J4C Construction Mumbai

Pvt.Ltd.
Document No. REV: 00 18/12/2023
Method statement of Site Installation Work
J4C/BOM10/MOS/001 Site : BOM -10

Contractor J4C Construction Mumbai Pvt.Ltd.

Client DIGITAL CONNEXION

Consultant CBRE

REV. Date of Description Prepared Checked Approved Approved


Rev. by by by PM by Client
J4C J4C

1
J4C Construction Mumbai
Pvt.Ltd.
Document No. REV: 00 18/12/2023
Method statement of Site Installation Work
J4C/BOM10/MOS/001 Site : BOM -10

TABEL OF CONTENT

SR. No. CONTENT Page No.


1 PURPOSE 3
2 SCOPE 3
3 RESPONSIBILITY OF KEY PERSONNEL 3
3.1 PROJECT MANAGER 3
3.2 CONSTRUCTION MANAGER 3
3.3 SITE ENGINEER 4
3.4 SAFETY OFFICER 4
3.5 SUPERVISOR 4
3.6 ENVIRONMENTAL OFFICER 5
4 RESOURCES 5
5 HEALTH AND SAFETY 5
5.1 HAZARD IDENTIFICATION AND RISK ASSESSMENT 5
5.2 PERSONNEL PROTECTIVE EQUIPMENTS 5
6 GENERAL 6
7 CONSTRUCTION METHOLODOLOGY- TASK STATEMENTS 7
7.1 TASK STATEMENT FOR CLEARING AND GRUBBING 8
7.2 TASK STATEMENT FOR SURVEY AND SETTING OUT 9
7.3 TASK STATEMENT FOR SITE GRADING 11
7.4 TASK STATEMENT FOR OFFICE CONTAINER INSTALLATION 12
7.5 TASK STATEMENT FOR SEWERAGE SYSTEM 13
7.6 TASK STATEMENT FOR TEMPORARY SHED & SAFETY 15
CONTAINER
7.7 TASK STATEMENT FOR INTERNAL FURNITURE/ELECTRICAL 16
INSTALLATION
8 ANNEXURE-A 16
8.1 HAZARD IDENTIFICATION AND RISK ASSESSMENT 17
1. PURPOSE

2
J4C Construction Mumbai
Pvt.Ltd.
Document No. REV: 00 18/12/2023
Method statement of Site Installation Work
J4C/BOM10/MOS/001 Site : BOM -10

The purpose of this method statement is to identify the


tasks involved in this work and to explain all the involved
parties’ step by step procedures adapted.
To ensure the works are carried out in a Safe, efficient
and environmentally friendly manner.

2. SCOPE

This method statement covers the Site installation area


for BOM 10 project only.

3. RESPONSIBILITIES OF KEY PERSONNEL

3.1 Project Manager

• Responsible for overall activity of the project.


• Coordinate with J4C site, HO team, CBRE team
and DIGITAL CONNEXION team for compliance
to all project requirements.
• Attends Weekly site walkthrough for HSE issues
3.2Construction Manager
• Responsible for overall Implementation,
monitoring and control of all activities.
• Interact with site team and DIGITAL
CONNEXION team and CBRE team to sort-out
all technical and HSE issues for the smooth
functioning of site.
• Attends Weekly site walkthrough for HSE
issues in the absence of Project Manager

3
J4C Construction Mumbai
Pvt.Ltd.
Document No. REV: 00 18/12/2023
Method statement of Site Installation Work
J4C/BOM10/MOS/001 Site : BOM -10

3.3 Site Engineer

• Responsible for all the activities that being carried out at


site.
• Coordinate with site team DIGITAL
CONNEXION Supervisory team for
compliance to Technical and HSE guidelines.
• Attends daily Toolbox meeting and work briefing to
workers.
• Attends Weekly site walkthrough for HSE issues.
• Prepare site level DPR and get it endorsed to DIGITAL
CONNEXION supervisory team.
3.4 Safety Officer
• Conduct necessary induction training for workers.
• Responsible for ensuring that all
applicable safety and environmental
measures are implemented during the
period of construction.
• Ensure that recipients understand method statements
and construction.
• Attends Weekly site walkthrough for HSE issues
3.5 Supervisor
• Responsible for material handling, loading and
unloading of equipment observe safety and
quality standards, materials, tools safekeeping,
monitor labor workforce.
• Executing the work as per all specification and schedule.
• Ensure our boundaries for office and camp area.
• Read the drawing and execute the work according to the
drawing.
• Ensure that brief the TASC to workmen related to the
concern job.

4
J4C Construction Mumbai
Pvt.Ltd.
Document No. REV: 00 18/12/2023
Method statement of Site Installation Work
J4C/BOM10/MOS/001 Site : BOM -10

• Work must be executed according to the approved


method of statement and HIRA must be followed to
eliminate the risk involved in the activities.
• Ensured all safety measures in place during working at
height.
• Monitoring separation of solid waste.
• Monitoring daily housekeeping

3.6 Environmental Officer


• Monitor and construction of silt fences.
• Control of erosion.
• Monitoring Top soil striping and Stock pile.
• Monitoring unsuitable material stockpile.
• Monitoring rehabilitation of affected area.

• Waste management and control.


• Conducting focus audit on environmental activities.

• Ensuring complying general environmental standard.

• Attends Weekly site walkthrough for HSE issues.


Ensure requirement of land clearance certificate are
strictly complied with.

4. RESOURCES
Use actual resources used like JCB, Farana crane,
-
Equipment’s Tools Materials
Crane 80 Aluminum frame Ladder Cement I Sand
Excavator Lifting belts Welding Electrodes
Back Hoe Lifting Slings Rebar / Structural
steel
Grader D 'Shackles Ready mixed
Concrete
Compactor -5 tons Welding Kit Slit fence

5
J4C Construction Mumbai
Pvt.Ltd.
Document No. REV: 00 18/12/2023
Method statement of Site Installation Work
J4C/BOM10/MOS/001 Site : BOM -10

Trailer Tape & Line threads Geotextile sheet


Plate compactor Spirit level
Dumper Wheelbarrow
Loader Shovel
PTC Vibrio Hammer Cutlasses
Platform Water Tank

5. HEALTH AND SAFETY

5.1 HAZARD IDENTIFICATION AND RISK ASSESSMENT

Please refer to attached individual Task HIRA for this section

5.2 Personal Protective Equipment

• Hard Helmet
• Safety Shoes / Boot
• Leather & Cotton Gloves & chemical resistance gloves.
• Goggles/ Safety glasses (At all time)
• High Visibility vest
• Double lanyard and shock absorber with Full body
Harness

• Welding Shield

6. GENERAL

• All workers shall be made aware of the activities


being carried out, Safe work procedure and
emergency response plan.
• Working area will be barricaded locally, signboards,
traffic control etc. will be arranged to prevent entry
of the other unauthorized workers.

• The Task methodology shall be explained to all the key


personnel and workmen involved in that activity and standing
instructions will be given.

6
J4C Construction Mumbai
Pvt.Ltd.
Document No. REV: 00 18/12/2023
Method statement of Site Installation Work
J4C/BOM10/MOS/001 Site : BOM -10

• Safety induction will be done for all workers before carrying


out the job.
• Tool box meeting will be conducted daily for each activity.

• Work area shall be cleaned from the debris, steel waste, paint
etc.
• First aid facilities will be available at site.

• Trained First-Aider shall be deployed at site.

7. CONSTRUCTION METHODOLOGY

1. Clearing and Grubbing

2. Survey work

3. Site Grading

4. Office Container Installation

5. Sewage System
6. Temporary Shed & Safety room.
7. Internal furniture/Electrical Installation.

7
J4C Construction Mumbai
Pvt.Ltd.
Document No. REV: 00 18/12/2023
Method statement of Site Installation Work
J4C/BOM10/MOS/001 Site : BOM -10

7.1 Task statement for Clearing and Grubbing


USE actual photographs of BOM10 site Images

• After the area is approved and allotted, necessary


recognition survey of the area shall be done with
DIGITAL CONNEXION/ CBRE's as per Environmental
standard manual.
• All the bushes shall be cleared by machinery and
necessary care must be taken to drive away poisonous
insects and snakes if any.
• The site features like pits, manholes, structures, cable
ducts, water ducts, cable line and others shall be
identified and barricaded with safety tapes.
• Top soil is to be striped only from those area that will be
disturbed by any activity.
• Sediment basins, diversions and other controls for storm
water and sediment control must be put in place before
starting to striping to soil or clear & grub.

8
J4C Construction Mumbai
Pvt.Ltd.
Document No. REV: 00 18/12/2023
Method statement of Site Installation Work
J4C/BOM10/MOS/001 Site : BOM -10

• Before striping the topsoil, identify topsoil storage area.


• Striping of the topsoil will be done manually if the area is
infested with services and or by Dozer/Pay loader if the area is
free of any utilities.
• Installation of Erosion and sediment control is to be arrange as
per J4C
• Environmental aspect.
• All top soil and organic material to be stored in a top
soil stock pit area as per site layouts and prepared as per
standards and specification for top soil stock pits.
• Banks man/ Flag man shall direct the movement of dumper,
dozer and
• Excavator.
• Traffic management plan must be available on site.

7.2 Task statement for Survey and Setting out


USE actual photographs of BOM10 site Images

• Barricade the area and put up necessary warning signs.


• Make a walk through and identify the available
project Bench Mark (BM}, confirm the
coordinates, Reduce Level (RL) and prepare the

9
J4C Construction Mumbai
Pvt.Ltd.
Document No. REV: 00 18/12/2023
Method statement of Site Installation Work
J4C/BOM10/MOS/001 Site : BOM -10

survey path and setting out as per drawings.

• Check all the survey equipment’s for


calibration and measuring tapes for cut and
alternation
• Ensure Survey equipment and cools are properly
handled, stored and always kept under shade.
• No vehicle is allowed in to the setting out area
and necessary precautions shall be taken to
post a signal man if the survey is carried out
along the road.
• Carry out the survey and mark the points with
wooden sieges printed with white color to
improve the visibility and to avoid tripping of
workers.
• Safeguard the transferred BM and control
Points with barricading tapes.
• All the ground marking shall be carried out with lime
powder Or non-hazardous marking powder. On
completion of setting out all the temporary pegs must be
removed.
• Site Benchmarks & Control Points and all
activities (item wise) workplace & post
survey work should be approved by
DIGITAL CONNEXION/ J4C surveyor.

10
J4C Construction Mumbai
Pvt.Ltd.
Document No. REV: 00 18/12/2023
Method statement of Site Installation Work
J4C/BOM10/MOS/001 Site : BOM -10

7.3 Task statement for Site Grading


USE actual photographs of BOM10 site Images

• Prepare necessary survey drawing with


necessary gradient for proper drainage
of water.
• Identify and barricade the particular days of work area.
• Based on the prepared survey drawings mark the areas of
cut and fill.
• Inspect and identify underground utilities
by digging with the help of excavator/hand
tools and mark them and inform to J4C
/DIGITAL CONNEXION representative.

• Signal man shall be deployed at site to guide the movement of


equipment.
• Suitable soil originated from excavation will be-hauled and
used as fill material within site limits
• Soil to be inspected by QC Engineer and DIGITAL
CONNEXION representative and shall be checked
with CBRE representative. Unsuitable soil
originated from e x c a v a t i o n and striping

11
J4C Construction Mumbai
Pvt.Ltd.
Document No. REV: 00 18/12/2023
Method statement of Site Installation Work
J4C/BOM10/MOS/001 Site : BOM -10

works will b e hauled to a designated / disposal


area as per DIGITAL CONNEXION /CBRE
representative instructions.
• Erosion and sediment control to be installed before dumping of
subsoil.
• Storm water trenches/ ditches to be installed.
• Laying of backfilling soil layer wise filled with testing of compaction
level.
• Filling works shall be carried out by means of
hauling fill material from approved /borrow
pits.
• Caution must be taken to avoid spillage on
roads and suitable no. of workers shall be
deployed to clear the spillage (if any).

7.4 Task statement for Office Container Installation


USE actual photographs of BOM10 site Images

• Porta cabin location is marked as per the layout.


• Working area shall be barricaded from unauthorized person.
• Wooden/ Concrete sleeper shall be placed as per the layout.
• 30T crane shall be used for lifting and placing of Office container.
• Wire rope1" thickness type of slings to used,
and competent rigger shall climb on the
12
J4C Construction Mumbai
Pvt.Ltd.
Document No. REV: 00 18/12/2023
Method statement of Site Installation Work
J4C/BOM10/MOS/001 Site : BOM -10

container by using safe inspected ladder,


further hook and ensure that all the 4
corners of the container is properly slinged
with I- bolt and once again he ensures that all
the latches are properly tightened.
• During period of lifting and shifting vehicular
Movement shall be restricted for the duration
period.
• After placing of Container, Interior arrangement
like furniture and electrical Installation shall be
done.
• Before start of the job, Toilet facility for Staff
and workers shall be done outside of
container near the premises.

7.5 Task statement for Sewerage System


USE actual photographs of BOM10 site Images

• Plan and prepare the necessary installation drawings


based on the site levels with suitable gradient.
• The erection area shall be barricaded with barricading tape.
• Setting out will be done with marking lime power / or suitable

13
J4C Construction Mumbai
Pvt.Ltd.
Document No. REV: 00 18/12/2023
Method statement of Site Installation Work
J4C/BOM10/MOS/001 Site : BOM -10

wooden pegs.
• Signal man and riggers will be deployed for guiding the
excavator and dumpers.
• Excavation for ditch shall be carried out by excavator
and immediately laid with PVC pipes and back filled.
Warning tape shall be installed.
• Septic tank shall be construct in three
compartment o r chamber with underflow system
before it goes to the soak.
• The following sequence shall be followed as per site
requirement.
• Brick lining work will be done according to
the drawing and constructed in chambers.
Flooring of the tank shall be concreted.
• Inlet and outlet pipe connection shall be
done after the concrete work is completed
and finally Laying of pre cast cover slab
and sealing of sides to be done.
• Utility fittings shall be connected and tested for leakages.
• Excavation safety consideration- inspection- sloping - soil placement.
• Activator for assisting biological degrading of
sewerage to be added to septic tank.
• Drain will be at least 5 meters away from
septic tank and 100 meters away from
boreholes. (Septic Tank and drain drawing will
be submitted separately).

14
J4C Construction Mumbai
Pvt.Ltd.
Document No. REV: 00 18/12/2023
Method statement of Site Installation Work
J4C/BOM10/MOS/001 Site : BOM -10

7.6 Task Statement for Temporary Shed, Induction Room & First
aid Centre
USE actual photographs of BOM10 site Images

• Area shall be cleared for temporary shed & Safety facility.


• Store and Rest room area shall be marked with the help
of line length and
L i me powder.

• Area shall be levelled with cunning and filling of soil.

• Precast Foundation Blocks shall be installed for Safety


containers.
• 2 no’s Safety containers shall be installed with the help of
30T crane.

• Shed work shall be done adjacent to the Safety container.

• Lean (PCC) concreting shall be done for floor.


• Wooden frame shall be erected for shed.
• After framework: PVC Sheets shall be installed for roofing.

15
J4C Construction Mumbai
Pvt.Ltd.
Document No. REV: 00 18/12/2023
Method statement of Site Installation Work
J4C/BOM10/MOS/001 Site : BOM -10

• Benches shall be provide for sitting arrangement.


• Drinking water facility shall be provided at shed.
• Before start the work, pit latrine facility shall be provide
outside of shed at the corner of fencing.
• Disposal of solid waste from the Mobile toilet
shall be pumped out regularly by
sanitation disposal chamber
compartment type septic tank is to be
provided at site.
• Septic tank design and layout to be
submitted to project environmental team
for review and approval prior to start
construction.

7.7 Task Statement for Internal furniture


• Internal office furniture i.e., Table, Chair, cupboard,
Conference table etc. for J4C/BAM DL
representative shall be provided.

7.8 Task Statement for Electrical Installation

• After positioning of office container Electrical Installation


i.e., Internet line,
Power line, lighting arrangement shall be done.

• After Electrical and furniture Installation,


computers shall be setup at designated place.

• Need cables to be installed as per project standard-


Demarcated.

• Tripping circuit/earth leakage required 220V distribution


boxes.

• All electrical work is inspected and verified by


appointed electrical J4C/BM DLR representative
will be issued only if compliance is verified.

16
J4C Construction Mumbai
Pvt.Ltd.
Document No. REV: 00 18/12/2023
Method statement of Site Installation Work
J4C/BOM10/MOS/001 Site : BOM -10

8. ANNEXURE:-A

Refer Hazard Identification and Risk Assessment

17
J4C Construction Mumbai
Pvt.Ltd.
Document No. REV: 00 18/12/2023
Method statement of Site Installation Work
J4C/BOM10/MOS/001 Site : BOM -10

J4C Construction Mumbai Pvt.Ltd.


Date:-15.12.23 Rev. Date :
PAGE No. 01 of 01
Activity: Site Office (Porta cabin)Installation
S Category Work Hazard Conseque Existing / Proba S P R Risk Additional S P R Risk Date Re Suppor
r. /Area Activity nces / Risk Present ble Lev Risk Control Lev of vis ting
N Risk accid el Measure el inclu on Docum
o. Control ent / (H/M (H/M sion dat ents
measure ill /L) : /L) : e
s healt
h&
perso
n at
risk.
Severit Probabil Ris Risk Level (H/M/L) : Severit Probabil Ris Risk Level (H/M/L) :
y(S) ity(P) k y(S) ity(P) k
fact Fac
or tor
1 A Gate Surface a)lack of Hand a) Proper Involv 3 2 6 M a) Proper 3 1 3 L 15.12.
area preparation knowledg Injury ,Finge housekeep ed support to be 23
e the r Injury, Leg ing and worker provided to
work to injury clear s, the staked
be passage labour material.
performe maintaine s b)Material
d d at the shall not be
b)General work allowed to
Slip/Trip location. stacked near
hazard b) Storage the edge of
stand installation
provided pit
for
material
stacking.
c)
Required
PPEs used
by the

18
J4C Construction Mumbai
Pvt.Ltd.
Document No. REV: 00 18/12/2023
Method statement of Site Installation Work
J4C/BOM10/MOS/001 Site : BOM -10

workmen
during the
work.
2 Heavy a) Collide Hand Injury, a) Always Involv 3 2 6 M a)Front visor 3 1 3 L
Vehicle of vehicle Finger follow the ed and side
moment b) Contact Injury, leg rod safety worker mirrors must
with injury, rules s, clean for
overhead material/Pro b) Follow Loader effective
live power perty instruction /rigger vision b)All
cables. c) damaged from s indicators
Incompet single man and horn and
ency of or flagman rare camera
driver/op while must be in
erator. reversing working
d) Vehicle the vehicle condition
c)Wheel
Overloadi c)Only
chokers are
ng authorised
carried with
operator/
vehicle
driver is
d)First aid
allowed to box &fire
worked)TP extinguisher
I &other also kept in
legal drivers cabin,
document
s must be
check
thoroughly
before
entering in
premises
e)Require
d PPEs
used by
the
workmen
during the
work.

19
J4C Construction Mumbai
Pvt.Ltd.
Document No. REV: 00 18/12/2023
Method statement of Site Installation Work
J4C/BOM10/MOS/001 Site : BOM -10

3 Heavy lift a)object Hand Injury, a)Only Involv 3 3 9 M a)TBT 3 1 3 L


with crane falling Finger Standard ed conducted
from Injury, Head lifting worker before
lifted load Injury. technique s, starting the
b)contact s and tools work b)Load
with are indicator and
overhead lowered other safety
power b)Only devices must
cables c) Trained be inspect
resting on and before
uneven Competen starting the
surface t work’s)Comp
etent
d)incomp manpower
signalman
etency of should be
must
operator allowed to
allocated for
e)bad work
operator
weather c)Lifting assistance’s)A
conditions plan must dequate
be make in illumination
considera must be
tion provided in
before night shift.
starting
the work
c) Area
must be
barricaded
with highly
visible
markings
d) Lifting
machine
TPI and
other legal
document
must be
inspect

20
J4C Construction Mumbai
Pvt.Ltd.
Document No. REV: 00 18/12/2023
Method statement of Site Installation Work
J4C/BOM10/MOS/001 Site : BOM -10

thoroughly
e) All
required
PPEs used
by the
workmen
who are
involved in
the work.
4 Lifting/ a) Risk of Hand a) area of Involv 2 3 6 M a)Monitors the 2 2 4 L
Shifting of load Injury ,Finge crane ed cranes lifting
portable shifting r Injury, leg radius worker limit do not
cabin due to injury must e s, overload the
incorrect barricaded Carpe crane’s)Do not
rigging no worker nters operate in bad
b)Overhe should weather
ad power work or condition c)
lines pass Spotter must
c)poor below the me assigned
visibility suspended to correct the
due to load b) sign
size of Load must
cabinet d) not be
swing over
the
workers
are
working
c)riggers
must be
ensure or
double
check for
correct
slinging
method
and

21
J4C Construction Mumbai
Pvt.Ltd.
Document No. REV: 00 18/12/2023
Method statement of Site Installation Work
J4C/BOM10/MOS/001 Site : BOM -10

everything
on load is
secured)d
o not
operate
near
power
cables
without
taking
authorised
permission
from the
power
departme
nt.
5 Welding/ a)Fire Hand a) obtain Involv 2 3 6 M a) Suitable 2 2 4 L
Cutting work hazard Injury ,Finge permit ed fire
b)Electroc r Injury, from worker extinguisher
ution c) Head authorised s, made
agronomi Injury,Burn, authority Carpe available
cs hazards Breathig for Hot nters before work
issue work b)All starts b) No
machinery unauthorised
and PPEs personal is
must be allowed
thoroughly c)Effective
inspected supervision is
provided
and
tagged C)
Only
competent
personal is
allowed
for HOT
work
D)Area

22
J4C Construction Mumbai
Pvt.Ltd.
Document No. REV: 00 18/12/2023
Method statement of Site Installation Work
J4C/BOM10/MOS/001 Site : BOM -10

must b
barricaded
and free
from any
other
combustib
le
material.
6 Equipment a) Hand a)clear Involv 2 3 6 M a) operator 2 2 4 L
movement slip ,trip Injury ,Finge walk ways ed /Driver must
for septic fall r Injury, Leg work area worker possess valid
tank b)Stuck by injury, air of s, liscense,b)
installation heavy pollution ,no equipment Impart
object / ise pollution s,b) mark training for
vehicle identify or defensive
moment barricade driving
c) Flying other c)Vehicle
debris d) obstructio should be
Vibration ns ,c) operated in
Provide safe speed
proper limit) Horn
access to and sound
person an must on
avoid fall during
of person reversing
d) Use vehicle) EAR
proper plug must be
PPE provided to
minimize noise
pollution risk
7 Excavation a)calve in) Hand a) before Involv 3 3 9 H a)Before start 2 2 4 L
for septic undergro Injury ,Finge starting ed of work
tank with und r Injury, Leg the work worker inspect all
excavator utilities c) injury,chanc follow the s, safety features
access/eg ess of excavation are working or
ress disability permit) not)No vehicle
Excavated movements

23
J4C Construction Mumbai
Pvt.Ltd.
Document No. REV: 00 18/12/2023
Method statement of Site Installation Work
J4C/BOM10/MOS/001 Site : BOM -10

soil must are allowed


be kept near
one meter excavated
way from area c)One
excavated flag man
area c) should be
safe deployed o
access to attend the
be equipment
provided movement
to be get d)Before start
in or out) of work know
Before the weather
starting forecast
the work
area must
be
barricade
to avoid
untheorize
d entry) If
power line
is present
then
inform
authorised
person to
isolate it)
Proper
slop to be
maintain
to avoid
cave in or
collapse of
soil)
proper
warning

24
J4C Construction Mumbai
Pvt.Ltd.
Document No. REV: 00 18/12/2023
Method statement of Site Installation Work
J4C/BOM10/MOS/001 Site : BOM -10

signs to be
displayed.
8 Shifting of a) Hand Injury, a) Wheel Involv 2 3 6 M a)Training 2 2 4 L
septic tank slip ,trip Finger stopper ed must be
material fall b) Injury, Head must be worker provided for
(Block,Ceme Flying Injury. used for s, safe handling
nt,sand debris sudden and storing of
etc.,) c)Back movement material)
injury) of vehicle material must
falling of for loading store as per
material /unloading size, shape
during )Use and
movemen proper weight)Effectiv
t, PPE to e supervision
avoid any must be
injury)Acc provided till
ess of end of
loading worked)
unloading
area
should be
cleaned)M
aterial
should be
handle
with
proper
handling
procedure
to avoid
any back
injury)Mat
erial must
be stacked
in proper
mannered
)No over

25
J4C Construction Mumbai
Pvt.Ltd.
Document No. REV: 00 18/12/2023
Method statement of Site Installation Work
J4C/BOM10/MOS/001 Site : BOM -10

loading of
material
allowed

26