Download as xls, pdf, or txt
Download as xls, pdf, or txt
You are on page 1of 328

SUMMARY

A-SUB STRUCTURE

1 EXCAVATION AND EARTH WORK……………… BIRR 93746.12

2 MASONRY WORK…………………………………………BIRR 73761.89

3 CONCRETE WORK…………………………………………
BIRR 178427.71

SUB TOTAL A……………………. BIRR 345935.72

B-SUPER STRUCTURE

1 CONCRETE WORK…………………………………………
BIRR 569613.74

2 BLOCK WORK………………………………………………
BIRR 79253.11

3 ROOFING WORKS ………………………….…………. BIRR 75488.63

3 CARPENTRY AND JOINERY…………………………. BIRR 57209.01

4 METAL AND ALUMINUM WORK……………………… BIRR 77549.90

5 FINISHING WORK…………………………………………BIRR 271683.01

7 PAINTING………………………………………………………
BIRR 145102.01

6 GLAZING……………………………………………………BIRR 20378.24

9 SANITARY INSTALLATION………………………………BIRR 99422.62

9 SITE WORKS ……………………………… BIRR 56188.20

8 ELECTRICAL INSTALLATION…………………………. BIRR

SUB TOTAL B……………………. BIRR 1,451,888.46

TOTAL A+B……………………. BIRR 1,797,824.18

'The Amen' Consulting Architects and Engineers


15% VAT ………….. BIRR 107,869.45

Grand Total ………………… BIRR 1,905,693.63

16,196.61
17,168.41

'The Amen' Consulting Architects and Engineers


'The Amen' Consulting Architects and Engineers
ITEM DESCRIPTION UNIT QTY. RATE AMOUNT
A. SUB STRUCTURE

1. EXCAVATION & EARTH WORK

1.1 Excavate over site to remove all objectionable


materials to an average depth of 30cm. Area
of excavation includes pavement around
building. M2 150.00 20.51 3076.5

1.2 Bulk excavation in ordinary soil to reduce the


level to an average depth of 355cm below
natural ground level. M3 66.54 145.47 9679.5738

1.3 Pit excavation for isolated foundation in


ordinary soil to a depth of 300cm starting
from reduced level. M3 32.40 180.09 5834.792826

1.4 Trench excavation for external stair case masonry


wall in ordinary soil to a depth of 100cm starting
from reduced ground level. M3 20.45 161.63 3305.01024

1.5 Back fill around footing pits with non expansive


granular selected material maximum size 60mm
with fine particles 5-10% by weight in layers
of 20 cm thick wet and well rolled until attains
a minimum of 95% proctor density. M3 30.04 557.97 16760.02388

1.6 Back fill non expansive well graded granular


selected material around masonry wall
with different layers to allow the circulation of
water for perforated pipe and well rolled until
attains a minimum of 95% proctor density. M3 26.95 557.97 15037.2915

1.7 130 cm thick back fill with non expansive granular


selected material maximum size 60mm with fine
particles 5-10% by weight to raise the stripped
ground level to the bottom of hardcore in layers
of 20 cm thick wet and well rolled until attains
a minimum of 95% proctor density. M3 4.13 557.97 2301.62625

1.8 Cart away surplus excavated material and


deposit at a suitable distance. M3 135.81 59.15 8033.0432

1.9 25cm thick basaltic or equivalent stone


hard core well rolled consolidated and blinded
with crushed stone. M2 86.08 345.24 29718.2592

Total to Summary……………………………..
…………………………...…….Birr 93746.1209

'The Amen' Consulting Architects and Engineers 4


ITEM DESCRIPTION UNIT QTY. RATE AMOUNT

2. MASONRY WORK

2.1 50 cm thick hard trachitic or equivalent stone


masonry foundation wall bedded in cement
mortar (1:4) below natural ground level. M3 22.65 2047.04 46365.456

2.2 50 cm thick hard trachitic or equivalent stone


masonry foundation wall bedded in cement
mortar (1:4) above natural ground level. M3 11.33 2187.34 24771.6255

2.3 ditto for enterance stairs M3 1.20 2187.34 2624.808

Total to Summary…………………………….
…………………….Birr 73761.8895

3. CONCRETE WORK

Particular attention is to be given to the


following remarks along with the technical
specification and method of measurement.

Ingredients for concrete work :

The quality of materials and workman ship must


fulfill the requirements and concrete trial mixes
shall be prepared and certified by laboratory test
results before any casting of structural elements.
During casting samples should be taken for
laboratory tests following specification requirement.

Concrete :

The specified concrete strength must be


confirmed by laboratory test.

Reinforcement bar :

The specified yield strength and other


related properties of reinforcement bar
must be confirmed either by manufacturer's
catalogue/manual or / and by laboratory test.

3.1 5cm thick lean concrete in C-5 with minimum


cement content of 150Kg/m3under:

a. Footing pads M2 12.00 114.43 1373.16

b. Masonry wall M2 37.75 114.43 4319.7325

3.2 Reinforced concrete quality C-25 with 360kg


cement/M3 of concrete filled in to formwork

'The Amen' Consulting Architects and Engineers 5


ITEM DESCRIPTION UNIT QTY. RATE AMOUNT
and vibrated around rod reinforcement bars.
(Steel and form work measured separately)

a. In isolated footing pads M3 3.00 3137.36 9412.08

b. In foundation column M3 1.28 3254.63 4149.65325

c. In grade beam M3 4.93 3137.36 15454.63536

d. In ground floor slab M2 86.08 313.74 27006.7392

3.4 Provide, cut and fix in position sawn Zigba


wood or metal panel form work:

a. In isolated footing pads M2 12.30 291.60 3586.68

b. In foundation column M2 22.44 291.60 6543.504

c. In grade beam M2 43.26 291.60 12614.616

3.5 Reinforcement bar according to structural


drawings. Price includes cutting, bending,
placing in position & tying wires.

Diameter 6mm undeformed bars Kg 275 101.67 27925

Diameter 8mm deformed bars Kg 0 87.73 0

Diameter 10mm deformed bars Kg 208 92.48 19206

Diameter 12mm deformed bars Kg 521 89.81 46835

Diameter 14mm deformed bars Kg 0 91.28 0

Total to Summary……………...………………
……………………….Birr 178427.709

B. SUPER STRUCTURE

1. CONCRETE WORK

Particular attention is to be given to the


following remarks along with the technical
specification and method of measurement.

Ingredients for concrete work :

The quality of materials and workman ship must


fulfill the requirements and concrete trial mixes

'The Amen' Consulting Architects and Engineers 6


ITEM DESCRIPTION UNIT QTY. RATE AMOUNT

shall be prepared and certified by laboratory test


results before any casting of structural elements.
During casting samples should be taken for
laboratory tests following specification requirement.

Concrete :

The specified concrete strength must be


confirmed by laboratory test.

Reinforcement bar :

The specified yield strength and other


related properties of reinforcement bar
must be confirmed either by manufacturer's
catalogue/manual or / and by laboratory test.

1.1 Reinforced concrete quality C-25 with 360kg


cement/M3 of concrete filled in to formwork
and vibrated around rod reinforcement bars.
(Steel and form work measured separately)

a. In elevation column M3 2.99 3377.17 10106.18

b. In Top beams M3 91 3242.84 295098.44

c, seat of water tank M3 0.04 3242.84 129.71

d. In parapet concrete gutter M3 9.83 3242.84 31877.12

e. arch beam M3 0.32 3242.84 1037.71

1.2 Provide, cut and fix in position metal panel or


sawn Zigba wood form work

a. In elevation column M2 57.57 304.56 17534.28

b. In Top beams M2 57.47 304.56 17503.06

c, seat of water tank M2 4.35 304.56 1324.84

d. In parapet concrete gutter M2 141.74 304.56 43168.33

e. arch beam M2 4.80 304.56 1461.89

1.3 Reinforcement bar according to structural


drawings. Price includes cutting, bending,
placing in position & tying wires.

'The Amen' Consulting Architects and Engineers 7


ITEM DESCRIPTION UNIT QTY. RATE AMOUNT

Diameter 6mm deformed bars Kg 57 101.67 5832

Diameter 8mm deformed bars Kg 630 87.73 55270

Diameter 10mm deformed bars Kg 371 92.48 34292

Diameter 12mm deformed bars Kg 612 89.81 54978

Diameter 14mm deformed bars Kg 0 91.28 0

Total to Summary……………..…………..
……..……..…….……………….Birr 569613.738

2. BLOCK WORK

In addition to strength, size, and other specified


requirements HCB blocks must satisfy the weight
requirements specified in EBCS - 1, 1995.

2.1 20cm thick class-B H.C.B wall bedded and


Joined in cement mortar mix 1:3 both sides
left for plaster. m2 150.96 404.36 61041.78124

2.2 Ditto but 15cm thick. m2 52.61 346.19 18211.32495

Total to Summary………………………….
……………………….Birr 79253.1062

3, ROOFING WORKS

3.1 Roof cover G-28 CIS m2 51.85 612.47 31757.34

3.1 Roof cover G-30 CIS m2 0.00 554.13 0.00

3.1 Roof cover G-32 CIS m2 0.00 512.47 0.00

3.1 Roof cover G-35 CIS m2 0.00 512.47 0.00

3.2 Roof cover Asbestos m2 83.33 355.98 29662.10

3.3 ridged covers m2 14.60 172.41 2517.19

3.3 valley covers m2 22.50 243.20 5472.00

3.4 Gutter m2 25.00 243.20 6080.00

Total to Summary………………………….
……………………….Birr 75488.63

'The Amen' Consulting Architects and Engineers 8


ITEM DESCRIPTION UNIT QTY. RATE AMOUNT

4 . CARPENTRY & JOINERY


4.1 carpentery work

φ8-10cm thick equaliptesvertical and diagonal post ml 176.46 49.21 8683.60

φ10-12cm thick equaliptes rafter ml 292.16 57.55 16813.81

φ50mm*70mmmm thick zigba purlin ml 140.10 92.99 13027.90

4.2 Joinery

Flush door comprising of 4cm thick semi-


solid flush door both sides covered with 4mm
thick kerero ply wood equipped with suitable
hinges, bolts and handles of the best quality.
The locks shall be cylinder. All wooden door
should receive primer stopping, grinding and
two coats of varnish paint.

a Type D-1 size 3.15 x 1.2 pcs 1.00 12843.20 12843.20102

b Type D-2 size 2.10 x 0.80 pcs 1.00 5840.51 5840.508813

Total to Summary…………….………………
……………………….Birr 57209.0134

5. METAL AND ALUMINUM WORK

All windows and door are manufactured from Aluminum


metal profiles.(or equivalent product approved by the
architect.) All works should be cut and assembled
to sizes and shapes of the window and door schedule
upon submitting workshop drawing by the contractor.
Unit price includes anchor bolts 2mm thick metal
cover plates, quality lock, door stoppers and other
necessary accessories for completing the work. All
according to architectural door and window schedule.

5.1 Metal works


a for main door

Type D-6, size 3.40x 3m m2 10.20 5075.25 51767.53543

5.2 Almunium works

'The Amen' Consulting Architects and Engineers 9


ITEM DESCRIPTION UNIT QTY. RATE AMOUNT
5.2.1 DOORs

a Type D-3,size 0.80 x 3.15 cm m2 5.04 934.87 4711.764191

b Type D-4,size 0.90x 3.15 cm m2 2.84 934.87 2650.367358

c Type D-7,size 0.70 x 3.15cm m2 2.20 934.87 2061.396834

5.2.2 WINDOWS

a Type W-1,size 1.05 x 2.15 cm m2 6.77 935.11 6333.044125

b Type W-2,size 0.80 x 215 cm m2 1.72 935.11 1608.392159

4.3 CURTAIN WALL


The material should be thermal resistance and
heat insulator.
a Type CW-1,size 1.91 x 3.15 cm m2 6.02 978.82 5889.096615

b Type CW-2,size 0.82 x 3.15 cm m2 2.58 978.82 2528.303259

4.4 Supply and fix in position handrails and balusters


aluminum profile as per the detail drawing given
by the consultant.
40x40x2.5 SHS for handrails KG 59.92 0

65x65x5 SHS for handrails KG 54.66 0

Total to Summary……………...…………….. ……………………….Birr 77549.9

6 . FINISHING WORK

Finishing work shall include all surface


pre-cleaning preparation application of finish,
polishing and cleaning at the end of finishing
work.
6.1. WALL FINISHING
6.1.1 Apply two coats of plaster in cement mortar
mix 1:3 to receive Quartz paints . Provide grooves recessed
by 30cm over all external surface excluding of verandah walls

a. External block wall surface m2 144.23 147.57 21284.02

b.for edge of exposed concrete gutter, beams and columns ml 431.95 20.00 8639.00

6.1.2 Apply two coats of plaster in cement mortar


mix 1:3 to receive gypsum painting.

'The Amen' Consulting Architects and Engineers 10


ITEM DESCRIPTION UNIT QTY. RATE AMOUNT

a. for verandah and Internal block wall surface m2 274.00 147.57 40434.48

6.1.3 Apply two coats of plaster in cement mortar


mix 1:2 to wall receiving internal ceramic wall tile. m2 43.08 80.31 3459.82

6.1.4 200x200x6mm thick glazed ceramic wall tile


applied to plastered wall on and including
cement mortar (1:3) backing and white
cement grouting. m2 43.08 515.48 22206.88

6.2. FLOOR FINISHING

Supply and lay 40x40x0.9cm thick porcelain floor tile fixed on floor with
6.2.1 42mm thick cement mortar of 1:3 ratio. m2 75.03 1868.00 140146.70

2mm thick high quality PVC floor tile flooring laid with approved
6.2.2 type of adhesive material. m2 7.06 536.74 3790.46

3cm thick Welega black marble tile for edge of verandah on with
6.2.3 proper grouting of joints in cement mortar mix of 1:3 m2 2.80 4211.85 11793.18

Supply and lay 10x0.6cm thick porcelain tile skirting fixed on wall with cement
mortar of 1:3 mix ratio and including with cement mortar of 1:1 mix ratio
6.2.4 backing. ml 87.76 103.75 9105.10

6.3 CEILING WORK

A. Gypsum Ceiling m2 83.33 45.00 3749.715

6.4 Door Sill and Window Sill


6.4.1 Window Sill

Marble window cill on and including cement


mortar bed jointed in cement mortar mix of 1:3.

a. Size 27 x 3cm ml 4.20 623.68 2619.46

6.4.2 Door Sill

Marble door cill on and including cement mortar


bed jointed in cement mortar mix of 1:3

a. Size 20 x 3cm ml 8.62 516.73 4454.21

Total to Summary………………………..…….
……………………….Birr 271683.01

7. Painting

'The Amen' Consulting Architects and Engineers 11


ITEM DESCRIPTION UNIT QTY. RATE AMOUNT
7.1 Prepare the surface and apply three coats
of Granite paint of chosen type
and clour to:

a External plastered surface m2 190.73 657.92 125485.0816

7.2 Prepare the surface and apply three coats


of plastic emulsion paint of chosen type
and clour to:

a Internal plastered surface m2 197.18 66.40 13092.6856

7.3 Prepare the surface and apply three coats


syntactic oil paint to:

a All toilets and Kitchen area above ceramic wall tile m2 74.31 87.80 6524.2424

Total to Summary……………………………
……………………….Birr 145102.01

8 . Glazing

8.1 Supply and properly fix chosen colour and type


glass to windows, doors and curtain walls. Curtain
wall should be thermal insulator and wind force
resistance. Use proper workmanship specially for
fixing curtain wall.

a. 4mm thick door and window glass m2 17.69 713.00 12615.92895

b. 5mm thick glazing curtain wall m2 8.235 942.60 7762.311

Total to Summary……………………………
……………………….Birr 20378.24

9.SANITARY INSTALLATION
A. Interior Installation

Water Supply Pipes & fittings

9.1 Supply and install galvanized steel pipes from elevated water
tank to cold and hot water distibution to all santitary fixtures as
shown on the drawing

Diameter 15 mm ml 28.00 131.60 3684.8

Diameter 20 mm ml 5.50 247.90 1363.45

Diameter 25mm ml 21.00 320.50 6730.5

9.2 Supply and install gate valves made of brass

'The Amen' Consulting Architects and Engineers 12


ITEM DESCRIPTION UNIT QTY. RATE AMOUNT

complete with rubber gaskets, hand wheels and


connecting pieces such as unions etc, for all fixtures

Diameter 15 mm Pcs 21.00 256.40 5384.4

Diameter 25 mm Pcs 21.00 349.40 7337.4

9.22 Supply and install galvanized steel pipe from main


line to roof fibre glass water tank complete with
all the necessary accessories.

Diameter 32mm Ml 15.00 357.00 5355

9.23 Supply and install water meter complete with all


the necessary acessories

Diameter 25 mm ml 1.00 1288.10 1288.1

Elevated water tank

9.3 Supply and mount 1m³ fibre glass water tank on


roof complete with all the necessary accessories

a) Size of water tank = 1000 lit Pc 1.00 5419.80 5419.8

Sanitary Fixtures

9.6 Supply and install high level water closet


white glazed vitreous China WC pan of approved
quality complete with all the necessary accessories Pcs 1.00 3918.90 3918.9

9.6 Supply and install low high water closet


white glazed vitreous China WC pan of approved
quality complete with all the necessary accessories Pcs 1.00 2189.80 2189.8

9.7 Supply and install hand wash basins made


of white vitreous China with two tap holes
complete with all the necessary accessories

Size :- 500 x 405 mm Pcs 2.00 4347.80 8695.6

9.8 Supply and fix toilet paper holder in white vitreous


China complete with all the necessary accessories Pcs 2.00 463.50 927

9.9 Supply and fix crystal glass mirror 500 x 400 mm


including chrome plated brass clips and screws Pcs 2.00 1313.00 2626

9.10 Supply and fix soap holder in white shower


vitreous for hand wash basin and bath tub
complete with all necessary accessories Pcs 5.00 563.50 2817.5

'The Amen' Consulting Architects and Engineers 13


ITEM DESCRIPTION UNIT QTY. RATE AMOUNT
9.11 Supply and fix towel hanger 610 x 25 mm
with chrome plated tubular towel rail complete
with the necessary accessories. Pcs 3.00 458.90 1376.7

9.12 Supply and install stainless steel kitchen sink


with double bowl with chrome plated taps, uPVC
siphon complete with all necessary accessories

Size :- 1,500 x 600 mm Pcs 1.00 4212.70 4212.7

9.13 Supply and fix electric water heater complete


with all the necessary accessories

Capacity 50 litre Pcs 1.00 8835.50 8835.5

9.14 Supply and install floor drainage complete with all the
necessary accessories.

size=150x150mm Pcs 3.00 155.40 466.2

9.15 Supply and install shower units made of


enamelled fiber plate including shower head
and trap mixing battery,waste water trap complete
with all the accessories
. Size 700x700mm Pcs 2.00 2615.80 5231.6

9.16 Supply and install bath tub of enamelled cast iron


complete with all the necesssary accessories. Pc 1.00 5135.50 5135.5

6. Waste water & Ventilation Pipe

9.17 Supply and install soil , waste and vent pipe in


horizontal branches and vertical stacks made
of PVC including the necessary fittings such as
bends, branches tees, elbow etc. All horizontal
branches should be laid at a slope of 2% .

Diameter 50 mm ml 9.70 102.10 990.37

Diameter 80 mm ml 10.00 212.30 2123

Diameter 100 mm ml 10.00 245.30 2453

9.18 Supply and install vent caps made of PVC


at vent pipes fitted with PVC pipe roof weathering
slate at roof level.
Diameter 50 mm Pc 2.00 33.30 66.6

Down Pipe

9.19 Supply and fix diameter PVC down pipes secured


to walls with iron straps and given two coats of sun

'The Amen' Consulting Architects and Engineers 14


ITEM DESCRIPTION UNIT QTY. RATE AMOUNT
reflecting paint

Diameter100mm ml 44.00 245.30 10793.2

Total to Summary……………………………
……………………….Birr 99422.62

9.SITE WORKS

sanitary manholes & concrete pipe for sewerage


9.20 Construct sanitary manholes on a domestic sewer
lines in double brick wall on a base of mass
concrete slab 150mm thick with proper slope for
smooth flow and with 80 mm R.C slab cover and
steel bar handle as shown on the detail drawing.

Size:- 60 x 60cm Pc 2.00 2427.26 4854.527444


Avg. depth =60 cm

9.21 Supply and lay concrete pipe for sewerage


according to the drawing

Diameter 150 mm Ml 5.50 298.17 1639.920958

Septic Tank

9.24 Construct septic tank with capacity 25m³ as shown


on the detail drawing.

1. EXCAVATION & EARTH WORK

1.3 Pit excavation for isolated foundation in


ordinary soil to a depth of 300cm starting
from reduced level. M3 60.93 180.09 10973.3589

1.4 Trench excavation for external stair case masonry


wall in ordinary soil to a depth of 100cm starting
from reduced ground level. M3 9.90 167.11 1654.347528

1.6 Back fill non expansive well graded granular


selected material around masonry wall
with different layers to allow the circulation of
water for perforated pipe and well rolled until
attains a minimum of 95% proctor density. M3 3.30 298.99 986.6514232

1.8 Cart away surplus excavated material and


deposit at a suitable distance. M3 70.83 103.43 7326.208201

'The Amen' Consulting Architects and Engineers 15


ITEM DESCRIPTION UNIT QTY. RATE AMOUNT

2. MASONRY WORK

2.1 50 cm thick hard trachitic or equivalent stone


masonry foundation wall bedded in cement
mortar (1:4) below natural ground level. M3 6.60 1545.82 10202.38204

3. CONCRETE WORK

3.1 5cm thick lean concrete in C-5 with minimum


cement content of 150Kg/m3under:

b. Masonry wall M2 12.00 84.87 1018.442298

3.2 Reinforced concrete quality C-25 with 360kg


cement/M3 of concrete filled in to formwork
and vibrated around rod reinforcement bars.
(Steel and form work measured separately)

c. In grade beam M3 0.52 3168.63 1647.688731

d. In ground floor slab M2 5.76 404.63 2330.648967

3.4 Provide, cut and fix in position sawn Zigba


wood or metal panel form work:

c. In grade beam M2 3.64 502.79 1830.154086

d. In ground floor slab M2 5.76 502.79 2896.068005

3.5 Reinforcement bar according to structural


drawings. Price includes cutting, bending,
placing in position & tying wires.

Diameter 6mm deformed bars Kg 10 52.36 521

Diameter 12mm deformed bars Kg 98 51.29 5019

Diameter 14mm deformed bars Kg 62 53.16 3288

Total to Summary……………………………
……………………….Birr 56188.1977

8. ELECTRICAL INSTALLATION

DISTRIBUTION BOARD
8.1 Flush mounted sub distribution board,SDB-C
with lockable door, earthing lead, connectors
and all the necessary accessories consisting of:-

'The Amen' Consulting Architects and Engineers 16


ITEM DESCRIPTION UNIT QTY. RATE AMOUNT

1Pc MCB of 32A, 3ph Icu = 10 KA


1Pc MCB of 25A, 3ph Icu = 10 KA
2Pcs MCB of 16A, 1ph Icu = 6 KA
4Pc MCB of 10A, 1ph Icu = 6KA
1pc contactor of 25A,3ph with thermal relay &
thermal setting coresponding to pump power.
all complete with 50A phase bar,ample reserve
spaces and all labled with appropriate labling
material and equipment. Nº 1 1550 1550

LIGHT POINTS
8.5 Light points fed through PVC conductor of.
2 x 2.5 sq.mm.in thermoplastic conduit of diam
16mm in/under surface including junction boxes
screw type connectors with insulating caps and
cover. Nº 198 95 18810

SWITCH
8.6 Flush mounted Legrand Suno range switch or
equivalent with non circular corresponding box:-
a. Single pole Nº 22 36 792
b. Double pole Nº 16 39 624
c. Triple pole Nº 5 45 225
d. Two way Nº 38 45 1710
e. Double Two way Nº 20 50 1000
f. Intermediate Nº 13 60 780

SOCKET OUTLET POINT


8.7 Socket outlets points for flush mounting fed
through PVC conductor of 3 x 2.5 sq.mm
in thermoplastic conduit of diameter 16mm
in/under surface including junction boxes,screw
type connectors and cover all complete Nº 115 110 12650

8.8 Ditto but fed through PVC coductor of 3x4


sq.mm in diameter 21 mm. Nº 5 130 650

SOCKET OUTLET
8.9 Flush mounted Legrand Suno range 2P+E /16A
schuo type or equivalent socket outlet with non
circular corresponding box. Nº 91 36 3276

8.10 Ditto but twin sockets. Nº 16 45 720

8.11 Ditto but for water heater with switch. Nº 8 60 480

8.12 Ditto but 20A for stove with switch. Nº 5 45 225

BELL SYSTEM
8.13 Bell points fed through PVC conductor of.
2 x 1 sq.mm.in thermoplastic conduit of diam.
13mm in/under surface including junction boxes

'The Amen' Consulting Architects and Engineers 17


ITEM DESCRIPTION UNIT QTY. RATE AMOUNT
screw type connectors with insulating caps and
cover. Nº 24 75 1800

BELL PUSH BUTTON


8.14 Flush mounted Legrand Suno range push bitton
or equivalent with non circular corresponding
box. Nº 28 36 1008

CHIME
8.15 Two note 220v Legrand melody chime. Nº 4 250 1000

8.16 Digital indicator of 4 numbers for 220v operation


with call canceling system. Nº 4 700 2800

TELEPHONE POINT:-
8.17 Telephone point:- Only conduit of diameter 19 -
29mm, outlet box, pull wire and tele terminal
box as per ETC rules and regulations Nº 28 60 1680

TV POINT:-
8.18 Tv point:- Only conduit of diameter 29mm,
outlet box & pull wire. Nº 20 60 1200

POWER CABLES
Siemens NYY .6/1KV

8.19 2x4 sq.mm. M 73 10 730


8.20 3x6 sq.mm. M 6 34 204
8.21 3x10 sq.mm. M 110 45 4950
8.22 5x10 sq.mm. M 30 75 2250
8.23 3x50/25 sq.mm tentative measurment. M 30 200 6000

PVC
8.24 diameter 32mm. M 4 9 36
8.25 diameter 40mm. M 80 11 880
8.26 diameter 50mm. M 21 13 273
8.27 diameter 110mm. M 25 30 750

MANHOLE
8.28 50x50x70 cms manhole with RC cover. Nº 4 350 1400
8.29 120x100x60 cms manhole with RC cover. Nº 1 800 800

GROUNDING
8.30 40x40x50 cms manhole with cover. Nº 1 300 300
8.31 1x25 sq.mm copper wire M 15 30 450
8.32 diameter 12.5 mm and 2m copper rod. Nº 1 450 450

FLOAT SWITCH
8.33 Mercury float switch for elavated water tank &
ground reservour. Nº 2 1500 3000
8.34 2x2.5 sq.mm tentative measument M 15 5 75
8.35 3x2.5 sq.mm tentative measument M 50 10 500

'The Amen' Consulting Architects and Engineers 18


ITEM DESCRIPTION UNIT QTY. RATE AMOUNT
LIGHTNING PREVENTOR
8.36 Pulsar/ P2 with 6 m mast , base & anchor all
complete. Nº 1 21000 21000
8.37 25x3 mm copper tape M 60 96 5760
8.37 1x70 sq.mm bare copper wire. M 20 25 500
8.38 Test point Nº 2 450 900
8.39 Diameter 16 mm & 2500 mm copper rod. Nº 2 520 1040
8.40 50x50x60 cms manhole with RC cover. Nº 2 350 700

LIGHT FIXTURES (optional)


As specified or equivalent
8.41 Pnilips TCS 120/418 IC M2 + 4x18w fl lamp. Nº 9 780 7020
8.42 Pnilips TCS 020/136 HFP M2 + 1x36w fl lamp
with emergency kit. Nº 5 2200 11000
8.43 Pnilips TCS 020/136 IC M2 + 1x36w fl lamp. Nº 36 350 12600
8.44 RZB 93 1044.342 + TC-TSE 15W/63 lamp. Nº 4 600 2400
8.45 RZB 58 310.863 + 100 w lamp. Nº 5 500 2500
8.46 Lombardo LB 51121 + 1x15w energy saving
lamp. Nº 13 250 3250
8.47 Pilux/Danpex MAL 1.18 DLTHSR + 1x18 w fl
lamp. Nº 13 260 3380
8.48 RZB 93 107.852 + 150 w lamp. Nº 18 950 17100
8.48 Massive 75 680/03/39 + 3x60w lamp. Nº 10 800 8000
8.49 Massive 80 681/13/39 + 60w lamp. Nº 20 250 5000
8.50 Philips DBS 201 + 40w lamp. Nº 16 650 10400
8.51 Massive 75 680/01/39 + 2x60w lamp. Nº 20 600 12000
8.52 Lombardo LB 51112 + 2x15w energy saving
lamp. Nº 4 350 1400
8.53 Lombardo LB 51122 + 1x15w energy saving
lamp. Nº 24 250 6000

EXTERNAL LIGHTING
8.54 Octagonal steel pole of 3.5m with base ,fuse box,
fuse of 6A ,inspection hole ,flange plate ,anchor
bolt and Fumagalli G40.B40.M smoked fixture
with 1x23 w delux lamp all complete Nº 6 3500 21000

8.55 16A, 1-ph isolating switch in water proof box


for external lirhting. Nº 1 150 150

Total to Summary……………………………..
…………………………...…….Birr 229128

'The Amen' Consulting Architects and Engineers 19


Project L-SHAPE Residential Home

Client W/ro Atilabachew

ITEM DESCRIPTION Timing SIZE

A SUB STRUCTURE

1 Excavation and earth work

1.1 Site clerance 1 15.00


10.00

1.2 Bulk excavation from 1 15.00


N.G.L not exiding adepth of 10.00
0.60cm 0.60

1.2 ditto for parking area 1 8.50


4.60
0.60

1.3 pit excavation over reduced level and not exceed 250cm

F1 12 1.50
1.50
1.20

1.5 Trench excavation for stone masonery


2 9.00
1.00
0.40

1 7.50
1.00
0.40

1 3.40
1.00
0.40

2 8.00
1.00
0.40

'The Amen' Consulting Architects and Engineers


1 2.22
1.00
0.40

1 4.00
1.00
0.40

1.6 Backfill non expansive well graded granular selected material

a around foundations pads 12 1.50


1.50
1.25

12 1.00
1.00
0.25

12 0.95
0.25
0.25

b around stone
masonry
1 77.00
1.00
0.70

1 77.00
0.70
0.50

c under hard core 1 8.50


4.00
0.25

1 8.00
3.50
0.25

'The Amen' Consulting Architects and Engineers


1.9 Cart away
1 82.10
0.20

1 66.54

1 32.40

1 20.45

1.9 Hard core


1 15.00
5.00

1 5.50
5.00

1 82.10
0.20

2 Stone masonery
2.1 BGL 1 77.00
0.60
0.50

Ditto for Footing columns 12 0.60


0.25
0.25

2.2 AGL 1 77.00


0.50
0.30

Ditto for Footing columns 12 0.30


0.25
0.25

2.3 For Entarance stair 2 2.00


0.90
0.30

'The Amen' Consulting Architects and Engineers


3 CONCRETE WORK

3.1 Lean concrete under


a footing pads
12 1.00
1.00

b stone masonery
on axis A-A & B-B 2 12.50
0.50

on axis A`-A` 1 8.00


0.50

axis C-C 1 4.00


0.50

on axis 1'-1',3-3,4-4 & 5-5 4 5.00


0.50

on axis 1-1& 2-2 2 10.00


0.50

Ditto for Footing columns 12 0.25


0.25

3.2 C-25 Concrete for


a Footing pads
FP-1 12 1.00
1.00
0.25

b Foundation column
FC1 12 1.70
0.25
0.25

c Grade Beams
on axis A-A & B-B 2 14.00
0.30
0.20

'The Amen' Consulting Architects and Engineers


on axis A`-A` 1 9.20
0.30
0.20

axis C-C 1 4.90


0.30
0.20

on axis 1'-1',3-3,4-4 & 5-5 4 5.00


0.30
0.20

on axis 1-1& 2-2 2 10.00


0.30
0.20

d ground Floor slab


1 15.00
5.00

1 5.50
5.00

ditto for grade beam 1 82.10


0.20

3.3 Formwork for


a Footing pads
F1 12 4.10
0.25

b Foundation column
FC1 12 1.70
1.1

d Grade Beams
on axis A-A & B-B 4 14.00
0.30

on axis A`-A` 2 9.20


0.30

'The Amen' Consulting Architects and Engineers


axis C-C 2 4.90
0.30

on axis 1'-1',3-3,4-4 & 5-5 8 5.00


0.30

on axis 1-1& 2-2 2 10.00


0.30

B SUPER STRUCTURE

1 CONCRETE WORK

1.1 C-25 CONCRETE for

a Elevation colunmn
C1 19 3.15
0.25
0.20

b top Beams
on axis A-A & B-B 2 14.00
0.25
0.20

on axis A`-A` 1 9.20


0.25
0.20

axis C-C 1 4.90


0.25
0.20

on axis 1'-1',3-3,4-4 & 5-5 4 5.00


0.25
0.20

on axis 1-1& 2-2 2 10.00


0.25
0.20

'The Amen' Consulting Architects and Engineers


c parapet concrete gutter
1 23.20
1.00
0.15

d arch beam 2 4.00


0.20
0.20

d seat of elivated water tank


1 1.00
0.20
0.20

1 1.50
1.50
0.15

1.2 Formwork for


a Elevation colunmn
C1 19 3.15
0.95

b top Beams
on axis A-A & B-B 2 14.00
0.70

on axis A`-A` 1 9.20


0.70

axis C-C 1 4.90


0.70

on axis 1'-1',3-3,4-4 & 5-5 4 5.00


0.70

on axis 1-1& 2-2 2 10.00


0.70

'The Amen' Consulting Architects and Engineers


c parapet concrete gutter
1 23.20
2.00

d arch beam 2 4.00


0.60

d seat of elivated water tank


1 1.50
0.80

1 1.50
1.50

4 1.50
0.15

2 BLOCK WORK
2.1 20cm thick HCB
a For External wall surface
on axis A-A & A`-A` 1 21.00
3.15

on axis B-B 1 2.70


3.15

axis C-C 1 4.75


3.15

on axis 1-1, 1'-1', 4-4 & 5-5 1 19.98


3.15

b For parapet wall surface


Parapet Walls1 1 24.25
0.90

triangular Parapet Walls1 0.5 3.25


2.00

triangular Parapet Walls2 0.5 4.25

'The Amen' Consulting Architects and Engineers


2.00

Ditto for opening of D1 1 3.15


1.20

Ditto for opening of D2 2 3.15


0.80

Ditto for opening of D3 1 3.15


0.90

Ditto for opening of D4 1 3.15


0.70

Ditto for opening of CW1 1 3.15


1.90

Ditto for opening of CW2 1 3.15


0.82

Ditto for opening of W1 3 2.15


1.05

Ditto for opening of W2 1 2.15


0.80

2.1 15cm thick HCB


a internal wall surface

on axis A`-A` 1 3.90


3.15

on axis 1'-1',2-2, 3-4 & 4-4 4 3.40


3.15

Ditto for opening of D2 1 3.15


0.80

3.1 ROOFING AND WATER


PROOFING
Roof cover G-28 CIS

'The Amen' Consulting Architects and Engineers


For rectangular roof area 1 4.95
1.96

For Trapizoid roof area 1 6.09


6.09 4.95

For Triangular roof area 0.5 4.85


4.95

Roof cover Asbestos

For Trapizoid roof area 4 3.65


3.29 3.29

0.5 5.00
3.2 For Triangular roof area 2 4.96

For Trapizoid roof area 4 1.66


1.66 1.58

ridged covers

2 14.6

valley covers

1 22.5

3.4 Gutter 1 25

4 Carpentery and Joinery

4.1 carpentery work

4.1.1 φ8-10cm thick equaliptes vertical and diagonal post

for T-1 7 3

'The Amen' Consulting Architects and Engineers


for T-2 & T-3 2 2.99

for T-4&T-5 1 3.17

for T-6 1 8.85

forT-7&T-8 2 5.15

for T-9,T-10&T-11 6 5.91

for T-12 4 13

for T-13 4 2.65

for T-14 2 9.5

for T-15 2 5.05

4.1.2 φ10-12cm thick equaliptes rafter

for T-1 7 10.1

for T-2 & T-3 2 8.65

for T-4&T-5 1 11.4

for T-6 2 10.2

forT-7&T-8 1 12.9

for T-9,T-10&T-11 6 7.7

for T-12 4 12.1

for T-13 4 4.8

for T-14 2 8.72

for T-15 2 14.11

4.1.3 φ50mm*70mmmm thick zigba purlin

'The Amen' Consulting Architects and Engineers


A) for shade roofs 1 75

B) for gable roof 2 65.1

4.2 Joinery work


Door
a) Type D-1 size 3.15 x 1.2 pcs 1

b) Type D-2 size 2.10 x 0.80 pcs 1

5 METAL AND ALUMINUM WORK

Metal work
for main door
Type D-6, size 3.40x 2.10 cm 1 3.4
3

4.2 Almunium works

4.2.1 DOOR

a Type D-3,size 0.80 x 3.15 cm 2 3.15


0.8

b Type D-4,size 0.90x 3.15 cm 1 3.15


0.9

c Type D-7,size 0.70 x 3.15cm 1 3.15


0.7

4.3 WINDOWS

a Type W-1,size 1.05 x 2.15 cm 3 2.15


1.05

b Type W-2,size 0.80 x 215 cm 1 2.15


0.8

'The Amen' Consulting Architects and Engineers


4.4 CURTAIN WALL

a Type CW-1,size 1.91x 3.15 cm 1 3.15


1.91

b Type CW-2,size 0.82 x 3.15 cm 1 3.15


0.82

5 . FINISHING WORK

5.1 WALL FINISHING


Apply 2 coats of plastering in cement mortar mix 1:3 to receive
5.1.1 quatz paint for external HCB wall surface.

a External block wall surface


on axis A-A ,B-B, & C-C 1 21.20
3.40

on axis 1-1 & 5-5 1 13.75


3.40

For parapet wall surface


Parapet Walls1 1 24.25
0.90

triangular Parapet Walls1 0.5 3.25


2.00

triangular Parapet Walls2 0.5 4.25


2.00

Ditto for opening of D4 1 3.15


0.70

Ditto for opening of W2 1 2.15


0.80

Apply 2 coats of plastering in cement mortar mix 1:3 to receive


quatz paint for exposed edge urface.

'The Amen' Consulting Architects and Engineers


for exposed column surface 1 31.00

for exposed edge of door surface 1 79.00

for exposed edge of curtain wall surface 1 30.64

for exposed edge of windows surface 1 50.20

for exposed beam surface 1 58.90

for exposed parapet wall surface 1 43.01

for exposed concrete gutter surface 1 139.20

Apply two coats of plastering in cement sand mortar (1:3) mix to


5.1.2 receive gypsum finishing to all internal wall.

a ON External wall surface


for verandah area 1 15.00
3.40

b internal block wall surface

for living room 1 20.00


3.40

for master bed room 1 14.10


3.40

For master Bath room 1 14.10


1.40

for guest bed room 1 12.70


3.40

for child bed room 1 13.50


3.40

for kitchen 1 14.82


3.40

'The Amen' Consulting Architects and Engineers


For common Bath room 1 5.20
1.40

Ditto for opening of D1 2 3.15


1.20

Ditto for opening of D2 2 2.10


0.80

Ditto for opening of D3 2 3.15


0.80

Ditto for opening of D4 2 3.15


0.90

Ditto for opening of D5 1 2.10


0.70

Ditto for opening of D7 1 3.15


0.70

Ditto for opening of CW1 2 3.15


1.90

Ditto for opening of CW2 2 3.15


0.82

Ditto for opening of W1 6 2.15


1.05

Ditto for opening of W2 2 2.15


0.80

Apply 2 coats of plastering in cement mortar mix 1:3 to receive


5.1.3 ceramic wall tile.

a For master Bath room 1 14.10


2.00

a For common Bath room 1 5.20


3.40

Ditto for opening of D5 1 2.00

'The Amen' Consulting Architects and Engineers


0.70

Ditto for opening of D7 1 2.00


0.70

5.1.4 200x200x6mm thick glazed ceramic wall tile


applied to plastered wall on and including
cement mortar (1:3) backing and white
cement grouting.

a For master Bath room 1 14.10


2.00

a For common Bath room 1 5.20


3.40

Ditto for opening of D5 1 2.00


0.70

Ditto for opening of D7 1 2.00


0.70

5.1 FLOOR FINISHING


Supply and lay 40x40x0.9cm thick porcelain floor tile fixed on wall with
a 42mm thick cement mortar of 1:3 ratio.

for living room 1 6.05


3.90

for master bed room 1 3.65


3.40

For master Bath room 1 3.40


1.40

for guest bed room 1 3.40


2.95

for child bed room 1 3.40


3.35

'The Amen' Consulting Architects and Engineers


for common bathroom 1 1.40
1.20

for verandah area 1 12.40


0.90

2mm thick high quality PVC floor tile flooring laid with
b approved type of adhesive material.

for kitchen room 1 3.30


2.14

3cm thick Welega black marble tile for edge of verandah on


c with proper grouting of joints in cement mortar mix of 1:3

a. Size 25 x 3cm
1 11.20
0.25

Supply and lay 10x0.9cm thick porcelain tile skirting fixed on wall with
cement mortar of 1:3 mix ratio and including with cement mortar of 1:1
d mix ratio backing.

for living room 1 19.90

for master bed room 1 14.10

For master Bath room 1 9.60

for guest bed room 1 12.70

for child bed room 1 13.50

for common bathroom 1 5.20

for kitchen room 1 14.90

for verandah area 1 13.60

'The Amen' Consulting Architects and Engineers


Ditto for opening of D1 2 1.20

Ditto for opening of D2 2 0.80

Ditto for opening of D3 3 0.80

Ditto for opening of D4 2 0.90

Ditto for opening of D5 2 0.70

Ditto for opening of D7 1 0.70

Ditto for opening of CW1 2 1.90

Ditto for opening of CW2 2 0.82

CEILING WORK
Supply and lay 10x0.9cm thick porcelain tile skirting fixed on wall with
cement mortar of 1:3 mix ratio and including with cement mortar of 1:1
mix ratio backing.

for living room 1 6.05


3.90

for master bed room 1 3.65


3.40

For master Bath room 1 3.40


1.40

for guest bed room 1 3.40


2.95

for child bed room 1 3.40


3.35

for kitchen room 1 3.30


2.14

for common bathroom 1 1.40


1.20

'The Amen' Consulting Architects and Engineers


for verandah area 1 12.40
1.00

Door cill and Window cill

Window Sill
Size 27 x 3cm Marble window cill on and including cement
mortar bed jointed in cement mortar mix of 1:3.

for opening of W1 3 1.10

for opening of W2 1 0.90

Door Sill

Size 20 x 3cm Marble door cill on and including cement


mortar bed jointed in cement mortar mix of 1:3

for opening of D1 1 1.20

for opening of D2 1 0.80

for opening of D3 2 0.80

for opening of D4 1 0.90

for opening of D5 1 0.70

for opening of D7 1 0.70

for opening of CW1 1 1.90

for opening of CW2 1 0.82

5 . PAINTING WORK
Prepare the surface and apply three coats
of Granite paint of chosen type
and clour to:

'The Amen' Consulting Architects and Engineers


a External block wall surface
on axis A-A ,B-B, & C-C 1 21.20
3.40

on axis 1-1 & 5-5 1 13.75


3.40

For parapet wall surface


Parapet Walls1 1 24.25
0.90

for concrete gutter surface 1 30.00


1.55

triangular Parapet Walls1 0.5 3.25


2.00

triangular Parapet Walls2 0.5 4.25


2.00

Ditto for opening of D4 1 3.15


0.70

Ditto for opening of W2 1 2.15


0.80

Prepare the surface and apply three coats


of plastic emulsion paint of chosen type
and clour to:

ON External wall surface


for verandah area 1 15.00
3.40

internal block wall surface

for living room 1 20.00


3.40

for master bed room 1 14.10


3.40

'The Amen' Consulting Architects and Engineers


for guest bed room 1 12.70
3.40

for child bed room 1 13.50


3.40

Ditto for opening of D1 2 3.15


1.20

Ditto for opening of D2 2 2.10


0.80

Ditto for opening of D3 3 3.15


0.80

Ditto for opening of D4 2 3.15


0.90

Ditto for opening of D5 1 2.10


0.70

Ditto for opening of CW1 2 3.15


1.90

Ditto for opening of CW2 2 3.15


0.82

Ditto for opening of W1 6 2.15


1.05

Prepare the surface and apply three coats


syntactic oil paint to:

For master Bath room 1 14.10


1.40

for kitchen 1 14.82


3.40

For common Bath room 1 5.20


1.40

Ditto for opening of D5 1 0.80

'The Amen' Consulting Architects and Engineers


0.70

Ditto for opening of D7 1 1.80


0.70

Ditto for opening of W2 2 0.80


0.80

5 . GLAZING WORK

Glazing
4mm thick clear glass

for opening of D1 1 1.20


0.30

1 3.14
0.42

for opening of D3 2 3.05


0.75

for opening of D4 1 3.05


0.85

for opening of D4 1 1.50


0.70

for opening of W1 3 2.05


1.00

for opening of W1 1 2.05


0.80

5mm thick Wired glass

for opening of CW1 1 3.05


1.9

for opening of CW2 1 3.05


0.8

'The Amen' Consulting Architects and Engineers


5 . SANITARY WORK

5.1 Interior Installation


A. Water Supply Pipes & fittings

Supply and install galvanized steel pipes from elevated


water tank to cold and hot water distibution to all santitary
fixtures as shown on the drawing

Diameter 15 mm 1 28

Diameter 20 mm 1 5.5

Diameter 25mm 1 21

Supply and install gate valves made of brass


complete with rubber gaskets, hand wheels and
connecting pieces such as unions etc, for all fixtures

Diameter 15 mm 1 21

Diameter 25 mm 1 21

Elevated water tank

Supply and mount 1m³ fibre glass water tank on


roof complete with all the necessary accessories

a) Size of water tank = 1.98 x 1.13 m 1 1

Sanitary Fixtures

for low level water closet white glazed vitreous China WC. 1 1

'The Amen' Consulting Architects and Engineers


Supply and install low high water closet white glazed
vitreous China WC. 1 1

for 0.5 x 0.45 m hand wash basins made of white vitreous


China with two tap holes 1 2

For toilet paper holder in white vitreous China 1 2

for crystal glass mirror 500 x 400 mm including chrome


plated brass clips and screws 1 2

soap holder in white shower vitreous for hand wash basin


and bath tub 1 5

for towel hanger 610 x 25 mm with chrome plated tubular


towel rail 1 3

1.5 x 0.60m stainless steel kitchen sink with double bowl


with chrome plated taps, uPVC siphon 1 1

Supply and fix 50 litre electric water heater 1 1

50x150mm floor drainage 1 3

'The Amen' Consulting Architects and Engineers


700x700mm shower units made of enamelled cast iron plate
complete with all the accessories 1 2

bath tub of enamelled cast iron complete with all the


accessories 1 1

6. Waste water & Ventilation Pipe

Supply and install soil , waste and vent pipe in


horizontal branches and vertical stacks made
of PVC including the necessary fittings such as
bends, branches tees, elbow etc. All horizontal
branches should be laid at a slope of 2% .

Diameter 50 mm 1 9.7

Diameter 80 mm 1 10

Diameter 100 mm 1 10

Supply and install vent caps made of PVC


at vent pipes fitted with PVC pipe roof weathering
slate at roof level.
Diameter 50 mm 1 2

Down Pipe

Supply and fix diameter PVC down pipes secured


to walls with iron straps and given two coats of sun
reflecting paint

Diameter 75mm 11 4

'The Amen' Consulting Architects and Engineers


B. Site Sanitary Work

Construct sanitary manholes on a domestic sewer


lines in double brick wall on a base of mass
concrete slab 150mm thick with proper slope for
smooth flow and with 80 mm R.C slab cover and
steel bar handle as shown on the detail drawing.

Size:- 60 x 60cm x 60 cm 1 2

Supply and lay PVC pipe for sewerage


according to the drawing

Diameter 150 mm 1 5.5

Supply and install galvanized steel pipe from main


line to roof fibre glass water tank complete with
all the necessary accessories.

Diameter 32mm 1 15

Diameter 32 mm water meter complete with all the


necessary acessories 1 1

Septic Tank

Construct septic tank with capacity 25m³ as shown on the


detail drawing.

1 Excavation and earth work

'The Amen' Consulting Architects and Engineers


1.3 pit excavation over reduced level and not exceed 250cm

1 4.33
4.33
3.25

1.5 Trench excavation for stone masonery

1 12.00
1.50
0.55

1.6 Backfill non expansive well graded granular selected material

b around stone
masonry 1 12.00
1.50
0.55

ditto for masonry walls 1 12.00


1.00
0.55

1.9 Cart away

1 60.93

1 9.90

2 Stone masonery
2.1 BGL 1 12.00
1.00
0.55

3 CONCRETE WORK

3.1 Lean concrete under

'The Amen' Consulting Architects and Engineers


a stone masonery
1 12.00
1.00

3.2 C-25 Concrete for


a Grade Beams
on axis A-A & B-B 2 2.80
0.25
0.20

on axis 1-1& 2-2 2 2.40


0.25
0.20

d ground Floor slab


1 2.40
2.40

3.3 Formwork for


a for slab
1 2.40
2.40

d Grade Beams
on axis A-A & B-B 2 2.80
0.35

on axis 1-1& 2-2 2 2.40


0.35

1 Excavation and earth work

1.3 pit excavation over reduced level and not exceed 250cm

1 0.85
0.85
0.65

'The Amen' Consulting Architects and Engineers


1.6 Backfill non expansive well graded granular selected material

b around Brick walls


1 0.85
0.85
0.65

ditto fo rbrick walls 1 0.73


0.73
0.65

2 Brick walls
2.1 BGL 1 2.36
0.45

3 CONCRETE WORK

3.2 C-25 Concrete for


for top cover
1 0.73
0.73

forbottom of manhole
1 0.73
0.73

'The Amen' Consulting Architects and Engineers


Quantity

150.00
150.00

90.00

23.46
66.54

32.40
32.40

7.20

3.00

1.36

6.40

'The Amen' Consulting Architects and Engineers


0.89

1.60
20.45

33.75

3.00

0.71
30.04

53.90

26.95
26.95

2.13

2.00
4.13

'The Amen' Consulting Architects and Engineers


16.42

66.54

32.40

20.45
135.81

75.00

27.50

16.42
86.08

23.10

0.45
22.65

11.55

0.22
11.33

1.20

'The Amen' Consulting Architects and Engineers


12.00
12.00

12.50 57.00
20
77.00
4.00

2.00

10.00

10.00

0.75
37.75

3.00
3.00

1.28
1.28

1.68

'The Amen' Consulting Architects and Engineers


0.55

0.29

1.20

1.20
4.93

75.00

27.50

16.42 102.50
86.08

12.30
12.30

22.44
22.44

16.80

5.52

'The Amen' Consulting Architects and Engineers


2.94

12.00

6.00
43.26

2.99
2.99

1.40

0.46

0.25

1.00

1.00
4.11

'The Amen' Consulting Architects and Engineers


3.48
9.83

0.32
0.32

0.04

0.34
0.38

56.86
57.57

19.60

6.44

3.43

14.00

14.00
57.47

'The Amen' Consulting Architects and Engineers


46.40
141.74

4.80
4.80

1.20

2.25

0.90
4.35

66.15

8.51

14.96

62.94

21.83

3.25

'The Amen' Consulting Architects and Engineers


4.25

3.78

5.04

2.84

2.20

5.98

2.58

6.77

1.72
150.96

12.29

42.84

2.52
52.61

'The Amen' Consulting Architects and Engineers


9.70

30.15

12.00
51.85

48.03

24.80

10.49
83.33

14.60
14.60

22.50
22.50

25.00
25.00

21.00

'The Amen' Consulting Architects and Engineers


5.98

3.17

8.85

10.30

35.46

52.00

10.60

19.00

10.10
176.46

70.70

17.30

11.40

20.40

12.90

46.20

48.40

19.20

17.44

28.22
292.16

'The Amen' Consulting Architects and Engineers


75.00

65.10
140.10

1.00

1.00

10.2
10.20

5.04
5.04

2.835
2.84

2.205
2.20

6.7725
6.77

1.72

'The Amen' Consulting Architects and Engineers


1.72

6.0165
6.02

2.583
2.58

72.08

46.75

21.83

3.25

4.25

2.20

1.72
144.23

'The Amen' Consulting Architects and Engineers


31.00

79.00

30.64

50.20

58.90

43.01

139.20
431.95

51.00

68.00

47.94

19.74

43.18

45.90

50.39

'The Amen' Consulting Architects and Engineers


7.28

7.56

3.36

5.04

5.67

1.47

2.20

11.97

5.17

13.55

3.44
274.00

28.20

17.68

'The Amen' Consulting Architects and Engineers


1.40

1.40
43.08

28.20

17.68

1.40

1.40
43.08

23.60

12.41

4.76

10.03

11.39

'The Amen' Consulting Architects and Engineers


1.68

11.16
75.03

7.06
7.06

2.80
2.80

19.90

14.10

9.60

12.70

13.50

5.20

14.90

13.60

'The Amen' Consulting Architects and Engineers


2.40

1.60

2.40

1.80

1.40

0.70

3.80

1.64
87.76

23.60

12.41

4.76

10.03

11.39

7.06

1.68

'The Amen' Consulting Architects and Engineers


12.40
83.33

3.30

0.90
4.20

1.20

0.80

1.60

0.90

0.70

0.70

1.90

0.82
8.62

'The Amen' Consulting Architects and Engineers


72.08

46.75

21.83

46.50

3.25

4.25

2.20

1.72
190.73

51.00

68.00

47.94

'The Amen' Consulting Architects and Engineers


43.18

45.90

7.56

3.36

7.56

5.67

1.47

11.97

5.17

13.55
197.18

19.74

50.39

7.28

'The Amen' Consulting Architects and Engineers


0.56

1.26

1.28
74.31

0.36

1.33

4.57

2.59

1.05

6.15

1.64
17.69

5.795

2.44

'The Amen' Consulting Architects and Engineers


8.235

28
28.00

5.5
5.50

21
21.00

21
21.00

21
21.00

1
1.00

'The Amen' Consulting Architects and Engineers


1.00

1
1.00

2
2.00

2
2.00

2
2.00

5
5.00

3
3.00

1
1.00

1
1.00

3
3.00

'The Amen' Consulting Architects and Engineers


2
2.00

1
1.00

9.7
9.70

10
10.00

10
10.00

2
2.00

44

'The Amen' Consulting Architects and Engineers


44.00

2
2.00

5.5
5.50

15
15.00

1
1.00

'The Amen' Consulting Architects and Engineers


60.93
60.93

9.90
9.90

9.90
9.90

6.60
3.30

60.93

9.90
70.83

6.60
6.60

'The Amen' Consulting Architects and Engineers


12.00
12.00

0.28

0.24
0.52

5.76
5.76

5.76
5.76

1.96

1.68
3.64

0.47
0.47

'The Amen' Consulting Architects and Engineers


0.47

0.35
0.12

1.06
1.06

0.53

0.53
1.07

'The Amen' Consulting Architects and Engineers


Location Ref Bar ID Dia Length No of Bars Dia Dia
No of
No of member No of Total bar
No Bars s blocks length 6 8

SUB-STRUCTURE-A
Footing pads
F-1 (a) 10 1.20 11 6 1 66.00
(b) 10 1.20 11 6 1 66.00
F-2 (a) 10 1.20 5.5 3 1 16.50
F-3 (a) 10 1.20 11 6 1 66.00
(b) 10 1.20 11 6 1 66.00
Foundation 0.00
columns FC1 12 3.00 4 5 1 20.00
FC2 12 3.10 4 1 1 4.00
FC2' 12 3.10 4 4 1 16.00
FC3 12 3.00 4 3 1 12.00
FC4 12 3.00 4 3 1 12.00
0.00
Stirrups FC1 ST-2 6 0.90 10 5 1 50.00 45.00
FC2 ST-2 6 0.90 10 1 1 10.00 9.00
FC2' ST-2 6 0.90 10 4 1 40.00 36.00
FC3 ST-2 6 0.90 10 3 1 30.00 27.00
FC4 ST-2 6 0.90 10 3 1 30.00 27.00
Grade beam 0.00
(+0.00 ) 0.00

on axies1-1 along axies GB1 12 10.47 4 1 1 4.00


A-A, B-B and D-D 12 3.59 1 1 1 1.00
6 0.90 47 1 1 47.25 42.53
0.00

on axies1'-1' along axies GB2 12 5.62 4 1 1 4.00


C-C, B-B and D-D 6 0.90 24 1 1 24.00 21.60
0.00
on axies 2-2 along axies
A-A,B-B, C-C, B-B and D- GB3 12 10.47 4 1 1 4.00
D 12 5.81 1 1 1 1.00
6 0.90 45 1 1 45.00 40.50
0.00

on axies3-3, 4-4, 5-5 along GB4 12 5.55 4 3 1 12.00


axies A-A, A'-A' and B-B 6 0.90 24.0 3 1 72.00 64.80
0.00

on axies A-A along axies GB5 12 8.00 2 1 1 2.00


1-1, 2-2, 3-3, 4-4 and 5-5

'The Amen' Consulting Archirects and Engineers


on axies A-A along axies
1-1, 2-2, 3-3, 4-4 and 5-5 12 9.95 2 1 1 2.00
12 9.12 2 1 1 2.00
12 7.72 2 1 1 2.00
12 3.58 1 1 1 1.00
6 0.90 70 1 1 70.00 63.00
0.00
on axies A'-A' along axies GB6 12 10.11 4 1 1 4.00
2-2, 3-3, 4-4 and 5-5 6 0.90 44 1 1 44.00 39.60
0.00
on axies B-B along axies
1-1, 1'-1', 2-2, 3-3, 4-4 and GB7 12 8.00 2 1 1 2.00
5-5 12 9.95 2 1 1 2.00
12 9.12 2 1 1 2.00
12 7.72 2 1 1 2.00
12 3.58 1 1 1 1.00
6 0.90 69 1 1 69.00 62.10
0.00

on axiesD-D along axies GB8 12 6.07 4 1 1 4.00


1-1 1'-1'and 2-2 6 0.90 29 1 1 29.00 26.10
Ground floor mesh 0.00
(+0.00 ) 0.00

b/n axies A-A and B-B 6 4.70 21 1 1 21.00 98.70


along axies 1-1 and 2-2 6 5.10 20 1 1 20.00 102.00
0.00
b/n axies B-B and D-D 6 4.70 21 1 1 21.00 98.70
along axies 1-1 and 2-2 6 4.90 20 1 1 20.00 98.00
0.00
b/n axies A-A and B-B 6 4.50 37 1 1 37.00 166.50
along axies 2-2 and 5-5 6 8.90 19 1 1 19.00 169.10
0.00 1237.23 0.00
0.00 0.222 0.395
0.00 275 0
0.00
0.00
septic tank 0.00
Grade beam 14 3.20 4 4 1 16.00
6 0.80 14 4 1 56.00 44.80
0.00
Ground floor mesh 12 2.90 19 2 1 38.00
0.00 44.80 0.00
0.00 0.222 0.395
0.00 10 0
0.00
Super structure 0.00 0.00

'The Amen' Consulting Archirects and Engineers


0.00
Elevation columns 0.00
C1,C2 and C3 12 3.53 4 9 1 36.00
6 0.80 17 9 1 153.00 122.40
C4 12 3.53 4 6 1 24.00
6 0.80 17 6 1 102.00 81.60
C2' 12 3.53 6 4 1 24.00
6 0.80 17 4 1 68.00 54.40
0.00
Grade beam 0.00
(+0.00 ) 0.00
GB1 12 10.47 4 1 1 4.00
on axies1-1 along axies A-A, B-
B and D-D 12 3.59 1 1 1 1.00
6 0.70 47 1 1 47.25 33.07
0.00
GB2 12 5.62 4 1 1 4.00
on axies1'-1' along axies C-C, B-
B and D-D 6 0.70 24 1 1 24.00 16.80
0.00
GB3 12 10.47 4 1 1 4.00
on axies 2-2 along axies A-A,B-
B, C-C, B-B and D-D 12 5.81 1 1 1 1.00
6 0.70 45 1 1 45.00 31.50
0.00
GB4 12 5.55 4 3 1 12.00
on axies3-3, 4-4, 5-5 along axies
A-A, A'-A' and B-B 6 0.70 24.0 3 1 72.00 50.40
0.00
GB5 12 8.00 2 1 1 2.00
on axies A-A along axies 1-1, 2-
2, 3-3, 4-4 and 5-5 12 9.95 2 1 1 2.00
12 9.12 2 1 1 2.00
12 7.72 2 1 1 2.00
12 3.58 1 1 1 1.00
6 0.70 70 1 1 70.00 49.00
0.00
GB6 12 10.11 4 1 1 4.00
on axies A'-A' along axies 2-2, 3-
3, 4-4 and 5-5 6 0.70 44 1 1 44.00 30.80
0.00
GB7 12 8.00 2 1 1 2.00
on axies B-B along axies 1-1, 1'-
1', 2-2, 3-3, 4-4 and 5-5 12 9.95 2 1 1 2.00
12 9.12 2 1 1 2.00
12 7.72 2 1 1 2.00
12 3.58 1 1 1 1.00
6 0.70 69 1 1 69.00 48.30

'The Amen' Consulting Archirects and Engineers


0.00
GB8 12 6.07 4 1 1 4.00
on axiesD-D along axies 1-1 1'-
1'and 2-2 6 0.70 29 1 1 29.00 20.30
0.00
concrete parapet gutter 10 3.98 151 1 1 151.00
8 30.00 21 1 1 21.00 630.00
258.40 630.00
0.222 0.395
57 630

'The Amen' Consulting Archirects and Engineers


Dia Dia Dia Dia Dia Dia

10 12 14 16 20 24

79.20
79.20
19.80
79.20
79.20

60.00
12.40
49.60
36.00
36.00

41.88
3.59

22.48

41.88
5.81

66.60

16.00

'The Amen' Consulting Archirects and Engineers


19.90
18.24
15.44
3.58

40.44

16.00
19.90
18.24
15.44
3.58

24.27

336.60 587.27 0.00 0.00 0.00 0.00


0.617 0.888 1.208 1.578 2.468 3.551
208 521 0 0 0 0

51.20

110.20
0.00 110.20 51.20 0.00 0.00 0.00
0.617 0.888 1.208 1.578 2.468 3.551
0 98 62 0 0 0

0.00 0.00 0.00 0.00 0.00 0.00

'The Amen' Consulting Archirects and Engineers


126.90

84.60

84.60

41.88
3.59

22.48

41.88
5.81

66.60

16.00
19.90
18.24
15.44
3.58

40.44

16.00
19.90
18.24
15.44
3.58

'The Amen' Consulting Archirects and Engineers


24.27

600.98

600.98 689.37 0.00 0.00 0.00 0.00


0.617 0.888 1.208 1.578 2.468 3.551
371 612 0 0 0 0

'The Amen' Consulting Archirects and Engineers


B. SUPER
5. CONC
ANALYSIS SHEET FO
PROJECT: CONCRETE WORK FOR COLUMN
WORK ITEM: ( 5.1 ) C-25 Concrete (Mechanical Mix) 1:2:3
TOTAL QUANTITY OF WORK ITEM: 1 m3

Material Cost (1:01)

Type of Material Unit Qty * Rate


Cement Qnt. 3.6 343.48
Sand m3 0.52 190.22
Gravel (02) m3 0.78 342.39
water lts 130 2.00
desail lts 1 16.30

Total (1:-01)

A= Materials Unit Cost 1878.80 Birr/m3

Remark ________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED O
PROJECT: CONCRETE WORK FOR TOP BEAM
WORK ITEM: ( 3.5 ) C-25 Concrete (Mechanical Mix) 1:2:3
TOTAL QUANTITY OF WORK ITEM: 1 m3

Material Cost (1:01)

Type of Material Unit Qty * Rate


Cement Qnt. 3.6 343.48
Sand m3 0.52 190.22
Gravel (02) m3 0.78 342.39
water lts 130 2.00
desail lts 1 16.30

Total (1:-01)

A= Materials Unit Cost 1878.80 Birr/m3

6. FO
ANALYSIS SHEET FOR DIR
PROJECT: FORM WORK FOR COLUMN
WORK ITEM: ( 5.2 ) Form Work.
TOTAL QUANTITY OF WORK ITEM : 1

Material Cost (1:01)


Type of Material Unit Qty * Rate
zigba panel m2 0.95 260.87
Eucalyptus ml 2.1 8.70
Nails Kg 0.3 69.57
Mould Oil Lit. 0.015 7.00

Total (1:-01)

A= Materials Unit Cost 287.06152 Birr/m2

Remark __________________________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED O
ANALYSIS SHEET FOR DIR
PROJECT: FORM WORK FOR BEAM
WORK ITEM: ( 5.2 ) Form Work.
TOTAL QUANTITY OF WORK ITEM : 1

Material Cost (1:01)

Type of Material Unit Qty * Rate


zigba panel m2 0.95 260.87
Eucalyptus ml 2.1 8.70
Nails Kg 0.3 69.57
Mould Oil Lit. 0.015 7.00

Total (1:-01)

A= Materials Unit Cost 287.06152 Birr/m2

Remark __________________________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED O

19. BAR

ANALYSIS SHEET FOR DIR


PROJECT : REINFORCEMENT BARS
WORK ITEM: ( 19.1 ) dia. 8 mm. deformed bars
TOTAL QANTITY OF WORK ITEM: 1 kg.

Material Cost (1:01)

Type of Material Unit Qty * Rate


8 mm deformed bars kg 1.05 39.81
1.2 mm black anneald wire kg 0.02 56.52

Total (1:-01)

A= Materials Unit Cost 42.93 birr/kg

Remark __________________________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED O

ANALYSIS SHEET FOR DIR


PROJECT : REINFORCEMENT BARS
WORK ITEM: ( 19.1 ) dia. 10 mm. deformed bars
TOTAL QANTITY OF WORK ITEM: 1 kg.

Material Cost (1:01)

Type of Material Unit Qty * Rate


10 mm deformed bars kg 1.05 39.13
1.2 mm black anneald wire kg 0.02 56.52
Total (1:-01)

A= Materials Unit Cost 42.22 birr/kg

Remark __________________________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED O

ANALYSIS SHEET FOR DIR


PROJECT : REINFORCEMENT BARS
WORK ITEM: ( 19.1 ) dia. 12mm. deformed bars
TOTAL QANTITY OF WORK ITEM: 1 kg.

Material Cost (1:01)

Type of Material Unit Qty * Rate


12 mm deformed bars kg 1.05 39.13
1.2 mm black anneald wire kg 0.02 56.52

Total (1:-01)

A= Materials Unit Cost 42.22 birr/kg


Remark __________________________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED O

ANALYSIS SHEET FOR DIR


PROJECT : REINFORCEMENT BARS
WORK ITEM: ( 19.1 ) dia. 14 mm. deformed bars
TOTAL QANTITY OF WORK ITEM: 1 kg.

Material Cost (1:01)

Type of Material Unit Qty * Rate


14 mm deformed bars kg 1.05 40.00
1.2 mm black anneald wire kg 0.02 56.52

Total (1:-01)

A= Materials Unit Cost 43.13 birr/kg

Remark __________________________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED O

7. BLO
ANALYSIS SHEET FOR DIR
PROJECT: HCB WORK
WORK ITEM: ( 6.11 ) 20 cm. thick HCB Wall Both Sides Left For Plaste
TOTAL QANTITY OF WORK ITEM: 1 m2

Material Cost (1:01)

Type of Material Unit Qty * Rate


20 cm. Thick HCB Pcs. 13 10.96
Cement Qt. 0.10 343.48
Sand m3 0.028 190.22
Water m3 0.04 0.001

Total (1:-01)

A= Materials Unit Cost 182.11 Birr/m2

UF: UTILIZATION FACTOR


*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED O

ANALYSIS SHEET FOR DIR


PROJECT: HCB WORK
WORK ITEM: ( 6.8 ) 15 cm. thick HCB Wall Both Sides Left For Plaste
TOTAL QANTITY OF WORK ITEM: 1 m2

Material Cost (1:01)

Type of Material Unit Qty * Rate


15 cm. Thick HCB Pcs. 13 9.22
Cement Qt. 0.075 343.48
Sand m3 0.022 190.22
Water m3 0.04 0.001

Total (1:-01)

A= Materials Unit Cost 149.77 Birr/m2

14.RO
ANALYSIS SHEET FOR DIR
PROJECT: ROOF WORK
WORK ITEM: ( 6.8 ) G-30 Roof cover
TOTAL QANTITY OF WORK ITEM: 1

Material Cost (1:01)

Type of Material Unit Qty * Rate


G-30 C.I.S. No. 0.79 278.26
Nails Kg 0.095 113.04

Total (1:-01)

A= Materials Unit Cost 230.59 Birr/m2

Remarks :
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED O

ANALYSIS SHEET FOR DIR


PROJECT: ROOF WORK
WORK ITEM: ( 6.8 ) Roof Asbestos
TOTAL QANTITY OF WORK ITEM: 1

Material Cost (1:01)

Type of Material Unit Qty * Rate


corrugated asbestos No. 0.79 366.09
Nails Kg 0.076 113.04
Total (1:-01)

A= Materials Unit Cost 297.80 Birr/m2

Remarks :
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED O

ANALYSIS SHEET FOR DIR


PROJECT: ROOF WORK
WORK ITEM: ( 6.8 ) rigde cover
TOTAL QANTITY OF WORK ITEM: 1

Material Cost (1:01)

Type of Material Unit Qty * Rate


rigde cover ml 0.9 113.04
Nails Kg 0.076 113.04

Total (1:-01)

A= Materials Unit Cost 110.33 Birr/m2


Remarks :
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED O

ANALYSIS SHEET FOR DIR


PROJECT: ROOF WORK
WORK ITEM: ( 6.8 ) valley cover
TOTAL QANTITY OF WORK ITEM: 1

Material Cost (1:01)

Type of Material Unit Qty * Rate


valley cover ml 0.9 121.74
Nails Kg 0.076 113.04

Total (1:-01)

A= Materials Unit Cost 118.16 Birr/m2

Remarks :
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED O

ANALYSIS SHEET FOR DIR


PROJECT: ROOF WORK
WORK ITEM: ( 6.8 ) G-28 flat sheet gutter
TOTAL QANTITY OF WORK ITEM: 1

Material Cost (1:01)

Type of Material Unit Qty * Rate


G-28 flat sheet ml 1.05 317.58
Nails Kg 0.076 113.04

Total (1:-01)

A= Materials Unit Cost 342.05 Birr/m2

Remarks :
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED O

13. CARPENTERY
ANALYSIS SHEET FOR DIR
PROJECT: CARPENTERY WORK
WORK ITEM: ( 6.8 ) 10cm-12cm Eucalyptus rafter
TOTAL QANTITY OF WORK ITEM: 1

Material Cost (1:01)

Type of Material Unit Qty * Rate


10-12cm euc. Tree m 1.5 18.63
Nails 12cm kg 0.04 69.57
Band iron kg 0.12 47.83

Total (1:-01)

A= Materials Unit Cost 36.47 Birr/m2

Remarks :
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED O
ANALYSIS SHEET FOR DIR
PROJECT: CARPENTERY WORK
WORK ITEM: ( 6.8 ) Verticals & Diagonals
TOTAL QANTITY OF WORK ITEM: 1

Material Cost (1:01)

Type of Material Unit Qty * Rate


8-10cm euc. Tree m 1.6 8.70
10cm Nails kg 0.04 71.30
Band iron kg 0.12 47.83

Total (1:-01)

A= Materials Unit Cost 22.50 Birr/m2

Remarks :
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED O

ANALYSIS SHEET FOR DIR


PROJECT: CARPENTERY WORK
WORK ITEM: ( 6.8 ) Zigba Purlin (5X7)cm
TOTAL QANTITY OF WORK ITEM: 1

Material Cost (1:01)

Type of Material Unit Qty * Rate


(5X7)cm wooden Purlin m 1.2 15.22
8cm Nails kg 0.15 71.30

Total (1:-01)
A= Materials Unit Cost 28.96 Birr/m2

Remarks :
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED O

ANALYSIS SHEET FOR DIR


PROJECT: JOINERY WORK
WORK ITEM: ( 6.8 ) wooden door (D2)
TOTAL QANTITY OF WORK ITEM: 1

Material Cost (1:01)

Type of Material Unit Qty * Rate


2.10x0.8m door m2 1.68 2869.57
9cm Nails kg 0.07 71.30

Total (1:-01)

A= Materials Unit Cost 4825.86 Birr/m2


Remarks :
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED O

ANALYSIS SHEET FOR DIR


PROJECT: JOINERY WORK
WORK ITEM: ( 6.8 ) two leaf wooden door (D1)
TOTAL QANTITY OF WORK ITEM: 1

Material Cost (1:01)

Type of Material Unit Qty * Rate


3.15x1.2m door m2 3.78 2869.57
9cm Nails kg 0.07 71.30

Total (1:-01)

A= Materials Unit Cost 10851.95 Birr/m2

Remarks :
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED O
16.METAL AND
ANALYSIS SHEET FOR DIR
PROJECT: METAL WORK
WORK ITEM: ( 6.8 ) Metal door
TOTAL QANTITY OF WORK ITEM: 1.00

Material Cost (1:01)

Type of Material Unit Qty * Rate


3.4x 3m door m2 1 4262.61

Total (1:-01)

A= Materials Unit Cost 4262.61 Birr/m2

Remarks :
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED O

ANALYSIS SHEET FOR DIR


PROJECT: METAL WORK
WORK ITEM: ( 6.8 ) 40x40x2.5 SHS for handrails
TOTAL QANTITY OF WORK ITEM: 1 kgs
Material Cost (1:01)

Type of Material Unit Qty * Rate


for 40x40x2.5 kgs 1.05 39.63
Electrode kgs 2 1.70
Anti rust kgs 0.01 40.00
Thinner kgs 0.026 22.00

Total (1:-01)

A= Materials Unit Cost 45.98 Birr/m2

Remarks :
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED O
ANALYSIS SHEET FOR DIR
PROJECT: REINFORCEMENT BAR

WORK ITEM: ( 6.8 ) 65x65x5 SHS for handrails


TOTAL QANTITY OF WORK ITEM: 1 kgs

Material Cost (1:01)

Type of Material Unit Qty * Rate


for 65x65x5 kgs 1.05 34.62
Electrode pcs 2 1.70
Anti rust lit 0.01 40.00
Thinner lit 0.026 22.00

Total (1:-01)

A= Materials Unit Cost 40.72 Birr/m2

Remarks :
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED O

ANALYSIS SHEET FOR DIR


PROJECT: ALUMINUM WORK
WORK ITEM: ( 6.8 ) Aluminum doors
TOTAL QANTITY OF WORK ITEM: 1

Material Cost (1:01)

Type of Material Unit Qty * Rate


Aluminum doors m2 1 695.65

Total (1:-01)
A= Materials Unit Cost 695.65 Birr/m2

ANALYSIS SHEET FOR DIR


PROJECT: ALUMINUM WORK
WORK ITEM: ( 6.8 ) Aluminum Window
TOTAL QANTITY OF WORK ITEM: 1

Material Cost (1:01)

Type of Material Unit Qty * Rate


Aluminum doors m2 1 695.65

Total (1:-01)

A= Materials Unit Cost 695.65 Birr/m2

ANALYSIS SHEET FOR DIR


PROJECT: CURTAIN WORK
WORK ITEM: ( 6.8 ) CURTAIN WALL
TOTAL QANTITY OF WORK ITEM: 1

Material Cost (1:01)

Type of Material Unit Qty * Rate


CURTAIN WAL m2 1 695.65

Total (1:-01)

A= Materials Unit Cost 695.65 Birr/m2

8. FINISH
ANALYSIS SHEET FOR DIR
PROJECT: WALL FINISHING
WORK ITEM: ( 6.8 ) 2 Coats of Cement internal wall plastering
TOTAL QANTITY OF WORK ITEM: 1

Material Cost (1:01)

Type of Material Unit Qty * Rate


Cement Qtl 0.1029 343.48
Sand m3 0.0022 190.22
Gypsum chack kg 2.2 4.3
Water m3 0.007 10.67

Total (1:-01)

A= Materials Unit Cost 45.40 Birr/m2

Remarks :
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED O
ANALYSIS SHEET FOR DIR

PROJECT: WALL FINISHING


WORK ITEM: ( 6.8 ) 2 Coats of Cement external wall plastering
TOTAL QANTITY OF WORK ITEM: 1

Material Cost (1:01)

Type of Material Unit Qty * Rate


Cement Qtl 0.1029 343.48
Sand m3 0.0022 190.22
Gypsum chack kg 2.2 4.3
Water m3 0.007 10.67
Total (1:-01)

A= Materials Unit Cost 45.40 Birr/m2

ANALYSIS SHEET FOR DIR


PROJECT: WALL FINISHING
WORK ITEM: ( 6.8 ) 2 Coats of Cement plastering for exposed edges
TOTAL QANTITY OF WORK ITEM: 1

Material Cost (1:01)

Type of Material Unit Qty * Rate


Cement Qtl 0.0046 343.48
Sand m3 0.001 190.22
Gypsum chack kg 2.2 4.3
Water m3 0.007 10.67

Total (1:-01)

A= Materials Unit Cost 11.41 Birr/m2


Remarks :
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED O

ANALYSIS SHEET FOR DIR


PROJECT: WALL FINISHING
WORK ITEM: ( 6.8 ) 2 Coats of Cement internal wall plastering to
TOTAL QANTITY OF WORK ITEM: 1

Material Cost (1:01)

Type of Material Unit Qty * Rate


Cement Qtl 0.10322 343.48
Sand m3 0.01434 190.22

Total (1:-01)

A= Materials Unit Cost 38.18 Birr/m2

Remarks :
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED O

ANALYSIS SHEET FOR DIR


PROJECT: WALL FINISHING
WORK ITEM: ( 6.8 ) Ceramic wall tile
TOTAL QANTITY OF WORK ITEM: 1

Material Cost (1:01)

Type of Material Unit Qty * Rate


Ceramic tile(20x20) No 27 12.00
White cement kg 0.01 30.43
Sand m3 0.0191 190.22
cement Qtl 0.137 343.48

Total (1:-01)

A= Materials Unit Cost 374.99 Birr/m2

Remarks :
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED O

ANALYSIS SHEET FOR DIR


PROJECT: FLOOR FINISHING
WORK ITEM: ( 6.8 ) Ceramic floor tile
TOTAL QANTITY OF WORK ITEM: 1

Material Cost (1:01)

Type of Material Unit Qty * Rate


Ceramic tile(40x40) No 6.5625 125.36
White cement kg 0.01 30.43
Cement Qtl 0.10322 343.48
Sand m3 0.01434 190.22

Total (1:-01)

A= Materials Unit Cost 861.14 Birr/m2

Remarks :
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED O

ANALYSIS SHEET FOR DIR


PROJECT: FLOOR FINISHING
WORK ITEM: PVC tile flooring
TOTAL QANTITY OF WORK ITEM: 1

Material Cost (1:01)

Type of Material Unit Qty * Rate


PVC tile(25x25) No 17 25.54
Adhesive lits 0.3 163.04
Polish lits 0.3 163.04

Total (1:-01)

A= Materials Unit Cost 532.07 Birr/m2

Remarks :
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED O

ANALYSIS SHEET FOR DIR


PROJECT: FLOOR FINISHING
WORK ITEM: marble tile flooring
TOTAL QANTITY OF WORK ITEM: 1

Material Cost (1:01)

Type of Material Unit Qty * Rate


2cm marble tile flooring No 1.02 956.52
White cement kg 0.01 30.43
Cement Qtl 0.10322 343.48
Sand m3 0.01434 190.22

Total (1:-01)
A= Materials Unit Cost 1014.14 Birr/m2

Remarks :
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED O

ANALYSIS SHEET FOR DIR


PROJECT: SKIRTING
WORK ITEM: ( 6.8 ) ceramic tile skirting
TOTAL QANTITY OF WORK ITEM: 1

Material Cost (1:01)

Type of Material Unit Qty * Rate


ceramic tile skirting ml 1.05 91.30
Cement Qt 0.0046 343.48
sand m3 0.001 190.22

Total (1:-01)

A= Materials Unit Cost 97.64 Birr/m2


Remarks :
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED O

ANALYSIS SHEET FOR DIR


PROJECT: CILLING WORK
WORK ITEM: ( 6.8 ) Gypsum cilling
TOTAL QANTITY OF WORK ITEM: 1

Material Cost (1:01)

Type of Material Unit Qty * Rate


Chip wood m2 1.05 0.00
4X5cm Batten m 4.6 0.00
4cm Nail kg 0.07 0.00
6cm Nail kg 0.07 0.00
Corner list m 1.75 0.00

Total (1:-01)

A= Materials Unit Cost 0.00 Birr/m2

Remarks :
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED O
12. DOOR AN
ANALYSIS SHEET FOR DIR
PROJECT: DOOR SILLING
WORK ITEM: ( 6.8 ) marble door sill
TOTAL QANTITY OF WORK ITEM: 1

Material Cost (1:01)

Type of Material Unit Qty * Rate


marble sill (27X3)cm ml 1.00 50.00
cement Qt 0.026 343.48
sand m3 0.007 190.22

Total (1:-01)

A= Materials Unit Cost 60.26 Birr/m2

Remarks :
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED O
ANALYSIS SHEET FOR DIR
PROJECT: WINDOW SILLING
WORK ITEM: ( 6.8 ) marble window sill
TOTAL QANTITY OF WORK ITEM: 1
Material Cost (1:01)

Type of Material Unit Qty * Rate


marble sill (27X3)cm ml 1.00 50.00
cement Qt 0.026 343.48
sand m3 0.007 190.22

Total (1:-01)

A= Materials Unit Cost 60.26 Birr/m2

Remarks :
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED O

9. PA
ANALYSIS SHEET FOR DIR
PROJECT: PAIINTING
WORK ITEM: ( 6.8 ) Three coats of plastic paint for internal and exte
TOTAL QANTITY OF WORK ITEM: 1

Material Cost (1:01)

Type of Material Unit Qty * Rate


Stucco kg 0.05 13.04
Animal or vinavil glue Kg 0.013 60.87
1st coat lits 0.07 76.09
2nd coat lits 0.06 76.09
3rd coat final coat lts 0.05 76.09
Gypsum Kg 0.03 4.35
Sand paper m2 0.01 26.09
Brush no 0.002 26.09
thinner lits 0.05 20.00
Total (1:-01)

A= Materials Unit Cost 15.55 Birr/m2

Remarks :
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED O
ANALYSIS SHEET FOR DIR
PROJECT: PAIINTING
WORK ITEM: ( 6.8 ) Three coats of syntactic oil paint for kitchen and
TOTAL QANTITY OF WORK ITEM: 1

Material Cost (1:01)

Type of Material Unit Qty * Rate


Stucco kg 0.05 13.04
Animal or vinavil glue Kg 0.013 60.87
1st coat lits 0.07 76.09
2nd coat lits 0.06 76.09
3rd coat final coat lts 0.05 76.09
Gypsum Kg 0.03 4.35
Sand paper m2 0.01 26.09
Brush no 0.002 26.09
Total (1:-01)

A= Materials Unit Cost 15.55 Birr/m2

ANALYSIS SHEET FOR DIR


PROJECT: PAIINTING
WORK ITEM: ( 6.8 ) Quartith Paint
TOTAL QANTITY OF WORK ITEM: 1

Material Cost (1:01)

Type of Material Unit Qty * Rate


Quartiz paint lts 2.50 97.39
Gypsum Kg 0.03 4.35
glue 0.01 60.87
Sand paper 0.2 26.09
Total (1:-01)

A= Materials Unit Cost 249.59 Birr/m2


Remarks :
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED O

18.GLAZ
ANALYSIS SHEET FOR DIR
PROJECT: GLAZING WORK
WORK ITEM: ( 6.8 ) 4mm thick clear glass
TOTAL QANTITY OF WORK ITEM: 1

Material Cost (1:01)

Type of Material Unit Qty * Rate


Glass m2 1.1 317.39
Putty kg 1 17.39

Total (1:-01)

A= Materials Unit Cost 366.52 Birr/m2

Remarks :
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED O

ANALYSIS SHEET FOR DIR


PROJECT: GLAZING WORK
WORK ITEM: ( 6.8 ) 5mm thick glass
TOTAL QANTITY OF WORK ITEM: 1

Material Cost (1:01)

Type of Material Unit Qty * Rate


Glass m2 1.1 391.30
Putty kg 1 17.39

Total (1:-01)

A= Materials Unit Cost 447.83 Birr/m2

Remarks :
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED O

15.SANIT
ANALYSIS SHEET FOR DIR
PROJECT: SANITERY WORK
WORK ITEM: ( 6.8 ) O15mm PPR
TOTAL QANTITY OF WORK ITEM: 1

Material Cost (1:01)

Type of Material Unit Qty * Rate


O15mm PPR m 0.175 85.33
union No 0.08 106.70
Plug No 0.16 70.00
elbow No 0.5 86.00
Tee No 0.25 64.00

Total (1:-01)

A= Materials Unit Cost 93.67 Birr/m2

Remarks :
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED O

ANALYSIS SHEET FOR DIR


PROJECT: SANITERY WORK
WORK ITEM: ( 6.8 ) O20mm PPR
TOTAL QANTITY OF WORK ITEM: 1
Material Cost (1:01)

Type of Material Unit Qty * Rate


O20mm PPR m 0.175 32.50
union No 0.08 23.00
Plug No 0.16 23.00
elbow No 0.5 23.00
Tee No 0.25 23.00

Total (1:-01)

A= Materials Unit Cost 28.46 Birr/m2

Remarks :
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED O

ANALYSIS SHEET FOR DIR


PROJECT: SANITERY WORK
WORK ITEM: ( 6.8 ) O25mm PPR
TOTAL QANTITY OF WORK ITEM: 1

Material Cost (1:01)

Type of Material Unit Qty * Rate


O25mm PPR m 0.175 37.50
union No 0.08 27.00
Plug No 0.16 27.00
elbow No 0.5 27.00
Tee No 0.25 27.00
reducer No 1.25 27.00

Total (1:-01)

A= Materials Unit Cost 67.04 Birr/m2

Remarks :
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED O

ANALYSIS SHEET FOR DIR


PROJECT: SANITERY WORK
WORK ITEM: ( 6.8 ) Gate vave
TOTAL QANTITY OF WORK ITEM: 1

Material Cost (1:01)

Type of Material Unit Qty * Rate


Gate vave 15mm pc 1 230.00
Fiber kg 0.005 215.00
Total (1:-01)

A= Materials Unit Cost 231.08 Birr/m2

Remarks :
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED O

ANALYSIS SHEET FOR DIR


PROJECT: SANITERY WORK
WORK ITEM: ( 6.8 ) Gate vave
TOTAL QANTITY OF WORK ITEM: 1

Material Cost (1:01)

Type of Material Unit Qty * Rate


Gate vave 25mm pc 1 230.00
Fiber kg 0.005 215.00

Total (1:-01)

A= Materials Unit Cost 231.08 Birr/m2


Remarks :
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED O

ANALYSIS SHEET FOR DIR


PROJECT: SANITERY WORK
WORK ITEM: ( 6.8 ) water tanker 1000 lts
TOTAL QANTITY OF WORK ITEM: 1

Material Cost (1:01)

Type of Material Unit Qty * Rate


Water tank No. 1.00 4500.00
Fittings (out let and inlate) No. 6.00 26.68
Float valve 3/4" No. 1.00 117.37
Fiber kg 0.05 215.00
Total (1:-01)

A= Materials Unit Cost 4788.17 Birr/m2

Remarks :
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED O

ANALYSIS SHEET FOR DIR


PROJECT: SANITERY WORK
WORK ITEM: ( 6.8 ) Low level WC
TOTAL QANTITY OF WORK ITEM: 1

Material Cost (1:01)

Type of Material Unit Qty * Rate


WC No 1 500.00
Fiber ( kacha ) kg 0.005 215.00

Total (1:-01)

A= Materials Unit Cost 501.08 Birr/m2

Remarks :
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED O

ANALYSIS SHEET FOR DIR


PROJECT: SANITERY WORK
WORK ITEM: ( 6.8 ) high level WC
TOTAL QANTITY OF WORK ITEM: 1
Material Cost (1:01)

Type of Material Unit Qty * Rate


WC No 1 3693.00
Gypsum kg 0.50 4.35
Fiber ( kacha ) kg 0.001 215.00

Total (1:-01)

A= Materials Unit Cost 3695.39 Birr/m2

Remarks :
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED O

ANALYSIS SHEET FOR DIR


PROJECT: SANITERY WORK
WORK ITEM: ( 6.8 ) Hand wash basin
TOTAL QANTITY OF WORK ITEM: 1

Material Cost (1:01)

Type of Material Unit Qty * Rate


Hand wash basin No 1 1800.00
Gypsum kg 0.50 4.35
Fiber ( kacha ) kg 0.001 215.00

Total (1:-01)

A= Materials Unit Cost 1802.39 Birr/m2

Remarks :
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED O

ANALYSIS SHEET FOR DIR


PROJECT: SANITERY WORK
WORK ITEM: ( 6.8 ) Toilet paper holder
TOTAL QANTITY OF WORK ITEM: 1

Material Cost (1:01)

Type of Material Unit Qty * Rate


Toilet paper holder No 1 256.00
cement Kg 0.5 343.48
white cement kg 0.01 30.43

Total (1:-01)

A= Materials Unit Cost 428.04 Birr/m2


Remarks :
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED O

ANALYSIS SHEET FOR DIR


PROJECT: SANITERY WORK
WORK ITEM: ( 6.8 ) glass mirror 500 x 400 mm
TOTAL QANTITY OF WORK ITEM: 1

Material Cost (1:01)

Type of Material Unit Qty * Rate


glass mirror 500 x 400 mm No 1 100.00

Total (1:-01)

A= Materials Unit Cost 100.00 Birr/m2

Remarks :
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED O

ANALYSIS SHEET FOR DIR


PROJECT: SANITERY WORK
WORK ITEM: ( 6.8 ) soap holder
TOTAL QANTITY OF WORK ITEM: 1

Material Cost (1:01)

Type of Material Unit Qty * Rate


soap holder No 1 182.00
cement Kg 0.5 343.48
white cement kg 0.01 30.43

Total (1:-01)

A= Materials Unit Cost 354.04 Birr/m2

Remarks :
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED O

ANALYSIS SHEET FOR DIR


PROJECT: SANITERY WORK
WORK ITEM: ( 6.8 ) Towel hanger 610 x 25 mm
TOTAL QANTITY OF WORK ITEM: 1

Material Cost (1:01)

Type of Material Unit Qty * Rate


Towel hanger 610 x 25 mm No 1 40.00
Screw Kg 4 30.43
Fisher kg 4 30.43

Total (1:-01)

A= Materials Unit Cost 283.48 Birr/m2

Remarks :
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED O

ANALYSIS SHEET FOR DIR


PROJECT: SANITERY WORK
WORK ITEM: ( 6.8 ) kitchen sink
TOTAL QANTITY OF WORK ITEM: 1

Material Cost (1:01)

Type of Material Unit Qty * Rate


kitchen sink No 1 750.00
Gypsum kg 0.5 4.35
Fiber ( kacha ) kg 0.001 215.00

Total (1:-01)

A= Materials Unit Cost 752.39 Birr/m2

Remarks :
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED O

ANALYSIS SHEET FOR DIR


PROJECT: SANITERY WORK
WORK ITEM: ( 6.8 ) electric water heater
TOTAL QANTITY OF WORK ITEM: 1

Material Cost (1:01)

Type of Material Unit Qty * Rate


electric water heater No 1 6500.00
Fisher Pc 2 30.43
Fiber ( kacha ) kg 0.005 215.00

Total (1:-01)
A= Materials Unit Cost 6561.94 Birr/m2

Remarks :
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED O

ANALYSIS SHEET FOR DIR


PROJECT: SANITERY WORK
WORK ITEM: ( 6.8 ) floor drean
TOTAL QANTITY OF WORK ITEM: 1

Material Cost (1:01)

Type of Material Unit Qty * Rate


floor drean No 1 60.00

Total (1:-01)

A= Materials Unit Cost 60.00 Birr/m2


Remarks :
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED O

ANALYSIS SHEET FOR DIR


PROJECT: SANITERY WORK
WORK ITEM: ( 6.8 ) Shower plate
TOTAL QANTITY OF WORK ITEM: 1

Material Cost (1:01)

Type of Material Unit Qty * Rate


Shower plate No 1 450.00
Fiber ( kacha ) kg 0.001 215.00

Total (1:-01)

A= Materials Unit Cost 450.22 Birr/m2

Remarks :
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED O
ANALYSIS SHEET FOR DIR
PROJECT: SANITERY WORK
WORK ITEM: ( 6.8 ) bath tub
TOTAL QANTITY OF WORK ITEM: 1

Material Cost (1:01)

Type of Material Unit Qty * Rate


bath tub No 1 1500.00
Brick No 65 6.61
cement kg 20 343.48
sand m3 0.3 190.22

Total (1:-01)

A= Materials Unit Cost 8856.20 Birr/m2

Remarks :
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED O

ANALYSIS SHEET FOR DIR


PROJECT: SANITERY WORK
WORK ITEM: ( 6.8 ) O50mm PVC
TOTAL QANTITY OF WORK ITEM: 1

Material Cost (1:01)


Type of Material Unit Qty * Rate
O50mm PVC No 0.175 18.33
union No 0.08 21.74
Plug No 0.16 21.74
elbow No 0.5 21.74
Tee No 0.25 21.74
Y No 0.025 21.74
glue lt 0.10 85.00

Total (1:-01)

A= Materials Unit Cost 33.77 Birr/m2

Remarks :
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED O

ANALYSIS SHEET FOR DIR


PROJECT: SANITERY WORK
WORK ITEM: ( 6.8 ) O75mm PVC
TOTAL QANTITY OF WORK ITEM: 1

Material Cost (1:01)

Type of Material Unit Qty * Rate


O75mm PVC No 0.175 27.54
union No 0.08 34.78
Plug No 0.16 34.78
elbow No 0.5 34.78
Reducer No 0.08 34.78
Tee No 0.25 34.78
Y No 0.025 34.78
glue lt 0.10 85.00
Total (1:-01)

A= Materials Unit Cost 51.41 Birr/m2

Remarks :
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED O
ANALYSIS SHEET FOR DIR
PROJECT: SANITERY WORK
WORK ITEM: ( 6.8 ) O100mm PVC
TOTAL QANTITY OF WORK ITEM: 1

Material Cost (1:01)

Type of Material Unit Qty * Rate


O100mm PVC No 0.175 34.78
union No 0.08 52.17
Plug No 0.16 52.17
elbow No 0.5 52.17
Reducer No 0.08 52.17
Tee No 0.25 52.17
Y No 0.025 52.17
glue lt 0.10 85.00
Total (1:-01)

A= Materials Unit Cost 71.72 Birr/m2

Remarks :
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED O

ANALYSIS SHEET FOR DIR


PROJECT: SANITERY WORK
WORK ITEM: ( 6.8 ) O50mm PVC vent cups
TOTAL QANTITY OF WORK ITEM: 1

Material Cost (1:01)

Type of Material Unit Qty * Rate


O50mm PVC No 0.175 231.00
glue lt 0.10 85.00

Total (1:-01)

A= Materials Unit Cost 48.93 Birr/m2


Remarks :
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED O

ANALYSIS SHEET FOR DIR


PROJECT: SANITERY WORK
WORK ITEM: ( 6.8 ) pvc down pipe
TOTAL QANTITY OF WORK ITEM: 1

Material Cost (1:01)

Type of Material Unit Qty * Rate


O100mm PVC No 1.05 25.20
fixing bracket No 0.43 13.30
fixer No 1 5.30
Bolt and nut No 2 5.30

Total (1:-01)

A= Materials Unit Cost 48.08 Birr/m2


Remarks :
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED O

ANALYSIS SHEET FOR DIR


PROJECT: SANITERY WORK
WORK ITEM: ( 6.8 ) 15cm thick H.C.B manholes
TOTAL QANTITY OF WORK ITEM: 1
Size:- 60 x 60 x60cm
Material Cost (1:01)

Type of Material Unit Qty * Rate


15 cm. Thick H.CB Pcs. 14.772 9.22
Cement Qt. 3.6966 343.48
Sand m3 0.5451 190.22
aggragete m3 0.7847 342.39
8mm rebar kgs 3.16 39.81
Water lts 0.04 0.120
Total (1:-01)

A= Materials Unit Cost 1904.02 Birr/m2

Remarks :
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED O
ANALYSIS SHEET FOR DIR
PROJECT: SANITERY WORK
WORK ITEM: ( 6.8 ) O150mm concrete sewer pipe
TOTAL QANTITY OF WORK ITEM: 1

Material Cost (1:01)

Type of Material Unit Qty * Rate


O150mm pipe ml 1.05 200.00
cement No 0.01472 343.48
Sand m3 0.04 190.22
red ash 0.0105 152.17
Water lts 0.04 0.120

Total (1:-01)

A= Materials Unit Cost 224.27 Birr/m2

Remarks :
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED O

ANALYSIS SHEET FOR DIR


PROJECT: SANITERY WORK
WORK ITEM: ( 6.8 ) O25mm GSP
TOTAL QANTITY OF WORK ITEM: 1

Material Cost (1:01)


Type of Material Unit Qty * Rate
O25mm GSP No 0.175 85.33
union No 0.08 106.70
Plug No 0.16 70.00
elbow No 0.5 86.00
Reducer No 0.08 86.00
Tee No 0.25 64.00
Fiber Kg 0.005 215.00
Total (1:-01)

A= Materials Unit Cost 101.62 Birr/m2

Remarks :
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED O

ANALYSIS SHEET FOR DIR


PROJECT: SANITERY WORK
WORK ITEM: ( 6.8 ) Water meter
TOTAL QANTITY OF WORK ITEM: 1

Material Cost (1:01)

Type of Material Unit Qty * Rate


32mm Water meter No 1 232.00
Total (1:-01)

A= Materials Unit Cost 232.00 Birr/m2

Remarks :
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED O
B. SUPER-STRUCTURE
5. CONCRETE WORK
ANALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS
LABOUR HOURLY OUTPUT:
echanical Mix) 1:2:3 EQUIPEMENT: Mixer & Vibrator
RESULT:

Labour (1:02)
Cost per Labour by ** Indexed Hourly
Unit Trade No. UF Hourly Cost Cost
1236.52 Mason 1 1 59.59 59.59
98.91 DL 18 1 25.54 459.72
267.07 foreman 1 0.25 46.44 11.61
260.00 Mixer Op. 1 1 42.57 42.57
16.30 Carpenter 1 1 51.08 51.08
Vibrator Op. 1 1 30.65 30.65

1878.80 Total (1:02) 655.22

B=Manpower Unit Cost 1048.35 Br./m3


Total of (1:02)
Hourly Output
Direct Cost of work item = A+B+C = 3134.83 Birr/m3
Overhead Cost: 10%
Profit Cost: 5%
Total Unit Cost :

E RELATED TO TARGETED OUTPUT.


LABOUR HOURLY OUTPUT:
echanical Mix) 1:2:3 EQUIPEMENT: Mixer & Vibrator
RESULT:

Labour (1:02)
Cost per Labour by ** Indexed Hourly
Unit Trade No. UF Hourly Cost Cost
1236.52 Mason 1 1 59.59 59.59
98.91 DL 18 1 25.54 459.72
267.07 foreman 1 0.25 46.44 11.61
260.00 Mixer Op. 1 1 42.57 42.57
16.30 Carpenter 1 1 51.08 51.08
Vibrator Op. 1 1 30.65 30.65

1878.80 Total (1:02) 655.22

B=Manpower Unit Cost 748.82 Br./m3


Total of (1:02)
Hourly Output
Direct Cost of work item = A+B+C = 2775.96 Birr/m3
Overhead Cost: 10%
Profit Cost: 5%
Total Unit Cost :

6. FORMWORK
ALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS
LABOUR HOURLY OUTPUT:
EQUIPEMENT:
m2 RESULT:

Labour (1:02)
Cost per Labour by ** Indexed Hourly
Unit Grade No. UF Hourly Cost Cost
247.83 Foreman 1 0.25 46.44 11.61
18.26 Carpenter 1 1 51.08 51.08
20.87 DL 2 1 25.54 51.08
0.11

287.06 Total (1:02) 113.77

B= Manpower Unit Cost 182.031 Birr/m2 C=Equipment Unit Cost


Total of (1:02)
Hourly Output:
Direct Cost of Work Item = A+B+C = 478.69 Birr/m2
O Over head cost : 10%
Pr Profit Cost: 5%
Tot Total Unit Cost :
_________________________

E RELATED TO TARGETED OUTPUT.


ALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS
LABOUR HOURLY OUTPUT:
EQUIPEMENT:
m2 RESULT:

Labour (1:02)
Cost per Labour by ** Indexed Hourly
Unit Grade No. UF Hourly Cost Cost
247.83 Foreman 1 0.25 46.44 11.61
18.26 Carpenter 1 1 51.08 51.08
20.87 DL 2 1 25.54 51.08
0.11

287.06 Total (1:02) 113.77

B= Manpower Unit Cost 151.692 Birr/m2 C=Equipment Unit Cost


Total of (1:02)
Hourly Output:
Direct Cost of Work Item = A+B+C = 446.75 Birr/m2
O Over head cost : 10%
Pr Profit Cost: 5%
Tot Total Unit Cost :
_________________________

E RELATED TO TARGETED OUTPUT.

19. BAR SCHEDULE

ALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS


LABOUR HOURLY OUTPUT:
EQUIPEMENT:
RESULT:

Labour (1:02)
Cost per Labour by ** Indexed Hourly
Unit Grade No. UF Hourly Cost Cost
41.7991304 Foreman 1 0.25 46.44 11.61
1.13043478 Barbender 1 1 34.05 34.05
D/L 2 1 25.54 51.08

42.93 Total (1:02) 96.74

B= Manpower Unit Cost 2.58 Birr/kg.


Total of (1:02)
hourly output:
Direct Cost of Work Item = A+B+C = 45.71 Birr/kg.
Over head cost : 10%
Profit Cost: 5%
Total Unit Cost :
_________________________

E RELATED TO TARGETED OUTPUT.

ALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS


LABOUR HOURLY OUTPUT:
EQUIPEMENT:
RESULT:

Labour (1:02)
Cost per Labour by ** Indexed Hourly
Unit Grade No. UF Hourly Cost Cost
41.0869565 Foreman 1 0.25 46.44 11.61
1.13043478 Barbender 1 1 34.05 34.05
D/L 2 1 25.54 51.08
42.22 Total (1:02) 96.74

B= Manpower Unit Cost 2.50 Birr/kg.


Total of (1:02)
hourly output:
Direct Cost of Work Item = A+B+C = 44.91 Birr/kg.
Over head cost : 10%
Profit Cost: 5%
Total Unit Cost :
_________________________

E RELATED TO TARGETED OUTPUT.

ALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS


LABOUR HOURLY OUTPUT:
EQUIPEMENT:
RESULT:

Labour (1:02)
Cost per Labour by ** Indexed Hourly
Unit Grade No. UF Hourly Cost Cost
41.0869565 Foreman 1 0.25 46.44 11.61
1.13043478 Barbender 1 1 34.05 34.05
D/L 2 1 25.54 51.08

42.22 Total (1:02) 96.74

B= Manpower Unit Cost 2.21 Birr/kg.


Total of (1:02)
hourly output:
Direct Cost of Work Item = A+B+C = 44.60 Birr/kg.
Over head cost : 10%
Profit Cost: 5%
Total Unit Cost :
_________________________

E RELATED TO TARGETED OUTPUT.

ALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS


LABOUR HOURLY OUTPUT:
EQUIPEMENT:
RESULT:

Labour (1:02)
Cost per Labour by ** Indexed Hourly
Unit Grade No. UF Hourly Cost Cost
42 Foreman 1 0.25 46.44 11.61
1.13043478 Barbender 1 1 34.05 34.05
D/L 2 1 25.54 51.08

43.13 Total (1:02) 96.74

B= Manpower Unit Cost 2.15 Birr/kg.


Total of (1:02)
hourly output:
Direct Cost of Work Item = A+B+C = 45.45 Birr/kg.
Over head cost : 10%
Profit Cost: 5%
Total Unit Cost :
_________________________
E RELATED TO TARGETED OUTPUT.

7. BLOCK WORK
ALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS
LABOUR HOURLY OUTPUT:
all Both Sides Left For Plastering. EQUIPEMENT:
RESULT:

Labour (1:02)
Cost per Labour by ** Indexed Hourly
Unit Grade No. UF Hourly Cost Cost
142.434783 Foreman 1 1 46.44 46.44
34.3478261 Mason 1 1 25.00 25.00
5.32608696 D/L 2 1 13.33 26.66
0.00004

182.11 Total ( 1:02 ) 98.10

B= Manpower Unit Cost 78.48 Birr/m2


Total of (1:02)
Hourly Output: _______________________
Direct Cost of Work Item = A+B+C = 262.19 Birr/m2
O Over head cost : 10%
Pr Profit Cost: 5%
Tot Total Unit Cost :

E RELATED TO TARGETED OUTPUT.

ALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS


LABOUR HOURLY OUTPUT:
all Both Sides Left For Plastering. EQUIPEMENT:
RESULT:

Labour (1:02)
Cost per Labour by ** Indexed Hourly
Unit Grade No. UF Hourly Cost Cost
119.826087 Foreman 1 1 0.00 0.00
25.7608696 Mason 1 1 25.00 25.00
4.18478261 D/L 2 1 13.33 26.66
0.00004

149.77 Total ( 1:02 ) 51.66

B= Manpower Unit Cost 41.33 Birr/m2


Total of (1:02)
Hourly Output: _______________________
Direct Cost of Work Item = A+B+C = 192.70 Birr/m2
O Over head cost : 10%
Pr Profit Cost: 5%
Tot Total Unit Cost :

14.ROOF WORK
ALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS
LABOUR HOURLY OUTPUT:
EQUIPEMENT:
m2 RESULT:

Labour (1:02)
Cost per Labour by ** Indexed Hourly
Unit Grade No. UF Hourly Cost Cost
219.826087 carpenter 1 1 51.08 51.08
10.7660455 ass carpente 1 1 30.65 30.65
D/L 2 1 25.54 51.08
forman 1 0.5 46.44 23.22

230.59Total ( 1:02 ) 156.03

B= Manpower Unit Cost 24.00 Birr/m2


Total of (1:02)
Hourly Output: _______________________
Direct Cost of Work Item = A+B+C = 254.75 Birr/m2
O Over head cost : 10%
Pr Profit Cost: 5%
Tot Total Unit Cost :

E RELATED TO TARGETED OUTPUT.

ALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS


LABOUR HOURLY OUTPUT:
EQUIPEMENT:
m2 RESULT:

Labour (1:02)
Cost per Labour by ** Indexed Hourly
Unit Grade No. UF Hourly Cost Cost
289.208696 carpenter 1 1 51.08 51.08
8.59130435 ass carpente 1 1 30.65 30.65
D/L 2 1 25.54 51.08
forman 1 0.5 46.44 23.22
297.80Total ( 1:02 ) 156.03

B= Manpower Unit Cost 46.23 Birr/m2


Total of (1:02)
Hourly Output: _______________________
Direct Cost of Work Item = A+B+C = 344.33 Birr/m2
O Over head cost : 10%
Pr Profit Cost: 5%
Tot Total Unit Cost :

E RELATED TO TARGETED OUTPUT.

ALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS


LABOUR HOURLY OUTPUT:
EQUIPEMENT:
ml RESULT:

Labour (1:02)
Cost per Labour by ** Indexed Hourly
Unit Grade No. UF Hourly Cost Cost
101.73913 Carpenter 1 1 51.08 51.08
8.59130435 forman 1 1 46.44 46.44
DL 2 1 25.54 51.08

110.33Total ( 1:02 ) 148.60

B= Manpower Unit Cost 19.81 Birr/m2


Total of (1:02)
Hourly Output: _______________________
Direct Cost of Work Item = A+B+C = 130.28 Birr/m2
O Over head cost : 10%
Pr Profit Cost: 5%
Tot Total Unit Cost :

E RELATED TO TARGETED OUTPUT.

ALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS


LABOUR HOURLY OUTPUT:
EQUIPEMENT:
ml RESULT:

Labour (1:02)
Cost per Labour by ** Indexed Hourly
Unit Grade No. UF Hourly Cost Cost
109.565217 carpenter 1 1 51.08 51.08
8.59130435 ass carpente 1 1 30.65 30.65
D/L 2 1 25.54 51.08
forman 1 0.5 46.44 23.22

118.16Total ( 1:02 ) 156.03

B= Manpower Unit Cost 17.83 Birr/m2


Total of (1:02)
Hourly Output: _______________________
Direct Cost of Work Item = A+B+C = 136.10 Birr/m2
O Over head cost : 10%
Pr Profit Cost: 5%
Tot Total Unit Cost :
E RELATED TO TARGETED OUTPUT.

ALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS


LABOUR HOURLY OUTPUT:
EQUIPEMENT:
ml RESULT:

Labour (1:02)
Cost per Labour by ** Indexed Hourly
Unit Grade No. UF Hourly Cost Cost
333.459357 carpenter 1 1 51.08 51.08
8.59130435 ass carpente 1 1 30.65 30.65
D/L 2 1 25.54 51.08
forman 1 0.5 46.44 23.22

342.05Total ( 1:02 ) 156.03

B= Manpower Unit Cost 20.80 Birr/m2


Total of (1:02)
Hourly Output: _______________________
Direct Cost of Work Item = A+B+C = 362.99 Birr/m2
O Over head cost : 10%
Pr Profit Cost: 5%
Tot Total Unit Cost :

E RELATED TO TARGETED OUTPUT.

13. CARPENTERY AND JOINERY WORK


ALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS
LABOUR HOURLY OUTPUT:
EQUIPEMENT:
truss RESULT:

Labour (1:02)
Cost per Labour by ** Indexed Hourly
Unit Grade No. UF Hourly Cost Cost
27.9503106 carpenter 1 1 51.08 51.08
2.7826087 ass carpente 1 1 30.65 30.65
5.73913043 D/L 2 1 25.54 51.08
forman 1 0.5 46.44 23.22

36.47Total ( 1:02 ) 132.81

B= Manpower Unit Cost 13.28 Birr/m2


Total of (1:02)
Hourly Output: _______________________
Direct Cost of Work Item = A+B+C = 49.95 Birr/m2
O Over head cost : 10%
Pr Profit Cost: 5%
Tot Total Unit Cost :

E RELATED TO TARGETED OUTPUT.


ALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS
LABOUR HOURLY OUTPUT:
EQUIPEMENT:
truss RESULT:

Labour (1:02)
Cost per Labour by ** Indexed Hourly
Unit Grade No. UF Hourly Cost Cost
13.9130435 carpenter 1 1 51.08 51.08
2.85217391 ass carpente 1 1 30.65 30.65
5.73913043 D/L 2 1 25.54 51.08
forman 1 0.5 46.44 23.22

22.50Total ( 1:02 ) 156.03

B= Manpower Unit Cost 20.80 Birr/m2


Total of (1:02)
Hourly Output: _______________________
Direct Cost of Work Item = A+B+C = 43.57 Birr/m2
O Over head cost : 10%
Pr Profit Cost: 5%
Tot Total Unit Cost :

E RELATED TO TARGETED OUTPUT.

ALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS


LABOUR HOURLY OUTPUT:
EQUIPEMENT:
ml RESULT:

Labour (1:02)
Cost per Labour by ** Indexed Hourly
Unit Grade No. UF Hourly Cost Cost
18.2608696 carpenter 1 1 51.08 51.08
10.6956522 ass carpente 1 1 30.65 30.65
D/L 2 1 25.54 51.08
forman 1 0.5 46.44 23.22

28.96Total ( 1:02 ) 156.03


B= Manpower Unit Cost 16.64 Birr/m2
Total of (1:02)
Hourly Output: _______________________
Direct Cost of Work Item = A+B+C = 45.81 Birr/m2
O Over head cost : 10%
Pr Profit Cost: 5%
Tot Total Unit Cost :

E RELATED TO TARGETED OUTPUT.

ALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS


LABOUR HOURLY OUTPUT:
EQUIPEMENT:
pc RESULT:

Labour (1:02)
Cost per Labour by ** Indexed Hourly
Unit Grade No. UF Hourly Cost Cost
4820.86957 carpenter 1 1 51.08 51.08
4.99130435 ass carpente 1 1 30.65 30.65
D/L 2 1 25.54 51.08
forman 1 0.5 46.44 23.22

4825.86Total ( 1:02 ) 156.03

B= Manpower Unit Cost 249.64 Birr/m2


Total of (1:02)
Hourly Output: _______________________
Direct Cost of Work Item = A+B+C = 5078.70 Birr/m2
O Over head cost : 10%
Pr Profit Cost: 5%
Tot Total Unit Cost :

E RELATED TO TARGETED OUTPUT.

ALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS


LABOUR HOURLY OUTPUT:
EQUIPEMENT:
pc RESULT:

Labour (1:02)
Cost per Labour by ** Indexed Hourly
Unit Grade No. UF Hourly Cost Cost
10846.9565 carpenter 1 1 51.08 51.08
4.99130435 ass carpente 1 1 30.65 30.65
D/L 2 1 25.54 51.08
forman 1 0.5 46.44 23.22

10851.95Total ( 1:02 ) 156.03

B= Manpower Unit Cost 312.05 Birr/m2


Total of (1:02)
Hourly Output: _______________________
Direct Cost of Work Item = A+B+C = ### Birr/m2
O Over head cost : 10%
Pr Profit Cost: 5%
Tot Total Unit Cost :

E RELATED TO TARGETED OUTPUT.


16.METAL AND ALUMINUM WORK
ALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS
LABOUR HOURLY OUTPUT:
EQUIPEMENT:
pcs RESULT:

Labour (1:02) Equipment Cost (1:03)


Cost per Labour by ** Indexed Hourly
Unit Grade No. UF Hourly Cost Cost
4262.6087 D/L 3 1 25.54 76.62
0 mason 1 1 59.59 59.59
Chiseler 1 1 30.65 30.65
Forman 1 0.5 46.44 23.22
4262.61Total ( 1:02 ) 190.08

B= Manpower Unit Cost 149.08 Birr/m2


Total of (1:02)
Hourly Output: _______________________
Direct Cost of Work Item = A+B+C = 4413.26 Birr/m2
O Over head cost : 10%
Pr Profit Cost: 5%
Tot Total Unit Cost :

E RELATED TO TARGETED OUTPUT.

ALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS


LABOUR HOURLY OUTPUT:
S for handrails EQUIPEMENT:
RESULT:
Labour (1:02)
Cost per Labour by ** Indexed Hourly
Unit Grade No. UF Hourly Cost Cost
41.61 Foreman 1 1 46.44 23.22
3.40 Welder 1 1 59.59 59.59
0.40 D/L 1 1 25.54 25.54
0.57 Carpenter1 1 1 51.08 51.08

45.98Total ( 1:02 ) 159.43

B= Manpower Unit Cost 3.19 Birr/m2


Total of (1:02)
Hourly Output: _______________________
Direct Cost of Work Item = A+B+C = 49.25 Birr/m2
Over head cost : 10%
Profit Cost: 5%
Total Unit Cost :

E RELATED TO TARGETED OUTPUT.


ALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS
LABOUR HOURLY OUTPUT:

for handrails EQUIPEMENT:


RESULT:

Labour (1:02)
Cost per Labour by ** Indexed Hourly
Unit Grade No. UF Hourly Cost Cost
36.3461538 Foreman 1 1 46.44 23.22
3.4 Welder 1 1 59.59 59.59
0.4 D/L 1 1 25.54 25.54
0.572 Carpenter1 1 1 51.08 51.08

40.72Total ( 1:02 ) 159.43

B= Manpower Unit Cost 3.19 Birr/m2


Total of (1:02)
Hourly Output: _______________________
Direct Cost of Work Item = A+B+C = 43.99 Birr/m2
Over head cost : 10%
Profit Cost: 5%
Total Unit Cost :

E RELATED TO TARGETED OUTPUT.

ALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS


LABOUR HOURLY OUTPUT:
EQUIPEMENT:
m2 RESULT:

Labour (1:02) Equipment Cost (1:03)


Cost per Labour by ** Indexed Hourly
Unit Grade No. UF Hourly Cost Cost
695.652174 D/L 2 1 25.54 51.08
0 mason 1 1 59.59 59.59
Chiseler 1 1 30.65 30.65
Forman 1 0.5 46.44 23.22
695.65Total ( 1:02 ) 164.54
B= Manpower Unit Cost 115.87 Birr/m2
Total of (1:02)
Hourly Output: _______________________
Direct Cost of Work Item = A+B+C = 812.93 Birr/m2
O Over head cost : 10%
Pr Profit Cost: 5%
Tot Total Unit Cost :

ALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS


LABOUR HOURLY OUTPUT:
EQUIPEMENT:
m2 RESULT:

Labour (1:02) Equipment Cost (1:03)


Cost per Labour by ** Indexed Hourly
Unit Grade No. UF Hourly Cost Cost
695.652174 D/L 2 1 25.54 51.08
0 mason 1 1 59.59 59.59
Chiseler 1 1 30.65 30.65
Forman 1 0.5 46.44 23.22
695.65Total ( 1:02 ) 164.54

B= Manpower Unit Cost 116.08 Birr/m2


Total of (1:02)
Hourly Output: _______________________
Direct Cost of Work Item = A+B+C = 813.14 Birr/m2
O Over head cost : 10%
Pr Profit Cost: 5%
Tot Total Unit Cost :

ALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS


LABOUR HOURLY OUTPUT:
EQUIPEMENT:
m2 RESULT:

Labour (1:02) Equipment Cost (1:03)


Cost per Labour by ** Indexed Hourly
Unit Grade No. UF Hourly Cost Cost
695.652174 D/L 2 1 25.54 51.08
0 mason 1 1 59.59 59.59
Chiseler 1 1 30.65 30.65
Forman 1 0.5 46.44 23.22
695.65Total ( 1:02 ) 164.54

B= Manpower Unit Cost 153.63 Birr/m2


Total of (1:02)
Hourly Output: _______________________
Direct Cost of Work Item = A+B+C = 851.15 Birr/m2
O Over head cost : 10%
Pr Profit Cost: 5%
Tot Total Unit Cost :

8. FINISHING WORK
ALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS
LABOUR HOURLY OUTPUT:
internal wall plastering EQUIPEMENT:
m2 RESULT:

Labour (1:02) Equipment Cost


Cost per Labour by ** Indexed Hourly
Unit Grade No. UF Hourly Cost Cost
35.343913 plasterer 1 1 59.59 59.59
0.41847826 D/L 2 1 25.54 51.08
9.6 Forman 1 0.5 46.44 23.22
0.07

45.40Total ( 1:02 ) 133.89

B= Manpower Unit Cost 26.78 Birr/m2


Total of (1:02)
Hourly Output: _______________________
Direct Cost of Work Item = A+B+C = 73.10 Birr/m2
O Over head cost : 10%
Pr Profit Cost: 5%
Tot Total Unit Cost :

E RELATED TO TARGETED OUTPUT.


ALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS

LABOUR HOURLY OUTPUT:


external wall plastering EQUIPEMENT:
m2 RESULT:

Labour (1:02) Equipment Cost


Cost per Labour by ** Indexed Hourly
Unit Grade No. UF Hourly Cost Cost
35.343913 plasterer 1 1 59.59 59.59
0.41847826 D/L 2 1 25.54 51.08
9.6 Forman 1 0.5 46.44 23.22
0.07
45.40Total ( 1:02 ) 133.89

B= Manpower Unit Cost 30.60 Birr/m2


Total of (1:02)
Hourly Output: _______________________
Direct Cost of Work Item = A+B+C = 77.06 Birr/m2
O Over head cost : 10%
Pr Profit Cost: 5%
Tot Total Unit Cost :

ALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS


LABOUR HOURLY OUTPUT:
astering for exposed edges EQUIPEMENT:
ml RESULT:

Labour (1:02) Equipment Cost


Cost per Labour by ** Indexed Hourly
Unit Grade No. UF Hourly Cost Cost
1.58 plasterer 1 1 59.59 59.59
0.19021739 D/L 2 1 25.54 51.08
9.6
0.07

11.41Total ( 1:02 ) 110.67

B= Manpower Unit Cost 49.19 Birr/m2


Total of (1:02)
Hourly Output: _______________________
Direct Cost of Work Item = A+B+C = 62.64 Birr/m2
O Over head cost : 10%
Pr Profit Cost: 5%
Tot Total Unit Cost :

E RELATED TO TARGETED OUTPUT.

ALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS


LABOUR HOURLY OUTPUT:
internal wall plastering to receive ceramic EQUIPEMENT:
m2 RESULT:

Labour (1:02) Equipment Cost


Cost per Labour by ** Indexed Hourly
Unit Grade No. UF Hourly Cost Cost
35.4538261 plasterer 1 1 59.59 59.59
2.72695652 D/L 2 1 25.54 51.08
Forman 1 0.5 46.44 23.22

38.18Total ( 1:02 ) 133.89

B= Manpower Unit Cost 30.60 Birr/m2


Total of (1:02)
Hourly Output: _______________________
Direct Cost of Work Item = A+B+C = 69.84 Birr/m2
O Over head cost : 10%
Pr Profit Cost: 5%
Tot Total Unit Cost :
E RELATED TO TARGETED OUTPUT.

ALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS


LABOUR HOURLY OUTPUT:
EQUIPEMENT:
m2 1:2 mix ratio RESULT:

Labour (1:02)
Cost per Labour by ** Indexed Hourly
Unit Grade No. UF Hourly Cost Cost
324 forman 1 1 46.44 46.44
0.30434783 tiler 1 1 59.59 59.59
3.63315217 D/L 2 0.25 25.54 12.77
47.0565217

374.99Total ( 1:02 ) 118.80

B= Manpower Unit Cost 135.77 Birr/m2


Total of (1:02)
Hourly Output: _______________________
Direct Cost of Work Item = A+B+C = 514.19 Birr/m2
O Over head cost : 10%
Pr Profit Cost: 5%
Tot Total Unit Cost :

E RELATED TO TARGETED OUTPUT.

ALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS


LABOUR HOURLY OUTPUT:
EQUIPEMENT:
m2 RESULT:

Labour (1:02)
Cost per Labour by ** Indexed Hourly
Unit Grade No. UF Hourly Cost Cost
822.652174 tailer 1 1 59.59 59.59
0.30434783 D/L 2 1 25.54 51.08
35.4538261 Forman 1 0.25 46.44 11.61
2.72695652

861.14Total ( 1:02 ) 122.28

B= Manpower Unit Cost 97.83 Birr/m2


Total of (1:02)
Hourly Output: _______________________
Direct Cost of Work Item = A+B+C = 961.36 Birr/m2
O Over head cost : 10%
Pr Profit Cost: 5%
Tot Total Unit Cost :

E RELATED TO TARGETED OUTPUT.

ALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS


LABOUR HOURLY OUTPUT:
EQUIPEMENT:
m2 RESULT:

Labour (1:02)
Cost per Labour by ** Indexed Hourly
Unit Grade No. UF Hourly Cost Cost
434.23913 tailer 1 1 59.59 59.59
48.9130435 D/L 2 1 25.54 51.08
48.9130435 Forman 1 0.25 46.44 11.61

532.07Total ( 1:02 ) 122.28

B= Manpower Unit Cost 57.54 Birr/m2


Total of (1:02)
Hourly Output: _______________________
Direct Cost of Work Item = A+B+C = 589.61 Birr/m2
O Over head cost : 10%
Pr Profit Cost: 5%
Tot Total Unit Cost :

E RELATED TO TARGETED OUTPUT.

ALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS


LABOUR HOURLY OUTPUT:
EQUIPEMENT:
m2 RESULT:

Labour (1:02)
Cost per Labour by ** Indexed Hourly
Unit Grade No. UF Hourly Cost Cost
975.652174 tailer 1 1 59.59 59.59
0.30434783 D/L 2 1 25.54 51.08
35.4538261 Forman 1 0.25 46.44 11.61
2.72695652

1014.14Total ( 1:02 ) 122.28


B= Manpower Unit Cost 81.52 Birr/m2
Total of (1:02)
Hourly Output: _______________________
Direct Cost of Work Item = A+B+C = 1095.66 Birr/m2
O Over head cost : 10%
Pr Profit Cost: 5%
Tot Total Unit Cost :

E RELATED TO TARGETED OUTPUT.

ALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS


LABOUR HOURLY OUTPUT:
EQUIPEMENT:
m RESULT:

Labour (1:02)
Cost per Labour by ** Indexed Hourly
Unit Grade No. UF Hourly Cost Cost
95.8695652 forman 1 0.5 46.44 23.22
1.58 tailer 1 1 59.59 59.59
0.19021739 D/L 2 1 25.54 51.08

97.64Total ( 1:02 ) 133.89

B= Manpower Unit Cost 66.95 Birr/m2


Total of (1:02)
Hourly Output: _______________________
Direct Cost of Work Item = A+B+C = 166.09 Birr/m2
O Over head cost : 10%
Pr Profit Cost: 5%
Tot Total Unit Cost :

E RELATED TO TARGETED OUTPUT.

ALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS


LABOUR HOURLY OUTPUT:
EQUIPEMENT:
m RESULT:

Labour (1:02)
Cost per Labour by ** Indexed Hourly
Unit Grade No. UF Hourly Cost Cost
0 carpenter 2 1 0.00 0.00
0 ass carpente 2 1 0.00 0.00
0 D/L 3 1 0.00 0.00
0 forman 1 1 0.00 0.00
0

0.00Total ( 1:02 ) 0.00

B= Manpower Unit Cost 0.00 Birr/m2


Total of (1:02)
Hourly Output: _______________________
Direct Cost of Work Item = A+B+C = 1.00 Birr/m2
O Over head cost : 10%
Pr Profit Cost: 5%
Tot Total Unit Cost :

E RELATED TO TARGETED OUTPUT.


12. DOOR AND WINDOW SILL
ALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS
LABOUR HOURLY OUTPUT:
EQUIPEMENT:
m RESULT:

Labour (1:02)
Cost per Labour by ** Indexed Hourly
Unit Grade No. UF Hourly Cost Cost
50 forman 1 1 46.44 46.44
8.93043478 tailer 1 1 59.59 59.59
1.33152174 D/L 2 1 25.54 51.08

60.26Total ( 1:02 ) 157.11

B= Manpower Unit Cost 78.56 Birr/m2


Total of (1:02)
Hourly Output: _______________________
Direct Cost of Work Item = A+B+C = 140.32 Birr/m2
Over head cost : 10%
Profit Cost: 5%
Total Unit Cost :

E RELATED TO TARGETED OUTPUT.


ALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS
LABOUR HOURLY OUTPUT:
EQUIPEMENT:
m RESULT:
Labour (1:02)
Cost per Labour by ** Indexed Hourly
Unit Grade No. UF Hourly Cost Cost
50 forman 1 1 46.44 46.44
8.93043478 tailer 1 1 59.59 59.59
1.33152174 D/L 2 1 25.54 51.08

60.26Total ( 1:02 ) 157.11

B= Manpower Unit Cost 78.56 Birr/m2


Total of (1:02)
Hourly Output: _______________________
Direct Cost of Work Item = A+B+C = 140.32 Birr/m2
Over head cost : 10%
Profit Cost: 5%
Total Unit Cost :

E RELATED TO TARGETED OUTPUT.

9. PAINTING
ALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS
LABOUR HOURLY OUTPUT:
paint for internal and external verandah wall, beam and co EQUIPEMENT:
m2 RESULT:

Labour (1:02)
Cost per Labour by ** Indexed Hourly
Unit Grade No. UF Hourly Cost Cost
0.65217391 forman 1 0.1 46.436 4.64
0.76086957 D/L 1 1 25.540 25.54
5.32608696 painter 1 1 59.593 59.59
4.56521739
3.80434783
0.13043478
0.26086957
0.05217391
1
15.55Total ( 1:02 ) 89.78

B= Manpower Unit Cost 23.94 Birr/m2


Total of (1:02)
Hourly Output: _______________________
Direct Cost of Work Item = A+B+C = 39.49 Birr/m2
O Over head cost : 10%
Pr Profit Cost: 5%
Tot Total Unit Cost :

E RELATED TO TARGETED OUTPUT.


ALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS
LABOUR HOURLY OUTPUT:
tic oil paint for kitchen and bathrooms EQUIPEMENT:
m2 RESULT:

Labour (1:02)
Cost per Labour by ** Indexed Hourly
Unit Grade No. UF Hourly Cost Cost
0.65217391 forman 1 0.1 46.436 4.64
0.76086957 D/L 1 1 25.540 25.54
5.32608696 painter 1 1 59.593 59.59
4.56521739
3.80434783
0.13043478
0.26086957
0.05217391
15.55Total ( 1:02 ) 89.78

B= Manpower Unit Cost 28.73 Birr/m2


Total of (1:02)
Hourly Output: _______________________
Direct Cost of Work Item = A+B+C = 44.28 Birr/m2
O Over head cost : 10%
Pr Profit Cost: 5%
Tot Total Unit Cost :

ALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS


LABOUR HOURLY OUTPUT:
EQUIPEMENT:
m2 RESULT:

Labour (1:02) Equipment Cost (1:03)


Cost per Labour by ** Indexed Hourly
Unit Grade No. UF Hourly Cost Cost
243.478261 forman 1 0.1 46.436 4.64
0.13043478 D/L 1 1 25.540 25.54
0.76086957 painter 1 1 59.593 59.59
5.2173913
249.59Total ( 1:02 ) 89.78

B= Manpower Unit Cost 59.85 Birr/m2


Total of (1:02)
Hourly Output: _______________________
Direct Cost of Work Item = A+B+C = 309.44 Birr/m2
O Over head cost : 10%
Pr Profit Cost: 5%
Tot Total Unit Cost :
E RELATED TO TARGETED OUTPUT.

18.GLAZING WORK
ALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS
LABOUR HOURLY OUTPUT:
EQUIPEMENT:
m2 RESULT:

Labour (1:02)
Cost per Labour by ** Indexed Hourly
Unit Grade No. UF Hourly Cost Cost
349.130435 glazer 1 1 38.70 38.70
17.3913043 ass glazer 1 1 34.05 34.05
forman 1 0.5 46.44 23.22

366.52Total ( 1:02 ) 95.97

B= Manpower Unit Cost 54.84 Birr/m2


Total of (1:02)
Hourly Output: _______________________
Direct Cost of Work Item = A+B+C = 422.50 Birr/m2
O Over head cost : 10%
Pr Profit Cost: 5%
Tot Total Unit Cost :
E RELATED TO TARGETED OUTPUT.

ALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS


LABOUR HOURLY OUTPUT:
EQUIPEMENT:
m2 RESULT:

Labour (1:02)
Cost per Labour by ** Indexed Hourly
Unit Grade No. UF Hourly Cost Cost
430.434783 glazer 2 1 38.70 77.39
17.3913043 ass glazer 1 1 34.05 34.05
forman 1 0.5 0.00 0.00

447.83Total ( 1:02 ) 111.45

B= Manpower Unit Cost 63.68 Birr/m2


Total of (1:02)
Hourly Output: _______________________
Direct Cost of Work Item = A+B+C = 511.97 Birr/m2
O Over head cost : 10%
Pr Profit Cost: 5%
Tot Total Unit Cost :

E RELATED TO TARGETED OUTPUT.

15.SANITERY WORK
ALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS
LABOUR HOURLY OUTPUT:
EQUIPEMENT:
ml RESULT:

Labour (1:02)
Cost per Labour by ** Indexed Hourly
Unit Grade No. UF Hourly Cost Cost
14.9333333 Plumber 1 1 59.59 59.59
8.536 DL 2 1 25.54 51.08
11.2
43
16

93.67Total ( 1:02 ) 110.67

B= Manpower Unit Cost 22.13 Birr/m2


Total of (1:02)
Hourly Output: _______________________
Direct Cost of Work Item = A+B+C = 117.60 Birr/m2
O Over head cost : 10%
Pr Profit Cost: 5%
Tot Total Unit Cost :

E RELATED TO TARGETED OUTPUT.

ALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS


LABOUR HOURLY OUTPUT:
EQUIPEMENT:
ml RESULT:
Labour (1:02)
Cost per Labour by ** Indexed Hourly
Unit Grade No. UF Hourly Cost Cost
5.6875 Plumber 1 1 59.59 59.59
1.84 DL 2 1 25.54 51.08
3.68
11.5
5.75

28.46Total ( 1:02 ) 110.67

B= Manpower Unit Cost 17.71 Birr/m2


Total of (1:02)
Hourly Output: _______________________
Direct Cost of Work Item = A+B+C = 47.61 Birr/m2
O Over head cost : 10%
Pr Profit Cost: 5%
Tot Total Unit Cost :

E RELATED TO TARGETED OUTPUT.

ALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS


LABOUR HOURLY OUTPUT:
EQUIPEMENT:
ml RESULT:

Labour (1:02)
Cost per Labour by ** Indexed Hourly
Unit Grade No. UF Hourly Cost Cost
6.5625 Plumber 1 1 59.59 59.59
2.16 DL 2 1 25.54 51.08
4.32
13.5
6.75
33.75

67.04Total ( 1:02 ) 110.67

B= Manpower Unit Cost 17.71 Birr/m2


Total of (1:02)
Hourly Output: _______________________
Direct Cost of Work Item = A+B+C = 86.19 Birr/m2
O Over head cost : 10%
Pr Profit Cost: 5%
Tot Total Unit Cost :

E RELATED TO TARGETED OUTPUT.

ALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS


LABOUR HOURLY OUTPUT:
EQUIPEMENT:
pcs RESULT:

Labour (1:02)
Cost per Labour by ** Indexed Hourly
Unit Grade No. UF Hourly Cost Cost
230 Plumber 1 1 59.59 59.59
1.08 DL 2 1 25.54 51.08
231.08Total ( 1:02 ) 110.67

B= Manpower Unit Cost 59.03 Birr/m2


Total of (1:02)
Hourly Output: _______________________
Direct Cost of Work Item = A+B+C = 294.90 Birr/m2
O Over head cost : 10%
Pr Profit Cost: 5%
Tot Total Unit Cost :

E RELATED TO TARGETED OUTPUT.

ALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS


LABOUR HOURLY OUTPUT:
EQUIPEMENT:
pcs RESULT:

Labour (1:02)
Cost per Labour by ** Indexed Hourly
Unit Grade No. UF Hourly Cost Cost
230 Plumber 1 1 59.59 59.59
1.08 DL 1 1 25.54 25.54

231.08Total ( 1:02 ) 85.13

B= Manpower Unit Cost 45.40 Birr/m2


Total of (1:02)
Hourly Output: _______________________
Direct Cost of Work Item = A+B+C = 281.28 Birr/m2
O Over head cost : 10%
Pr Profit Cost: 5%
Tot Total Unit Cost :

E RELATED TO TARGETED OUTPUT.

ALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS


LABOUR HOURLY OUTPUT:
EQUIPEMENT:
pcs RESULT:

Labour (1:02)
Cost per Labour by ** Indexed Hourly
Unit Grade No. UF Hourly Cost Cost
4500.00 Plumber 1 1 59.59 59.59
160.05 DL 3 1 25.54 76.62
117.37
10.75
4788.17Total ( 1:02 ) 136.21

B= Manpower Unit Cost 544.85 Birr/m2


Total of (1:02)
Hourly Output: _______________________
Direct Cost of Work Item = A+B+C = 5369.02 Birr/m2
O Over head cost : 10%
Pr Profit Cost: 5%
Tot Total Unit Cost :
E RELATED TO TARGETED OUTPUT.

ALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS


LABOUR HOURLY OUTPUT:
EQUIPEMENT:
pcs RESULT:

Labour (1:02)
Cost per Labour by ** Indexed Hourly
Unit Grade No. UF Hourly Cost Cost
500 Plumber 1 1 59.59 59.59
1.08 DL 2 1 25.54 51.08

501.08Total ( 1:02 ) 110.67

B= Manpower Unit Cost 295.13 Birr/m2


Total of (1:02)
Hourly Output: _______________________
Direct Cost of Work Item = A+B+C = 820.20 Birr/m2
O Over head cost : 10%
Pr Profit Cost: 5%
Tot Total Unit Cost :

E RELATED TO TARGETED OUTPUT.

ALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS


LABOUR HOURLY OUTPUT:
EQUIPEMENT:
pcs RESULT:
Labour (1:02)
Cost per Labour by ** Indexed Hourly
Unit Grade No. UF Hourly Cost Cost
3693 forman 1 0.25 46.44 11.61
2.17 plumber 1 1 59.59 59.59
0.22 Chiseler 1 1 30.65 30.65

3695.39Total ( 1:02 ) 101.85

B= Manpower Unit Cost 271.60 Birr/m2


Total of (1:02)
Hourly Output: _______________________
Direct Cost of Work Item = A+B+C = 3990.99 Birr/m2
O Over head cost : 10%
Pr Profit Cost: 5%
Tot Total Unit Cost :

E RELATED TO TARGETED OUTPUT.

ALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS


LABOUR HOURLY OUTPUT:
EQUIPEMENT:
pcs RESULT:

Labour (1:02)
Cost per Labour by ** Indexed Hourly
Unit Grade No. UF Hourly Cost Cost
1800 forman 1 0.25 46.44 11.61
2.17 plumber 1 1 59.59 59.59
0.22 Chiseler 1 1 30.65 30.65

1802.39Total ( 1:02 ) 101.85

B= Manpower Unit Cost 271.60 Birr/m2


Total of (1:02)
Hourly Output: _______________________
Direct Cost of Work Item = A+B+C = 2097.99 Birr/m2
O Over head cost : 10%
Pr Profit Cost: 5%
Tot Total Unit Cost :

E RELATED TO TARGETED OUTPUT.

ALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS


LABOUR HOURLY OUTPUT:
EQUIPEMENT:
pcs RESULT:

Labour (1:02)
Cost per Labour by ** Indexed Hourly
Unit Grade No. UF Hourly Cost Cost
256 Plumber 1 1 59.59 59.59
171.74 DL 2 1 25.54 51.08
0.30

428.04Total ( 1:02 ) 110.67

B= Manpower Unit Cost 126.48 Birr/m2


Total of (1:02)
Hourly Output: _______________________
Direct Cost of Work Item = A+B+C = 564.81 Birr/m2
O Over head cost : 10%
Pr Profit Cost: 5%
Tot Total Unit Cost :

E RELATED TO TARGETED OUTPUT.

ALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS


LABOUR HOURLY OUTPUT:
EQUIPEMENT:
pcs RESULT:

Labour (1:02)
Cost per Labour by ** Indexed Hourly
Unit Grade No. UF Hourly Cost Cost
100 Plumber 1 1 59.59 59.59
DL 2 1 25.54 51.08

100.00Total ( 1:02 ) 110.67

B= Manpower Unit Cost 44.27 Birr/m2


Total of (1:02)
Hourly Output: _______________________
Direct Cost of Work Item = A+B+C = 147.87 Birr/m2
O Over head cost : 10%
Pr Profit Cost: 5%
Tot Total Unit Cost :
E RELATED TO TARGETED OUTPUT.

ALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS


LABOUR HOURLY OUTPUT:
EQUIPEMENT:
pcs RESULT:

Labour (1:02)
Cost per Labour by ** Indexed Hourly
Unit Grade No. UF Hourly Cost Cost
182 Plumber 1 1 59.59 59.59
171.74 DL 2 1 25.54 51.08
0.30

354.04Total ( 1:02 ) 110.67

B= Manpower Unit Cost 126.48 Birr/m2


Total of (1:02)
Hourly Output: _______________________
Direct Cost of Work Item = A+B+C = 490.81 Birr/m2
O Over head cost : 10%
Pr Profit Cost: 5%
Tot Total Unit Cost :

E RELATED TO TARGETED OUTPUT.

ALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS


LABOUR HOURLY OUTPUT:
EQUIPEMENT:
pcs RESULT:

Labour (1:02)
Cost per Labour by ** Indexed Hourly
Unit Grade No. UF Hourly Cost Cost
40 Plumber 1 1 59.59 59.59
121.73913 DL 2 1 25.54 51.08
121.73913

283.48Total ( 1:02 ) 110.67

B= Manpower Unit Cost 126.48 Birr/m2


Total of (1:02)
Hourly Output: _______________________
Direct Cost of Work Item = A+B+C = 420.25 Birr/m2
O Over head cost : 10%
Pr Profit Cost: 5%
Tot Total Unit Cost :

E RELATED TO TARGETED OUTPUT.

ALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS


LABOUR HOURLY OUTPUT:
EQUIPEMENT:
pcs RESULT:

Labour (1:02)
Cost per Labour by ** Indexed Hourly
Unit Grade No. UF Hourly Cost Cost
750 Plumber 1 1 59.59 59.59
2.17 DL 2 1 25.54 51.08
0.22

752.39Total ( 1:02 ) 110.67

B= Manpower Unit Cost 295.13 Birr/m2


Total of (1:02)
Hourly Output: _______________________
Direct Cost of Work Item = A+B+C = 1071.52 Birr/m2
O Over head cost : 10%
Pr Profit Cost: 5%
Tot Total Unit Cost :

E RELATED TO TARGETED OUTPUT.

ALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS


LABOUR HOURLY OUTPUT:
EQUIPEMENT:
pcs RESULT:

Labour (1:02)
Cost per Labour by ** Indexed Hourly
Unit Grade No. UF Hourly Cost Cost
6500 Plumber 1 1 59.59 59.59
60.8695652 DL 2 1 25.54 51.08
1.075

6561.94Total ( 1:02 ) 110.67


B= Manpower Unit Cost 221.35 Birr/m2
Total of (1:02)
Hourly Output: _______________________
Direct Cost of Work Item = A+B+C = 6801.29 Birr/m2
O Over head cost : 10%
Pr Profit Cost: 5%
Tot Total Unit Cost :

E RELATED TO TARGETED OUTPUT.

ALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS


LABOUR HOURLY OUTPUT:
EQUIPEMENT:
pcs RESULT:

Labour (1:02)
Cost per Labour by ** Indexed Hourly
Unit Grade No. UF Hourly Cost Cost
60 Plumber 1 1 59.59 59.59
DL 2 1 25.54 51.08

60.00Total ( 1:02 ) 110.67

B= Manpower Unit Cost 44.27 Birr/m2


Total of (1:02)
Hourly Output: _______________________
Direct Cost of Work Item = A+B+C = 107.87 Birr/m2
O Over head cost : 10%
Pr Profit Cost: 5%
Tot Total Unit Cost :

E RELATED TO TARGETED OUTPUT.

ALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS


LABOUR HOURLY OUTPUT:
EQUIPEMENT:
pcs RESULT:

Labour (1:02)
Cost per Labour by ** Indexed Hourly
Unit Grade No. UF Hourly Cost Cost
450 Plumber 1 1 59.59 59.59
0.22 DL 2 1 25.54 51.08

450.22Total ( 1:02 ) 110.67

B= Manpower Unit Cost 295.13 Birr/m2


Total of (1:02)
Hourly Output: _______________________
Direct Cost of Work Item = A+B+C = 769.34 Birr/m2
O Over head cost : 10%
Pr Profit Cost: 5%
Tot Total Unit Cost :

E RELATED TO TARGETED OUTPUT.


ALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS
LABOUR HOURLY OUTPUT:
EQUIPEMENT:
pcs RESULT:

Labour (1:02)
Cost per Labour by ** Indexed Hourly
Unit Grade No. UF Hourly Cost Cost
1500 Plumber 1 1 59.59 59.59
429.565217 DL 2 1 25.54 51.08
6869.56522
57.0652174

8856.20Total ( 1:02 ) 110.67

B= Manpower Unit Cost 442.69 Birr/m2


Total of (1:02)
Hourly Output: _______________________
Direct Cost of Work Item = A+B+C = 9334.89 Birr/m2
O Over head cost : 10%
Pr Profit Cost: 5%
Tot Total Unit Cost :

E RELATED TO TARGETED OUTPUT.

ALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS


LABOUR HOURLY OUTPUT:
EQUIPEMENT:
ml RESULT:

Labour (1:02)
Cost per Labour by ** Indexed Hourly
Unit Grade No. UF Hourly Cost Cost
3.208 Plumber 1 1 59.59 59.59
1.739 DL 2 1 25.54 51.08
3.478
10.870
5.435
0.543
8.50

33.77Total ( 1:02 ) 110.67

B= Manpower Unit Cost 22.13 Birr/m2


Total of (1:02)
Hourly Output: _______________________
Direct Cost of Work Item = A+B+C = 57.71 Birr/m2
O Over head cost : 10%
Pr Profit Cost: 5%
Tot Total Unit Cost :

E RELATED TO TARGETED OUTPUT.

ALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS


LABOUR HOURLY OUTPUT:
EQUIPEMENT:
ml RESULT:

Labour (1:02)
Cost per Labour by ** Indexed Hourly
Unit Grade No. UF Hourly Cost Cost
4.819 Plumber 1 1 59.59 59.59
2.783 DL 2 1 25.54 51.08
5.565
17.391
2.783
8.696
0.870
8.50
51.41Total ( 1:02 ) 110.67

B= Manpower Unit Cost 22.13 Birr/m2


Total of (1:02)
Hourly Output: _______________________
Direct Cost of Work Item = A+B+C = 75.34 Birr/m2
O Over head cost : 10%
Pr Profit Cost: 5%
Tot Total Unit Cost :

E RELATED TO TARGETED OUTPUT.


ALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS
LABOUR HOURLY OUTPUT:
EQUIPEMENT:
ml RESULT:

Labour (1:02)
Cost per Labour by ** Indexed Hourly
Unit Grade No. UF Hourly Cost Cost
6.087 Plumber 1 1 59.59 59.59
4.174 DL 2 1 25.54 51.08
8.348
26.087
4.174
13.043
1.304
8.50
71.72Total ( 1:02 ) 110.67

B= Manpower Unit Cost 22.13 Birr/m2


Total of (1:02)
Hourly Output: _______________________
Direct Cost of Work Item = A+B+C = 95.65 Birr/m2
O Over head cost : 10%
Pr Profit Cost: 5%
Tot Total Unit Cost :

E RELATED TO TARGETED OUTPUT.

ALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS


LABOUR HOURLY OUTPUT:
EQUIPEMENT:
pcs RESULT:

Labour (1:02)
Cost per Labour by ** Indexed Hourly
Unit Grade No. UF Hourly Cost Cost
40.425 Plumber 1 1 59.59 59.59
8.50 DL 2 1 25.54 51.08

48.93Total ( 1:02 ) 110.67

B= Manpower Unit Cost 12.65 Birr/m2


Total of (1:02)
Hourly Output: _______________________
Direct Cost of Work Item = A+B+C = 62.60 Birr/m2
O Over head cost : 10%
Pr Profit Cost: 5%
Tot Total Unit Cost :

E RELATED TO TARGETED OUTPUT.

ALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS


LABOUR HOURLY OUTPUT:
EQUIPEMENT:
ml RESULT:

Labour (1:02)
Cost per Labour by ** Indexed Hourly
Unit Grade No. UF Hourly Cost Cost
26.460 Plumber 1 1 59.59 59.59
5.719 DL 2 1 25.54 51.08
5.300
10.600

48.08Total ( 1:02 ) 110.67

B= Manpower Unit Cost 22.13 Birr/m2


Total of (1:02)
Hourly Output: _______________________
Direct Cost of Work Item = A+B+C = 72.01 Birr/m2
O Over head cost : 10%
Pr Profit Cost: 5%
Tot Total Unit Cost :

E RELATED TO TARGETED OUTPUT.

ALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS


LABOUR HOURLY OUTPUT:
EQUIPEMENT:
pcs RESULT:

Labour (1:02)
Cost per Labour by ** Indexed Hourly
Unit Grade No. UF Hourly Cost Cost
136.16 Mason 1 1 25.00 25.00
1269.70 D/L 2 1 13.33 26.66
103.69
268.67
125.80
0.00
1904.02 Total ( 1:02 ) 51.66

B= Manpower Unit Cost 206.64 Birr/m2


Total of (1:02)
Hourly Output: _______________________
Direct Cost of Work Item = A+B+C = 2110.66 Birr/m2
O Over head cost : 10%
Pr Profit Cost: 5%
Tot Total Unit Cost :

E RELATED TO TARGETED OUTPUT.


ALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS
LABOUR HOURLY OUTPUT:
EQUIPEMENT:
ml RESULT:

Labour (1:02)
Cost per Labour by ** Indexed Hourly
Unit Grade No. UF Hourly Cost Cost
210.000 Foreman 1 0.25 46.44 11.61
5.056 Mason 1 1 59.59 59.59
7.609 D/L 2 1 25.54 51.08
1.598
0.005

224.27Total ( 1:02 ) 122.28

B= Manpower Unit Cost 32.61 Birr/m2


Total of (1:02)
Hourly Output: _______________________
Direct Cost of Work Item = A+B+C = 259.28 Birr/m2
O Over head cost : 10%
Pr Profit Cost: 5%
Tot Total Unit Cost :

E RELATED TO TARGETED OUTPUT.

ALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS


LABOUR HOURLY OUTPUT:
EQUIPEMENT:
ml RESULT:

Labour (1:02)
Cost per Labour by ** Indexed Hourly
Unit Grade No. UF Hourly Cost Cost
14.933 Plumber 1 1 59.59 59.59
8.536 DL 2 1 25.54 51.08
11.200
43.000
6.880
16.000
1.08
101.62Total ( 1:02 ) 110.67

B= Manpower Unit Cost 7.38 Birr/m2


Total of (1:02)
Hourly Output: _______________________
Direct Cost of Work Item = A+B+C = 109.60 Birr/m2
O Over head cost : 10%
Pr Profit Cost: 5%
Tot Total Unit Cost :

E RELATED TO TARGETED OUTPUT.

ALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS


LABOUR HOURLY OUTPUT:
EQUIPEMENT:
ml RESULT:

Labour (1:02)
Cost per Labour by ** Indexed Hourly
Unit Grade No. UF Hourly Cost Cost
232.000 Plumber 1 1 59.59 59.59
DL 2 1 25.54 51.08
232.00Total ( 1:02 ) 110.67

B= Manpower Unit Cost 35.42 Birr/m2


Total of (1:02)
Hourly Output: _______________________
Direct Cost of Work Item = A+B+C = 270.30 Birr/m2
O Over head cost : 10%
Pr Profit Cost: 5%
Tot Total Unit Cost :

E RELATED TO TARGETED OUTPUT.


Y OUTPUT: 0.625 m3 / hr.
Mixer & Vibrator
3605.05 Birr/m3

Equipment Cost (1:03)


Type of Hourly Hourly
Equipment No. Rental Cost
Mixer 1 85 85
Tools 3 1.6 4.8
Vibrator 1 40 40

Total (1:03) 129.8

C= Equipment Unit 207.68 Br./m3


Total of (1:03)
Hourly output:

313.48 Birr/m3
156.74 Birr/m3
3605.05 Birr/m3
Y OUTPUT: 0.875 m3 / hr.
Mixer & Vibrator
3192.36 Birr/m3

Equipment Cost (1:03)


Type of Hourly Hourly
Equipment No. Rental Cost
Mixer 1 85 85
Tools 3 1.6 4.8
Vibrator 1 40 40

Total (1:03) 129.8

C= Equipment Unit 148.34 Br./m3


Total of (1:03)
Hourly output:

277.60 Birr/m3
138.80 Birr/m3
3192.36 Birr/m3

Y OUTPUT: 0.625 m2/hr.

550.50 Birr/m2

Equipment Cost (1:03)


Type of Hourly Hourly
Equipment No. Rental Cost
Tools 3 2 6.00

Total (1:03) 6.00

C=Equipment Unit Cost 9.6 Birr/m2


Total of (1:03)
Hourly output: _________________

47.87 Birr/m2
23.93 Birr/m2
550.50 Birr/m2

Y OUTPUT: 0.75 m2/hr.

513.77 Birr/m2

Equipment Cost (1:03)


Type of Hourly Hourly
Equipment No. Rental Cost
Tools 3 2 6.00
Total (1:03) 6.00

C=Equipment Unit Cost 8 Birr/m2


Total of (1:03)
Hourly output: _________________

44.68 Birr/m2
22.34 Birr/m2
513.77 Birr/m2

Y OUTPUT: 37.5 kg/hr.

52.57 Birr/kg.

Equipment Cost (1:03)


Type of Hourly Hourly
Equipment No. Rental Cost
tools 4 1.9 7.60
Total (1:03) 7.60

Equipment Unit Cos 0.20 Birr/kg.


Total of (1:03)
Hourly output: ____________

4.57 Birr/kg.
2.29 Birr/kg.
52.57 Birr/kg.

Y OUTPUT: 38.75 kg/hr.

51.65 Birr/kg.

Equipment Cost (1:03)


Type of Hourly Hourly
Equipment No. Rental Cost
tools 4 1.9 7.60
Total (1:03) 7.60

Equipment Unit Cos 0.20 Birr/kg.


Total of (1:03)
Hourly output: ____________

4.49 Birr/kg.
2.25 Birr/kg.
51.65 Birr/kg.

Y OUTPUT: 43.75 kg/hr.

51.29 Birr/kg.

Equipment Cost (1:03)


Type of Hourly Hourly
Equipment No. Rental Cost
tools 4 1.9 7.60

Total (1:03) 7.60

Equipment Unit Cos 0.17 Birr/kg.


Total of (1:03)
Hourly output: ____________
4.46 Birr/kg.
2.23 Birr/kg.
51.29 Birr/kg.

Y OUTPUT: 45 kg/hr.

52.27 Birr/kg.

Equipment Cost (1:03)


Type of Hourly Hourly
Equipment No. Rental Cost
tools 4 1.9 7.60

Total (1:03) 7.60

Equipment Unit Cos 0.17 Birr/kg.


Total of (1:03)
Hourly output: ____________

4.54 Birr/kg.
2.27 Birr/kg.
52.27 Birr/kg.
Y OUTPUT: 1.25 m2/hr.
0.0924

301.51 Birr/m2
13.86
Equipment Cost (1:03)
Type of Hourly Hourly
Equipment No. Rental Cost
Tools 4 0.5 2

Total (1:03) 2.00

C=Equipment Unit C 1.6 Birr/m2


Total of (1:03)
Hourly output: __________________

26.22 Birr/m2
13.11 Birr/m2
301.51 Birr/m2
Y OUTPUT: 1.25 m2/hr.

221.60 Birr/m2

Equipment Cost (1:03)


Type of Hourly Hourly
Equipment No. Rental Cost
Tools 4 0.5 2

Total (1:03) 2.00

C=Equipment Unit C 1.6 Birr/m2


Total of (1:03)
Hourly output: __________________

19.27 Birr/m2
9.63 Birr/m2
221.60 Birr/m2

Y OUTPUT: 6.50 m2/hr.

292.96 Birr/m2

Equipment Cost (1:03)


Type of Hourly Hourly
Equipment No. Rental Cost
Tools 1 1 1

Total (1:03) 1.00

C=Equipment Unit C0.153846 Birr/m2


Total of (1:03)
Hourly output: __________________

25.48 Birr/m2
12.74 Birr/m2
292.96 Birr/m2

Y OUTPUT: 3.38 m2/hr.

395.98 Birr/m2

Equipment Cost (1:03)


Type of Hourly Hourly
Equipment No. Rental Cost
Tools 1 1 1
Total (1:03) 1.00

C=Equipment Unit C0.296296 Birr/m2


Total of (1:03)
Hourly output: __________________

34.43 Birr/m2
17.22 Birr/m2
395.98 Birr/m2

Y OUTPUT: 7.50 ml/hr.

149.82 Birr/m

Equipment Cost (1:03)


Type of Hourly Hourly
Equipment No. Rental Cost
Tools 1 1 1

Total (1:03) 1.00

C=Equipment Unit C0.133333 Birr/m2


Total of (1:03)
Hourly output: __________________
13.03 Birr/m2
6.51 Birr/m2
149.82 Birr/m2

Y OUTPUT: 8.75 ml/hr.

156.52 Birr/m

Equipment Cost (1:03)


Type of Hourly Hourly
Equipment No. Rental Cost
Tools 1 1 1

Total (1:03) 1.00

C=Equipment Unit C0.114286 Birr/m2


Total of (1:03)
Hourly output: __________________

13.61 Birr/m2
6.81 Birr/m2
156.52 Birr/m2
Y OUTPUT: 7.50 ml/hr.

417.44 Birr/ml

Equipment Cost (1:03)


Type of Hourly Hourly
Equipment No. Rental Cost
Tools 1 1 1

Total (1:03) 1.00

C=Equipment Unit C0.133333 Birr/m2


Total of (1:03)
Hourly output: __________________

36.30 Birr/m2
18.15 Birr/m2
417.44 Birr/m2
Y OUTPUT: 10.00 ml/hr.

57.45 Birr/m

Equipment Cost (1:03)


Type of Hourly Hourly
Equipment No. Rental Cost
Tools 2 1 2

Total (1:03) 2.00

C=Equipment Unit C 0.20 Birr/m2


Total of (1:03)
Hourly output: __________________

5.00 Birr/m2
2.50 Birr/m2
57.45 Birr/m2

Y OUTPUT: 7.50 ml/hr.

50.11 Birr/m

Equipment Cost (1:03)


Type of Hourly Hourly
Equipment No. Rental Cost
Tools 2 1 2
Total (1:03) 2.00

C=Equipment Unit C 0.27 Birr/m2


Total of (1:03)
Hourly output: __________________

4.36 Birr/m2
2.18 Birr/m2
50.11 Birr/m2

Y OUTPUT: 9.38 ml/hr.

52.68 Birr/ml

Equipment Cost (1:03)


Type of Hourly Hourly
Equipment No. Rental Cost
Tools 2 1 2

Total (1:03) 2.00


C=Equipment Unit C 0.21 Birr/m2
Total of (1:03)
Hourly output: __________________

4.58 Birr/m2
2.29 Birr/m2
52.68 Birr/m2

Y OUTPUT: 0.63 pc/hr.

5840.51 Birr/pc

Equipment Cost (1:03)


Type of Hourly Hourly
Equipment No. Rental Cost
Tools 2 1 2

Total (1:03) 2.00

C=Equipment Unit C 3.20 Birr/m2


Total of (1:03)
Hourly output: __________________

507.87 Birr/m2
253.94 Birr/m2
5840.51 Birr/m2

Y OUTPUT: 0.50 pc/hr.

12843.20 Birr/pc

Equipment Cost (1:03)


Type of Hourly Hourly
Equipment No. Rental Cost
Tools 2 1 2

Total (1:03) 2.00

C=Equipment Unit C 4.00 Birr/m2


Total of (1:03)
Hourly output: __________________

1116.80 Birr/m2
558.40 Birr/m2
12843.20 Birr/m2
Y OUTPUT: 1.275 m2/hr.

5075.25 Birr/m2

Equipment Cost (1:03)


Type of Hourly Hourly
Equipment No. Rental Cost
Tools 2 1 2

Total (1:03) 2.00

C=Equipment Unit C1.568627 Birr/m2


Total of (1:03)
Hourly output: __________________

441.33 Birr/m2
220.66 Birr/m2
5075.25 Birr/m2

Y OUTPUT: 50 kg/hr.

59.92 Birr/m2
Equipment Cost (1:03)
Type of Hourly Hourly
Equipment No. Rental Cost
tools 1 4 4.00

Total (1:03) 4.00

C=Equipment Unit C 0.08 Birr/m2


Total of (1:03)
Hourly output: __________________

5.93 Birr/m2
4.74 Birr/m2
59.92 Birr/m2

Y OUTPUT: 50 kg/hr.

54.66 Birr/m2

Equipment Cost (1:03)


Type of Hourly Hourly
Equipment No. Rental Cost
tools 1 4 4.00
Total (1:03) 4.00

C=Equipment Unit C 0.08 Birr/m2


Total of (1:03)
Hourly output: __________________

5.93 Birr/m2
4.74 Birr/m2
54.66 Birr/m2

Y OUTPUT: 1.42 m2/hr.

934.87 Birr/m2

Equipment Cost (1:03)


Type of Hourly Hourly
Equipment No. Rental Cost
Tools 2 1 2

Total (1:03) 2.00


C=Equipment Unit C1.408451 Birr/m2
Total of (1:03)
Hourly output: __________________

81.29 Birr/m2
40.65 Birr/m2
934.87 Birr/m2

Y OUTPUT: 1.4175 m2/hr.

935.11 Birr/m2

Equipment Cost (1:03)


Type of Hourly Hourly
Equipment No. Rental Cost
Tools 2 1 2

Total (1:03) 2.00

C=Equipment Unit C1.410935 Birr/m2


Total of (1:03)
Hourly output: __________________

81.31 Birr/m2
40.66 Birr/m2
935.11 Birr/m2
Y OUTPUT: 1.071 m2/hr.

978.82 Birr/m2

Equipment Cost (1:03)


Type of Hourly Hourly
Equipment No. Rental Cost
Tools 2 1 2

Total (1:03) 2.00

C=Equipment Unit C1.867414 Birr/m2


Total of (1:03)
Hourly output: __________________

85.12 Birr/m2
42.56 Birr/m2
978.82 Birr/m2

Y OUTPUT: 5.00 m2/hr.

84.07 Birr/m2

Equipment Cost (1:03)


Type of Hourly Hourly
Equipment No. Rental Cost
Tools 2 2.3 4.6
Total (1:03) 4.60

C=Equipment Unit C 0.92 Birr/m2


Total of (1:03)
Hourly output: __________________

7.31 Birr/m2
3.66 Birr/m2
84.07 Birr/m2

Y OUTPUT: 4.38 m2/hr.

88.62 Birr/m2

Equipment Cost (1:03)


Type of Hourly Hourly
Equipment No. Rental Cost
Tools 2 2.3 4.6
Total (1:03) 4.60

C=Equipment Unit C1.051429 Birr/m2


Total of (1:03)
Hourly output: __________________

7.71 Birr/m2
3.85 Birr/m2
88.62 Birr/m2

Y OUTPUT: 2.25 ml/hr.

72.04 Birr/ml

Equipment Cost (1:03)


Type of Hourly Hourly
Equipment No. Rental Cost
Tools 2 2.3 4.6

Total (1:03) 4.60

C=Equipment Unit C2.044444 Birr/m2


Total of (1:03)
Hourly output: __________________

6.26 Birr/m2
3.13 Birr/m2
72.04 Birr/m2

Y OUTPUT: 4.38 m2/hr.

80.31 Birr/m2

Equipment Cost (1:03)


Type of Hourly Hourly
Equipment No. Rental Cost
Tools 2 2.3 4.6

Total (1:03) 4.60

C=Equipment Unit C1.051429 Birr/m2


Total of (1:03)
Hourly output: __________________

6.98 Birr/m2
3.49 Birr/m2
80.31 Birr/m2
Y OUTPUT: 0.88 m2/hr.

591.32 Birr/m2

Equipment Cost (1:03)


Type of Hourly Hourly
Equipment No. Rental Cost
Tools 3 1 3

Total (1:03) 3.00

C=Equipment Unit C3.428571 Birr/m2


Total of (1:03)
Hourly output: __________________

51.42 Birr/m2
25.71 Birr/m2
591.32 Birr/m2

Y OUTPUT: 1.25 m2/hr.


1105.57 Birr/m2

Equipment Cost (1:03)


Type of Hourly Hourly
Equipment No. Rental Cost
Tools 3 1 3

Total (1:03) 3.00

C=Equipment Unit C 2.40 Birr/m2


Total of (1:03)
Hourly output: __________________

96.14 Birr/m2
48.07 Birr/m2
1105.57 Birr/m2

Y OUTPUT: 2.13 m2/hr.

678.05 Birr/m2

Equipment Cost (1:03)


Type of Hourly Hourly
Equipment No. Rental Cost
Total (1:03) 0.00

C=Equipment Unit C 0 Birr/m2


Total of (1:03)
Hourly output: __________________

58.96 Birr/m2
29.48 Birr/m2
678.05 Birr/m2

Y OUTPUT: 1.50 m2/hr.

1260.01 Birr/m2

Equipment Cost (1:03)


Type of Hourly Hourly
Equipment No. Rental Cost

Total (1:03) 0.00


C=Equipment Unit C 0 Birr/m2
Total of (1:03)
Hourly output: __________________

109.57 Birr/m2
54.78 Birr/m2
1260.01 Birr/m2

Y OUTPUT: 2.00 m/hr.

191.00 Birr/m

Equipment Cost (1:03)


Type of Hourly Hourly
Equipment No. Rental Cost
Tools 3 1 3

Total (1:03) 3.00

C=Equipment Unit C 1.5 Birr/m2


Total of (1:03)
Hourly output: __________________

16.61 Birr/m2
8.30 Birr/m2
191.00 Birr/m2

Y OUTPUT: 2.00 m/hr.

1.15 Birr/m

Equipment Cost (1:03)


Type of Hourly Hourly
Equipment No. Rental Cost
Tools 2 1 2

Total (1:03) 2.00

C=Equipment Unit C 1.00 Birr/m2


Total of (1:03)
Hourly output: __________________

0.10 Birr/m2
0.05 Birr/m2
1.15 Birr/m2
Y OUTPUT: 2.00 m/hr.

161.36 Birr/m

Equipment Cost (1:03)


Type of Hourly Hourly
Equipment No. Rental Cost
Tools 3 1 3

Total (1:03) 3.00

C=Equipment Unit C 1.5 Birr/m2


Total of (1:03)
Hourly output: __________________

14.03 Birr/m2
7.02 Birr/m2
161.36 Birr/m2

Y OUTPUT: 2.00 m/hr.

161.36 Birr/m
Equipment Cost (1:03)
Type of Hourly Hourly
Equipment No. Rental Cost
Tools 3 1 3

Total (1:03) 3.00

C=Equipment Unit C 1.5 Birr/m2


Total of (1:03)
Hourly output: __________________

14.03 Birr/m2
7.02 Birr/m2
161.36 Birr/m2

Y OUTPUT: 3.75 m2/hr.

45.42 Birr/m2

Equipment Cost (1:03)


Type of Hourly Hourly
Equipment No. Rental Cost
Total (1:03) 0.00

C=Equipment Unit Cost Birr/m2


Total of (1:03)
Hourly output: __________________

3.95 Birr/m2
1.97 Birr/m2
45.42 Birr/m2

Y OUTPUT: 3.13 m2/hr.

50.92 Birr/m2

Equipment Cost (1:03)


Type of Hourly Hourly
Equipment No. Rental Cost
Total (1:03) 0.00

C=Equipment Unit Cost Birr/m2


Total of (1:03)
Hourly output: __________________

4.43 Birr/m2
2.21 Birr/m2
50.92 Birr/m2

Y OUTPUT: 1.50 m2/hr.

355.85 Birr/m2

Equipment Cost (1:03)


Type of Hourly Hourly
Equipment No. Rental Cost

Total (1:03) 0.00

C=Equipment Unit C 0 Birr/m2


Total of (1:03)
Hourly output: __________________

30.94 Birr/m2
15.47 Birr/m2
355.85 Birr/m2
Y OUTPUT: 1.75 m2/hr.

485.88 Birr/m2

Equipment Cost (1:03)


Type of Hourly Hourly
Equipment No. Rental Cost
Tools 1 2 2

Total (1:03) 2.00

C=Equipment Unit C 1.14 Birr/m2


Total of (1:03)
Hourly output: __________________

42.25 Birr/m2
21.13 Birr/m2
485.88 Birr/m2
Y OUTPUT: 1.75 m2/hr.

588.76 Birr/m2

Equipment Cost (1:03)


Type of Hourly Hourly
Equipment No. Rental Cost
Tools 1 0.8 0.8

Total (1:03) 0.80

C=Equipment Unit C 0.46 Birr/m2


Total of (1:03)
Hourly output: __________________

51.20 Birr/m2
25.60 Birr/m2
588.76 Birr/m2
Y OUTPUT: 5 ml/hr.

135.24 Birr/ml

Equipment Cost (1:03)


Type of Hourly Hourly
Equipment No. Rental Cost
Tools 3 3 9

Total (1:03) 9.00

C=Equipment Unit C 1.80 Birr/m2


Total of (1:03)
Hourly output: __________________

11.76 Birr/m2
5.88 Birr/m2
135.24 Birr/m2

Y OUTPUT: 6.25 ml/hr.

54.75 Birr/ml
Equipment Cost (1:03)
Type of Hourly Hourly
Equipment No. Rental Cost
Tools 3 3 9

Total (1:03) 9.00

C=Equipment Unit C 1.44 Birr/m2


Total of (1:03)
Hourly output: __________________

4.76 Birr/m2
2.38 Birr/m2
54.75 Birr/m2

Y OUTPUT: 6.25 ml/hr.

99.12 Birr/ml

Equipment Cost (1:03)


Type of Hourly Hourly
Equipment No. Rental Cost
Tools 3 3 9
Total (1:03) 9.00

C=Equipment Unit C 1.44 Birr/m2


Total of (1:03)
Hourly output: __________________

8.62 Birr/m2
4.31 Birr/m2
99.12 Birr/m2

Y OUTPUT: 1.875 ml/pcs

339.14 Birr/ml

Equipment Cost (1:03)


Type of Hourly Hourly
Equipment No. Rental Cost
Tools 3 3 9
Total (1:03) 9.00

C=Equipment Unit C 4.80 Birr/m2


Total of (1:03)
Hourly output: __________________

29.49 Birr/m2
14.75 Birr/m2
339.14 Birr/m2

Y OUTPUT: 1.875 ml/pcs

323.47 Birr/ml

Equipment Cost (1:03)


Type of Hourly Hourly
Equipment No. Rental Cost
Tools 3 3 9

Total (1:03) 9.00

C=Equipment Unit C 4.80 Birr/m2


Total of (1:03)
Hourly output: __________________

28.13 Birr/m2
14.06 Birr/m2
323.47 Birr/m2

Y OUTPUT: 0.25 pcs/hr.

6174.38 Birr/pcs

Equipment Cost (1:03)


Type of Hourly Hourly
Equipment No. Rental Cost
Tools 3 3 9

Total (1:03) 9.00

C=Equipment Unit C 36 Birr/m2


Total of (1:03)
Hourly output: __________________

536.90 Birr/m2
268.45 Birr/m2
6174.38 Birr/m2
Y OUTPUT: 0.375 pcs/hr.

943.24 Birr/pcs

Equipment Cost (1:03)


Type of Hourly Hourly
Equipment No. Rental Cost
Tools 3 3 9

Total (1:03) 9.00

C=Equipment Unit C 24 Birr/m2


Total of (1:03)
Hourly output: __________________

82.02 Birr/m2
41.01 Birr/m2
943.24 Birr/m2

Y OUTPUT: 0.375 pcs/hr.

4589.64 Birr/pcs
Equipment Cost (1:03)
Type of Hourly Hourly
Equipment No. Rental Cost
Tools 3 3 9

Total (1:03) 9.00

C=Equipment Unit C 24 Birr/m2


Total of (1:03)
Hourly output: __________________

399.10 Birr/m2
199.55 Birr/m2
4589.64 Birr/m2

Y OUTPUT: 0.375 pcs/hr.

2412.69 Birr/pcs

Equipment Cost (1:03)


Type of Hourly Hourly
Equipment No. Rental Cost
Tools 3 3 9
Total (1:03) 9.00

C=Equipment Unit C 24 Birr/m2


Total of (1:03)
Hourly output: __________________

209.80 Birr/m2
104.90 Birr/m2
2412.69 Birr/m2

Y OUTPUT: 0.875 pcs/hr.

649.54 Birr/pcs

Equipment Cost (1:03)


Type of Hourly Hourly
Equipment No. Rental Cost
Tools 3 3 9

Total (1:03) 9.00

C=Equipment Unit C10.28571 Birr/m2


Total of (1:03)
Hourly output: __________________

56.48 Birr/m2
28.24 Birr/m2
649.54 Birr/m2

Y OUTPUT: 2.5 pcs/hr.

170.05 Birr/pcs

Equipment Cost (1:03)


Type of Hourly Hourly
Equipment No. Rental Cost
Tools 3 3 9

Total (1:03) 9.00

C=Equipment Unit C 3.6 Birr/m2


Total of (1:03)
Hourly output: __________________

14.79 Birr/m2
7.39 Birr/m2
170.05 Birr/m2
Y OUTPUT: 0.875 pcs/hr.

564.44 Birr/pcs

Equipment Cost (1:03)


Type of Hourly Hourly
Equipment No. Rental Cost
Tools 3 3 9

Total (1:03) 9.00

C=Equipment Unit C10.28571 Birr/m2


Total of (1:03)
Hourly output: __________________

49.08 Birr/m2
24.54 Birr/m2
564.44 Birr/m2

Y OUTPUT: 0.875 pcs/hr.


483.29 Birr/pcs

Equipment Cost (1:03)


Type of Hourly Hourly
Equipment No. Rental Cost
Tools 3 3 9

Total (1:03) 9.00

C=Equipment Unit C10.28571 Birr/m2


Total of (1:03)
Hourly output: __________________

42.02 Birr/m2
21.01 Birr/m2
483.29 Birr/m2

Y OUTPUT: 0.375 pcs/hr.

1232.25 Birr/pcs

Equipment Cost (1:03)


Type of Hourly Hourly
Equipment No. Rental Cost
Tools 3 3 9

Total (1:03) 9.00

C=Equipment Unit C 24 Birr/m2


Total of (1:03)
Hourly output: __________________

107.15 Birr/m2
53.58 Birr/m2
1232.25 Birr/m2

Y OUTPUT: 0.5 pcs/hr.

7821.49 Birr/pcs

Equipment Cost (1:03)


Type of Hourly Hourly
Equipment No. Rental Cost
Tools 3 3 9

Total (1:03) 9.00


C=Equipment Unit C 18 Birr/m2
Total of (1:03)
Hourly output: __________________

680.13 Birr/m2
340.06 Birr/m2
7821.49 Birr/m2

Y OUTPUT: 2.5 pcs/hr.

124.05 Birr/pcs

Equipment Cost (1:03)


Type of Hourly Hourly
Equipment No. Rental Cost
Tools 3 3 9

Total (1:03) 9.00

C=Equipment Unit C 3.6 Birr/m2


Total of (1:03)
Hourly output: __________________

10.79 Birr/m2
5.39 Birr/m2
124.05 Birr/m2

Y OUTPUT: 0.375 pcs/hr.

884.75 Birr/pcs

Equipment Cost (1:03)


Type of Hourly Hourly
Equipment No. Rental Cost
Tools 3 3 9

Total (1:03) 9.00

C=Equipment Unit C 24 Birr/m2


Total of (1:03)
Hourly output: __________________

76.93 Birr/m2
38.47 Birr/m2
884.75 Birr/m2
Y OUTPUT: 0.25 pcs/hr.

10735.12 Birr/pcs

Equipment Cost (1:03)


Type of Hourly Hourly
Equipment No. Rental Cost
Tools 3 3 9

Total (1:03) 9.00

C=Equipment Unit C 36 Birr/m2


Total of (1:03)
Hourly output: __________________

933.49 Birr/m2
466.74 Birr/m2
10735.12 Birr/m2

Y OUTPUT: 5 ml/hr.

66.36 Birr/ml

Equipment Cost (1:03)


Type of Hourly Hourly
Equipment No. Rental Cost
Tools 3 3 9

Total (1:03) 9.00

C=Equipment Unit C 1.8 Birr/m2


Total of (1:03)
Hourly output: __________________

5.77 Birr/m2
2.89 Birr/m2
66.36 Birr/m2

Y OUTPUT: 5 ml/hr.

86.64 Birr/ml

Equipment Cost (1:03)


Type of Hourly Hourly
Equipment No. Rental Cost
Tools 3 3 9
Total (1:03) 9.00

C=Equipment Unit C 1.8 Birr/m2


Total of (1:03)
Hourly output: __________________

7.53 Birr/m2
3.77 Birr/m2
86.64 Birr/m2

Y OUTPUT: 5 ml/hr.

110.00 Birr/ml

Equipment Cost (1:03)


Type of Hourly Hourly
Equipment No. Rental Cost
Tools 3 3 9
Total (1:03) 9.00

C=Equipment Unit C 1.8 Birr/m2


Total of (1:03)
Hourly output: __________________

9.57 Birr/m2
4.78 Birr/m2
110.00 Birr/m2

Y OUTPUT: 8.75 ml/hr.

71.99 Birr/ml

Equipment Cost (1:03)


Type of Hourly Hourly
Equipment No. Rental Cost
Tools 3 3 9

Total (1:03) 9.00

C=Equipment Unit C1.028571 Birr/m2


Total of (1:03)
Hourly output: __________________
6.26 Birr/m2
3.13 Birr/m2
71.99 Birr/m2

Y OUTPUT: 5 ml/hr.

82.82 Birr/ml

Equipment Cost (1:03)


Type of Hourly Hourly
Equipment No. Rental Cost
Tools 3 3 9

Total (1:03) 9.00

C=Equipment Unit C 1.8 Birr/m2


Total of (1:03)
Hourly output: __________________

7.20 Birr/m2
3.60 Birr/m2
82.82 Birr/m2

Y OUTPUT: 0.25 m2/hr.

2427.26 Birr/m2

Equipment Cost (1:03)


Type of Hourly Hourly
Equipment No. Rental Cost

Total (1:03) 0.00

C=Equipment Unit C 0 Birr/m2


Total of (1:03)
Hourly output: __________________

211.07 Birr/m2
105.53 Birr/m2
2427.26 Birr/m2
Y OUTPUT: 3.75 ml/hr.

298.17 Birr/ml

Equipment Cost (1:03)


Type of Hourly Hourly
Equipment No. Rental Cost
Tools 3 3 9

Total (1:03) 9.00

C=Equipment Unit C 2.4 Birr/m2


Total of (1:03)
Hourly output: __________________

25.93 Birr/m2
12.96 Birr/m2
298.17 Birr/m2

Y OUTPUT: 15 ml/hr.

126.04 Birr/ml

Equipment Cost (1:03)


Type of Hourly Hourly
Equipment No. Rental Cost
Tools 3 3 9

Total (1:03) 9.00

C=Equipment Unit C 0.6 Birr/m2


Total of (1:03)
Hourly output: __________________

10.96 Birr/m2
5.48 Birr/m2
126.04 Birr/m2

Y OUTPUT: 3.125 ml/hr.

310.84 Birr/ml

Equipment Cost (1:03)


Type of Hourly Hourly
Equipment No. Rental Cost
Tools 3 3 9
Total (1:03) 9.00

C=Equipment Unit C 2.88 Birr/m2


Total of (1:03)
Hourly output: __________________

27.03 Birr/m2
13.51 Birr/m2
310.84 Birr/m2
A. SUB-STRUCTURE

1. EARTH WORK
ANALYSIS SHEET FOR DIRECT & INDI
PROJECT: EXCAVATION AND EARTH WORK.
WORK ITEM: ( 1.1 ) 20 cm. Clearing on loose & dry soil.
TOTAL QANTITY OF WORK ITEM: 1 m2

Material Cost (1:01) Labour Co

Cost per
Type of Material Unit Qty * Rate Unit Labour by Grade
Diesel lts 0.1 16.3 1.63 Forman
Loader Operator
Daily labourer

Total (1:-01) 1.63 Total (1:02

A= Materials Unit Cos 1.63 Birr/m2 B= Manpower Unit Cost


Total of (1:01) Total of (1:02)
total quantity Hourly Output:
Direct Cost of Work Item = A+B+C =

Remark __________________________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED O
ANALYSIS SHEET FOR DIRECT & I
PROJECT: EXCAVATION AND EARTH WORK.
WORK ITEM: ( 1.2 ) Bulk excav. to a depth not exceeding 150cm loose and dry soil.
TOTAL QANTITY OF WORK ITEM: 1 m3

Material Cost (1:01) Labour Co

Cost per
Type of Material Unit Qty * Rate Unit Labour by Grade
Diesel lts 1 16.3 16.3 Forman
Loader operator
Daily Labourer

Total (1:-01) 16.3 Total (1:02

A= Materials Unit Cos 16.3 Birr/m3 B= Manpower Unit Cost


Total of (1:01) Total of (1:02)
total quantity Hourly Output:
Direct Cost of Work Item = A+B+C =

Remark __________________________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED O

ANALYSIS SHEET FOR DIRECT & I


PROJECT: EXCAVATION AND EARTH WORK.
WORK ITEM: ( 1.4) Trench excavation not exceeding 150cm. in loose and dry soil.
TOTAL QANTITY OF WORK ITEM: 1 m3

Material Cost (1:01) Labour Co

Cost per
Type of Material Unit Qty * Rate Unit Labour by Grade
forman
Daily labourer

Total (1:-01) Total (1:02

A= Materials Unit Cos 0 Birr/m3 B= Manpower Unit Cost


Total of (1:01) Total of (1:02)
total quantity Hourly Output:
Direct Cost of Work Item = A+B+C =

Remark __________________________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED O

ANALYSIS SHEET FOR DIRECT & I


PROJECT: EXCAVATION AND EARTH WORK.
WORK ITEM: ( 1.3) Excavation foundation pits to adepth of 150cm. In loose soil.
TOTAL QANTITY OF WORK ITEM: 1 m3

Material Cost (1:01) Labour Co

Cost per
Type of Material Unit Qty * Rate Unit Labour by Grade
forman
Daily labourer

Total (1:-01) Total (1:02

A= Materials Unit Cos 0 Birr/m3 B= Manpower Unit Cost


Total of (1:01) Total of (1:02)
total quantity Hourly Output:
Direct Cost of Work Item = A+B+C =
Remark __________________________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED O

ANALYSIS SHEET FOR DIRECT & I


ROJECT: EXCAVATION AND EARTH WORK.
WORK ITEM: ( 1.5) Back fill excavated materials from the site.
TOTAL QANTITY OF WORK ITEM: 1 m3

Material Cost (1:01) Labour Co

Cost per
Type of Material Unit Qty * Rate Unit Labour by Grade
Borrowed material m3 1.2 152.17 182.61 foreman
Diesel lts 0.08 16.3 1.304 DL

Total (1:-01) 183.91 Total (1:02

A= Materials Unit Cos 183.9127 Birr/m3 B= Manpower Unit Cost


Total of (1:01) Total of (1:02)
total quantity Hourly Output:
Direct Cost of Work Item = A+B+C =
Remark __________________________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED O

ANALYSIS SHEET FOR DIRECT & I


PROJECT: EXCAVATION AND EARTH WORK.
WORK ITEM: ( 1.6) Cart away surplus excavated soil 1km. from the site.
TOTAL QANTITY OF WORK ITEM: 1 m3

Material Cost (1:01) Labour Co

Cost per
Type of Material Unit Qty * Rate Unit Labour by Grade
Diesel lts 1 16.3 16.3 Loader Op.
DT driver
ass driver
DL

Total (1:-01) 16.3 Total (1:02

A= Materials Unit Cos 16.3 Birr/m3 B= Manpower Unit Cost


Total of (1:01) Total of (1:02)
total quantity Hourly Output:
Direct Cost of Work Item = A+B+C =

Remark __________________________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED O

ANALYSIS SHEET FOR DIRECT & INDI


PROJECT: EXCAVATION AND EARTH WORK.
WORK ITEM: ( 3.2) 25cm. thick basaltic hard core.
TOTAL QANTITY OF WORK ITEM: 1 m2

Material Cost (1:01) Labour Co

Cost per
Type of Material Unit Qty * Rate Unit Labour by Grade
Basaltic stone m3 0.28 304.35 85.22 foreman
mason
DL

Total (1:-01) 85.22 Total (1:02

A= Materials Unit Cos 21.30435 Birr/m2 B= Manpower Unit Cost


Total of (1:01) Total of (1:02)
total quantity Hourly Output:
Direct Cost of Work Item = A+B+C =

Remark __________________________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED O

3. MASONRY WORK
ANALYSIS SHEET FOR DIRECT &
PROJECT: MASONRY WORKS
WORK ITEM : ( 3.1 ) 50cm. thick masonry foundation beded in 1:4 (B.G.L).
TOTAL QANTITY OF WORK ITEM: 1 m3

Material Cost (1:01) Labour Co

Cost per
Type of Material Unit Qty * Rate Unit Labour by Grade
Stone m3 1 334.45 334.4482 Foreman
Cement Qt 1.5 343.48 515.2174 Mason
Sand m3 0.42 190.22 79.8913 ass mason
water lts 25 2.00 50.00 D/L
Total (1:-01) 979.5569 Total (1:02

A= Material unit cos 979.5569 Birr/m3 B=Manpower Unit Cost


Total of (1:01) Total of (1:02)
total quantity Hourly Output
Direct Cost of work item = A + B + C =
Overhead Cost :
Profit Cost:
Total Unit Cost :

Remark : _____________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED O

2. CONCRETE WORK
ANALYSIS SHEET FOR DIRECT &
PROJECT: CONCRETE WORK
WORK ITEM: ( 2.1 ) C-5 Lean Concrete (Hand mix) 1:5:7
TOTAL QUANTITY OF WORK ITEM: 1 m2 0.05

Material Cost (1:01) Labour Co

Cost per
Type of Material Unit Qty * Rate Unit Labour by Trade
Cement Qt 1.5 343.48 515.2174 Mason
Sand m3 0.5 190.22 95.1087 Daily Labourer
Aggregate m3 0.9 342.39 308.1522 forman
water lts 25 2.00 50.00 Mixer operator
desail lts 1 16.30 16.3

Total (1:-01) 984.78 Total (1:02

A= Materials Unit Cost 49.24 Br./m2 B=Manpower Unit Cost


Total of (1:01) Total of (1:02)
total quantity 21.41Br./m3 X 0.05m. Hourly Output
Direct Cost of work item= A+B+C=

Remark ________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED O

ANALYSIS SHEET FOR DIRECT &


PROJECT: CONCRETE WORK
WORK ITEM: ( 2.2.1C-25 Concrete fooing (Mechanical Mix) 1:2:3
TOTAL QUANTITY OF WORK ITEM: 1 m3

Material Cost (1:01) Labour Co

Cost per
Type of Material Unit Qty * Rate Unit Labour by Trade
Cement Qt 3.6 343.48 1236.52 Mason
Sand m3 0.52 190.22 98.91 DL
Aggregate m3 0.78 342.39 267.07 foreman
water lts 130 2.00 260.00 Mixer Op.
desail lts 1 16.30 16.30 Vibrator Op.
Total (1:-01) 1878.80 Total (1:02

A= Materials Unit Cos 1878.80 Birr/m3 B=Manpower Unit Cost


Total of (1:01) Total of (1:02)
total quantity Hourly Output
Direct Cost of work item = A+B+C =

Remark ________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED O

ANALYSIS SHEET FOR DIRECT &


PROJECT: CONCRETEfoundaion
WORK
column
WORK ITEM: ( 2.2. C-25 Concrete (Mechanical Mix) 1:2:3
TOTAL QUANTITY OF WORK ITEM: 1 m3

Material Cost (1:01) Labour Co

Cost per
Type of Material Unit Qty * Rate Unit Labour by Trade
Cement Qnt. 3.6 343.48 1236.52 Mason
Sand m3 0.52 190.22 98.91 DL
Gravel (02) m3 0.78 342.39 267.07 foreman
water lts 130 2.00 260.00 Mixer Op.
desail lts 1 16.30 16.30 Vibrator Op.

Total (1:-01) 1878.8 Total (1:02

A= Materials Unit Cos 1878.80 Birr/m3 B=Manpower Unit Cost


Total of (1:01) Total of (1:02)
total quantity Hourly Output
Direct Cost of work item = A+B+C =

Remark ________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED O

ANALYSIS SHEET FOR DIRECT &


PROJECT: CONCRETEgrade beam
WORK
WORK ITEM: ( 2.2.3C-25 Concrete (Mechanical Mix) 1:2:3
TOTAL QUANTITY OF WORK ITEM: 1 m3

Material Cost (1:01) Labour Co


Cost per
Type of Material Unit Qty * Rate Unit Labour by Trade
Cement Qnt. 3.6 343.48 1236.52 Mason
Sand m3 0.52 190.22 98.91 DL
Gravel (02) m3 0.78 342.39 267.07 foreman
water lts 130 2.00 260.00 Mixer Op.
desail lts 1 16.30 16.30 Vibrator Op.

Total (1:-01) 1878.80 Total (1:02

A= Materials Unit Cos 1878.80 Birr/m3 B=Manpower Unit Cost


Total of (1:01) Total of (1:02)
total quantity Hourly Output
Direct Cost of work item = A+B+C =

Remark ________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED O

ANALYSIS SHEET FOR DIRECT &


PROJECT: CONCRETEground floor
WORK slab
WORK ITEM: ( 2.2.4 C-20 Concrete (Mechanical Mix) 1:2:3
TOTAL QUANTITY OF WORK ITEM: 1 m3 0.1 m. thick

Material Cost (1:01) Labour Co

Cost per
Type of Material Unit Qty * Rate Unit Labour by Trade
Cement Qnt. 3.6 343.48 1236.52 Mason
Sand m3 0.52 190.22 98.91 DL
Gravel (02) m3 0.78 342.39 267.07 foreman
water lts 130 2.00 260.00 Mixer Op.
desail lts 1 16.30 16.30 Carpenter
Vibrator Op.

Total (1:-01) 1878.80 Total (1:02

A= Materials Unit Cos 187.88 Br./m2 B=Manpower Unit Cost


Total of (1:01) Total of (1:02)
total quantity Hourly Output
Direct Cost of work item = A+B+C =

Remark ________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED O

4. FORMWORK
ANALYSIS SHEET FOR DIRECT & INDI
PROJECT: FORM WORK
WORK ITEM: ( 4.1 ) Form Work. For pod
TOTAL QUANTITY OF WORK ITEM : 1 m2

Material Cost (1:01) Labour Co

Cost per
Type of Material Unit Qty * Rate Unit Labour by Grade
zigba panel m2 0.925 260.87 241.30 Foreman
Eucalyptus ml 2.1 8.70 18.26 Carpenter
Nails Kg 0.3 69.57 20.87 DL
Mould Oil Lit. 0.015 7.00 0.11

Total (1:-01) 280.54 Total (1:02

A= Materials Unit Co 280.5398 Birr/m2 B= Manpower Unit Cost


Total of (1:01) Total of (1:02)
total quantity Hourly Output:
Direct Cost of Work Item = A+B+C =
Over head cost :
Profit Cost:
Total Unit Cost :
Remark __________________________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED O
ANALYSIS SHEET FOR DIRECT & INDI
PROJECT: FORM WORK
WORK ITEM: ( 4.2 ) Form Work. For footing column
TOTAL QUANTITY OF WORK ITEM : 1 m2

Material Cost (1:01) Labour Co

Cost per
Type of Material Unit Qty * Rate Unit Labour by Grade
zigba panel m2 0.925 260.87 241.30 Foreman
Eucalyptus ml 2.1 8.70 18.26 Carpenter
Nails Kg 0.3 69.57 20.87 DL
Mould Oil Lit. 0.015 7.00 0.11
Total (1:-01) 280.54 Total (1:02

A= Materials Unit Co 280.5398 Birr/m2 B= Manpower Unit Cost


Total of (1:01) Total of (1:02)
total quantity Hourly Output:
Direct Cost of Work Item = A+B+C =
Over head cost :
Profit Cost:
Total Unit Cost :
Remark __________________________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED O

ANALYSIS SHEET FOR DIRECT & INDI


PROJECT: FORM WORK
WORK ITEM: ( 4.3 ) Form Work. For grade beam
TOTAL QUANTITY OF WORK ITEM : 1 m2

Material Cost (1:01) Labour Co

Cost per
Type of Material Unit Qty * Rate Unit Labour by Grade
zigba panel m2 0.95 260.87 247.83 Foreman
Eucalyptus ml 2.1 8.70 18.26 Carpenter
Nails Kg 0.3 69.57 20.87 DL
Mould Oil Lit. 0.015 7.00 0.11
Total (1:-01) 287.06 Total (1:02

A= Materials Unit Co 287.0615 Birr/m2 B= Manpower Unit Cost


Total of (1:01) Total of (1:02)
total quantity Hourly Output:
Direct Cost of Work Item = A+B+C =
Over head cost :
Profit Cost:
Total Unit Cost :
Remark __________________________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED O

19. BAR SCHEDULE

ANALYSIS SHEET FOR DIRECT & INDI


PROJECT : REINFORCEMENT BARS
WORK ITEM: ( 19.1 dia. 6 mm. deformed bars
TOTAL QANTITY OF WORK ITEM: 1 kg.

Material Cost (1:01) Labour

Cost per
Type of Material Unit Qty * Rate Unit Labour by Grade
6 mm deformed bars kg 1.05 47.83 50.21739 Foreman
1.2 mm black anneald kg 0.02 56.52 1.130435 Barbender
D/L
Total (1:-01) 51.35 Total (1:02)

A= Materials Unit Cost 51.35 birr/kg B= Manpower Unit Cost


Total of (1:02)
hourly output:
Direct Cost of Work Item = A+B+C =

ANALYSIS SHEET FOR DIRECT & INDI


PROJECT : REINFORCEMENT BARS
WORK ITEM: ( 19.1 dia. 8 mm. deformed bars
TOTAL QANTITY OF WORK ITEM: 1 kg.

Material Cost (1:01) Labour

Cost per
Type of Material Unit Qty * Rate Unit Labour by Grade
8 mm deformed bars kg 1.05 39.81 41.79913 Foreman
1.2 mm black anneald kg 0.02 56.52 1.130435 Barbender
D/L
Total (1:-01) 42.93 Total (1:02)

A= Materials Unit Cost 42.93 birr/kg B= Manpower Unit Cost


Total of (1:02)
hourly output:
Direct Cost of Work Item = A+B+C =

Remark __________________________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED O

ANALYSIS SHEET FOR DIRECT & INDI


PROJECT : REINFORCEMENT BARS
WORK ITEM: ( 19.1 dia. 10 mm. deformed bars
TOTAL QANTITY OF WORK ITEM: 1 kg.

Material Cost (1:01) Labour

Cost per
Type of Material Unit Qty * Rate Unit Labour by Grade
10 mm deformed bar kg 1.05 39.13 41.08696 Foreman
1.2 mm black anneald kg 0.02 56.52 1.130435 Barbender
D/L
Total (1:-01) 42.22 Total (1:02)

A= Materials Unit Cost 42.22 birr/kg B= Manpower Unit Cost


Total of (1:02)
hourly output:
Direct Cost of Work Item = A+B+C =
Remark __________________________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED O

ANALYSIS SHEET FOR DIRECT & INDI


PROJECT : REINFORCEMENT BARS
WORK ITEM: ( 19.1 dia. 12mm. deformed bars
TOTAL QANTITY OF WORK ITEM: 1 kg.

Material Cost (1:01) Labour

Cost per
Type of Material Unit Qty * Rate Unit Labour by Grade
12 mm deformed bars kg 1.05 39.13 41.08696 Foreman
1.2 mm black anneald kg 0.02 56.52 1.130435 Barbender
D/L

Total (1:-01) 42.22 Total (1:02)

A= Materials Unit Cost 42.22 birr/kg B= Manpower Unit Cost


Total of (1:02)
hourly output:
Direct Cost of Work Item = A+B+C =

Remark __________________________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED O

ANALYSIS SHEET FOR DIRECT & INDI


PROJECT : REINFORCEMENT BARS
WORK ITEM: ( 19.1 dia. 14 mm. deformed bars
TOTAL QANTITY OF WORK ITEM: 1 kg.

Material Cost (1:01) Labour

Cost per
Type of Material Unit Qty * Rate Unit Labour by Grade
14 mm deformed bars kg 1.05 40.00 42 Foreman
1.2 mm black anneald kg 0.02 56.52 1.130435 Barbender
D/L

Total (1:-01) 43.13 Total (1:02)

A= Materials Unit Cost 43.13 birr/kg B= Manpower Unit Cost


Total of (1:02)
hourly output:
Direct Cost of Work Item = A+B+C =

Remark __________________________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED O
A. SUB-STRUCTURE

1. EARTH WORK
OR DIRECT & INDIRECT UNIT COSTS
LABOUR HOURLY OUTPUT: 145 m2/hr.
EQUIPEMENT: Loader tools
RESULT: 9.63 Birr/m2

Labour Cost (1:02) Equipment Cost (1:03)

** Indexed Hourly Type of Hourly Hourly


No. UF Hourly Cost Cost Equipment No. Rental Cost
1 1 46.44 46.44 Loader 1 800 800
1 1 77.39 77.39 tools 2 1.6 3.2
2 1 25.54 51.08

Total (1:02) 174.91 Total (1:03) 803.20

1.206281 Birr/m2 C= Equipment Unit Cost 5.54 Birr/m2


Total of (1:03)
Hourly output: ______________
em = A+B+C = 8.38 Birr/m2
Over head cost : 10% 0.84 Birr/m3
Profit Cost: 5% 0.42 Birr/m3
Total Unit Cost : 9.63 Birr/m2

_____________________
LATED TO TARGETED OUTPUT.
ET FOR DIRECT & INDIRECT UNIT COSTS
LABOUR HOURLY OUTPUT: 25.00 m3/hr.
EQUIPEMENT: Tool
RESULT: 61.50 Birr/m3

Labour Cost (1:02) Equipment Cost (1:03)

** Indexed Hourly Type of Hourly Hourly


No. UF Hourly Cost Cost Equipment No. Rental Cost
1 0.5 46.44 23.22 Loader 1 800 800
1 1 77.39 77.39 Tools 2 1.6 3.2
1 1 25.54 25.54

Total (1:02) 126.15 Total (1:03) 803.2

5.046096 Birr/m3 C= Equipment Unit Cost 32.13 Birr/m3


Total of (1:03)
Hourly output: _______________
em = A+B+C = 53.47 Birr/m2
Over head cost : 10% 5.35 Birr/m3
Profit Cost: 5% 2.67 Birr/m3
Total Unit Cost : 61.50 Birr/m3

_____________________
LATED TO TARGETED OUTPUT.

ET FOR DIRECT & INDIRECT UNIT COSTS


LABOUR HOURLY OUTPUT: 0.25 m3/hr.
EQUIPEMENT: Tool
RESULT: 167.11 Birr/m3

Labour Cost (1:02) Equipment Cost (1:03)

** Indexed Hourly Type of Hourly Hourly


No. UF Hourly Cost Cost Equipment No. Rental Cost
1 0.2 46.44 9.29 Tools 1 1.5 1.5
1 1 25.54 25.54

Total (1:02) 34.83 Total (1:03) 1.5

139.3094 Birr/m3 C= Equipment Unit Cost 6.00 Birr/m3


Total of (1:03)
Hourly output: ______________
em = A+B+C = 145.31 Birr/m3
Over head cost : 10% 14.53 Birr/m3
Profit Cost: 5% 7.27 Birr/m3
Total Unit Cost : 167.11 Birr/m3

_____________________
LATED TO TARGETED OUTPUT.

ET FOR DIRECT & INDIRECT UNIT COSTS


LABOUR HOURLY O 0.38 m3/hr.
EQUIPEMENT: Tool
RESULT: 180.09 Birr/m3

Labour Cost (1:02) Equipment Cost (1:03)

** Indexed Hourly Type of Hourly Hourly


No. UF Hourly Cost Cost Equipment No. Rental Cost
1 0.1 46.44 4.64 Tools 3 1 3
2 1 25.54 51.08

Total (1:02) 55.72 Total (1:03) 3

148.5967 Birr/m3 C= Equipment Unit Cost 8.00 Birr/m3


Total of (1:03)
Hourly output: _____________
em = A+B+C = 156.60 Birr/m3
Over head cost : 10% 15.66 Birr/m3
Profit Cost: 5% 7.83 Birr/m3
Total Unit Cost : 180.09 Birr/m3
_____________________

LATED TO TARGETED OUTPUT.

ET FOR DIRECT & INDIRECT UNIT COSTS


LABOUR HOURLY OUTPUT: 11.25 m3/hr.
EQUIPEMENT: Tool
RESULT: 298.99 Birr/m3

Labour Cost (1:02) Equipment Cost (1:03)

** Indexed Hourly Type of Hourly Hourly


No. UF Hourly Cost Cost Equipment No. Rental Cost
1 1 46.44 46.44 compactor 1 40 40
30 1 25.54 766.20 Tools 2 1.6 3.2

Total (1:02) 812.64 Total (1:03) 43.2

72.2345 Birr/m3 C= Equipment Unit Cost 3.84 Birr/m3


Total of (1:03)
Hourly output: ______________
em = A+B+C = 259.99 Birr/m3
Over head cost : 10% 26.00 Birr/m3
Profit Cost: 5% 13.00 Birr/m3
Total Unit Cost : 298.99 Birr/m3

_____________________

LATED TO TARGETED OUTPUT.

ET FOR DIRECT & INDIRECT UNIT COSTS


LABOUR HOURLY OUTPUT: 31.25 m3/hr.
EQUIPEMENT: Tool
RESULT: 103.43 Birr/m3

Labour Cost (1:02) Equipment Cost (1:03)

** Indexed Hourly Type of Hourly Hourly


No. UF Hourly Cost Cost Equipment No. Rental Cost
1 1 77.39 77.39 loader 1 800 800
2 1 30.96 61.92 dump truck 2 600 1200
2 1 15.48 30.96 Tools 2 1.6 3.2
5 1 25.54 127.70

Total (1:02) 297.97 Total (1:03) 2003.2

9.534955 Birr/m3 C= Equipment Unit Cost 64.10 Birr/m3


Total of (1:03)
Hourly output: _____________
em = A+B+C = 89.94 Birr/m3
Over head cost : 10% 8.99 Birr/m3
Profit Cost: 5% 4.50 Birr/m3
Total Unit Cost : 103.43 Birr/m3

_____________________

LATED TO TARGETED OUTPUT.

OR DIRECT & INDIRECT UNIT COSTS


LABOUR HOURLY OUTPUT: 2.25 m2/hr.
EQUIPEMENT: Tool
RESULT: 124.15 Birr/m2

Labour Cost (1:02) Equipment Cost (1:03)

** Indexed Hourly Type of Hourly Hourly


No. UF Hourly Cost Cost Equipment No. Rental Cost
1 0.5 46.44 23.22 Tools 2 5 10.00
1 1 59.59 59.59
4 1 25.54 102.16

Total (1:02) 184.97 Total (1:03) 10.00

82.20975 Birr/m2 C= Equipment Unit Cost 4.44 Birr/m2


Total of (1:03)
Hourly output: ______________
em = A+B+C = 107.96 Birr/m2
Over head cost : 10% 10.80 Birr/m2
Profit Cost: 5% 5.40 Birr/m2
Total Unit Cost : 124.15 Birr/m2

_____________________

LATED TO TARGETED OUTPUT.

3. MASONRY WORK
EET FOR DIRECT & INDIRECT UNIT COSTS
LABOUR HOURLY OUTPUT: 1 m3/hr.
EQUIPEMENT:
RESULT 1545.82 Birr/m3

Labour Cost (1:02) Equipment Cost (1:03)

** Indexed Hourly Type of Hourly Hourly


No. UF Hourly Cost Cost Equipment No. Rental Cost
1 1 46.44 46.44 Tools 2 1.6 3.2
2 1 59.59 119.19
2 1 34.05 68.11
5 1 25.54 127.70
Total (1:02) 361.43 Total (1:03) 3.20

361.4305 Birr/m3 C=Equipment Unit Cost 3.2 Birr/m3


Total of (1:03)
Hourly output: __________________
tem = A + B + C = 1344.19 Birr/m3
10% 134.42 Birr/m3
5% 67.21 Birr/m3
1545.82 Birr/m3

LATED TO TARGETED OUTPUT.

2. CONCRETE WORK
EET FOR DIRECT & INDIRECT UNIT COSTS
LABOUR HOURLY OUTPUT: 15 m2/hr.
EQUIPEMENT:
m. thick RESULT: 84.87 Birr/m2

Labour Cost (1:02) Equipment Cost (1:03)

** Indexed Hourly Type of Hourly Hourly


No. UF Hourly Cost Cost Equipment No. Rental Cost
1 1 59.59 59.59 Mixer 1 85 85
6 1 25.54 153.24 Tools 3 1.6 4.8
1 0.5 46.44 23.22
1 1 42.57 42.57

Total (1:02) 278.62 Total (1:03) 89.8

18.57 Br./m2 C=Equipment Unit 5.99 Br./m2


Total of (1:03)
Hourly output: __________________
ork item= A+B+C= 73.80 Birr/m2
Overhead Cost: 10% 7.38 Birr/m3
Profit Cost: 5% 3.69 Birr/m3
Total Unit Cost : 84.87 Birr/m2

LATED TO TARGETED OUTPUT.

EET FOR DIRECT & INDIRECT UNIT COSTS


LABOUR HOURLY OUTPUT: 1.5625 m3 / hr.
EQUIPEMENT: Mixer & Vibrator
RESULT: 2708.02 Birr/m3

Labour Cost (1:02) Equipment Cost (1:03)

** Indexed Hourly Type of Hourly Hourly


No. UF Hourly Cost Cost Equipment No. Rental Cost
1 1 59.59 59.59 Mixer 1 85 85
18 1 25.54 459.72 Tools 3 1 3
1 0.5 46.44 23.22 Vibrator 1 40 40
1 1 42.57 42.57
1 1 30.65 30.65
Total (1:02) 615.75 Total (1:03) 128

394.08 Br./m3 C= Equipment Unit 81.92 Br./m3


Total of (1:03)
Hourly output:
tem = A+B+C = 2354.80 Birr/m3
Overhead Cost: 10% 235.48 Birr/m3
Profit Cost: 5% 117.74 Birr/m3
Total Unit Cost : 2708.02 Birr/m3

LATED TO TARGETED OUTPUT.

EET FOR DIRECT & INDIRECT UNIT COSTS


LABOUR HOURLY OUTPUT: 0.625 m3 / hr.
EQUIPEMENT: Mixer & Vibrator
RESULT: 3529.12 Birr/m3

Labour Cost (1:02) Equipment Cost (1:03)

** Indexed Hourly Type of Hourly Hourly


No. UF Hourly Cost Cost Equipment No. Rental Cost
1 1 59.59 59.59 Mixer 1 85 85
18 1 25.54 459.72 Tools 3 1 3
1 0.5 46.44 23.22 Vibrator 1 40 40
1 1 42.57 42.57
1 1 30.65 30.65

Total (1:02) 615.75 Total (1:03) 128.00

985.20 Br./m3 C= Equipment Unit 204.80 Br./m3


Total of (1:03)
Hourly output:
tem = A+B+C = 3068.80 Birr/m3
Overhead Cost: 10% 306.88 Birr/m3
Profit Cost: 5% 153.44 Birr/m3
Total Unit Cost : 3529.12 Birr/m3

LATED TO TARGETED OUTPUT.

EET FOR DIRECT & INDIRECT UNIT COSTS


LABOUR HOURLY OUTPUT: 0.875 m3 / hr.
EQUIPEMENT: Mixer & Vibrator
RESULT: 3168.63 Birr/m3

Labour Cost (1:02) Equipment Cost (1:03)


** Indexed Hourly Type of Hourly Hourly
No. UF Hourly Cost Cost Equipment No. Rental Cost
1 1 59.59 59.59 Mixer 1 85 85
18 1 25.54 459.72 Tools 3 1 3
1 1 46.44 46.44 Vibrator 1 40 40
1 1 42.57 42.57
1 1 30.65 30.65

Total (1:02) 638.97 Total (1:03) 128.00

730.25 Br./m3 C= Equipment Unit 146.29 Br./m3


Total of (1:03)
Hourly output:
tem = A+B+C = 2755.33 Birr/m3
Overhead Cost: 10% 275.53 Birr/m3
Profit Cost: 5% 137.77 Birr/m3
Total Unit Cost : 3168.63 Birr/m3

LATED TO TARGETED OUTPUT.

EET FOR DIRECT & INDIRECT UNIT COSTS


LABOUR HOURLY OUTPUT: 5 m2/ hr.
EQUIPEMENT: Mixer & Vibrator
RESULT: 404.63 Birr/m2

Labour Cost (1:02) Equipment Cost (1:03)

** Indexed Hourly Type of Hourly Hourly


No. UF Hourly Cost Cost Equipment No. Rental Cost
1 1 59.59 59.59 Mixer 1 85 85
18 1 25.54 459.72 Tools 3 1.6 4.8
1 1 46.44 46.44 Vibrator 1 40 40
1 1 42.57 42.57
1 1 51.08 51.08
1 1 30.65 30.65

Total (1:02) 690.05 Total (1:03) 129.80

138.01 Br./m2 C= Equipment Unit 25.96 Br./m2


Total of (1:03)
Hourly output:
tem = A+B+C = 351.85 Br./m2
Overhead Cost: 10% 35.18 Br./m2
Profit Cost: 5% 17.59 Br./m2
Total Unit Cost : 404.63 Birr/m2

LATED TO TARGETED OUTPUT.

4. FORMWORK
OR DIRECT & INDIRECT UNIT COSTS
LABOUR HOURLY OUTPUT: 1.25 m2/hr.
EQUIPEMENT:
RESULT: 428.67 Birr/m2

Labour Cost (1:02) Equipment Cost (1:03)

** Indexed Hourly Type of Hourly Hourly


No. UF Hourly Cost Cost Equipment No. Rental Cost
1 0.25 46.44 11.61 Tools 3 0.5 1.50
1 1 51.08 51.08
2 1 25.54 51.08

Total (1:02) 113.77 Total (1:03) 1.50

91.01548 Birr/m2 C=Equipment Unit Cost 1.20 Birr/m2


Total of (1:03)
Hourly output: _________________
em = A+B+C = 372.76 Birr/m2
10% 37.28 Birr/m2
5% 18.64 Birr/m2
Cost : 428.67 Birr/m2
_____________________

LATED TO TARGETED OUTPUT.


OR DIRECT & INDIRECT UNIT COSTS
LABOUR HOURLY OUTPUT: 0.75 m2/hr.
EQUIPEMENT:
RESULT: 506.27 Birr/m2

Labour Cost (1:02) Equipment Cost (1:03)

** Indexed Hourly Type of Hourly Hourly


No. UF Hourly Cost Cost Equipment No. Rental Cost
1 0.25 46.44 11.61 Tools 3 2 6.00
1 1 51.08 51.08
2 1 25.54 51.08

Total (1:02) 113.77 Total (1:03) 6.00

151.6925 Birr/m2 C=Equipment Unit Cost 8.00 Birr/m2


Total of (1:03)
Hourly output: _________________
em = A+B+C = 440.23 Birr/m2
10% 44.02 Birr/m2
5% 22.01 Birr/m2
Cost : 506.27 Birr/m2
_____________________

LATED TO TARGETED OUTPUT.

OR DIRECT & INDIRECT UNIT COSTS


LABOUR HOURLY OUTPUT: 0.875 m2/hr.
EQUIPEMENT:
RESULT: 502.79 Birr/m2

Labour Cost (1:02) Equipment Cost (1:03)

** Indexed Hourly Type of Hourly Hourly


No. UF Hourly Cost Cost Equipment No. Rental Cost
1 0.5 46.44 23.22 Tools 3 2 6.00
1 1 51.08 51.08
2 1 25.54 51.08

Total (1:02) 125.38 Total (1:03) 6.00

143.2897 Birr/m2 C=Equipment Unit Cost 6.86 Birr/m2


Total of (1:03)
Hourly output: _________________
em = A+B+C = 437.21 Birr/m2
10% 43.72 Birr/m2
5% 21.86 Birr/m2
Cost : 502.79 Birr/m2
_____________________

LATED TO TARGETED OUTPUT.

19. BAR SCHEDULE

OR DIRECT & INDIRECT UNIT COSTS


LABOUR HOURLY OUTPUT: 28.125 kg/hr.
EQUIPEMENT:
RESULT: 61.84 Birr/kg.

Labour (1:02) Equipment Cost (1:03)

** Indexed Hourly Type of Hourly Hourly


No. UF Hourly Cost Cost Equipment No. Rental Cost
1 0.1 46.44 4.64 tools 4 1 4.00
1 1 34.05 34.05
1 1 25.54 25.54
tal (1:02) 64.24 Total (1:03) 4.00

2.28 Birr/kg. Equipment Unit Cos 0.14 Birr/kg.


Total of (1:03)
Hourly output: ____________
em = A+B+C = 53.77 Birr/kg.
Over head cost : 10% 5.38 Birr/kg.
Profit Cost: 5% 2.69 Birr/kg.
Total Unit Cost : 61.84 Birr/kg.

OR DIRECT & INDIRECT UNIT COSTS


LABOUR HOURLY OUTPUT: 37.5 kg/hr.
EQUIPEMENT:
RESULT: 52.36 Birr/kg.

Labour (1:02) Equipment Cost (1:03)

** Indexed Hourly Type of Hourly Hourly


No. UF Hourly Cost Cost Equipment No. Rental Cost
1 0.1 46.44 4.64 tools 4 1.9 7.60
1 1 34.05 34.05
2 1 25.54 51.08
tal (1:02) 89.78 Total (1:03) 7.60

2.39 Birr/kg. Equipment Unit Cos 0.20 Birr/kg.


Total of (1:03)
Hourly output: ____________
em = A+B+C = 45.53 Birr/kg.
Over head cost : 10% 4.55 Birr/kg.
Profit Cost: 5% 2.28 Birr/kg.
Total Unit Cost : 52.36 Birr/kg.
_____________________

LATED TO TARGETED OUTPUT.

OR DIRECT & INDIRECT UNIT COSTS


LABOUR HOURLY OUTPUT: 38.75 kg/hr.
EQUIPEMENT:
RESULT: 51.99 Birr/kg.

Labour (1:02) Equipment Cost (1:03)

** Indexed Hourly Type of Hourly Hourly


No. UF Hourly Cost Cost Equipment No. Rental Cost
1 0.5 46.44 23.22 tools 4 1.9 7.60
1 1 34.05 34.05
2 1 25.54 51.08
tal (1:02) 108.35 Total (1:03) 7.60

2.80 Birr/kg. Equipment Unit Cos 0.20 Birr/kg.


Total of (1:03)
Hourly output: ____________
em = A+B+C = 45.21 Birr/kg.
Over head cost : 10% 4.52 Birr/kg.
Profit Cost: 5% 2.26 Birr/kg.
Total Unit Cost : 51.99 Birr/kg.
_____________________

LATED TO TARGETED OUTPUT.

OR DIRECT & INDIRECT UNIT COSTS


LABOUR HOURLY OUTPUT: 43.75 kg/hr.
EQUIPEMENT:
RESULT: 53.55 Birr/kg.

Labour (1:02) Equipment Cost (1:03)

** Indexed Hourly Type of Hourly Hourly


No. UF Hourly Cost Cost Equipment No. Rental Cost
1 1 46.44 46.44 tools 4 1.9 7.60
1 1 34.05 34.05
4 1 25.54 102.16

tal (1:02) 182.65 Total (1:03) 7.60

4.17 Birr/kg. Equipment Unit Cos 0.17 Birr/kg.


Total of (1:03)
Hourly output: ____________
em = A+B+C = 46.57 Birr/kg.
Over head cost : 10% 4.66 Birr/kg.
Profit Cost: 5% 2.33 Birr/kg.
Total Unit Cost : 53.55 Birr/kg.
_____________________
LATED TO TARGETED OUTPUT.

OR DIRECT & INDIRECT UNIT COSTS


LABOUR HOURLY OUTPUT: 45 kg/hr.
EQUIPEMENT:
RESULT: 53.16 Birr/kg.

Labour (1:02) Equipment Cost (1:03)

** Indexed Hourly Type of Hourly Hourly


No. UF Hourly Cost Cost Equipment No. Rental Cost
1 1 46.44 46.44 tools 4 1.9 7.60
1 1 34.05 34.05
2 1 25.54 51.08

tal (1:02) 131.57 Total (1:03) 7.60

2.92 Birr/kg. Equipment Unit Cos 0.17 Birr/kg.


Total of (1:03)
Hourly output: ____________
em = A+B+C = 46.22 Birr/kg.
Over head cost : 10% 4.62 Birr/kg.
Profit Cost: 5% 2.31 Birr/kg.
Total Unit Cost : 53.16 Birr/kg.
_____________________

LATED TO TARGETED OUTPUT.


data collection for material cost

Item no material type unit material cost transport cost


1 EARTH WORK 166.35 0
1.1 Borrowed material m3 152.17
1.2 Diesel lits 14.17
2 CONCRETE 876.09 0
2.1 Cement Qt 343.48
2.2 Sand m3 190.22
2.3 Aggregate m3 342.39
3 MASONARY 638.80 0
3.1 Stone m3 334.45
3.2 Basaltic stone m3 304.35
4 FORM WORK 339.13 0
4.1 zigba panel m2 260.87
4.2 Eucalyptus ml 8.70
4.3 7cm Nails Kg 69.57
5 BRICK WORK 2.61 2
5.1 24x12x6cm brick No. 2.61 2
5 BLOCK WORK 16.52 6
5.1 20cm H.C.B. No. 6.96 2
5.2 15cm H.C.B. No. 5.22 2
5.3 10cm H.C.B. m3 4.35 2
6 PAINTING 393.04 0
6.1 Stucco Kg 13.04
6.2 Animal or vinavil glue kg 60.87
6.3 plastic paint lits 76.09
7.3 Oil base synthetic paint lits 63.04
6.4 Gypsum Kg 4.35
6.5 Sand paper ml 26.09
6.6 Brush no 26.09
7.6 primium lts 26.09
6.7 Quartiz paint lts 97.39
7 FLOOR AND WALL FINISH 1544.07 0
7.1 PVC tile(25x25) No 25.54
7.2 Adhesive lits 163.04
6.3 marble tile(2x25cm) m2 956.52
7.3 Ceramic tile(15x15) No 156.52
8.3 Ceramic wall tile(20x20) No 12.00
7.4 White cement kg 30.43
7.5 Ceramic tile(25x25) No 200.00
8.5 Ceramic tile(40x40) No 125.36
9.5 fisher pkts 30.43
8 SKIRTING 91.30 0
8.1 ceramic tile skirting ml 91.30
9 DOOR AND WINDOW SILL 50.00 0
9.1 terazo sill (27X3)cm ml 50.00
10 CARPENTRY AND JOINERY 3306.46 0
10.1 Chip wood m2 156.52
10.2 4X5cm Batten m 10.87
10.3 4cm Nail kg 52.17
10.4 6cm Nail kg 52.17
10.5 Corner list m 5.22
10.6 10-12cm euc. Tree m 18.63
10.8 Band iron kg 47.83
10.9 8-10cm euc. Tree m 8.70
10.9 12 cm Nails kg 69.57
10.9 (5X7)cm wooden Purlin m 15.22
10.9 wood door m2 2869.57
12.9 9cm Nails kg 71.30
11 ROOF WORK 1892.36 0
11.1 G-28 C.I.S. No. 317.58
12.1 G-30 C.I.S. No. 278.26
13.1 G-32 C.I.S. No. 226.09
14.1 G-35 C.I.S. No. 200.00
12.1 corrugated asbestos No. 366.09
13.1 G-28 flat metal sheet(gutter) ml 156.52
14.1 valley cover ml 121.74
14.1 ridge cover ml 113.04
11.2 Nails Kg 113.04
12 SANITARY INSTALLATION 23502.67 0
12.1 Hand wash basin aqua 55x45 No 1800.00
4.2 WC low flash gold dragon No 500.00
5.2 WC high flash gold dragon No 3693.00
9.2 double bowl stainless steel kitchen sink No 750.00
10.2 towel hanger 610 x 25 mm No 40.00
11.2 soap holder No 182.00
12.2 toilet paper holder No 256.00
13.2 crystal glass mirror 500 x 400 mm No 100.00
14.2 bath tub No 1500.00
12.3 Shower plate No 450.00
12.4 50 lit water heater No 6500.00
12.5 Floor drain O50 No 60.00
12.6 15mm gate valve No 230.00
13.6 25mm gate valve No 220.00
13.6 vent cups No 231.00
14.6 32mm water meter No 232.00
1000 lts water tank No 4500.00
O150mm concrete sewer pipe No 200.00
Fiber kg 215.00
Fittings (out let and inlate) no 27.00
Float valve 3/4" no 117.00
glue lt 85.00
14 O100mm down pipe 43.80 0
14.1 O100mm PVC m 25.20
14.2 fixing bracket No. 13.30
14.3 fixer No. 5.30
Bolt and nut No. 3.20
O25mm GSP ml 85.33
union No 106.70
Plug No 70.00
elbow No 86.00
Tee No 64.00
O15mm PPR ml 23.75
union No 20.00
Plug No 20.00
elbow No 20.00
Tee No 20.00
O20mm PPR ml 32.50
union No 23.00
Plug No 23.00
elbow No 23.00
Tee No 23.00
O25mm PPR ml 37.50
union No 27.00
Plug No 27.00
elbow No 27.00
Tee No 27.00
Reducer No 27.00
O50mm PVC ml 18.33
union No 21.74
Plug No 21.74
elbow No 21.74
Tee No 21.74
Y No 21.74
O75mm PVC ml 27.54
union No 34.78
Plug No 34.78
elbow No 34.78
Reducer No 34.78
Tee No 34.78
Y No 34.78
O110mm PVC ml 34.78
union No 52.17
Plug No 52.17
elbow No 52.17
Reducer No 52.17
Tee No 52.17
Y No 52.17
13 METAL AND ALUMINUM WORK 5653.91 0
Metal works
Metal door 3.4x3m for main gate m2 4262.61
Almunium works
for doors m2 695.65
for windows m2 695.65
13 CURTAIN WALL 43.80 0
Curtain wall works m2 695.65
15 GLAZING 726.09 0
15.1 4mm thick clear Glass m2 317.39
16.1 5mm thick clear Glass m3 391.30
15.2 Putty kg 17.39
16 Reinforcement 302.42 0
16.1 6mm kg 47.83
16.2 8mm kg 39.81
16.3 10mm kg 39.13
16.4 12mm kg 39.13
16.5 14mm kg 40.00
16.6 16mm kg 40.00
16.7 18mm kg
16.8 20mm kg
16.9 0.15mm Tying wire kg 56.52
17 RHS 1391.30 0
17.1 for 40x40x2.5 pcs 434.78
17.2 for 65x65x5 pcs 956.52
l cost
total material
loading cost unloding cost cost
0 0 166.35
152.17
14.17
0 0 876.09
343.48
190.22
342.39
0 0 638.80
334.45
304.35
0 0 339.13
260.87
8.70
69.57
1 1 6.61
1 1 6.61
3 3 28.52
1 1 10.96
1 1 9.22
1 1 8.35
0 0 393.04
13.04
60.87
76.09
63.04
4.35
26.09
26.09
26.09
97.39
0 0 1544.07
25.54
163.04
956.52
156.52
12.00
30.43
200.00
125.36
30.43
0 0 91.30
91.30
0 0 50.00
50.00
0 0 3306.46
156.52
10.87
52.17
52.17
5.22
18.63
47.83
8.70
69.57
15.22
2869.57
71.30
0 0 1892.36
317.58
278.26
226.09
200.00
366.09
156.52
121.74
113.04
113.04
0 0 23502.67
1800.00
500.00
3693.00
750.00
40.00
182.00
256.00
100.00
1500.00
450.00
6500.00
60.00
230.00
220.00
231.00
232.00
4500.00
200.00
215.00
27.00
117.00
85.00
0 0 43.80
25.20
13.30
5.30
3.20
85.33
106.70
70.00
86.00
64.00
23.75
20.00
20.00
20.00
20.00
32.50
23.00
23.00
23.00
23.00
37.50
27.00
27.00
27.00
27.00
27.00
18.33
21.74
21.74
21.74
21.74
21.74
27.54
34.78
34.78
34.78
34.78
34.78
34.78
34.78
52.17
52.17
52.17
52.17
52.17
52.17
0 0 5653.91
4262.61 full metal 1680/m2
half glazed 2300/m2
695.65
695.65
0 0 43.80
695.65
0 0 726.09
317.39
391.30
17.39
0 0 302.42
47.83
39.81
39.13
39.13
40.00
40.00
0.00
0.00
56.52
0 0 1391.30
434.78
956.52 1700/m2
1. LABOR INDEX CALCULATION
ITEM NO Type of index DAY/MONTH INDEXED FACTOR
(22day/month)
1 Reular salery (22day/month) 1.00
(1.5day/month)
2 annual leave (22day/month) 0.07
(1.08day/month)
3 public holiday (22day/month) 0.05
benefits for 18% of (22day/month)
4 worker (22day/month) 0.18
5 medical insurance
6 over time
7 avg annual increase
8 rainy season salary
sub-total 1.30

CONTINEGENCY (for work injury, dispute & labor union)


5% of sub total
indexed cost 0.06
GRAND TOTAL INDEXED FACTOR 1.36

data collection for labor cost

hourly
Item no types of labor monthly salary daily rate rate
1 Exc.Operator 10000 454.55 56.82
2 Mixer Op. 5500 250.00 31.25
3 Vibrator Op. 3960 180.00 22.50
compactor op. 3960 180.00 22.50
4 truck driver 4000 181.82 22.73
ass truck driver 2000 90.91 11.36
5 Loader Op. 10000 454.55 56.82
7 Forman 6000 272.73 34.09
8 Mason 7700 350.00 43.75
9 Mason ll 4400 200.00 25.00
10 Carpenter 6600 300.00 37.50
11 Carpenter ll 3960 180.00 22.50
12 Bar bender 4400 200.00 25.00
13 Bar bender ll 4400 200.00 25.00
14 Plasterer 7700 350.00 43.75
15 Chieseler 3960 180.00 22.50
16 tiler 7700 350.00 43.75
17 Welder 7700 350.00 43.75
18 Glazer 5000 227.27 28.41
19 Painter 7700 350.00 43.75
20 Plumber 7700 350.00 43.75
21 Elec 6600 300.00 37.50
22 DL 3300 150.00 18.75

data collection for labor cost

types of hourly
Item no equipment monthly salary daily rate rental rate
1 backhoe loader, 9 140800 6400 800
2 backhoe loader, 9 140800 6400 800
3 vibrator 7040 320 40
4 dump truck 105600 4800 600
5 mixer 14960 680 85
6 tools
7 compactor 7040 320 40
3960

hourly labor
indexed hourly
factor index
1.36 77.39
1.36 42.57
1.36 30.65
1.36 30.65
1.36 30.96
1.36 15.48
1.36 77.39
1.36 46.44
1.36 59.59
1.36 34.05
1.36 51.08
1.36 30.65
1.36 34.05
1.36 34.05
1.36 59.59
1.36 30.65
1.36 59.59
1.36 59.59
1.36 38.70
1.36 59.59
1.36 59.59
1.36 51.08
1.36 25.54
Calculating Labour Requirement
Item Labour Efficiencies
Activity Description Gang per day Work to be executed
A) SUBSTRUCTURE
1 Excavation and earth work

Site clearing to remove top soil to an


1.1 average depth of 20 cm 1D.L 8hr. 10m² 1.25m²/hrs
1.2 Trench excavation in ordinary soil
a) To a depth of 1m 1D.L 8hr. 1.25m3 0.16m³/hrs
b) To a depth of 2m 1D.L 8hr. 1.00m 3
0.13m³/hrs
c) To a depth of 4m 1D.L 8hr. 0.75m 3
0.094m³/hrs
1.3 Bulk excavation in ordinary soil
a) To a depth of 1.5m 1D.L 8hr. 1.5m3
1.4 pit excavation in ordinary soil
a) To a depth of 1.5m 1D.L 8hr. 1.5m3
a) To a depth of 1.5m 1D.L 8hr. 1.5m4
1.5 Back fill around foundation
a) Loose soil 1D.L 8hr. 2m3
b) Aggregate 1D.L 8hr. 11/2m3
1.6 Cart away
a) To 500m away from the site 1D.L 8hr. 1.5m3
b) To one km away from the site 1D.L 8hr. 1m3
1.7 Hard core 25cm thick 1m+4DL 8hr. 18m2

2 Concrete Work
2.1 C-5 Lean concrete
a) 5cm thick 1m+6D.L 8hr. 20m2
b) 8cm thick 1m+6D.L 8hr. 15m2
2.2 Floor Slab
a) 8cm thick 1m+6D.L 8hr. 15m2
b) 10cm thick 1m+6D.L 8hr. 12.5m2
c) 15cm thick 1m+6D.L 8hr. 10m2
2.3 Ground beam 1m+6D.L 8hr. 11/2m3
2.4 Footing 1m+6D.L 8hr. 11/2m3
2.5 Foundation column 1m+6D.L 8hr. 11/4m3

3 Masonry Work

3.1 Stone masonery B.G.L


a) 40cm thick 2m+6D.L 8hr. 5m3
b) 50cm thick 2m+6D.L 8hr. 6m3
c) 60cm thick 2m+6D.L 8hr. 7m3

3.2 Stone masonry A.G.L


a) 40cm thick 2m+6D.L 8hr. 3m3
b) 50cm thick 2m+6D.L 8hr. 4m3
c) 60cm thick 2m+6D.L 8hr. 5m3

B) SUPER STRUCTURE
4 Concrete Work
4.1 for elivation Column
a/ Column up to 2m 1m+6D.L 8hr. 11/4m3
b/ Column above 2m 1m+6D.L 8hr. 1m3
4.2 Upper tie beam 1m+6D.L 8hr. 1m3
4.3 Linton 1m+6D.L 8hr. 1m3
5 H.C.B Block Work
a) 20cm thick up to 2m 1m+2D.L 8hr. 10m2
b) 15cm thick up to 2m 1m+2D.L 8hr. 10m2
c) 10cm thick up to 2m 1m+2D.L 8hr. 8m2
d) 20cm thick from 2 - 4m 1m+2D.L 8hr. 8m2
e) 15cm thick form 2 - 4m 1m+2D.L 8hr. 8m2
f) 10cm thick form 2 - 4m 1m+2D.L 8hr. 6m2
6 Brick Work
a) 25cm thick up to 2m 1m+3D.L 8hr. 7m2
b) 12cm thick up to 20m 1m+3D.L 8hr. 9m2
c) 25cm thick up to 20m 1m+3D.L 8hr. 5m2
d) 12cm thick from 2 - 4m 1m+3D.L 8hr. 7m2

7 Roofing Work
7.1 Roof covering (G.C.I) 1c+2D.L 8hr. 40m2
Roof covering corrugated asbestos 1c+2D.L 8hr. 40m3
7.2 Ridge cover 1c+2D.L 8hr. 70ml
7.3 Valley cover 1c+2D.L 8hr. 70ml
7.4 Gutter fixing 1c+2D.L 8hr. 30ml
7.5 Joinion eucalyptus truss up to 10m span on 1c+2D.L 8hr. 4 truss
7.6 Down pipe fixing 1c+2D.L 8hr. 40ml
7.7 Truss erecting 1c+2D.L 8hr. 5 truss
7.8 Fixing corrugated asbestos 1c+2D.L 8hr. 25m2
7.9 Fixing EGA sheet joining 1c+2D.L 8hr. 30m2
7.1 Joining zigba truss up to 10m span on groun 1c+2D.L 8hr. 3 truss
7.11 Zigba truss erecting 1c+2D.L 8hr. 15 truss
7.12 Facial board fixing 1c+2D.L 8hr. 70ml

8 Joinery Work
8.1 Wooden door fixing 1c+2D.L 8 hr 3 pcs
8.2 Wooden Window fixing 1c+2D.L 8 hr 4 pcs
8.3 Chip wood ceiling fixing 1c+2D.L 8 hr 10 m2
8.4 Hard boared ceiling fixing 1c+2D.L 8 hr 10 m2
8.5 Abujedie Ceiling 1c+2D.L 8 hr 13 m2

9 Metal work
9.1 Metal door fixing 1c+2D.L 8 hr 3 pcs
9.1 Metal window fixing 1c+2D.L 8 hr 4 pcs
9.1 French window fixing 1c+2D.L 8 hr 2 pcs

10 Plastering and pointing


10.1 1st coat plastring 1p +2D.L 8 hr 35 m2
10.2 2 coat plastring
nd
1p +2D.L 8 hr 10 m2
10.3 3rd coat plastring 1p +2D.L 8 hr 14 m2
10.4 Pointing on stone wall
10.5 Pointing on brick wall 1p +2D.L 8 hr 8 m2
10.6 Pointing on Hollow block 1p +2D.L 8 hr 14 m2
10.7 Pointing on dressed stone 1p +2D.L 8 hr 12 m2
10.8 Rendering 1p +2D.L 8 hr 20 m2

11 Floor finishing
11.1 Cement screed 1m +2D.L 8 hr 14 m2
11.2 Cement tile fixing 1m +2D.L 8 hr 10 m2
11.3 Plastic tile fixing 1m +2D.L 8 hr 17 m2
11.4 Par-quet flooring 1m +2D.L 8 hr 15 m2
11.5 Wooden flooring 1m +2D.L 8 hr 8 m2
11.6 Ceramic wall tile 1m +2D.L 8 hr 7 m2
11.7 Plastic tile skirting 1m +2D.L 8 hr 40 ml
11.8 Ceramic tile kirting 1m +2D.L 8 hr 12 ml
11.9 Marble slate flooring 1m +2D.L 8 hr 12 ml
11.10 Marble slate skirting 1m +2D.L 8 hr 16 ml
11.11 Fixing pre-cast window sill 1m +2D.L 8 hr 10 ml
11.12 Fixing un pre-cast window sill 1m +2D.L 8 hr 6 ml

12 Glazing work
12.1 Cutting 1c+2D.L 8 hr 50 m2
12.2 Fixing 1c+2D.L 8 hr 20 m2

13 Painting work
a) plastic paint

10.1 Painting plastered wall surfac ( 3 coats) 1p +1D.L 8 hr 30 m2


10.2 Painting renedered wall 1p +1D.L 8 hr 25 m2
10.3 Paintig Abujedie ceiling 1p +1D.L 8 hr 20 m2
10.4 Painting Hard board ceiling 1p +1D.L 8 hr 20 m2
10.5 Painting Chip board ceiling 1p +1D.L 8 hr 20 m2
b) Synthetic Paint
10.6 Plastered wall surface in 3 coats 1p +1D.L 8 hr 25 m2
10.7 Wooden surface 1p +1D.L 8 hr 25 m2
10.8 Metal surface 1p +1D.L 8 hr 27 m2

14 Sanitary Work
14.1 G.I pipe lyeing in ground 1/2"-11/4" 1p +2D.L 8 hr 120 ml

Fixing Bath tab, shower complete, wash


14.2 basin water closet, bidet sink. 1p +1D.L 8 hr 1 pcs

15 Electrical Installation
15.1 Fixing conduits 1e +1D.L 8 hr 40 ml
15.2 Pulling wires 1e +1D.L 8 hr 50 ml
15.3 Fixing switch & out- lets 1e +1D.L 8 hr 20 pcs
15.4 Fixing Fittings 1e +1D.L 8 hr 10 pcs
15.5 Fitting distribution board 1e +1D.L 8 hr 10 pcs

16 Site Work
16.1 Drain laying
Ø 0.10 - 0.20 m 1m +3D.L 8 hr 30 ml
Ø 0.40 - 0.60 m 1m +3D.L 8 hr 20 ml
Ø 0.80 - 1.00 m 1m +3D.L 8 hr 10 ml
16.2 Curb stone 1m +3D.L 8 hr 30 ml
16.3 0.60x0.60x0.60m manhole out of brick 1m +3D.L 8 hr 3 pcs
17.4 0.60x0.60x0.60m manhole out of hollow block1m +3D.L 8 hr 2 pcs
18.5 Fencing with galvanized fencing net 1c + 2D.L 8 hr 50 m2

You might also like