LOCATION :
FENCING WORKS
ACTIVITY BLOCK NO. UNIT TOTAL QTY UNIT COST AMOUNT
DC CABLE
Excavation and civil work for DC Cables SQM. 24942 ₱ 1,200.00 ₱ 29,930,400.00
Sand filling for DC Cables SQM. 24942 ₱ 900.00 ₱ 22,447,800.00
Laying of DC Cables MTRS. 24942 ₱ 600.00 ₱ 14,965,200.00
Laying of auxiliary cable for SCB BLOCK 1-30 MTRS. 24942 ₱ 600.00 ₱ 14,965,200.00
RS 485 Comm. Cable MTRS. 24942 ₱ 600.00 ₱ 14,965,200.00
Warning filling MTRS. 24942 ₱ 75.00 ₱ 1,870,650.00
Soil filling up to NGL SQM. 24942 ₱ 250.00 ₱ 6,235,500.00
Total ₱ 201,079,950.00
HT CABLE
Excavation and HT Cables MTRS. 4776 ₱ 1,200.00 ₱ 5,731,200.00
Sand filling for HT Cables MTRS. 4776 ₱ 900.00 ₱ 4,298,400.00
HT Cable MTRS. 4776 ₱ 750.00 ₱ 3,582,000.00
BLOCK 1-30
Soil filling MTRS. 4776 ₱ 250.00 ₱ 1,194,000.00
Warning tape MTRS. 4776 ₱ 75.00 ₱ 358,200.00
Soil filling up to NGL SQM. 4776 ₱ 250.00 ₱ 1,194,000.00
Total ₱ 225,543,900.00
ROAD WORKS
ACTIVITY BLOCK NO. UNIT TOTAL QTY UNIT COST AMOUNT
SCB WORKS
ACTIVITY BLOCK NO. UNIT TOTAL QTY UNIT COST AMOUNT
Total ₱ 4,725,000.00
Total ₱ 3,690,000.00
EARTH PIT
ACTIVITY BLOCK NO. UNIT TOTAL QTY UNIT COST AMOUNT
Total ₱ 139,200.00
LIGHTING ARRESTER
ACTIVITY BLOCK NO. UNIT TOTAL QTY UNIT COST AMOUNT
Total ₱ 525,000.00