Professional Documents
Culture Documents
MOS - Site Installation Work
MOS - Site Installation Work
Pvt.Ltd.
Document No. REV: 00 18/12/2023
Method statement of Site Installation Work
J4C/BOM10/MOS/001 Site : BOM -10
Consultant CBRE
1
J4C Construction Mumbai
Pvt.Ltd.
Document No. REV: 00 18/12/2023
Method statement of Site Installation Work
J4C/BOM10/MOS/001 Site : BOM -10
TABEL OF CONTENT
2
J4C Construction Mumbai
Pvt.Ltd.
Document No. REV: 00 18/12/2023
Method statement of Site Installation Work
J4C/BOM10/MOS/001 Site : BOM -10
2. SCOPE
3
J4C Construction Mumbai
Pvt.Ltd.
Document No. REV: 00 18/12/2023
Method statement of Site Installation Work
J4C/BOM10/MOS/001 Site : BOM -10
4
J4C Construction Mumbai
Pvt.Ltd.
Document No. REV: 00 18/12/2023
Method statement of Site Installation Work
J4C/BOM10/MOS/001 Site : BOM -10
4. RESOURCES
Use actual resources used like JCB, Farana crane,
-
Equipment’s Tools Materials
Crane 80 Aluminum frame Ladder Cement I Sand
Excavator Lifting belts Welding Electrodes
Back Hoe Lifting Slings Rebar / Structural
steel
Grader D 'Shackles Ready mixed
Concrete
Compactor -5 tons Welding Kit Slit fence
5
J4C Construction Mumbai
Pvt.Ltd.
Document No. REV: 00 18/12/2023
Method statement of Site Installation Work
J4C/BOM10/MOS/001 Site : BOM -10
• Hard Helmet
• Safety Shoes / Boot
• Leather & Cotton Gloves & chemical resistance gloves.
• Goggles/ Safety glasses (At all time)
• High Visibility vest
• Double lanyard and shock absorber with Full body
Harness
• Welding Shield
6. GENERAL
6
J4C Construction Mumbai
Pvt.Ltd.
Document No. REV: 00 18/12/2023
Method statement of Site Installation Work
J4C/BOM10/MOS/001 Site : BOM -10
• Work area shall be cleaned from the debris, steel waste, paint
etc.
• First aid facilities will be available at site.
7. CONSTRUCTION METHODOLOGY
2. Survey work
3. Site Grading
5. Sewage System
6. Temporary Shed & Safety room.
7. Internal furniture/Electrical Installation.
7
J4C Construction Mumbai
Pvt.Ltd.
Document No. REV: 00 18/12/2023
Method statement of Site Installation Work
J4C/BOM10/MOS/001 Site : BOM -10
8
J4C Construction Mumbai
Pvt.Ltd.
Document No. REV: 00 18/12/2023
Method statement of Site Installation Work
J4C/BOM10/MOS/001 Site : BOM -10
9
J4C Construction Mumbai
Pvt.Ltd.
Document No. REV: 00 18/12/2023
Method statement of Site Installation Work
J4C/BOM10/MOS/001 Site : BOM -10
10
J4C Construction Mumbai
Pvt.Ltd.
Document No. REV: 00 18/12/2023
Method statement of Site Installation Work
J4C/BOM10/MOS/001 Site : BOM -10
11
J4C Construction Mumbai
Pvt.Ltd.
Document No. REV: 00 18/12/2023
Method statement of Site Installation Work
J4C/BOM10/MOS/001 Site : BOM -10
13
J4C Construction Mumbai
Pvt.Ltd.
Document No. REV: 00 18/12/2023
Method statement of Site Installation Work
J4C/BOM10/MOS/001 Site : BOM -10
wooden pegs.
• Signal man and riggers will be deployed for guiding the
excavator and dumpers.
• Excavation for ditch shall be carried out by excavator
and immediately laid with PVC pipes and back filled.
Warning tape shall be installed.
• Septic tank shall be construct in three
compartment o r chamber with underflow system
before it goes to the soak.
• The following sequence shall be followed as per site
requirement.
• Brick lining work will be done according to
the drawing and constructed in chambers.
Flooring of the tank shall be concreted.
• Inlet and outlet pipe connection shall be
done after the concrete work is completed
and finally Laying of pre cast cover slab
and sealing of sides to be done.
• Utility fittings shall be connected and tested for leakages.
• Excavation safety consideration- inspection- sloping - soil placement.
• Activator for assisting biological degrading of
sewerage to be added to septic tank.
• Drain will be at least 5 meters away from
septic tank and 100 meters away from
boreholes. (Septic Tank and drain drawing will
be submitted separately).
14
J4C Construction Mumbai
Pvt.Ltd.
Document No. REV: 00 18/12/2023
Method statement of Site Installation Work
J4C/BOM10/MOS/001 Site : BOM -10
7.6 Task Statement for Temporary Shed, Induction Room & First
aid Centre
USE actual photographs of BOM10 site Images
15
J4C Construction Mumbai
Pvt.Ltd.
Document No. REV: 00 18/12/2023
Method statement of Site Installation Work
J4C/BOM10/MOS/001 Site : BOM -10
16
J4C Construction Mumbai
Pvt.Ltd.
Document No. REV: 00 18/12/2023
Method statement of Site Installation Work
J4C/BOM10/MOS/001 Site : BOM -10
8. ANNEXURE:-A
17
J4C Construction Mumbai
Pvt.Ltd.
Document No. REV: 00 18/12/2023
Method statement of Site Installation Work
J4C/BOM10/MOS/001 Site : BOM -10
18
J4C Construction Mumbai
Pvt.Ltd.
Document No. REV: 00 18/12/2023
Method statement of Site Installation Work
J4C/BOM10/MOS/001 Site : BOM -10
workmen
during the
work.
2 Heavy a) Collide Hand Injury, a) Always Involv 3 2 6 M a)Front visor 3 1 3 L
Vehicle of vehicle Finger follow the ed and side
moment b) Contact Injury, leg rod safety worker mirrors must
with injury, rules s, clean for
overhead material/Pro b) Follow Loader effective
live power perty instruction /rigger vision b)All
cables. c) damaged from s indicators
Incompet single man and horn and
ency of or flagman rare camera
driver/op while must be in
erator. reversing working
d) Vehicle the vehicle condition
c)Wheel
Overloadi c)Only
chokers are
ng authorised
carried with
operator/
vehicle
driver is
d)First aid
allowed to box &fire
worked)TP extinguisher
I &other also kept in
legal drivers cabin,
document
s must be
check
thoroughly
before
entering in
premises
e)Require
d PPEs
used by
the
workmen
during the
work.
19
J4C Construction Mumbai
Pvt.Ltd.
Document No. REV: 00 18/12/2023
Method statement of Site Installation Work
J4C/BOM10/MOS/001 Site : BOM -10
20
J4C Construction Mumbai
Pvt.Ltd.
Document No. REV: 00 18/12/2023
Method statement of Site Installation Work
J4C/BOM10/MOS/001 Site : BOM -10
thoroughly
e) All
required
PPEs used
by the
workmen
who are
involved in
the work.
4 Lifting/ a) Risk of Hand a) area of Involv 2 3 6 M a)Monitors the 2 2 4 L
Shifting of load Injury ,Finge crane ed cranes lifting
portable shifting r Injury, leg radius worker limit do not
cabin due to injury must e s, overload the
incorrect barricaded Carpe crane’s)Do not
rigging no worker nters operate in bad
b)Overhe should weather
ad power work or condition c)
lines pass Spotter must
c)poor below the me assigned
visibility suspended to correct the
due to load b) sign
size of Load must
cabinet d) not be
swing over
the
workers
are
working
c)riggers
must be
ensure or
double
check for
correct
slinging
method
and
21
J4C Construction Mumbai
Pvt.Ltd.
Document No. REV: 00 18/12/2023
Method statement of Site Installation Work
J4C/BOM10/MOS/001 Site : BOM -10
everything
on load is
secured)d
o not
operate
near
power
cables
without
taking
authorised
permission
from the
power
departme
nt.
5 Welding/ a)Fire Hand a) obtain Involv 2 3 6 M a) Suitable 2 2 4 L
Cutting work hazard Injury ,Finge permit ed fire
b)Electroc r Injury, from worker extinguisher
ution c) Head authorised s, made
agronomi Injury,Burn, authority Carpe available
cs hazards Breathig for Hot nters before work
issue work b)All starts b) No
machinery unauthorised
and PPEs personal is
must be allowed
thoroughly c)Effective
inspected supervision is
provided
and
tagged C)
Only
competent
personal is
allowed
for HOT
work
D)Area
22
J4C Construction Mumbai
Pvt.Ltd.
Document No. REV: 00 18/12/2023
Method statement of Site Installation Work
J4C/BOM10/MOS/001 Site : BOM -10
must b
barricaded
and free
from any
other
combustib
le
material.
6 Equipment a) Hand a)clear Involv 2 3 6 M a) operator 2 2 4 L
movement slip ,trip Injury ,Finge walk ways ed /Driver must
for septic fall r Injury, Leg work area worker possess valid
tank b)Stuck by injury, air of s, liscense,b)
installation heavy pollution ,no equipment Impart
object / ise pollution s,b) mark training for
vehicle identify or defensive
moment barricade driving
c) Flying other c)Vehicle
debris d) obstructio should be
Vibration ns ,c) operated in
Provide safe speed
proper limit) Horn
access to and sound
person an must on
avoid fall during
of person reversing
d) Use vehicle) EAR
proper plug must be
PPE provided to
minimize noise
pollution risk
7 Excavation a)calve in) Hand a) before Involv 3 3 9 H a)Before start 2 2 4 L
for septic undergro Injury ,Finge starting ed of work
tank with und r Injury, Leg the work worker inspect all
excavator utilities c) injury,chanc follow the s, safety features
access/eg ess of excavation are working or
ress disability permit) not)No vehicle
Excavated movements
23
J4C Construction Mumbai
Pvt.Ltd.
Document No. REV: 00 18/12/2023
Method statement of Site Installation Work
J4C/BOM10/MOS/001 Site : BOM -10
24
J4C Construction Mumbai
Pvt.Ltd.
Document No. REV: 00 18/12/2023
Method statement of Site Installation Work
J4C/BOM10/MOS/001 Site : BOM -10
signs to be
displayed.
8 Shifting of a) Hand Injury, a) Wheel Involv 2 3 6 M a)Training 2 2 4 L
septic tank slip ,trip Finger stopper ed must be
material fall b) Injury, Head must be worker provided for
(Block,Ceme Flying Injury. used for s, safe handling
nt,sand debris sudden and storing of
etc.,) c)Back movement material)
injury) of vehicle material must
falling of for loading store as per
material /unloading size, shape
during )Use and
movemen proper weight)Effectiv
t, PPE to e supervision
avoid any must be
injury)Acc provided till
ess of end of
loading worked)
unloading
area
should be
cleaned)M
aterial
should be
handle
with
proper
handling
procedure
to avoid
any back
injury)Mat
erial must
be stacked
in proper
mannered
)No over
25
J4C Construction Mumbai
Pvt.Ltd.
Document No. REV: 00 18/12/2023
Method statement of Site Installation Work
J4C/BOM10/MOS/001 Site : BOM -10
loading of
material
allowed
26