Professional Documents
Culture Documents
BOQ For VILLA L-SHAPES 2014 E.C
BOQ For VILLA L-SHAPES 2014 E.C
A-SUB STRUCTURE
3 CONCRETE WORK…………………………………………
BIRR 178427.71
B-SUPER STRUCTURE
1 CONCRETE WORK…………………………………………
BIRR 569613.74
2 BLOCK WORK………………………………………………
BIRR 79253.11
7 PAINTING………………………………………………………
BIRR 145102.01
6 GLAZING……………………………………………………BIRR 20378.24
16,196.61
17,168.41
Total to Summary……………………………..
…………………………...…….Birr 93746.1209
2. MASONRY WORK
Total to Summary…………………………….
…………………….Birr 73761.8895
3. CONCRETE WORK
Concrete :
Reinforcement bar :
Total to Summary……………...………………
……………………….Birr 178427.709
B. SUPER STRUCTURE
1. CONCRETE WORK
Concrete :
Reinforcement bar :
Total to Summary……………..…………..
……..……..…….……………….Birr 569613.738
2. BLOCK WORK
Total to Summary………………………….
……………………….Birr 79253.1062
3, ROOFING WORKS
Total to Summary………………………….
……………………….Birr 75488.63
4.2 Joinery
Total to Summary…………….………………
……………………….Birr 57209.0134
5.2.2 WINDOWS
6 . FINISHING WORK
b.for edge of exposed concrete gutter, beams and columns ml 431.95 20.00 8639.00
a. for verandah and Internal block wall surface m2 274.00 147.57 40434.48
Supply and lay 40x40x0.9cm thick porcelain floor tile fixed on floor with
6.2.1 42mm thick cement mortar of 1:3 ratio. m2 75.03 1868.00 140146.70
2mm thick high quality PVC floor tile flooring laid with approved
6.2.2 type of adhesive material. m2 7.06 536.74 3790.46
3cm thick Welega black marble tile for edge of verandah on with
6.2.3 proper grouting of joints in cement mortar mix of 1:3 m2 2.80 4211.85 11793.18
Supply and lay 10x0.6cm thick porcelain tile skirting fixed on wall with cement
mortar of 1:3 mix ratio and including with cement mortar of 1:1 mix ratio
6.2.4 backing. ml 87.76 103.75 9105.10
Total to Summary………………………..…….
……………………….Birr 271683.01
7. Painting
a All toilets and Kitchen area above ceramic wall tile m2 74.31 87.80 6524.2424
Total to Summary……………………………
……………………….Birr 145102.01
8 . Glazing
Total to Summary……………………………
……………………….Birr 20378.24
9.SANITARY INSTALLATION
A. Interior Installation
9.1 Supply and install galvanized steel pipes from elevated water
tank to cold and hot water distibution to all santitary fixtures as
shown on the drawing
Sanitary Fixtures
9.14 Supply and install floor drainage complete with all the
necessary accessories.
Down Pipe
Total to Summary……………………………
……………………….Birr 99422.62
9.SITE WORKS
Septic Tank
2. MASONRY WORK
3. CONCRETE WORK
Total to Summary……………………………
……………………….Birr 56188.1977
8. ELECTRICAL INSTALLATION
DISTRIBUTION BOARD
8.1 Flush mounted sub distribution board,SDB-C
with lockable door, earthing lead, connectors
and all the necessary accessories consisting of:-
LIGHT POINTS
8.5 Light points fed through PVC conductor of.
2 x 2.5 sq.mm.in thermoplastic conduit of diam
16mm in/under surface including junction boxes
screw type connectors with insulating caps and
cover. Nº 198 95 18810
SWITCH
8.6 Flush mounted Legrand Suno range switch or
equivalent with non circular corresponding box:-
a. Single pole Nº 22 36 792
b. Double pole Nº 16 39 624
c. Triple pole Nº 5 45 225
d. Two way Nº 38 45 1710
e. Double Two way Nº 20 50 1000
f. Intermediate Nº 13 60 780
SOCKET OUTLET
8.9 Flush mounted Legrand Suno range 2P+E /16A
schuo type or equivalent socket outlet with non
circular corresponding box. Nº 91 36 3276
BELL SYSTEM
8.13 Bell points fed through PVC conductor of.
2 x 1 sq.mm.in thermoplastic conduit of diam.
13mm in/under surface including junction boxes
CHIME
8.15 Two note 220v Legrand melody chime. Nº 4 250 1000
TELEPHONE POINT:-
8.17 Telephone point:- Only conduit of diameter 19 -
29mm, outlet box, pull wire and tele terminal
box as per ETC rules and regulations Nº 28 60 1680
TV POINT:-
8.18 Tv point:- Only conduit of diameter 29mm,
outlet box & pull wire. Nº 20 60 1200
POWER CABLES
Siemens NYY .6/1KV
PVC
8.24 diameter 32mm. M 4 9 36
8.25 diameter 40mm. M 80 11 880
8.26 diameter 50mm. M 21 13 273
8.27 diameter 110mm. M 25 30 750
MANHOLE
8.28 50x50x70 cms manhole with RC cover. Nº 4 350 1400
8.29 120x100x60 cms manhole with RC cover. Nº 1 800 800
GROUNDING
8.30 40x40x50 cms manhole with cover. Nº 1 300 300
8.31 1x25 sq.mm copper wire M 15 30 450
8.32 diameter 12.5 mm and 2m copper rod. Nº 1 450 450
FLOAT SWITCH
8.33 Mercury float switch for elavated water tank &
ground reservour. Nº 2 1500 3000
8.34 2x2.5 sq.mm tentative measument M 15 5 75
8.35 3x2.5 sq.mm tentative measument M 50 10 500
EXTERNAL LIGHTING
8.54 Octagonal steel pole of 3.5m with base ,fuse box,
fuse of 6A ,inspection hole ,flange plate ,anchor
bolt and Fumagalli G40.B40.M smoked fixture
with 1x23 w delux lamp all complete Nº 6 3500 21000
Total to Summary……………………………..
…………………………...…….Birr 229128
A SUB STRUCTURE
1.3 pit excavation over reduced level and not exceed 250cm
F1 12 1.50
1.50
1.20
1 7.50
1.00
0.40
1 3.40
1.00
0.40
2 8.00
1.00
0.40
1 4.00
1.00
0.40
12 1.00
1.00
0.25
12 0.95
0.25
0.25
b around stone
masonry
1 77.00
1.00
0.70
1 77.00
0.70
0.50
1 8.00
3.50
0.25
1 66.54
1 32.40
1 20.45
1 5.50
5.00
1 82.10
0.20
2 Stone masonery
2.1 BGL 1 77.00
0.60
0.50
b stone masonery
on axis A-A & B-B 2 12.50
0.50
b Foundation column
FC1 12 1.70
0.25
0.25
c Grade Beams
on axis A-A & B-B 2 14.00
0.30
0.20
1 5.50
5.00
b Foundation column
FC1 12 1.70
1.1
d Grade Beams
on axis A-A & B-B 4 14.00
0.30
B SUPER STRUCTURE
1 CONCRETE WORK
a Elevation colunmn
C1 19 3.15
0.25
0.20
b top Beams
on axis A-A & B-B 2 14.00
0.25
0.20
1 1.50
1.50
0.15
b top Beams
on axis A-A & B-B 2 14.00
0.70
1 1.50
1.50
4 1.50
0.15
2 BLOCK WORK
2.1 20cm thick HCB
a For External wall surface
on axis A-A & A`-A` 1 21.00
3.15
0.5 5.00
3.2 For Triangular roof area 2 4.96
ridged covers
2 14.6
valley covers
1 22.5
3.4 Gutter 1 25
for T-1 7 3
forT-7&T-8 2 5.15
for T-12 4 13
forT-7&T-8 1 12.9
Metal work
for main door
Type D-6, size 3.40x 2.10 cm 1 3.4
3
4.2.1 DOOR
4.3 WINDOWS
5 . FINISHING WORK
2mm thick high quality PVC floor tile flooring laid with
b approved type of adhesive material.
a. Size 25 x 3cm
1 11.20
0.25
Supply and lay 10x0.9cm thick porcelain tile skirting fixed on wall with
cement mortar of 1:3 mix ratio and including with cement mortar of 1:1
d mix ratio backing.
CEILING WORK
Supply and lay 10x0.9cm thick porcelain tile skirting fixed on wall with
cement mortar of 1:3 mix ratio and including with cement mortar of 1:1
mix ratio backing.
Window Sill
Size 27 x 3cm Marble window cill on and including cement
mortar bed jointed in cement mortar mix of 1:3.
Door Sill
5 . PAINTING WORK
Prepare the surface and apply three coats
of Granite paint of chosen type
and clour to:
5 . GLAZING WORK
Glazing
4mm thick clear glass
1 3.14
0.42
Diameter 15 mm 1 28
Diameter 20 mm 1 5.5
Diameter 25mm 1 21
Diameter 15 mm 1 21
Diameter 25 mm 1 21
Sanitary Fixtures
for low level water closet white glazed vitreous China WC. 1 1
Diameter 50 mm 1 9.7
Diameter 80 mm 1 10
Diameter 100 mm 1 10
Down Pipe
Diameter 75mm 11 4
Size:- 60 x 60cm x 60 cm 1 2
Diameter 32mm 1 15
Septic Tank
1 4.33
4.33
3.25
1 12.00
1.50
0.55
b around stone
masonry 1 12.00
1.50
0.55
1 60.93
1 9.90
2 Stone masonery
2.1 BGL 1 12.00
1.00
0.55
3 CONCRETE WORK
d Grade Beams
on axis A-A & B-B 2 2.80
0.35
1.3 pit excavation over reduced level and not exceed 250cm
1 0.85
0.85
0.65
2 Brick walls
2.1 BGL 1 2.36
0.45
3 CONCRETE WORK
forbottom of manhole
1 0.73
0.73
150.00
150.00
90.00
23.46
66.54
32.40
32.40
7.20
3.00
1.36
6.40
1.60
20.45
33.75
3.00
0.71
30.04
53.90
26.95
26.95
2.13
2.00
4.13
66.54
32.40
20.45
135.81
75.00
27.50
16.42
86.08
23.10
0.45
22.65
11.55
0.22
11.33
1.20
12.50 57.00
20
77.00
4.00
2.00
10.00
10.00
0.75
37.75
3.00
3.00
1.28
1.28
1.68
0.29
1.20
1.20
4.93
75.00
27.50
16.42 102.50
86.08
12.30
12.30
22.44
22.44
16.80
5.52
12.00
6.00
43.26
2.99
2.99
1.40
0.46
0.25
1.00
1.00
4.11
0.32
0.32
0.04
0.34
0.38
56.86
57.57
19.60
6.44
3.43
14.00
14.00
57.47
4.80
4.80
1.20
2.25
0.90
4.35
66.15
8.51
14.96
62.94
21.83
3.25
3.78
5.04
2.84
2.20
5.98
2.58
6.77
1.72
150.96
12.29
42.84
2.52
52.61
30.15
12.00
51.85
48.03
24.80
10.49
83.33
14.60
14.60
22.50
22.50
25.00
25.00
21.00
3.17
8.85
10.30
35.46
52.00
10.60
19.00
10.10
176.46
70.70
17.30
11.40
20.40
12.90
46.20
48.40
19.20
17.44
28.22
292.16
65.10
140.10
1.00
1.00
10.2
10.20
5.04
5.04
2.835
2.84
2.205
2.20
6.7725
6.77
1.72
6.0165
6.02
2.583
2.58
72.08
46.75
21.83
3.25
4.25
2.20
1.72
144.23
79.00
30.64
50.20
58.90
43.01
139.20
431.95
51.00
68.00
47.94
19.74
43.18
45.90
50.39
7.56
3.36
5.04
5.67
1.47
2.20
11.97
5.17
13.55
3.44
274.00
28.20
17.68
1.40
43.08
28.20
17.68
1.40
1.40
43.08
23.60
12.41
4.76
10.03
11.39
11.16
75.03
7.06
7.06
2.80
2.80
19.90
14.10
9.60
12.70
13.50
5.20
14.90
13.60
1.60
2.40
1.80
1.40
0.70
3.80
1.64
87.76
23.60
12.41
4.76
10.03
11.39
7.06
1.68
3.30
0.90
4.20
1.20
0.80
1.60
0.90
0.70
0.70
1.90
0.82
8.62
46.75
21.83
46.50
3.25
4.25
2.20
1.72
190.73
51.00
68.00
47.94
45.90
7.56
3.36
7.56
5.67
1.47
11.97
5.17
13.55
197.18
19.74
50.39
7.28
1.26
1.28
74.31
0.36
1.33
4.57
2.59
1.05
6.15
1.64
17.69
5.795
2.44
28
28.00
5.5
5.50
21
21.00
21
21.00
21
21.00
1
1.00
1
1.00
2
2.00
2
2.00
2
2.00
5
5.00
3
3.00
1
1.00
1
1.00
3
3.00
1
1.00
9.7
9.70
10
10.00
10
10.00
2
2.00
44
2
2.00
5.5
5.50
15
15.00
1
1.00
9.90
9.90
9.90
9.90
6.60
3.30
60.93
9.90
70.83
6.60
6.60
0.28
0.24
0.52
5.76
5.76
5.76
5.76
1.96
1.68
3.64
0.47
0.47
0.35
0.12
1.06
1.06
0.53
0.53
1.07
SUB-STRUCTURE-A
Footing pads
F-1 (a) 10 1.20 11 6 1 66.00
(b) 10 1.20 11 6 1 66.00
F-2 (a) 10 1.20 5.5 3 1 16.50
F-3 (a) 10 1.20 11 6 1 66.00
(b) 10 1.20 11 6 1 66.00
Foundation 0.00
columns FC1 12 3.00 4 5 1 20.00
FC2 12 3.10 4 1 1 4.00
FC2' 12 3.10 4 4 1 16.00
FC3 12 3.00 4 3 1 12.00
FC4 12 3.00 4 3 1 12.00
0.00
Stirrups FC1 ST-2 6 0.90 10 5 1 50.00 45.00
FC2 ST-2 6 0.90 10 1 1 10.00 9.00
FC2' ST-2 6 0.90 10 4 1 40.00 36.00
FC3 ST-2 6 0.90 10 3 1 30.00 27.00
FC4 ST-2 6 0.90 10 3 1 30.00 27.00
Grade beam 0.00
(+0.00 ) 0.00
10 12 14 16 20 24
79.20
79.20
19.80
79.20
79.20
60.00
12.40
49.60
36.00
36.00
41.88
3.59
22.48
41.88
5.81
66.60
16.00
40.44
16.00
19.90
18.24
15.44
3.58
24.27
51.20
110.20
0.00 110.20 51.20 0.00 0.00 0.00
0.617 0.888 1.208 1.578 2.468 3.551
0 98 62 0 0 0
84.60
84.60
41.88
3.59
22.48
41.88
5.81
66.60
16.00
19.90
18.24
15.44
3.58
40.44
16.00
19.90
18.24
15.44
3.58
600.98
Total (1:-01)
Remark ________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED O
PROJECT: CONCRETE WORK FOR TOP BEAM
WORK ITEM: ( 3.5 ) C-25 Concrete (Mechanical Mix) 1:2:3
TOTAL QUANTITY OF WORK ITEM: 1 m3
Total (1:-01)
6. FO
ANALYSIS SHEET FOR DIR
PROJECT: FORM WORK FOR COLUMN
WORK ITEM: ( 5.2 ) Form Work.
TOTAL QUANTITY OF WORK ITEM : 1
Total (1:-01)
Remark __________________________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED O
ANALYSIS SHEET FOR DIR
PROJECT: FORM WORK FOR BEAM
WORK ITEM: ( 5.2 ) Form Work.
TOTAL QUANTITY OF WORK ITEM : 1
Total (1:-01)
Remark __________________________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED O
19. BAR
Total (1:-01)
Remark __________________________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED O
Remark __________________________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED O
Total (1:-01)
Total (1:-01)
Remark __________________________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED O
7. BLO
ANALYSIS SHEET FOR DIR
PROJECT: HCB WORK
WORK ITEM: ( 6.11 ) 20 cm. thick HCB Wall Both Sides Left For Plaste
TOTAL QANTITY OF WORK ITEM: 1 m2
Total (1:-01)
Total (1:-01)
14.RO
ANALYSIS SHEET FOR DIR
PROJECT: ROOF WORK
WORK ITEM: ( 6.8 ) G-30 Roof cover
TOTAL QANTITY OF WORK ITEM: 1
Total (1:-01)
Remarks :
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED O
Remarks :
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED O
Total (1:-01)
Total (1:-01)
Remarks :
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED O
Total (1:-01)
Remarks :
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED O
13. CARPENTERY
ANALYSIS SHEET FOR DIR
PROJECT: CARPENTERY WORK
WORK ITEM: ( 6.8 ) 10cm-12cm Eucalyptus rafter
TOTAL QANTITY OF WORK ITEM: 1
Total (1:-01)
Remarks :
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED O
ANALYSIS SHEET FOR DIR
PROJECT: CARPENTERY WORK
WORK ITEM: ( 6.8 ) Verticals & Diagonals
TOTAL QANTITY OF WORK ITEM: 1
Total (1:-01)
Remarks :
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED O
Total (1:-01)
A= Materials Unit Cost 28.96 Birr/m2
Remarks :
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED O
Total (1:-01)
Total (1:-01)
Remarks :
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED O
16.METAL AND
ANALYSIS SHEET FOR DIR
PROJECT: METAL WORK
WORK ITEM: ( 6.8 ) Metal door
TOTAL QANTITY OF WORK ITEM: 1.00
Total (1:-01)
Remarks :
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED O
Total (1:-01)
Remarks :
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED O
ANALYSIS SHEET FOR DIR
PROJECT: REINFORCEMENT BAR
Total (1:-01)
Remarks :
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED O
Total (1:-01)
A= Materials Unit Cost 695.65 Birr/m2
Total (1:-01)
Total (1:-01)
8. FINISH
ANALYSIS SHEET FOR DIR
PROJECT: WALL FINISHING
WORK ITEM: ( 6.8 ) 2 Coats of Cement internal wall plastering
TOTAL QANTITY OF WORK ITEM: 1
Total (1:-01)
Remarks :
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED O
ANALYSIS SHEET FOR DIR
Total (1:-01)
Total (1:-01)
Remarks :
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED O
Total (1:-01)
Remarks :
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED O
Total (1:-01)
Remarks :
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED O
Total (1:-01)
Remarks :
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED O
Total (1:-01)
A= Materials Unit Cost 1014.14 Birr/m2
Remarks :
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED O
Total (1:-01)
Total (1:-01)
Remarks :
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED O
12. DOOR AN
ANALYSIS SHEET FOR DIR
PROJECT: DOOR SILLING
WORK ITEM: ( 6.8 ) marble door sill
TOTAL QANTITY OF WORK ITEM: 1
Total (1:-01)
Remarks :
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED O
ANALYSIS SHEET FOR DIR
PROJECT: WINDOW SILLING
WORK ITEM: ( 6.8 ) marble window sill
TOTAL QANTITY OF WORK ITEM: 1
Material Cost (1:01)
Total (1:-01)
Remarks :
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED O
9. PA
ANALYSIS SHEET FOR DIR
PROJECT: PAIINTING
WORK ITEM: ( 6.8 ) Three coats of plastic paint for internal and exte
TOTAL QANTITY OF WORK ITEM: 1
Remarks :
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED O
ANALYSIS SHEET FOR DIR
PROJECT: PAIINTING
WORK ITEM: ( 6.8 ) Three coats of syntactic oil paint for kitchen and
TOTAL QANTITY OF WORK ITEM: 1
18.GLAZ
ANALYSIS SHEET FOR DIR
PROJECT: GLAZING WORK
WORK ITEM: ( 6.8 ) 4mm thick clear glass
TOTAL QANTITY OF WORK ITEM: 1
Total (1:-01)
Remarks :
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED O
Total (1:-01)
Remarks :
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED O
15.SANIT
ANALYSIS SHEET FOR DIR
PROJECT: SANITERY WORK
WORK ITEM: ( 6.8 ) O15mm PPR
TOTAL QANTITY OF WORK ITEM: 1
Total (1:-01)
Remarks :
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED O
Total (1:-01)
Remarks :
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED O
Total (1:-01)
Remarks :
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED O
Remarks :
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED O
Total (1:-01)
Remarks :
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED O
Total (1:-01)
Remarks :
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED O
Total (1:-01)
Remarks :
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED O
Total (1:-01)
Remarks :
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED O
Total (1:-01)
Total (1:-01)
Remarks :
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED O
Total (1:-01)
Remarks :
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED O
Total (1:-01)
Remarks :
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED O
Total (1:-01)
Remarks :
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED O
Total (1:-01)
A= Materials Unit Cost 6561.94 Birr/m2
Remarks :
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED O
Total (1:-01)
Total (1:-01)
Remarks :
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED O
ANALYSIS SHEET FOR DIR
PROJECT: SANITERY WORK
WORK ITEM: ( 6.8 ) bath tub
TOTAL QANTITY OF WORK ITEM: 1
Total (1:-01)
Remarks :
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED O
Total (1:-01)
Remarks :
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED O
Remarks :
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED O
ANALYSIS SHEET FOR DIR
PROJECT: SANITERY WORK
WORK ITEM: ( 6.8 ) O100mm PVC
TOTAL QANTITY OF WORK ITEM: 1
Remarks :
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED O
Total (1:-01)
Total (1:-01)
Remarks :
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED O
ANALYSIS SHEET FOR DIR
PROJECT: SANITERY WORK
WORK ITEM: ( 6.8 ) O150mm concrete sewer pipe
TOTAL QANTITY OF WORK ITEM: 1
Total (1:-01)
Remarks :
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED O
Remarks :
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED O
Remarks :
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED O
B. SUPER-STRUCTURE
5. CONCRETE WORK
ANALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS
LABOUR HOURLY OUTPUT:
echanical Mix) 1:2:3 EQUIPEMENT: Mixer & Vibrator
RESULT:
Labour (1:02)
Cost per Labour by ** Indexed Hourly
Unit Trade No. UF Hourly Cost Cost
1236.52 Mason 1 1 59.59 59.59
98.91 DL 18 1 25.54 459.72
267.07 foreman 1 0.25 46.44 11.61
260.00 Mixer Op. 1 1 42.57 42.57
16.30 Carpenter 1 1 51.08 51.08
Vibrator Op. 1 1 30.65 30.65
Labour (1:02)
Cost per Labour by ** Indexed Hourly
Unit Trade No. UF Hourly Cost Cost
1236.52 Mason 1 1 59.59 59.59
98.91 DL 18 1 25.54 459.72
267.07 foreman 1 0.25 46.44 11.61
260.00 Mixer Op. 1 1 42.57 42.57
16.30 Carpenter 1 1 51.08 51.08
Vibrator Op. 1 1 30.65 30.65
6. FORMWORK
ALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS
LABOUR HOURLY OUTPUT:
EQUIPEMENT:
m2 RESULT:
Labour (1:02)
Cost per Labour by ** Indexed Hourly
Unit Grade No. UF Hourly Cost Cost
247.83 Foreman 1 0.25 46.44 11.61
18.26 Carpenter 1 1 51.08 51.08
20.87 DL 2 1 25.54 51.08
0.11
Labour (1:02)
Cost per Labour by ** Indexed Hourly
Unit Grade No. UF Hourly Cost Cost
247.83 Foreman 1 0.25 46.44 11.61
18.26 Carpenter 1 1 51.08 51.08
20.87 DL 2 1 25.54 51.08
0.11
Labour (1:02)
Cost per Labour by ** Indexed Hourly
Unit Grade No. UF Hourly Cost Cost
41.7991304 Foreman 1 0.25 46.44 11.61
1.13043478 Barbender 1 1 34.05 34.05
D/L 2 1 25.54 51.08
Labour (1:02)
Cost per Labour by ** Indexed Hourly
Unit Grade No. UF Hourly Cost Cost
41.0869565 Foreman 1 0.25 46.44 11.61
1.13043478 Barbender 1 1 34.05 34.05
D/L 2 1 25.54 51.08
42.22 Total (1:02) 96.74
Labour (1:02)
Cost per Labour by ** Indexed Hourly
Unit Grade No. UF Hourly Cost Cost
41.0869565 Foreman 1 0.25 46.44 11.61
1.13043478 Barbender 1 1 34.05 34.05
D/L 2 1 25.54 51.08
Labour (1:02)
Cost per Labour by ** Indexed Hourly
Unit Grade No. UF Hourly Cost Cost
42 Foreman 1 0.25 46.44 11.61
1.13043478 Barbender 1 1 34.05 34.05
D/L 2 1 25.54 51.08
7. BLOCK WORK
ALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS
LABOUR HOURLY OUTPUT:
all Both Sides Left For Plastering. EQUIPEMENT:
RESULT:
Labour (1:02)
Cost per Labour by ** Indexed Hourly
Unit Grade No. UF Hourly Cost Cost
142.434783 Foreman 1 1 46.44 46.44
34.3478261 Mason 1 1 25.00 25.00
5.32608696 D/L 2 1 13.33 26.66
0.00004
Labour (1:02)
Cost per Labour by ** Indexed Hourly
Unit Grade No. UF Hourly Cost Cost
119.826087 Foreman 1 1 0.00 0.00
25.7608696 Mason 1 1 25.00 25.00
4.18478261 D/L 2 1 13.33 26.66
0.00004
14.ROOF WORK
ALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS
LABOUR HOURLY OUTPUT:
EQUIPEMENT:
m2 RESULT:
Labour (1:02)
Cost per Labour by ** Indexed Hourly
Unit Grade No. UF Hourly Cost Cost
219.826087 carpenter 1 1 51.08 51.08
10.7660455 ass carpente 1 1 30.65 30.65
D/L 2 1 25.54 51.08
forman 1 0.5 46.44 23.22
Labour (1:02)
Cost per Labour by ** Indexed Hourly
Unit Grade No. UF Hourly Cost Cost
289.208696 carpenter 1 1 51.08 51.08
8.59130435 ass carpente 1 1 30.65 30.65
D/L 2 1 25.54 51.08
forman 1 0.5 46.44 23.22
297.80Total ( 1:02 ) 156.03
Labour (1:02)
Cost per Labour by ** Indexed Hourly
Unit Grade No. UF Hourly Cost Cost
101.73913 Carpenter 1 1 51.08 51.08
8.59130435 forman 1 1 46.44 46.44
DL 2 1 25.54 51.08
Labour (1:02)
Cost per Labour by ** Indexed Hourly
Unit Grade No. UF Hourly Cost Cost
109.565217 carpenter 1 1 51.08 51.08
8.59130435 ass carpente 1 1 30.65 30.65
D/L 2 1 25.54 51.08
forman 1 0.5 46.44 23.22
Labour (1:02)
Cost per Labour by ** Indexed Hourly
Unit Grade No. UF Hourly Cost Cost
333.459357 carpenter 1 1 51.08 51.08
8.59130435 ass carpente 1 1 30.65 30.65
D/L 2 1 25.54 51.08
forman 1 0.5 46.44 23.22
Labour (1:02)
Cost per Labour by ** Indexed Hourly
Unit Grade No. UF Hourly Cost Cost
27.9503106 carpenter 1 1 51.08 51.08
2.7826087 ass carpente 1 1 30.65 30.65
5.73913043 D/L 2 1 25.54 51.08
forman 1 0.5 46.44 23.22
Labour (1:02)
Cost per Labour by ** Indexed Hourly
Unit Grade No. UF Hourly Cost Cost
13.9130435 carpenter 1 1 51.08 51.08
2.85217391 ass carpente 1 1 30.65 30.65
5.73913043 D/L 2 1 25.54 51.08
forman 1 0.5 46.44 23.22
Labour (1:02)
Cost per Labour by ** Indexed Hourly
Unit Grade No. UF Hourly Cost Cost
18.2608696 carpenter 1 1 51.08 51.08
10.6956522 ass carpente 1 1 30.65 30.65
D/L 2 1 25.54 51.08
forman 1 0.5 46.44 23.22
Labour (1:02)
Cost per Labour by ** Indexed Hourly
Unit Grade No. UF Hourly Cost Cost
4820.86957 carpenter 1 1 51.08 51.08
4.99130435 ass carpente 1 1 30.65 30.65
D/L 2 1 25.54 51.08
forman 1 0.5 46.44 23.22
Labour (1:02)
Cost per Labour by ** Indexed Hourly
Unit Grade No. UF Hourly Cost Cost
10846.9565 carpenter 1 1 51.08 51.08
4.99130435 ass carpente 1 1 30.65 30.65
D/L 2 1 25.54 51.08
forman 1 0.5 46.44 23.22
Labour (1:02)
Cost per Labour by ** Indexed Hourly
Unit Grade No. UF Hourly Cost Cost
36.3461538 Foreman 1 1 46.44 23.22
3.4 Welder 1 1 59.59 59.59
0.4 D/L 1 1 25.54 25.54
0.572 Carpenter1 1 1 51.08 51.08
8. FINISHING WORK
ALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS
LABOUR HOURLY OUTPUT:
internal wall plastering EQUIPEMENT:
m2 RESULT:
Labour (1:02)
Cost per Labour by ** Indexed Hourly
Unit Grade No. UF Hourly Cost Cost
324 forman 1 1 46.44 46.44
0.30434783 tiler 1 1 59.59 59.59
3.63315217 D/L 2 0.25 25.54 12.77
47.0565217
Labour (1:02)
Cost per Labour by ** Indexed Hourly
Unit Grade No. UF Hourly Cost Cost
822.652174 tailer 1 1 59.59 59.59
0.30434783 D/L 2 1 25.54 51.08
35.4538261 Forman 1 0.25 46.44 11.61
2.72695652
Labour (1:02)
Cost per Labour by ** Indexed Hourly
Unit Grade No. UF Hourly Cost Cost
434.23913 tailer 1 1 59.59 59.59
48.9130435 D/L 2 1 25.54 51.08
48.9130435 Forman 1 0.25 46.44 11.61
Labour (1:02)
Cost per Labour by ** Indexed Hourly
Unit Grade No. UF Hourly Cost Cost
975.652174 tailer 1 1 59.59 59.59
0.30434783 D/L 2 1 25.54 51.08
35.4538261 Forman 1 0.25 46.44 11.61
2.72695652
Labour (1:02)
Cost per Labour by ** Indexed Hourly
Unit Grade No. UF Hourly Cost Cost
95.8695652 forman 1 0.5 46.44 23.22
1.58 tailer 1 1 59.59 59.59
0.19021739 D/L 2 1 25.54 51.08
Labour (1:02)
Cost per Labour by ** Indexed Hourly
Unit Grade No. UF Hourly Cost Cost
0 carpenter 2 1 0.00 0.00
0 ass carpente 2 1 0.00 0.00
0 D/L 3 1 0.00 0.00
0 forman 1 1 0.00 0.00
0
Labour (1:02)
Cost per Labour by ** Indexed Hourly
Unit Grade No. UF Hourly Cost Cost
50 forman 1 1 46.44 46.44
8.93043478 tailer 1 1 59.59 59.59
1.33152174 D/L 2 1 25.54 51.08
9. PAINTING
ALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS
LABOUR HOURLY OUTPUT:
paint for internal and external verandah wall, beam and co EQUIPEMENT:
m2 RESULT:
Labour (1:02)
Cost per Labour by ** Indexed Hourly
Unit Grade No. UF Hourly Cost Cost
0.65217391 forman 1 0.1 46.436 4.64
0.76086957 D/L 1 1 25.540 25.54
5.32608696 painter 1 1 59.593 59.59
4.56521739
3.80434783
0.13043478
0.26086957
0.05217391
1
15.55Total ( 1:02 ) 89.78
Labour (1:02)
Cost per Labour by ** Indexed Hourly
Unit Grade No. UF Hourly Cost Cost
0.65217391 forman 1 0.1 46.436 4.64
0.76086957 D/L 1 1 25.540 25.54
5.32608696 painter 1 1 59.593 59.59
4.56521739
3.80434783
0.13043478
0.26086957
0.05217391
15.55Total ( 1:02 ) 89.78
18.GLAZING WORK
ALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS
LABOUR HOURLY OUTPUT:
EQUIPEMENT:
m2 RESULT:
Labour (1:02)
Cost per Labour by ** Indexed Hourly
Unit Grade No. UF Hourly Cost Cost
349.130435 glazer 1 1 38.70 38.70
17.3913043 ass glazer 1 1 34.05 34.05
forman 1 0.5 46.44 23.22
Labour (1:02)
Cost per Labour by ** Indexed Hourly
Unit Grade No. UF Hourly Cost Cost
430.434783 glazer 2 1 38.70 77.39
17.3913043 ass glazer 1 1 34.05 34.05
forman 1 0.5 0.00 0.00
15.SANITERY WORK
ALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS
LABOUR HOURLY OUTPUT:
EQUIPEMENT:
ml RESULT:
Labour (1:02)
Cost per Labour by ** Indexed Hourly
Unit Grade No. UF Hourly Cost Cost
14.9333333 Plumber 1 1 59.59 59.59
8.536 DL 2 1 25.54 51.08
11.2
43
16
Labour (1:02)
Cost per Labour by ** Indexed Hourly
Unit Grade No. UF Hourly Cost Cost
6.5625 Plumber 1 1 59.59 59.59
2.16 DL 2 1 25.54 51.08
4.32
13.5
6.75
33.75
Labour (1:02)
Cost per Labour by ** Indexed Hourly
Unit Grade No. UF Hourly Cost Cost
230 Plumber 1 1 59.59 59.59
1.08 DL 2 1 25.54 51.08
231.08Total ( 1:02 ) 110.67
Labour (1:02)
Cost per Labour by ** Indexed Hourly
Unit Grade No. UF Hourly Cost Cost
230 Plumber 1 1 59.59 59.59
1.08 DL 1 1 25.54 25.54
Labour (1:02)
Cost per Labour by ** Indexed Hourly
Unit Grade No. UF Hourly Cost Cost
4500.00 Plumber 1 1 59.59 59.59
160.05 DL 3 1 25.54 76.62
117.37
10.75
4788.17Total ( 1:02 ) 136.21
Labour (1:02)
Cost per Labour by ** Indexed Hourly
Unit Grade No. UF Hourly Cost Cost
500 Plumber 1 1 59.59 59.59
1.08 DL 2 1 25.54 51.08
Labour (1:02)
Cost per Labour by ** Indexed Hourly
Unit Grade No. UF Hourly Cost Cost
1800 forman 1 0.25 46.44 11.61
2.17 plumber 1 1 59.59 59.59
0.22 Chiseler 1 1 30.65 30.65
Labour (1:02)
Cost per Labour by ** Indexed Hourly
Unit Grade No. UF Hourly Cost Cost
256 Plumber 1 1 59.59 59.59
171.74 DL 2 1 25.54 51.08
0.30
Labour (1:02)
Cost per Labour by ** Indexed Hourly
Unit Grade No. UF Hourly Cost Cost
100 Plumber 1 1 59.59 59.59
DL 2 1 25.54 51.08
Labour (1:02)
Cost per Labour by ** Indexed Hourly
Unit Grade No. UF Hourly Cost Cost
182 Plumber 1 1 59.59 59.59
171.74 DL 2 1 25.54 51.08
0.30
Labour (1:02)
Cost per Labour by ** Indexed Hourly
Unit Grade No. UF Hourly Cost Cost
40 Plumber 1 1 59.59 59.59
121.73913 DL 2 1 25.54 51.08
121.73913
Labour (1:02)
Cost per Labour by ** Indexed Hourly
Unit Grade No. UF Hourly Cost Cost
750 Plumber 1 1 59.59 59.59
2.17 DL 2 1 25.54 51.08
0.22
Labour (1:02)
Cost per Labour by ** Indexed Hourly
Unit Grade No. UF Hourly Cost Cost
6500 Plumber 1 1 59.59 59.59
60.8695652 DL 2 1 25.54 51.08
1.075
Labour (1:02)
Cost per Labour by ** Indexed Hourly
Unit Grade No. UF Hourly Cost Cost
60 Plumber 1 1 59.59 59.59
DL 2 1 25.54 51.08
Labour (1:02)
Cost per Labour by ** Indexed Hourly
Unit Grade No. UF Hourly Cost Cost
450 Plumber 1 1 59.59 59.59
0.22 DL 2 1 25.54 51.08
Labour (1:02)
Cost per Labour by ** Indexed Hourly
Unit Grade No. UF Hourly Cost Cost
1500 Plumber 1 1 59.59 59.59
429.565217 DL 2 1 25.54 51.08
6869.56522
57.0652174
Labour (1:02)
Cost per Labour by ** Indexed Hourly
Unit Grade No. UF Hourly Cost Cost
3.208 Plumber 1 1 59.59 59.59
1.739 DL 2 1 25.54 51.08
3.478
10.870
5.435
0.543
8.50
Labour (1:02)
Cost per Labour by ** Indexed Hourly
Unit Grade No. UF Hourly Cost Cost
4.819 Plumber 1 1 59.59 59.59
2.783 DL 2 1 25.54 51.08
5.565
17.391
2.783
8.696
0.870
8.50
51.41Total ( 1:02 ) 110.67
Labour (1:02)
Cost per Labour by ** Indexed Hourly
Unit Grade No. UF Hourly Cost Cost
6.087 Plumber 1 1 59.59 59.59
4.174 DL 2 1 25.54 51.08
8.348
26.087
4.174
13.043
1.304
8.50
71.72Total ( 1:02 ) 110.67
Labour (1:02)
Cost per Labour by ** Indexed Hourly
Unit Grade No. UF Hourly Cost Cost
40.425 Plumber 1 1 59.59 59.59
8.50 DL 2 1 25.54 51.08
Labour (1:02)
Cost per Labour by ** Indexed Hourly
Unit Grade No. UF Hourly Cost Cost
26.460 Plumber 1 1 59.59 59.59
5.719 DL 2 1 25.54 51.08
5.300
10.600
Labour (1:02)
Cost per Labour by ** Indexed Hourly
Unit Grade No. UF Hourly Cost Cost
136.16 Mason 1 1 25.00 25.00
1269.70 D/L 2 1 13.33 26.66
103.69
268.67
125.80
0.00
1904.02 Total ( 1:02 ) 51.66
Labour (1:02)
Cost per Labour by ** Indexed Hourly
Unit Grade No. UF Hourly Cost Cost
210.000 Foreman 1 0.25 46.44 11.61
5.056 Mason 1 1 59.59 59.59
7.609 D/L 2 1 25.54 51.08
1.598
0.005
Labour (1:02)
Cost per Labour by ** Indexed Hourly
Unit Grade No. UF Hourly Cost Cost
14.933 Plumber 1 1 59.59 59.59
8.536 DL 2 1 25.54 51.08
11.200
43.000
6.880
16.000
1.08
101.62Total ( 1:02 ) 110.67
Labour (1:02)
Cost per Labour by ** Indexed Hourly
Unit Grade No. UF Hourly Cost Cost
232.000 Plumber 1 1 59.59 59.59
DL 2 1 25.54 51.08
232.00Total ( 1:02 ) 110.67
313.48 Birr/m3
156.74 Birr/m3
3605.05 Birr/m3
Y OUTPUT: 0.875 m3 / hr.
Mixer & Vibrator
3192.36 Birr/m3
277.60 Birr/m3
138.80 Birr/m3
3192.36 Birr/m3
550.50 Birr/m2
47.87 Birr/m2
23.93 Birr/m2
550.50 Birr/m2
513.77 Birr/m2
44.68 Birr/m2
22.34 Birr/m2
513.77 Birr/m2
52.57 Birr/kg.
4.57 Birr/kg.
2.29 Birr/kg.
52.57 Birr/kg.
51.65 Birr/kg.
4.49 Birr/kg.
2.25 Birr/kg.
51.65 Birr/kg.
51.29 Birr/kg.
Y OUTPUT: 45 kg/hr.
52.27 Birr/kg.
4.54 Birr/kg.
2.27 Birr/kg.
52.27 Birr/kg.
Y OUTPUT: 1.25 m2/hr.
0.0924
301.51 Birr/m2
13.86
Equipment Cost (1:03)
Type of Hourly Hourly
Equipment No. Rental Cost
Tools 4 0.5 2
26.22 Birr/m2
13.11 Birr/m2
301.51 Birr/m2
Y OUTPUT: 1.25 m2/hr.
221.60 Birr/m2
19.27 Birr/m2
9.63 Birr/m2
221.60 Birr/m2
292.96 Birr/m2
25.48 Birr/m2
12.74 Birr/m2
292.96 Birr/m2
395.98 Birr/m2
34.43 Birr/m2
17.22 Birr/m2
395.98 Birr/m2
149.82 Birr/m
156.52 Birr/m
13.61 Birr/m2
6.81 Birr/m2
156.52 Birr/m2
Y OUTPUT: 7.50 ml/hr.
417.44 Birr/ml
36.30 Birr/m2
18.15 Birr/m2
417.44 Birr/m2
Y OUTPUT: 10.00 ml/hr.
57.45 Birr/m
5.00 Birr/m2
2.50 Birr/m2
57.45 Birr/m2
50.11 Birr/m
4.36 Birr/m2
2.18 Birr/m2
50.11 Birr/m2
52.68 Birr/ml
4.58 Birr/m2
2.29 Birr/m2
52.68 Birr/m2
5840.51 Birr/pc
507.87 Birr/m2
253.94 Birr/m2
5840.51 Birr/m2
12843.20 Birr/pc
1116.80 Birr/m2
558.40 Birr/m2
12843.20 Birr/m2
Y OUTPUT: 1.275 m2/hr.
5075.25 Birr/m2
441.33 Birr/m2
220.66 Birr/m2
5075.25 Birr/m2
Y OUTPUT: 50 kg/hr.
59.92 Birr/m2
Equipment Cost (1:03)
Type of Hourly Hourly
Equipment No. Rental Cost
tools 1 4 4.00
5.93 Birr/m2
4.74 Birr/m2
59.92 Birr/m2
Y OUTPUT: 50 kg/hr.
54.66 Birr/m2
5.93 Birr/m2
4.74 Birr/m2
54.66 Birr/m2
934.87 Birr/m2
81.29 Birr/m2
40.65 Birr/m2
934.87 Birr/m2
935.11 Birr/m2
81.31 Birr/m2
40.66 Birr/m2
935.11 Birr/m2
Y OUTPUT: 1.071 m2/hr.
978.82 Birr/m2
85.12 Birr/m2
42.56 Birr/m2
978.82 Birr/m2
84.07 Birr/m2
7.31 Birr/m2
3.66 Birr/m2
84.07 Birr/m2
88.62 Birr/m2
7.71 Birr/m2
3.85 Birr/m2
88.62 Birr/m2
72.04 Birr/ml
6.26 Birr/m2
3.13 Birr/m2
72.04 Birr/m2
80.31 Birr/m2
6.98 Birr/m2
3.49 Birr/m2
80.31 Birr/m2
Y OUTPUT: 0.88 m2/hr.
591.32 Birr/m2
51.42 Birr/m2
25.71 Birr/m2
591.32 Birr/m2
96.14 Birr/m2
48.07 Birr/m2
1105.57 Birr/m2
678.05 Birr/m2
58.96 Birr/m2
29.48 Birr/m2
678.05 Birr/m2
1260.01 Birr/m2
109.57 Birr/m2
54.78 Birr/m2
1260.01 Birr/m2
191.00 Birr/m
16.61 Birr/m2
8.30 Birr/m2
191.00 Birr/m2
1.15 Birr/m
0.10 Birr/m2
0.05 Birr/m2
1.15 Birr/m2
Y OUTPUT: 2.00 m/hr.
161.36 Birr/m
14.03 Birr/m2
7.02 Birr/m2
161.36 Birr/m2
161.36 Birr/m
Equipment Cost (1:03)
Type of Hourly Hourly
Equipment No. Rental Cost
Tools 3 1 3
14.03 Birr/m2
7.02 Birr/m2
161.36 Birr/m2
45.42 Birr/m2
3.95 Birr/m2
1.97 Birr/m2
45.42 Birr/m2
50.92 Birr/m2
4.43 Birr/m2
2.21 Birr/m2
50.92 Birr/m2
355.85 Birr/m2
30.94 Birr/m2
15.47 Birr/m2
355.85 Birr/m2
Y OUTPUT: 1.75 m2/hr.
485.88 Birr/m2
42.25 Birr/m2
21.13 Birr/m2
485.88 Birr/m2
Y OUTPUT: 1.75 m2/hr.
588.76 Birr/m2
51.20 Birr/m2
25.60 Birr/m2
588.76 Birr/m2
Y OUTPUT: 5 ml/hr.
135.24 Birr/ml
11.76 Birr/m2
5.88 Birr/m2
135.24 Birr/m2
54.75 Birr/ml
Equipment Cost (1:03)
Type of Hourly Hourly
Equipment No. Rental Cost
Tools 3 3 9
4.76 Birr/m2
2.38 Birr/m2
54.75 Birr/m2
99.12 Birr/ml
8.62 Birr/m2
4.31 Birr/m2
99.12 Birr/m2
339.14 Birr/ml
29.49 Birr/m2
14.75 Birr/m2
339.14 Birr/m2
323.47 Birr/ml
28.13 Birr/m2
14.06 Birr/m2
323.47 Birr/m2
6174.38 Birr/pcs
536.90 Birr/m2
268.45 Birr/m2
6174.38 Birr/m2
Y OUTPUT: 0.375 pcs/hr.
943.24 Birr/pcs
82.02 Birr/m2
41.01 Birr/m2
943.24 Birr/m2
4589.64 Birr/pcs
Equipment Cost (1:03)
Type of Hourly Hourly
Equipment No. Rental Cost
Tools 3 3 9
399.10 Birr/m2
199.55 Birr/m2
4589.64 Birr/m2
2412.69 Birr/pcs
209.80 Birr/m2
104.90 Birr/m2
2412.69 Birr/m2
649.54 Birr/pcs
56.48 Birr/m2
28.24 Birr/m2
649.54 Birr/m2
170.05 Birr/pcs
14.79 Birr/m2
7.39 Birr/m2
170.05 Birr/m2
Y OUTPUT: 0.875 pcs/hr.
564.44 Birr/pcs
49.08 Birr/m2
24.54 Birr/m2
564.44 Birr/m2
42.02 Birr/m2
21.01 Birr/m2
483.29 Birr/m2
1232.25 Birr/pcs
107.15 Birr/m2
53.58 Birr/m2
1232.25 Birr/m2
7821.49 Birr/pcs
680.13 Birr/m2
340.06 Birr/m2
7821.49 Birr/m2
124.05 Birr/pcs
10.79 Birr/m2
5.39 Birr/m2
124.05 Birr/m2
884.75 Birr/pcs
76.93 Birr/m2
38.47 Birr/m2
884.75 Birr/m2
Y OUTPUT: 0.25 pcs/hr.
10735.12 Birr/pcs
933.49 Birr/m2
466.74 Birr/m2
10735.12 Birr/m2
Y OUTPUT: 5 ml/hr.
66.36 Birr/ml
5.77 Birr/m2
2.89 Birr/m2
66.36 Birr/m2
Y OUTPUT: 5 ml/hr.
86.64 Birr/ml
7.53 Birr/m2
3.77 Birr/m2
86.64 Birr/m2
Y OUTPUT: 5 ml/hr.
110.00 Birr/ml
9.57 Birr/m2
4.78 Birr/m2
110.00 Birr/m2
71.99 Birr/ml
Y OUTPUT: 5 ml/hr.
82.82 Birr/ml
7.20 Birr/m2
3.60 Birr/m2
82.82 Birr/m2
2427.26 Birr/m2
211.07 Birr/m2
105.53 Birr/m2
2427.26 Birr/m2
Y OUTPUT: 3.75 ml/hr.
298.17 Birr/ml
25.93 Birr/m2
12.96 Birr/m2
298.17 Birr/m2
Y OUTPUT: 15 ml/hr.
126.04 Birr/ml
10.96 Birr/m2
5.48 Birr/m2
126.04 Birr/m2
310.84 Birr/ml
27.03 Birr/m2
13.51 Birr/m2
310.84 Birr/m2
A. SUB-STRUCTURE
1. EARTH WORK
ANALYSIS SHEET FOR DIRECT & INDI
PROJECT: EXCAVATION AND EARTH WORK.
WORK ITEM: ( 1.1 ) 20 cm. Clearing on loose & dry soil.
TOTAL QANTITY OF WORK ITEM: 1 m2
Cost per
Type of Material Unit Qty * Rate Unit Labour by Grade
Diesel lts 0.1 16.3 1.63 Forman
Loader Operator
Daily labourer
Remark __________________________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED O
ANALYSIS SHEET FOR DIRECT & I
PROJECT: EXCAVATION AND EARTH WORK.
WORK ITEM: ( 1.2 ) Bulk excav. to a depth not exceeding 150cm loose and dry soil.
TOTAL QANTITY OF WORK ITEM: 1 m3
Cost per
Type of Material Unit Qty * Rate Unit Labour by Grade
Diesel lts 1 16.3 16.3 Forman
Loader operator
Daily Labourer
Remark __________________________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED O
Cost per
Type of Material Unit Qty * Rate Unit Labour by Grade
forman
Daily labourer
Remark __________________________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED O
Cost per
Type of Material Unit Qty * Rate Unit Labour by Grade
forman
Daily labourer
Cost per
Type of Material Unit Qty * Rate Unit Labour by Grade
Borrowed material m3 1.2 152.17 182.61 foreman
Diesel lts 0.08 16.3 1.304 DL
Cost per
Type of Material Unit Qty * Rate Unit Labour by Grade
Diesel lts 1 16.3 16.3 Loader Op.
DT driver
ass driver
DL
Remark __________________________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED O
Cost per
Type of Material Unit Qty * Rate Unit Labour by Grade
Basaltic stone m3 0.28 304.35 85.22 foreman
mason
DL
Remark __________________________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED O
3. MASONRY WORK
ANALYSIS SHEET FOR DIRECT &
PROJECT: MASONRY WORKS
WORK ITEM : ( 3.1 ) 50cm. thick masonry foundation beded in 1:4 (B.G.L).
TOTAL QANTITY OF WORK ITEM: 1 m3
Cost per
Type of Material Unit Qty * Rate Unit Labour by Grade
Stone m3 1 334.45 334.4482 Foreman
Cement Qt 1.5 343.48 515.2174 Mason
Sand m3 0.42 190.22 79.8913 ass mason
water lts 25 2.00 50.00 D/L
Total (1:-01) 979.5569 Total (1:02
Remark : _____________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED O
2. CONCRETE WORK
ANALYSIS SHEET FOR DIRECT &
PROJECT: CONCRETE WORK
WORK ITEM: ( 2.1 ) C-5 Lean Concrete (Hand mix) 1:5:7
TOTAL QUANTITY OF WORK ITEM: 1 m2 0.05
Cost per
Type of Material Unit Qty * Rate Unit Labour by Trade
Cement Qt 1.5 343.48 515.2174 Mason
Sand m3 0.5 190.22 95.1087 Daily Labourer
Aggregate m3 0.9 342.39 308.1522 forman
water lts 25 2.00 50.00 Mixer operator
desail lts 1 16.30 16.3
Remark ________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED O
Cost per
Type of Material Unit Qty * Rate Unit Labour by Trade
Cement Qt 3.6 343.48 1236.52 Mason
Sand m3 0.52 190.22 98.91 DL
Aggregate m3 0.78 342.39 267.07 foreman
water lts 130 2.00 260.00 Mixer Op.
desail lts 1 16.30 16.30 Vibrator Op.
Total (1:-01) 1878.80 Total (1:02
Remark ________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED O
Cost per
Type of Material Unit Qty * Rate Unit Labour by Trade
Cement Qnt. 3.6 343.48 1236.52 Mason
Sand m3 0.52 190.22 98.91 DL
Gravel (02) m3 0.78 342.39 267.07 foreman
water lts 130 2.00 260.00 Mixer Op.
desail lts 1 16.30 16.30 Vibrator Op.
Remark ________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED O
Remark ________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED O
Cost per
Type of Material Unit Qty * Rate Unit Labour by Trade
Cement Qnt. 3.6 343.48 1236.52 Mason
Sand m3 0.52 190.22 98.91 DL
Gravel (02) m3 0.78 342.39 267.07 foreman
water lts 130 2.00 260.00 Mixer Op.
desail lts 1 16.30 16.30 Carpenter
Vibrator Op.
Remark ________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED O
4. FORMWORK
ANALYSIS SHEET FOR DIRECT & INDI
PROJECT: FORM WORK
WORK ITEM: ( 4.1 ) Form Work. For pod
TOTAL QUANTITY OF WORK ITEM : 1 m2
Cost per
Type of Material Unit Qty * Rate Unit Labour by Grade
zigba panel m2 0.925 260.87 241.30 Foreman
Eucalyptus ml 2.1 8.70 18.26 Carpenter
Nails Kg 0.3 69.57 20.87 DL
Mould Oil Lit. 0.015 7.00 0.11
Cost per
Type of Material Unit Qty * Rate Unit Labour by Grade
zigba panel m2 0.925 260.87 241.30 Foreman
Eucalyptus ml 2.1 8.70 18.26 Carpenter
Nails Kg 0.3 69.57 20.87 DL
Mould Oil Lit. 0.015 7.00 0.11
Total (1:-01) 280.54 Total (1:02
Cost per
Type of Material Unit Qty * Rate Unit Labour by Grade
zigba panel m2 0.95 260.87 247.83 Foreman
Eucalyptus ml 2.1 8.70 18.26 Carpenter
Nails Kg 0.3 69.57 20.87 DL
Mould Oil Lit. 0.015 7.00 0.11
Total (1:-01) 287.06 Total (1:02
Cost per
Type of Material Unit Qty * Rate Unit Labour by Grade
6 mm deformed bars kg 1.05 47.83 50.21739 Foreman
1.2 mm black anneald kg 0.02 56.52 1.130435 Barbender
D/L
Total (1:-01) 51.35 Total (1:02)
Cost per
Type of Material Unit Qty * Rate Unit Labour by Grade
8 mm deformed bars kg 1.05 39.81 41.79913 Foreman
1.2 mm black anneald kg 0.02 56.52 1.130435 Barbender
D/L
Total (1:-01) 42.93 Total (1:02)
Remark __________________________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED O
Cost per
Type of Material Unit Qty * Rate Unit Labour by Grade
10 mm deformed bar kg 1.05 39.13 41.08696 Foreman
1.2 mm black anneald kg 0.02 56.52 1.130435 Barbender
D/L
Total (1:-01) 42.22 Total (1:02)
Cost per
Type of Material Unit Qty * Rate Unit Labour by Grade
12 mm deformed bars kg 1.05 39.13 41.08696 Foreman
1.2 mm black anneald kg 0.02 56.52 1.130435 Barbender
D/L
Remark __________________________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED O
Cost per
Type of Material Unit Qty * Rate Unit Labour by Grade
14 mm deformed bars kg 1.05 40.00 42 Foreman
1.2 mm black anneald kg 0.02 56.52 1.130435 Barbender
D/L
Remark __________________________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED O
A. SUB-STRUCTURE
1. EARTH WORK
OR DIRECT & INDIRECT UNIT COSTS
LABOUR HOURLY OUTPUT: 145 m2/hr.
EQUIPEMENT: Loader tools
RESULT: 9.63 Birr/m2
_____________________
LATED TO TARGETED OUTPUT.
ET FOR DIRECT & INDIRECT UNIT COSTS
LABOUR HOURLY OUTPUT: 25.00 m3/hr.
EQUIPEMENT: Tool
RESULT: 61.50 Birr/m3
_____________________
LATED TO TARGETED OUTPUT.
_____________________
LATED TO TARGETED OUTPUT.
_____________________
_____________________
_____________________
3. MASONRY WORK
EET FOR DIRECT & INDIRECT UNIT COSTS
LABOUR HOURLY OUTPUT: 1 m3/hr.
EQUIPEMENT:
RESULT 1545.82 Birr/m3
2. CONCRETE WORK
EET FOR DIRECT & INDIRECT UNIT COSTS
LABOUR HOURLY OUTPUT: 15 m2/hr.
EQUIPEMENT:
m. thick RESULT: 84.87 Birr/m2
4. FORMWORK
OR DIRECT & INDIRECT UNIT COSTS
LABOUR HOURLY OUTPUT: 1.25 m2/hr.
EQUIPEMENT:
RESULT: 428.67 Birr/m2
hourly
Item no types of labor monthly salary daily rate rate
1 Exc.Operator 10000 454.55 56.82
2 Mixer Op. 5500 250.00 31.25
3 Vibrator Op. 3960 180.00 22.50
compactor op. 3960 180.00 22.50
4 truck driver 4000 181.82 22.73
ass truck driver 2000 90.91 11.36
5 Loader Op. 10000 454.55 56.82
7 Forman 6000 272.73 34.09
8 Mason 7700 350.00 43.75
9 Mason ll 4400 200.00 25.00
10 Carpenter 6600 300.00 37.50
11 Carpenter ll 3960 180.00 22.50
12 Bar bender 4400 200.00 25.00
13 Bar bender ll 4400 200.00 25.00
14 Plasterer 7700 350.00 43.75
15 Chieseler 3960 180.00 22.50
16 tiler 7700 350.00 43.75
17 Welder 7700 350.00 43.75
18 Glazer 5000 227.27 28.41
19 Painter 7700 350.00 43.75
20 Plumber 7700 350.00 43.75
21 Elec 6600 300.00 37.50
22 DL 3300 150.00 18.75
types of hourly
Item no equipment monthly salary daily rate rental rate
1 backhoe loader, 9 140800 6400 800
2 backhoe loader, 9 140800 6400 800
3 vibrator 7040 320 40
4 dump truck 105600 4800 600
5 mixer 14960 680 85
6 tools
7 compactor 7040 320 40
3960
hourly labor
indexed hourly
factor index
1.36 77.39
1.36 42.57
1.36 30.65
1.36 30.65
1.36 30.96
1.36 15.48
1.36 77.39
1.36 46.44
1.36 59.59
1.36 34.05
1.36 51.08
1.36 30.65
1.36 34.05
1.36 34.05
1.36 59.59
1.36 30.65
1.36 59.59
1.36 59.59
1.36 38.70
1.36 59.59
1.36 59.59
1.36 51.08
1.36 25.54
Calculating Labour Requirement
Item Labour Efficiencies
Activity Description Gang per day Work to be executed
A) SUBSTRUCTURE
1 Excavation and earth work
2 Concrete Work
2.1 C-5 Lean concrete
a) 5cm thick 1m+6D.L 8hr. 20m2
b) 8cm thick 1m+6D.L 8hr. 15m2
2.2 Floor Slab
a) 8cm thick 1m+6D.L 8hr. 15m2
b) 10cm thick 1m+6D.L 8hr. 12.5m2
c) 15cm thick 1m+6D.L 8hr. 10m2
2.3 Ground beam 1m+6D.L 8hr. 11/2m3
2.4 Footing 1m+6D.L 8hr. 11/2m3
2.5 Foundation column 1m+6D.L 8hr. 11/4m3
3 Masonry Work
B) SUPER STRUCTURE
4 Concrete Work
4.1 for elivation Column
a/ Column up to 2m 1m+6D.L 8hr. 11/4m3
b/ Column above 2m 1m+6D.L 8hr. 1m3
4.2 Upper tie beam 1m+6D.L 8hr. 1m3
4.3 Linton 1m+6D.L 8hr. 1m3
5 H.C.B Block Work
a) 20cm thick up to 2m 1m+2D.L 8hr. 10m2
b) 15cm thick up to 2m 1m+2D.L 8hr. 10m2
c) 10cm thick up to 2m 1m+2D.L 8hr. 8m2
d) 20cm thick from 2 - 4m 1m+2D.L 8hr. 8m2
e) 15cm thick form 2 - 4m 1m+2D.L 8hr. 8m2
f) 10cm thick form 2 - 4m 1m+2D.L 8hr. 6m2
6 Brick Work
a) 25cm thick up to 2m 1m+3D.L 8hr. 7m2
b) 12cm thick up to 20m 1m+3D.L 8hr. 9m2
c) 25cm thick up to 20m 1m+3D.L 8hr. 5m2
d) 12cm thick from 2 - 4m 1m+3D.L 8hr. 7m2
7 Roofing Work
7.1 Roof covering (G.C.I) 1c+2D.L 8hr. 40m2
Roof covering corrugated asbestos 1c+2D.L 8hr. 40m3
7.2 Ridge cover 1c+2D.L 8hr. 70ml
7.3 Valley cover 1c+2D.L 8hr. 70ml
7.4 Gutter fixing 1c+2D.L 8hr. 30ml
7.5 Joinion eucalyptus truss up to 10m span on 1c+2D.L 8hr. 4 truss
7.6 Down pipe fixing 1c+2D.L 8hr. 40ml
7.7 Truss erecting 1c+2D.L 8hr. 5 truss
7.8 Fixing corrugated asbestos 1c+2D.L 8hr. 25m2
7.9 Fixing EGA sheet joining 1c+2D.L 8hr. 30m2
7.1 Joining zigba truss up to 10m span on groun 1c+2D.L 8hr. 3 truss
7.11 Zigba truss erecting 1c+2D.L 8hr. 15 truss
7.12 Facial board fixing 1c+2D.L 8hr. 70ml
8 Joinery Work
8.1 Wooden door fixing 1c+2D.L 8 hr 3 pcs
8.2 Wooden Window fixing 1c+2D.L 8 hr 4 pcs
8.3 Chip wood ceiling fixing 1c+2D.L 8 hr 10 m2
8.4 Hard boared ceiling fixing 1c+2D.L 8 hr 10 m2
8.5 Abujedie Ceiling 1c+2D.L 8 hr 13 m2
9 Metal work
9.1 Metal door fixing 1c+2D.L 8 hr 3 pcs
9.1 Metal window fixing 1c+2D.L 8 hr 4 pcs
9.1 French window fixing 1c+2D.L 8 hr 2 pcs
11 Floor finishing
11.1 Cement screed 1m +2D.L 8 hr 14 m2
11.2 Cement tile fixing 1m +2D.L 8 hr 10 m2
11.3 Plastic tile fixing 1m +2D.L 8 hr 17 m2
11.4 Par-quet flooring 1m +2D.L 8 hr 15 m2
11.5 Wooden flooring 1m +2D.L 8 hr 8 m2
11.6 Ceramic wall tile 1m +2D.L 8 hr 7 m2
11.7 Plastic tile skirting 1m +2D.L 8 hr 40 ml
11.8 Ceramic tile kirting 1m +2D.L 8 hr 12 ml
11.9 Marble slate flooring 1m +2D.L 8 hr 12 ml
11.10 Marble slate skirting 1m +2D.L 8 hr 16 ml
11.11 Fixing pre-cast window sill 1m +2D.L 8 hr 10 ml
11.12 Fixing un pre-cast window sill 1m +2D.L 8 hr 6 ml
12 Glazing work
12.1 Cutting 1c+2D.L 8 hr 50 m2
12.2 Fixing 1c+2D.L 8 hr 20 m2
13 Painting work
a) plastic paint
14 Sanitary Work
14.1 G.I pipe lyeing in ground 1/2"-11/4" 1p +2D.L 8 hr 120 ml
15 Electrical Installation
15.1 Fixing conduits 1e +1D.L 8 hr 40 ml
15.2 Pulling wires 1e +1D.L 8 hr 50 ml
15.3 Fixing switch & out- lets 1e +1D.L 8 hr 20 pcs
15.4 Fixing Fittings 1e +1D.L 8 hr 10 pcs
15.5 Fitting distribution board 1e +1D.L 8 hr 10 pcs
16 Site Work
16.1 Drain laying
Ø 0.10 - 0.20 m 1m +3D.L 8 hr 30 ml
Ø 0.40 - 0.60 m 1m +3D.L 8 hr 20 ml
Ø 0.80 - 1.00 m 1m +3D.L 8 hr 10 ml
16.2 Curb stone 1m +3D.L 8 hr 30 ml
16.3 0.60x0.60x0.60m manhole out of brick 1m +3D.L 8 hr 3 pcs
17.4 0.60x0.60x0.60m manhole out of hollow block1m +3D.L 8 hr 2 pcs
18.5 Fencing with galvanized fencing net 1c + 2D.L 8 hr 50 m2