Timeline Ampelmann - Rev.3 (08122023)

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 1

[Open] #

NO ACTIVITY 27/10/23 30/10/23 6/11/23 17/11/23 23/11/23 24/11/23 27/11/23 28/11/23 29/11/23 30/11/23 1/12/23 7/12/23 8/12/23 11/12/23 12/12/23 13/12/23 15/12/23 18/12/23 26/12/23 27/12/23 28/12/23 4/1/24 5/1/24 9/1/24 10/1/24 13/1/24 14/1/24 15/1/24 16/1/24 17/1/24 18/1/24 19/1/24 20/1/24 21/1/24 22/1/24 25/1/24 26/1/24 27/1/24
TECHNICAL
1 TECHNICAL DISCUSSION
DISCUSSION
COP SUBMISSION AND
2 COP SUBMISSION BY MMHE RESUBMISSION BY MMHE

3 COP REVIEW AND APPROVAL BY PCSB COP REVIEW AND APPROVAL BY PCSB
BARCO
LETTER OF LOA ISSUED PO
LOA RECEIVED, REVIEWED RECEIVED
SI/SO RECEIVED BY BARCO CONFIRMATION TO ACKNOWLED
4 AND ACCEPTANCE BY AND
-LOA AND SO TO AMPELMANN RECEIVED BY AMPELMAN BY
BARCO ACKNOWLE
BARCO N BY BARCO AMPELMANN
DGED SO
ENGINEERING & WORKABILITY ENGINEERING & WORKABILITY STUDY - 4 WEEKS CHALLENGE GRILLAGE DRAWING ISSUANCE BY AMPELMANN 3RD
5 PARTY - 2 WEEKS
STUDY SESSION
FABRICATION OF GRILLAGE AT SIBU FABRICATION OF GRILLAGE AT SIBU YARD - 3 WEEKS
6
YARD
AMPELMANN
7 WORK PERMIT APPLICATION BY AMPELMANN - 4 WEEKS OPERATOR
WORK PERMIT ETC. AVAILABILITY
VERIFICATION BY CLIENT
LIVE VIDEO WITNESS
8 -To perform live video witness for
FOR FAT
FAT
MOB AMPELMANN FROM
9 NETHERLANDS TO BINTULU (SEA MOB AMPELMANN FROM NETHERLAND TO BINTULU (SEA FREIGHT) - 2 WEEKS
FREIGHT)
CLASS APPROVAL FOR AMPELMANN CLASS APPROVAL FOR AMPELMANN INSTALLATION - 1 WEEK
10
INSTALLATION
MODIFICATION AT CS5 BEFORE MODIFICATION AT CS5 BEFORE GRILLAGE INSTALLATION - 1 WEEK
11
GRILLAGE INSTALLATION
12 PETI/ESP FOR AMPELMANN
SEAFASTENING AT
13 MOB GRILLAGE TO KS FIELD
AHTS & MOB
INSTALLATION OF GRILLAGE AT CS5 - 3
14 INSTALLATION OF GRILLAGE AT CS5 DAYS
MOB AMPELMANN FROM BINTULU MOB FROM BINTULU TO
15 KS FIELD
TO KS FIELD
INSTALLATION OF
16 AMPELMANN INCLUDING
INSTALLATION OF AMPELMANN COMMISSIONING - 4 DAYS

REMARKS

based on weather condition