Gantt Chart Progress Update For Renovation & ID Work
Gantt Chart Progress Update For Renovation & ID Work
PROJECT NAME : GIEM ACADEMY - RENOVATION & ID WORKS @ECO SKY, JALAN KUCHING
PROJECT TIMELINE 2023 - 2024
UPDATED: 10 NOVEMBER 2023
Required:
Item Description of Works Date 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
No of Days
1 - PRELIMINARIES
3.02 DB Board 11
5 - WALL PARTITION
6 - CEILING FINISHES
7 - PAINTING
8 - CUSTOM FURNITURE
Required:
Item Description of Works Date 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
No of Days
10 - FINISHING WORK
11 - OTHERS
11.04 Decoration 5
SCHEDULE 2
PROJECT NAME : GIEM ACADEMY - RENOVATION & ID WORKS @ECO SKY, JALAN KUCHING
PROJECT TIMELINE 2023 - 2024
UPDATED: 21 DECEMBER 2023
Required:
Item Description of Works Date 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
No of Days
1 - PRELIMINARIES
3.02 DB Board 11
5 - WALL PARTITION
6 - CEILING FINISHES
7 - PAINTING
8 - CUSTOM FURNITURE
Required:
Item Description of Works Date 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
No of Days
10 - FINISHING WORK
11 - OTHERS
11.04 Decoration 5