixed products are labeled with the chemical name listed on the SDS for each toxic or
hazardous substance in the mixture. It is recommended that containers of mixtures also be labeled with
the common name of the mixture.
Rather than labelling, individual process containers or vessels, signs, placards, process sheets, batch tickets,
operating procedures, or other such written materials may be used. Each alternative method shall identify the
container or containers to which it applies, identify the hazardous substance(s) in the container, and show
appropriate hazard warnings. These written materials shall be readily accessible to employees in the work area
during each shift.
Pipelines containing hazardous substances are not considered containers and need not be labeled. However,
risk assessments will address how employees working on unlabeled pipelines are protected from chemical
hazards.
If a substance-specific standard is adopted for a chemical in a workplace, the labelling requirements of that
standard supersede the requirements of the COSHH standard.
If a labeled container is covered by a secondary container or a covering that remains in place while the contents
of the container are withdrawn or used, the required labels shall also appear on the secondary container or
covering.
R03-C07C01 – Construction Phase Health & Safety Management Plan Rev. 00 Page 44 of 66
ABDUL MOHSEN AL TAMIMI CONTRACTING COMPANY
Coastal Village Sports and Beach Club
Construction Health and Safety Management Plan
Revision # 00 Date of issue Oct. 28, 2023
If through the risk assessment process, it is identified that staff are potentially at risk from exposure to
substances hazardous to health, then monitoring of staff groups will be implemented. This will include staff
groups undertaking identical or similar tasks and being exposed to similar risks.
Monitoring will be carried out by trained and experienced staff in monitoring exposure and be:
• Familiar with monitoring standard methods
• Adequate knowledge of exposure limits and exposure strategies
• Writing professional development
• Provide sensible and proportionate advice
Where health surveillance shows an employee’s health is being affected the following steps will be
implemented:
• Review of the risk assessment, if necessary, modify control measures.
16.5 Transport/Shipping
It is likely that specific regulatory requirements will apply to the transportation of substances hazardous to
health, and therefore contractor shall ensure that they are familiar and compliant with these requirements.
Specific hazards to consider when transporting hazardous materials in vehicles include:
• Impact during an accident when carrying small cylinders of oxygen or other gases under pressure.
• Asphyxiation by inert gases when carried in the vehicle cabin.
• Spillage.
• Incompatibility with other hazardous materials.
• Transporting of hazardous materials shall be risk assessed and completed in a manner consistent with
its SDS.
16.6 Storage
Storage of hazardous materials shall be as indicated in the SDS:
• In a cool, dry environment, free from extremes of temperature and humidity.
• In a manner that separates them from other materials (including flammables and oxidizers) and from
each other.
R03-C07C01 – Construction Phase Health & Safety Management Plan Rev. 00 Page 45 of 66
ABDUL MOHSEN AL TAMIMI CONTRACTING COMPANY
Coastal Village Sports and Beach Club
Construction Health and Safety Management Plan
Revision # 00 Date of issue Oct. 28, 2023
16.7 Training
AMT shall notify all employees of the hazards of chemicals to be used on the worksite.
The H&S Representative arranges employee training at the time of the employee’s initial assignment, annually,
and when a new hazard is introduced to the jobsite. This training can be organized and presented to groups or
on a work area by work area basis, depending on the operation.
The H&S Representative discusses the project COSHH plan during the initial orientation of occasional and
business visitors, as well as Contractors, who are subject to exposure to hazardous substances.
Specific training for non-routine tasks and the hazards associated with chemicals contained in unlabeled pipes
in the employees’ immediate work area is provided to affected employees. Supervisors are responsible for
identifying training needs during risk mitigation planning (2 week look-ahead).
Employees are advised of their rights to chemical hazard information and to specific training with respect to
hazardous substances in the workplace. At a minimum, the information and training include the following topics:
• Details of the project COSHH Plan.
• Who to contact for questions regarding chemicals.
• How to obtain a copy of an SDS.
• How to read SDSs, labels, and hazard classifications.
• Details on specific chemicals present at the workplace:
o Identity and location of hazardous substances in the workplace.
o Physical and health hazards of hazardous substances and potential exposure routes.
o Methods and observations available for detecting the presence or release of a hazardous chemical in
the workplace. Methods can include monitoring conducted by a designated employee. Observations
may include the appearance of or the detection of odors of substances.
o Symptoms of overexposure.
o Procedures to follow if employees are overexposed to hazardous chemicals.
o How to handle substances safely.
o Steps employees shall take to protect themselves from hazards, including control procedures, work
practices, and PPE.
o Steps the employer has taken to reduce or prevent exposure to hazardous chemicals.
o Emergency response procedures.
R03-C07C01 – Construction Phase Health & Safety Management Plan Rev. 00 Page 46 of 66
ABDUL MOHSEN AL TAMIMI CONTRACTING COMPANY
Coastal Village Sports and Beach Club
Construction Health and Safety Management Plan
Revision # 00 Date of issue Oct. 28, 2023
16.8 Documentation
The records custodian maintains a record of all training or instruction given to employees, using an acceptable
training form. This form is also maintained as a record of training. AMT maintains project records at the site for
the duration of the project and archives them for a minimum retention time of 10 years from creation date.
17.1 Requirements
• Identify the clear roles and responsibilities of individuals, RSG departments, Facilities Management
Service Provider, RSG Contractors and visitors.
• Identify the potential emergency specific to the location.
• Establishing an emergency response action and arrangements.
• Training and competency requirements.
• Compliance to applicable legal and other requirements.
• Establish communication process, notification channels and emergency contact list.
• Evacuation layout and guidance.
• Appendix A – Emergency Man-Overboard.
• Appendix B - Emergency Operation Center (EOC)
R03-C07C01 – Construction Phase Health & Safety Management Plan Rev. 00 Page 47 of 66
ABDUL MOHSEN AL TAMIMI CONTRACTING COMPANY
Coastal Village Sports and Beach Club
Construction Health and Safety Management Plan
Revision # 00 Date of issue Oct. 28, 2023
R03-C07C01 – Construction Phase Health & Safety Management Plan Rev. 00 Page 48 of 66
ABDUL MOHSEN AL TAMIMI CONTRACTING COMPANY
Coastal Village Sports and Beach Club
Construction Health and Safety Management Plan
Revision # 00 Date of issue Oct. 28, 2023
To ensure AMT compliance, RSG may verify conformity with this requirement through conducting regular
inspections and audit of PTW activities. Activities to be included within AMT’s Permit to Work systems shall
include but not limited to:
• Excavation Works
• Confined Spaces
• Work at Height
• Electrical/Mechanical Isolation
• Hot Work
• Cold Work
R03-C07C01 – Construction Phase Health & Safety Management Plan Rev. 00 Page 49 of 66
ABDUL MOHSEN AL TAMIMI CONTRACTING COMPANY
Coastal Village Sports and Beach Club
Construction Health and Safety Management Plan
Revision # 00 Date of issue Oct. 28, 2023
• Lifting Activity
• Night/Holiday/extended work activities etc.
18.1 Responsibilities
Project Manager
The Project Manager shall identify all requirements for permit to work arrangements from the recognized
hazards, results of the specific job risk assessment prior to start of any work.
R03-C07C01 – Construction Phase Health & Safety Management Plan Rev. 00 Page 50 of 66
ABDUL MOHSEN AL TAMIMI CONTRACTING COMPANY
Coastal Village Sports and Beach Club
Construction Health and Safety Management Plan
Revision # 00 Date of issue Oct. 28, 2023
• Before starting work on any excavation or trench, utility services companies or owners will be contacted
within established or customary local response times, advised of the proposed work, and asked to establish
the location of the utility underground installations (such as sewer, telephone, water, fuel, electric, gas lines
etc.) prior to the start of actual excavation.
• When utility companies or owners cannot respond to a request to locate underground utility installations
within 24 hours (unless a longer period is required by state or local law), or cannot establish the exact
location of these installations, AMT may proceed by notifying the employer with caution and using an
approved detection equipment or other acceptable means to locate utility installations.
• When excavation operations approach the estimated location of underground installations, the exact
location of the installations will be determined by safe and acceptable means, such as hand digging and pot
holing.
• While the excavation is open, underground installations will be protected, supported, or removed as
necessary to safeguard employees.
• Contractors shall ensure that all health and safety checks have been performed and necessary controls are
established prior to any work proceeding inside an excavated space.
• All contractors must obtain PTW authorization from RSG construction team prior to any underground work
going ahead. They must apply in writing using the permit to dig application form TRS-HS-FRM-0096 to get
the necessary approval.
R03-C07C01 – Construction Phase Health & Safety Management Plan Rev. 00 Page 51 of 66
ABDUL MOHSEN AL TAMIMI CONTRACTING COMPANY
Coastal Village Sports and Beach Club
Construction Health and Safety Management Plan
Revision # 00 Date of issue Oct. 28, 2023
18.4 Procedure
18.4.1 General
A Permit to Work system is a formal written system used to control certain types of work, which are identified
as potentially hazardous. Essential features of a Permit to Work system are:
1. Clear identification of who may authorize particular jobs,
2. Training and instruction in the issue and use of permits.
3. Monitoring and auditing to ensure that the system works as intended.
R03-C07C01 – Construction Phase Health & Safety Management Plan Rev. 00 Page 52 of 66
ABDUL MOHSEN AL TAMIMI CONTRACTING COMPANY
Coastal Village Sports and Beach Club
Construction Health and Safety Management Plan
Revision # 00 Date of issue Oct. 28, 2023
a. Cross Reference
1. It is important to make sure that one activity under a Permit to Work does not create danger
for another ongoing activity.
2. The site HEALTH & SAFETY team should be aware of potential interaction and should check
when a permit is prepared whether it impinges on one already issued.
b. Permit Revalidation
1. When a permit is authorized by site HEALTH & SAFETY team, it will have a time expiry placed on
it. This may vary form a few hours to a full shift, depending upon the nature of the work being
undertaken and the frequency at which the activity is repeated.
2. If, at the end of this time period, the work being controlled by the permit is not complete the
permit may be revalidated by the responsible person, who shall ensure, together with the site
HEALTH & SAFETY team, that the original conditions required by the permit are still being met.
18.4.7 Review
The Permit to Work system will be reviewed regularly to assess its effectiveness and amended and updated as
necessary.
The purpose of this procedure defines the requirements for site based incentive and disciplinary schemes. These
schemes will vary from project implementation. This procedure does not apply or affect existing incentive and
disciplinary schemes run by subcontractors for their own personnel. It is to motivate all personnel working on
R03-C07C01 – Construction Phase Health & Safety Management Plan Rev. 00 Page 53 of 66
ABDUL MOHSEN AL TAMIMI CONTRACTING COMPANY
Coastal Village Sports and Beach Club
Construction Health and Safety Management Plan
Revision # 00 Date of issue Oct. 28, 2023
site to work safely, creating awareness and recognition of safe behaviors. In addition, Carelessness or disregard
of accepted health, safety and fire protection standards will not be tolerated. This program will detail in the
disciplinary of the project to all site personnel and the subcontractor will implement a safety related disciplinary
program.
R03-C07C01 – Construction Phase Health & Safety Management Plan Rev. 00 Page 54 of 66
ABDUL MOHSEN AL TAMIMI CONTRACTING COMPANY
Coastal Village Sports and Beach Club
Construction Health and Safety Management Plan
Revision # 00 Date of issue Oct. 28, 2023
R03-C07C01 – Construction Phase Health & Safety Management Plan Rev. 00 Page 55 of 66
ABDUL MOHSEN AL TAMIMI CONTRACTING COMPANY
Coastal Village Sports and Beach Club
Construction Health and Safety Management Plan
Revision # 00 Date of issue Oct. 28, 2023
R03-C07C01 – Construction Phase Health & Safety Management Plan Rev. 00 Page 56 of 66
ABDUL MOHSEN AL TAMIMI CONTRACTING COMPANY
Coastal Village Sports and Beach Club
Construction Health and Safety Management Plan
Revision # 00 Date of issue Oct. 28, 2023
R03-C07C01 – Construction Phase Health & Safety Management Plan Rev. 00 Page 57 of 66
ABDUL MOHSEN AL TAMIMI CONTRACTING COMPANY
Coastal Village Sports and Beach Club
Construction Health and Safety Management Plan
Revision # 00 Date of issue Oct. 28, 2023
R03-C07C01 – Construction Phase Health & Safety Management Plan Rev. 00 Page 58 of 66
ABDUL MOHSEN AL TAMIMI CONTRACTING COMPANY
Coastal Village Sports and Beach Club
Construction Health and Safety Management Plan
Revision # 00 Date of issue Oct. 28, 2023
Labor Law General Arabic shall be the language used for data,
09/27/2005 In Compliance
Occupational records, files, work contracts and the like as
§9 Health and Safety provided for in this Law or in any decision 23/10/1426 H
Requirements issued in implementation of its provisions
as well as the instructions issued by the
employer to his workers.
If the employer uses a foreign language
beside Arabic in any of the mentioned
cases, the Arabic text shall prevail.
R03-C07C01 – Construction Phase Health & Safety Management Plan Rev. 00 Page 59 of 66
ABDUL MOHSEN AL TAMIMI CONTRACTING COMPANY
Coastal Village Sports and Beach Club
Construction Health and Safety Management Plan
Revision # 00 Date of issue Oct. 28, 2023
R03-C07C01 – Construction Phase Health & Safety Management Plan Rev. 00 Page 60 of 66
ABDUL MOHSEN AL TAMIMI CONTRACTING COMPANY
Coastal Village Sports and Beach Club
Construction Health and Safety Management Plan
Revision # 00 Date of issue Oct. 28, 2023
R03-C07C01 – Construction Phase Health & Safety Management Plan Rev. 00 Page 61 of 66
ABDUL MOHSEN AL TAMIMI CONTRACTING COMPANY
Coastal Village Sports and Beach Club
Construction Health and Safety Management Plan
Revision # 00 Date of issue Oct. 28, 2023
R03-C07C01 – Construction Phase Health & Safety Management Plan Rev. 00 Page 62 of 66
ABDUL MOHSEN AL TAMIMI CONTRACTING COMPANY
Coastal Village Sports and Beach Club
Construction Health and Safety Management Plan
Revision # 00 Date of issue Oct. 28, 2023
In
The periods designated for rest, prayers and 09/27/2005
Labor Law Compliance
Employee Medical meals shall not be included in the actual
§ 102 and Well-Being working hours. During such periods, the 23/10/1426 H
Requirements worker shall not be under the employer’s
authority.
The employer shall not require the worker
to remain at the workplace during such
breaks.
Labor Law
Employee Medical Friday shall be the weekly rest day for all In
09/27/2005
§ 104 and Well-Being workers. Compliance
Requirements 23/10/1426 H
After proper notification of the competent
labor office, the employer may replace this
day for some of his workers by any otherday
of the week. The employer shall allow the
workers to perform their religious
obligations. The weekly rest day may not be
compensated by cash.
The weekly rest day shall be at full pay and
shall not be less than twenty-four
consecutive hours.
In
Labor Law Employee Medical The employer shall pay the worker for 09/27/2005 Compliance
and Well-Being overtime working hours an additional
§ 107 23/10/1426 H
Requirements amount equal to the hourly wage plus
٥۰%of his basic wage.
If the firm is operated on the basis of weekly
working hours, the hours in excess of the
hours taken as the criterion shall bedeemed
overtime hours.
R03-C07C01 – Construction Phase Health & Safety Management Plan Rev. 00 Page 63 of 66
ABDUL MOHSEN AL TAMIMI CONTRACTING COMPANY
Coastal Village Sports and Beach Club
Construction Health and Safety Management Plan
Revision # 00 Date of issue Oct. 28, 2023
Royal Decree General Employer must train All workers in basic 15/11/1969 In
# 21 Occupational safety and the use of first-aid kits. Compliance
Health and Safety 6/9/1389 H
Employer must assign A health and safety
Requirements
official shall to ensure that safety
procedures are being followed by all
employees.
Royal Decree Work Environment Employer must post Clear signs for exit 15/11/1969 In
# 21 and Controls doors and windows. Compliance
6/9/1389 H
Employer must post signs illustrating work-
related injuries related to the type of
business.
Employer must provide facilities for fire
prevention and fighting:
(1) Provide suitable evacuation routes.
(2) Provide suitable fire extinguishing
equipment and sufficient personnel
must be trained to use it.
(3) There must be fire alarm system and
personnel must be trained in
responding to fire warnings.
Employer must provide fire safety doors
signs with instructions for fire prevention
must be displayed in inflammable places (in
Arabic & other languages understood by
workers.
R03-C07C01 – Construction Phase Health & Safety Management Plan Rev. 00 Page 64 of 66
ABDUL MOHSEN AL TAMIMI CONTRACTING COMPANY
Coastal Village Sports and Beach Club
Construction Health and Safety Management Plan
Revision # 00 Date of issue Oct. 28, 2023
Employee Medical In
Ministerial The private sector companies and 2010
and Well-Being Compliance
Resolution establishments are not allowed to let their
Requirements
Order # 443 employees work under the sun from 12
p.m. to 3 p.m. during the three-month
period ending on Sept. 15. All employers
have been instructed to ensure their
workers stay out of sun for three hours
during the period. The ministry is keen on
protecting the safety and health of
workers in the private sector and providing
them a secure working environment, away
for exposure to any health hazards.
There will be exemption for outdoor work
ban in some regions of the Kingdom in view
of low temperatures in those areas. “The
branches of the ministry are coordinating
with the governorates of those regions with
regard to taking a decision whether to ban
work under sun or not”. The work ban will
not be applicable to workers of oil and gas
companies or those engaged in emergency
maintenance works.
R03-C07C01 – Construction Phase Health & Safety Management Plan Rev. 00 Page 65 of 66
ABDUL MOHSEN AL TAMIMI CONTRACTING COMPANY
Coastal Village Sports and Beach Club
Construction Health and Safety Management Plan
Revision # 00 Date of issue Oct. 28, 2023
R03-C07C01 – Construction Phase Health & Safety Management Plan Rev. 00 Page 66 of 66