Professional Documents
Culture Documents
2023.03.14 Final Contract 4086 Main
2023.03.14 Final Contract 4086 Main
BETWEEN
AND
FOR
INSTALLATION OF NEW GAS FIRED BOILER
MAIN PACKAGE
PACKAGE NO. III
VOLUME -II
(CONTRACT TECHNICAL SPECIFICATION)
Annexures
Schedules
Drawings
2.2.4 Blast Furnace Gas / Coke Oven Gas firing System & Other Utility
Lines
Blast furnace gas/ coke oven gas shall be tapped from the existing
headers at OPP.
Necessary isolation goggle valves and U seals shall be provided
after the tapping for BF gas line. Encased type, slide plate goggle
valves shall be provided 1 no. at main header and 1 no. at branch
for proposed boiler in BF gas line.
Necessary motorised isolation valves and U seals shall be provided
after the tapping for CO gas line.
Necessary nitrogen purging lines shall also be laid after tapping
from existing nitrogen header near OPP.
LP steam lines shall be provided for startup and purging purpose.
2.2.5 Compressed Air System
Dry compressed air shall be used for instrument operation.
2 nos. (1w+1s) oil-lubricated / non-lubricated screw type
compressors, each capable of catering to the instrument air (of
required air quality) as well as service air requirement of new gas
fired boiler and other proposed systems shall be installed.
The system shall be complete with 2 nos. air dryers (1w+1s), pipe
network, valves and fittings, instruments and control etc.
2.4 ELECTRICAL
2.4.1 Major equipment / facilities for electrical works are mentioned below:
Sl. Description Quantity
No.
1. New 11 kV, 1250A VCB feeder (With breaker 2 sets
each, CTs, numerical relays, auxiliary relays,
metering, indication and associated accessories)
11kV power supply of the new Boiler shall be
tapped from two adjacent bus-sections of OPP
11kV board at 33/11kV substation under NPP
Power Evacuation Scheme.
The middle bus-section has a spare panel for
11kV OPP board at Evacuation Package S/Stn.
Extension of bus for bus-sections No. 1 & 3, shall
be done under this project.
Bus-section No. 1 & 3 is fed from same NPP
feeder while the middle bus-section (No. 2) is
fed from the second NPP feeder, different bus
section.
Thus one 11kV feeder for the new Boiler shall be
tapped from the middle (No. 2) bus-section,
while the other 11kV feeder for the new Boiler
shall be tapped from No. 3 bus-section, i.e., the
two feeders would be tapped from adjacent bus-
section. Hence, 11kV supply for the New Boiler
will be tapped from adjacent bus-sections of
11kV board of S/Stn under NPP Power
Evacuation Scheme. For this, bus will be
extended in section 3 to provide feeder for the
same.
Control Panels (as per existing) for 11kV breakers
DSP PAGE 2.11 CONTRACT NO..
INSTALLATION OF NEW GAS FIRED
BOILER
Sl. Description Quantity
No.
to be considered
The cable will be laid partly through employer’s
overhead gallery and the rest through buried
cable trench. The new LT substation will have 2
no’s 2 MVA transformers and a Power Control
Centre (PCC) which will cater the entire LT loads
of proposed boiler. Proposed power network of
new LT S/S may be referred in enclosed Drg no.
CET RN 4086 EE1 00 001.
System shall be designed so as to prevent
unnecessary tripping of critical electrical drives
on under-voltage/ similar conditions caused by
external system disturbances.
2. 1250A Vacuum Circuit Breakers (VCBs) as 2 sets
isolators
VCB make / Panel make for 11kV Board (feeding
to Transformers) shall preferably be of same
make/model as to be supplied for 11KV
breakers/ board at NPH (as mentioned in the
above point) from where the 11kV power will be
sourced.
Since the VCBs mentioned under this clause are
to be used only for isolation, therefore there will
be no Protection releases or numerical
protection relay in these 2 breaker panels.
3. Min 2 MVA, 11/ 0.433kV AN distribution 2 sets
transformers at new LT substation which will be
fed from new 11 kV feeders of upcoming 11 kV
HT Switchboard.
Location: new LT substation
4. 4000 A LT busduct 2 sets
Aluminium bus duct shall be considered from
secondary of the transformers to new LT
Switchboard/ PCC.
Suitable cable supporting arrangement, cable
box for connecting cables at primary side of
2.7 CIVIL
2.7.1 The major scope under civil engineering works are as follows:
1) Construction of RCC foundations for technological equipment
such as boiler, ID fans, FD fans, pipe supports, chimney, AVG filters,
pumps & dosing system equipment including inserts, bolts,
grouting etc. as per technological & system requirements
2) RCC foundation for structural steel shed of boiler house including
construction of RCC framed building with brick cladding wall for
compressor room, control room, office, toilets & its
interconnection with existing sewerage system & plumbing
system, RCC peripheral drain & its interconnection with existing
drain, all finishes, doors, windows & RCC floor with floor finish
over compacted boulder soling in shed, roof treatment, inserts,
bolts, grouting etc. as per technological & system requirement.
Discipline Description
Process and 1. General Layout, PFD and G.A. drawings of the
Technology complete system & equipment, Duct / pipe
route drawing including sections showing full
details along with bill of materials
2. Data sheet of boiler, pumps, fans, compressors
and other equipment
3. Design calculations for system, sizing, etc.
4. QAPs for equipment & system
6. Any other information required by the
Employer / Consultant
Utilities 1. Layout, GA, Design calculation & datasheets of
Air conditioning and ventilation system
2.8.7 Format of contractor drawing list shall have minimum following fields:-
1) Sl. No.
2) Employer drawing No
3) Contractor drawing No
4) Name of consortium member
5) Area
6) Drawing/Document Name
7) Category (Approval/Reference)
8) Discipline
9) Stage (BE/DE)
DSP PAGE 2.34 CONTRACT NO..
INSTALLATION OF NEW GAS FIRED
BOILER
10) Schedule date of submission
11) Remarks
2.8.8 Drawing list shall be in excel format. Any additional field, if required,
shall be added after Column 11. In case the drawing has more than one
sheet, employer drawing shall include the sheet number as part of
drawing number.
2.8.9 Editable format soft copies (3 sets) on suitable media of all “As-Built”
drawings (full set of drawings as per the approved drawing list) and
manufacturing drawings of critical parts, spares and fast wearing parts
shall be supplied by the contractor.
2.8.10 In case the proposed plant uses any process, equipment or software
which is covered under any patent and SAIL / plant is required to have
the relevant user’s license for the same, the scope of work of this bid
shall include transferring such licenses to SAIL and indemnifying SAIL
against infringement of any intellectual property rights.
2.9 BATTERY LIMIT
Incoming
Utilities --
Make-up Piping shall be laid considering requirement for future 1
water no. similar capacity boiler.
system This shall be taken from existing DN 600 settled water
main of Water Management Department (WMD) at ‘L’
chamber of OPP coal yard. Distance 150 m (approx.).
Pressure 0.75 kgf/cm2 (g).
Alternate water line shall be laid from filtered make up
water line of OPP to proposed area. Distance 150 m
(approx.). Pressure – 2.0 kgf/cm2 (g).
Fire water From existing DN 200 fire water header at furnace street.
Pressure 9.0 kgf/cm2 (g). Approx distance -300m
BF Gas From the existing DN 2100 header with motorised
isolation valve. Pressure 250 to 450 mmWC, temperature
50oC. Approx distance - 150m.
Minimum gas pressures will be available near burner side
however contractor will design the burner considering
given range
CO Gas From the existing DN 700 header with motorised isolation
Outgoing
Utilities --
3.1.3.4 Hazardous area classification for COG & BFG lines. - Gas lines Safety
Zone may be considered as per applicable TAC norms & Indian
Industrial practices. Contractor to decide the hazardous area
requirement based on fuel.
3.2 PROCESS AND TECHNOLOGY
3.2.1 Boiler & Auxiliaries
3.2.2.1 Operating Parameters
3.2.2.2 Boiler shall be field mounted, natural circulation, balanced draft design
as per IBR. Boilers shall be designed for full load with BF gas firing. Coke
oven gas will be used as start-up fuel as well as back-up fuel. Design
provision shall be kept for consumption of around 7000-10000 Nm3/h
of COG during normal boiler operation.
3.2.2.3 Furnace
The boiler furnace shall be membrane wall construction. Peepholes,
access doors etc. shall be provided in the furnace side wall. The roof
tubes shall be suitably staggered to allow super heater coils to pass
through, however the superheater tube arrangement will be as per
contractor’s design. The headers shall be manufactured from seamless
pipes. The headers shall be provided with drain connections, air vent
connection and hand holes for inspection as required.
There shall be required nos. of burner (concentric for both BF gas & CO
gas).
Shall not have any direct flame impingement. Shall be provided with 2
nos. inspection door.
3.2.2.4 Drum
Shall be fusion-welded construction with semi-ellipsoidal dished ends.
The drum dished ends shall be provided with properly sized manholes
and manhole covers. Shall be equipped with suitable internals like
3 Minimum Quantity 1W + 1S
Filter media shall be graded sand and gravel of approved size and
quality. The filter body will be fabricated from Tubular section/ plate
conforming to IS 2062: 2011. Inside surface of filter shall be Tar-Epoxy
based anticorrosive paint. Contractor shall provide flanged nozzles for
connecting various fittings. Instruments shall be provided as per
approved drawings. Inspection manhole of adequate size, tray for inlet
water distribution and collector system for filtered water shall be
provided. Empty space below the filtered water collector shall be filled
with concrete.
3.2.3 RO Water Plant
The proposed RO water plant shall consist of pre-treatment section,
storage & pumping facilities for RO water and neutralisation system. A
three-stream RO water plant with each stream having minimum capacity
of 60 m3/h to meet the makeup water requirement of proposed boiler
shall be provided. The plant shall be fully automatic and shall be
capable to be operated without human intervention. Considering the
makeup water quality necessity of filters, no. of treatment stages etc.
shall be decided. Necessary monitoring and control instruments for
automatic operation shall be provided.
DSP PAGE 3.15 CONTRACT NO..
INSTALLATION OF NEW GAS FIRED BOILER
3.2.3.1 Technical specification of RO water plant:
1 No. of stream : 03 nos.
2 Function : To generate RO water as per
reqd. quality
3 RO water quality : Contractor to specify (as per
boiler feed requirement)
4 Supply : Continuous
5 Regeneration cycle : Contractor to specify
6 RO water piping : Stainless steel - SS–316
The plant shall be equipped with all facilities (including electrical,
instrumentation and handling) for producing required quality of RO
water.
3.2.3.2 Design Basis
Input water quality for RO water plant design is given in Clause No.
3.1.3.3. The treated water quality shall be as per requirement of Boiler
manufacturer.
3.2.3.3 Operating Philosophy of Automatic RO Water Plant
The proposed RO water plant shall be required to meet the makeup and
first fill RO water requirement for the proposed boiler. RO water plant
shall be automatically operated through PLC.
Regeneration/Backwash/cleaning shall be done by the respective end
product of the unit for the pre-planned duration. Human intervention
shall be limited to ensure timely refill of various chemical dosing tanks.
All filters, RO water storage tank and chemical tanks shall be
construction of suitable materials and fitted with corrosion resistant
internals.
All chemical dosing tanks shall be of high-density polyethylene
(MSRL/HDPE) construction.
The capacity/ size of RO unit, all filters, all pumps, agitators, air blower,
measuring tanks, piping and valves shall be as per the calculation/
engineering of Contractor and approved by Employer/ Consultant.
3.2.3.4 Specification for major equipment of RO Water System
A) Electric motor operated Pumps
The selection of Pumps shall be carried out by the contractor
to suit the requirement of the system supplied by him.
Technical Specification shall be as per following table.
Note: 1. The pump shall be complete with a plug for priming and air
cock for releasing entrapped air in the casing (wherever applicable)
3.2.4 Compressed Air System
3.2.4.1 General
2 nos. air compressors shall be provided each capable of delivering total
air requirement for the boiler for instrument air as well as service air.
The minimum discharge capacity of each compressor will be 2.5
Nm3/min at operating pressure of 6-7 kg/cm2 (g)
Instrument quality air shall be dry, oil free, with dust content <5 micron
and dew point – 40oC. Heatless regenerative 2 nos. (1W+1S) driers shall
be installed for supplying instrument grade air.
3.2.4.2 Compressor
1) Air compressor shall be screw type. Design code shall be IS
12258:1987.
2) Compressor shall be provided with suction air filter with silencer,
inter cooler (if required), after cooler, moisture separator, air dryer
etc.
3) Tests shall be carried out as per manufacturers standard /
applicable codes such as IS 11780:1986.
3.2.4.3 Air Drier
1. Type Heatless
2. Inlet Air Temperature 45oC (max.) *
3. Working Pressure 7 kg/cm2(g) *
4. Quantity 1W+1S
5. Atmospheric Dew Point -40 oC
6. Pressure Dew point -22 oC
DSP PAGE 3.18 CONTRACT NO..
INSTALLATION OF NEW GAS FIRED BOILER
7. Allowable pressure drop Contractor to design
8. Purge Loss Contractor to design
9. Standard Accessories Pre Filter for oil removal & After
Filter for desiccant dust removal
with auto drain system
3.2.4.4 Air Receiver
1) 2 nos. air receiver of minimum capacity 2 m3 each for service air
and instrument quality air complete with accessories like safety
valve, vent valve, drain valve, inlet & outlet opening complete with
matching flanges, gaskets, bolts & nuts, and inspection door. The
capacity & other design features of air receiver shall confirm to IS
7938:1976.
2) Major parameters of air receiver shall be as follows:
Parameters Description
Type Vertical, self-supporting, cylindrical in
welded construction
Capacity Minimum capacity 2 m3 each
Operating Pressure To be decided based on discharge
pressure of Compressor
Nozzles and accessories Inlet & outlet connections with
of Air Receiver companion flanges, drain, vent, manhole,
safety plug, pressure gauge, lifting lug
etc. as per provisions of IS – 7938, 1976
Material of Construction IS2002 Gr–2A / SA 516 Gr70
Design, Manufacturing IS 2825: 1969/IS 7938 : 1976
Testing Code
3) Air receiver shall be provided with necessary pressure system
monitoring and control to achieve capacity regulation of the air
compressors. Provision of bypass valve and auto condensate trap is
optional as per requirement of the project
3.2.5 Piping, Valves & Fittings
3.2.5.1 General
1) The piping supplied shall include all piping required for the boiler
viz. main steam, auxiliary steam, feed water, condensate, drains,
vents etc. of the main principle thermal scheme and process steam
line and other ancillary systems of chemical injection, make-up
water, Compressed air and Instrument air, etc. Sizing shall be done
as per good engineering practice.
4) Thermal insulation
Weather proof insulation shall be applied to piping, valves, vessels, heat
exchanges etc. to keep the surface temperature to 55oC maximum after
completion of satisfactory hydraulic / pneumatic test. All insulating
material, fixing cladding and protection shall be new and best of their
quality. Insulation materials shall be non-corrosive to the surface
insulated, fire proof, free from asbestos, starch etc. The insulation
materials shall be machine made resin bonded mattresses confirming to
IS: 8183 1993.
The insulation materials shall be rockwool of density 120 kg/m3 with GI
binding wire as per IS: 9842, 1994 machine made resin bonded
mattresses confirming to IS: 8183, 1993. The amount of resin in the rock
DSP PAGE 3.24 CONTRACT NO..
INSTALLATION OF NEW GAS FIRED BOILER
wool shall be 1 to 3 by weight as may be required for ideal and
adequate bindings.
Dry insulation shall be applied on metal surface free from dirt, oil, loose
scale etc. The insulation joint shall be stitched with 22 SWG soft
galvanized iron wire. The mattresses shall be further secured with 20
SWG GI wires tied, circumferentially at interval of 250 mm.
The insulation shall be applied in multi layers with joints staggered
when thickness is more than 75 mm. 0.8 mm. Aluminum jacketing shall
be as per IS 737:2008 overlapped by minimum 50 mm. Longitudinal
joints shall be staggered & avoided on top of pipe.
12 mm wide stainless steel bands shall be placed circumferentially at
250 mm centres to prevent slipping.
Insulation applied on flanges, valves shall be done in two halves for
quick removal and fixing without damage to the insulation.
In case of multiplayer insulation, all longitudinal and circumferential
joints shall be staggered to avoid direct heat transfer paths.
Valves, fittings shall be insulated with removable lined covers. Covers
shall comprise of two sections from plain aluminium alloy sheeting 1.2
mm thick and lined with the same insulation materials and thickness as
adjacent pipes.
3.2.5.3 Technical Condition for Erection of Valves
Before erection of valves, contractor shall ensure that:
All grit and foreign materials are removed from the inside of the valves.
All machined faces are thoroughly cleaned and coated with a thin layer
of mineral grease before erection.
Installation of valve shall be carried out as per drawing. Clearance
between the top of stuffing box and underside of gland shall be uniform
on all the sides.
Gland shall not be tightened hard. Hemp packing shall be adequately
soaked in grease and shall not be allowed to remain dry (except valves
for oxygen service).
The valves shall be tightly closed when being installed, as this keeps the
valve rigid and prevents any foreign material from getting in between
the working parts of the valves.
While installing flanged valves, diametrically opposite nuts shall be
tightened slowly and proper care shall be taken to tighten them
alternately. The practice of fully tightening the nuts one after another is
not permitted.
DSP PAGE 3.25 CONTRACT NO..
INSTALLATION OF NEW GAS FIRED BOILER
After installation of the valves, the pipeline shall be flushed with water/
compressed air/ nitrogen, as the case may be, to remove any foreign
material that may be present in them. If any leak is detected at the
valve-seat, the same shall be examined and rectified by scrapping or
replacing wherever necessary.
All valves shall be operated a few times to check free movement and
operation of various limit switches/ inter locks.
3.2.5.4 Erection, Testing and Commissioning of Pipelines
All pipelines shall be laid by the Contractor as per detailed drawings and
instruction to be given by the Employer. The interfacing and joining of
the proposed pipeline with the existing pipeline/equipment /facility are
in the scope of work. Following technical condition apply for erection,
testing and commissioning of all pipe work:
1. Mitre fittings and shaped parts shall be fabricated from the pipes of
same specifications as that of pipes. All bends will be provided with
bend radius of 1.5d unless specified otherwise in detailed
engineering drawing.
2. Before erection, pipes, valves, fittings etc. shall be thoroughly cleaned
and scales, rust, dirt, oil, grease etc. shall be completely removed
from inside as well as outside. The Contractor shall provide all
cleaning materials required for this purpose.
3. Contacting surfaces of flanges shall be strictly perpendicular to pipes
and shaped parts axes. Insertion of gaskets of unusual thickness shall
not be allowed.
4. In case of pipes running horizontally, all the flanges and flanged
fittings, etc. shall be installed in such a way that top bolt holes are
displaced by half pitch from the vertical axis.
5. Flanges shall be fabricated from steel plates and shall be machined.
Un machined flanges shall not be used.
Rotary flanges shall freely rotate without any jamming and closely fit
with flange rings.
6. While laying several pipelines parallel to each other, flanged joints
shall be staggered suitably.
7. Gasket materials and dimensions shall conform to the instructions
given in the relevant working / erection drawings, unless specified
otherwise.
8. Slope of pipelines, drainage, vents, and arrangement of pipe-
connections for inlet and outlet of various services etc. shall be in
conformity with the drawings.
xxiii. Door Safety Landing doors shall prevent the lift from
starting unless they are fully shut. Once the
lift leaves a particular floor, that door cannot
be opened.
Electro mechanical Limit safety shall be
installed inside the cabin
xxiv. Cabin Control Designed with stainless steel switches for all
stations, Emergency Alarm, Light, Fan with auto
sleep arrangement, Emergency Stop Switch
with clock
xxv. Machine room size & As per IS & shall be at the top of the lift shaft
location
xxvi. Motor Squirrel Cage TEFC, VVVF Drive, Duty S4, 60%
CDF, 150 starts/hr, Insulation Class F
xxvii. Coupling & Shaft As per requirement
xxviii. Brake DCEM Shoe type
xxix. Gearbox As per requirement
xxx. Wire ropes As per requirement
xxxi. Guide Rail Heavy Duty Guide Rails are anchored on the
sidewalls with the help of guide brackets as per
site requirements. 2 Nos. Guide Rails each are
provided for the cabin
5. Cleaning
1) Cleaning before installation
Before installation, the pipe inside shall be chemically cleaned
form oil and grease, paint, rust-preventive oil, mill scale, etc.
2) Pickling
a) The foreign matter shall be removed by pickling, consisting of
processes such as pickling, rinsing, neutralization, rinsing and drying.
b) For pickling, dilute hydrochloric acid (20 % v/v) shall generally be
used. Pickling shall be conducted at high temperatures or room
temperature.
c) Neutralization shall be done using a caustic soda solution after
pickling and rinsing. Then, rinsing and drying by steam flushing or
the like shall be performed to prevent rusting.
3) Degreasing
a) Carbon tetrachloride (Ccl4) or equivalent shall be used as a
degreasing agent. Since carbon tetrachloride is toxic, it shall be
handled with great cane.
b) Drying shall be performed to remove all trace of degreasing agent.
c) The degreasing agent to be used shall be pure and clean.
d) Piping shall be subjected to dip cleaning and shall be checked for
complete degreasing.
e) Valves shall be subjected to dip cleaning for degreasing before
shipment and installation.
4) The cleaned pipes and valves shall be capped to prevent entry of
foreign matter. If they are to be left for along time after cleaning, they shall
be filled with nitrogen gas to prevent re-oxidation.
5) Cleaning after installation
3.3 UTILITIES
1) Design Conditions
The design consideration for dry pressurized ventilation system is as
follows:
2) Brief Specification
The dry pressurised system shall comprise of the following:
i) Centrifugal fan, floor mounted with motor
ii) Bird protection screen
iii) Air filter
iv) Over pressure gravity louvers
v) DOL starter
vi) Mounting structures
vii) Vibration isolator pads
viii) Power & control cables, conduit, etc.
a) Centrifugal Fan
The fan (s) shall be centrifugal single width with
radial/forward/back ward curved blades depending upon pressure
requirement. It shall be coupled to drive motor through Vee belt.
HP of drive motor shall be at least 15% higher than shaft BHP of
fan. The fan shall be statically and dynamically balanced at
different speed. The fan shall be fitted with self-aligning, self-
lubricated ball / roller bearings. Suitable vibration isolators shall be
provided at the fan pedestal. The centrifugal fan shall conform to
IS: 4894-1987/ BS: 848/ AMCA: 210. The fan shall be fitted with
variable inlet vanes for accurate control of air volume. To prevent
transmission of fan vibration, flexible canvas connection shall be
provided at the fan inlet and outlet.
b) Overpressure Gravity Louvers
The gravity type louvers shall be fabricated from 0.6 mm thick M.S.
sheet finished with two coats of primer and two coats of finished
DSP PAGE 3.52 CONTRACT NO..
INSTALLATION OF NEW GAS FIRED BOILER
paints matching to the interior decor. The number and location of
exhaust air grills shall be carefully decided considering room size,
air velocity and 2mm WG positive inside pressure, etc.
c) Grills and Diffusers
The grills and diffusers shall be fabricated from M.S. sheet of
thickness not less than 18G / 20G. All supply air grills shall be square
/ circular type with adjustable louvers, whereas return air grill shall
be fixed type
d) Duct for Ventilation System
Galvanized steel sheet (GSS) conforming to IS-277: 2003 (Class VIII)
with thickness: 0.63mm for sizes upto 750 mm and 0.8 mm for sizes
beyond that shall be considered. Velocity of air within the header
duct shall be restricted to 10 m/s. First 5m of supply air duct near
fan shall be acoustically insulated from inside with 12 mm thick
rigid board fiber glass wool covered with perforated aluminium
sheet / finished RP Tissue paper. If the duct is exposed to the
atmosphere then together with 50mm thick PUF thermal insulation
shall be provided
3.3.3 Exhaust Ventilation System
1) Design Conditions
The design consideration for exhaust ventilation system is as follows:
2) Brief Specification
The dry pressurised system shall comprise of the following:
i) Heavy duty industrial tube axial type wall mounted fan with motor
ii) Bird protection screen
iii) Panel type washable air filter
iv) DOL starter
v) Mounting structures
vi) Vibration isolator pads
vii) Power & control cables, conduit, etc.
a) Tube Axial Fan
The fan shall be heavy duty wall mounted type, suitable for
continuous operation, statically and dynamically balanced, single
stage, directly coupled with drive motor and shall be
manufactured, tested according to IS: 3588-1987. The drive motor
shall be suitable for operation in 415 V, 3 phase, 50 Hz, AC power
supply system. Head of the fans to be 15 mmWC (min). Fan
impeller shall be as per Cast Al Alloy, IS 617:1994 and shaft shall be
as per C-45 as per IS 1570 (Part-II)-1979 or equivalent. The fans shall
have rain protection cowls.
5) Test Requirements
3.4.12.3 Microprocessor based non communicable type release for PDB incomer
and bus coupler feeder and thermal magnetic release for outgoing
feeders shall be considered.
3.4.13 Technical Specifications of LT Motors
Sl. Specific aspects Technical features
No.
1. Type of motor Squirrel Cage Induction Motor (SCIM)
C Rotation 4 X 90 deg.
D Earthing stud Inside Terminal Block
E Miscellaneous - Shall be gasketed between the T.B.
halves.
- The conduit box shall be field
convertible to cast iron.
- External screws and bolts shall be
plated to resist corrosion.
5.0 Cooling - TEFC, Effective bi-directional (forced
cooling fan mounted on the non-drive
DSP PAGE 3.105 CONTRACT NO..
INSTALLATION OF NEW GAS FIRED BOILER
end (NDE) of the rotor shaft)
- Thermistors shall be provided in the
windings.
6.0 Quality of operation
A Vibration intensity - Shall be limited as per IS 12075-1986.
B Noise level As per IS: 12065-1987
7.0 Electrical design
A Power Supply 415 V +10 & - 15%, 50 Hz +/- 6%, 4-wire
AC, 50 kA for 1 second, solidly earthed.
B Starting Variable Frequency Drive
C Service factor - 1.0 for VFD power .
- 1.15 for sine wave power .
D Peak transient 1600 V
voltage
E Minimum rise time 0.1 microsecond
F Starting Torque 200 % rated torque for 1 minute below
base speed
G Constant hp 1.5 times base speed.
operation
H Duty Application dependent
I Max speed 150 % rated for 2 minutes
permissible
J Derating for VFD As per above mentioned standard
K Insulation Class H limited to class F.
L Load Type Constant torque / variable torque
(As per application)
M Space Heater - Outdoor motors above 45 kW
- Indoor motor above 110 kW
N No. of Poles 4/6/8
8.0 Operating Characteristics
A Operation with Motors shall operate successfully under
variation in the running conditions at rated load with
PLC memory module Static RAM shall be minimum 16 MB. CPU memory
loading shall not exceed 60% of rated capacity. No
extended memory shall be used for USER program
other than CPU inbuilt Memory.
Input/ output I/O cards shall be rack mounted type with card
modules level diagnostic features
Interrogation voltage 24 V DC
Output voltage 24 V DC
A/I cards 8/16 channel isolated type / 2 wire differential, 4-
20 mA
3.5.3.6 Thermocouples
Conductivity Sensor
Temperature Sensor
Resolution 0.1 °C / °F
Sensor PT100
Alarm Functions
Display
Electromagnetic
Compliance (EMC)
DSP PAGE 3.154 CONTRACT NO..
INSTALLATION OF NEW GAS FIRED BOILER
Specifications
Immunity to EN 61 326
Interference
Environmental
Conditions
Ambient temperature 0 to 40 °C
operating range
Power Supply
Pollution Degree 2
Transient Overvoltage II
category
Enclosure
pH Sensor
pH Range 2.00 to 12.00 pH
Resolution & Accuracy 0.01 pH & ± 0.01 pH
mV Range 0 to 100% or -1000 to 1000 mV
Resolution & Accuracy 0.1% or 1 mV / ± 1 mV
Temperature -9.9 to 125 oC (15.0 to 257.0 oF)
Resolution & Accuracy 0.1 & ± 0.5 oC (± 1.0 oF)
Sensor Pt 100
Temperature Automatic (± 10 oC / ± 18 oF offset adjustment) /
Compensation Manual
Set-point And
Controller Functions
Function Limit / Proportional Control / Proportional Integral
(Pulse Length or Pulse Frequency)
Integral time 999.9 minutes
Pickup / Dropout 0 to 1999 seconds
Delay
Wash Cycle (If 0.1 to 199.9 hours
required-optional)
Wash Duration (If 1 to 1999 seconds
required-optional)
Switching pH 0.1 to 1 pH
Hysteresis
Switching ORP 1 to 10.0 % / 10 to 100 mV
Hysteresis
Contact Outputs, 1 SPDT; 3 SPST relays
Controller
Switching Max 250 VAC / Max 3A / Max 600 VA
Voltage/Current/Power
Alarm Functions
Function (switchable) Latching / pulse
Pickup delay 0 to 1999 seconds
Switching Max 250 VAC / Max 3A / Max 600 VA
Voltage/Current/Power
Load Max.600 Ω
pH / ORP Input BNC (1012 Impedance)
Connection terminal (1 x 3-pin; 1 x 9-pin & 1 x 19-pin terminal blocks)
Main fuse 250 mA, anti-surge
Enclosure
Dimensions Panel Mount
Insulation IP 54 (front) , IP 40 (housing)
Type Direct
Mounting On line (Local)
Dial size 150 mm
Case Cast Aluminium
Blowout protection Required
Moving parts matl. SS 316
Accuracy + 2%
PROCESS CONNECTION 1/2 " BSPT(M)
3.5.3.22 R.F.Earthing
1. The R.F. earthing system shall conform to I.E. rules and latest
revision of relevant Indian Standards.
2. Minimum two separate grounding stations each comprising of two
earth pits at minimum distance of 3 meters shall be provided.
Earthing resistance of the pit should not be more than 0.5 ohms.
3. A continuous copper bus (size 25 mm x 3 mm) shall be provided as
logical earth grid. Whenever needed the earth bus should be
converted to a net of buses as per requirement. The safety ground
and the signal bus should never be connected together inside the
control room.
4. The metal frames or enclosures of each electrical equipment shall
be connected firmly to the safety ground at the nearest point, The
connection should be protected such that it does not loose the
bond by vibration or personnel movement.
5. The logic ground bus shall run near each panel / equipment and
shall be connected to logic ground of each equipment with
smallest length of wire as possible.
3.5.3.23 General
1. The equipment shall conform to the safety requirements of IS
8495-1987 – specification for electrical instruments for hazardous
atmospheres, IS-9858-1992 – Safety requirements for electronic
measuring apparatus etc. Wherever Indian Standards do not exist,
ISA, IEEE or NEEMA Standards or the ones laid down hereafter be
followed. Devices should be intrinsically safe.
2. All instrumentation power supply system shall be through isolation
transformers and system voltage shall be 220 V +/- 5%, 50 Hz.
Instrumentation system working on unified current signal of 4 – 20
mA DC only shall be used.
3. The control electronics chassis shall be of 19 inch frame
construction and shall be provided for housing various electronic
plug-in modules used for signal detection, conditioning,
processing etc. The construction shall be modular and shall
3.5.6.2 50 pair jelly filled armoured telephone cable (approx. 700 m) shall be
laid to SMS substation from BF office and 20 pair jelly filled armoured
telephone cable (approx. 150 m) shall be laid from SMS substation to
the new gas fired boiler respectively.
3.5.6.3 All the telephone cable between JBs inside the boiler area shall be 5/10
pair armoured cable.
3.5.6.4 Short length cables shall be unarmoured PVC type and should be laid
through GI (outside) / PVC (inside) conduit.
3.5.6.5 CLI Push Button telephones with 2-pin rossete box shall be provided as
per requirement.
3.5.6.6 All the telephone JBs in the boiler area shall be of 10/20/50/100 pairs.
3.5.6.7 Standard push button telephone sets shall be supplied and installed at
subscriber end.
3.5.6.8 Push button telephone
Type CLI (Name and telephone
number shall be displayed)
FSK/DTMF Compatibility Both Required
Name/ Phone Book 10 Numbers With
Names(Minimum)
Incoming Calls Memory 10(Minimum)
Outgoing Calls memory 10 (Minimum
Display 16 Digit LCD Display With
Backlight
3.5.7 PA System
3.5.7.1 Analogue type Loudspeaker talk back system shall be provided for
facilitating reliable two-way intercommunication between various
strategic points of the plant complex. The subscriber stations shall be
provided at locations having very high ambient noise level. The PA
system shall be of digital type comprising of the following:-
1) Programmable type digital master control station – 1no
2) Wall mounted outdoor handset station (weather proof) with
numeric key pad in die cast aluminium alloy body – 6 nos
3) Desk top / wall mounted hand set station in die cast aluminium
alloy body along with speaker and numeric key pad for control
room – 1 no
4) Industrial horn type speaker – 6 nos
5) UPS and battery backup for 4 hours
Electrical
Maximum Power 15W
Rated Power 10W
Sound Pressure level
at 10 W / 1 W ( 1 KHz 118.6 dB / 106.6 dB (SPL)
3.5.7.9 S at 1m)
t Effective frequency
400 Hz - 4 kHz
a range (-10 dB)
t Opening Angle at 1
150° / 32°
i KHz / 4 KHz (-6 dB)
oRated Voltage 100 V
n Rated impedance 1000 ohm
Environmental
J Operating
u temperature -25 ºC to +55 ºC
n Storage temperature -40 ºC to +70 ºC
c
tion Box
Material of Body Pressure Die Cast Aluminium Alloy
Material of Glands Galvanized Iron (G.I.)
Terminals 6X Elmax Connector for up to 5mm Mains Cable
3.5.7.10 Speaker JB
Material of Body Pressure Die Cast Aluminum Alloy
Material of Glands Galvanized Iron (G.I.)
Terminals 4 X TB10 Rapid make barrier type terminals
No. of Glands 3
Insulation resistance
between Terminal & 500 m OHMS
body
HV Test 1.5KV for 1 min
IP Protection IP 55
Voltage 230VAC
Power Consumption 80 Watts
Temperature Range 200-450 Deg C
3.6 STRUCTURAL
3.6.1 Design parameters
The steel structures envisaged here shall be designed as per IS: 800-
1984, IS: 11592-2011 and for chimney IS: 6533-1989 Superimposed
loads shall be considered in accordance with IS: 875-1987 in addition to
technological loads from equipment as supplied by equipment
manufacturer. The design shall take into account all dynamic loading
DSP PAGE 3.186 CONTRACT NO..
INSTALLATION OF NEW GAS FIRED BOILER
effects in vertical, lateral and longitudinal directions apart from dead
and superimposed loads from dynamic equipment. Structures shall be
designed either for wind or seismic loads whichever produces worse
effect. Wind load on structures shall be considered as per IS: 875-1987
whereas seismic loads shall be taken as per IS: 1893-2002. Structural
steel work shall be of welded construction as far as possible. Necessary
provision in the design shall be kept for temporary loads, which are
expected during erection and maintenance of equipment.
Design drawings of structures prepared by the contractor shall contain:-
Dimension
Level
Plan and sectional views showing general arrangement of
structures
Member sizes
Member forces
Complete base plate details including welding detail
Nature and type of connection details of beams, girders, bracings
etc. showing weld details (type, size, length etc.), gusset plate /
face plate thickness etc. Connection detail shall be shown for all
major members
Bolt hole details (number, diameter, dimension etc.)
Quantity of structural steel involved etc.
For all major structural columns, base shear shall be transferred to the
foundation by shear keys only and not through foundation bolts.
Tension in column member shall be transferred to foundation by
foundation bolts.
Steel structural design drawing shall have all necessary information
required for preparing fabrication drawings. Necessary attention shall
be given while preparing fabrication detail such that it facilitates both
fabrication and erection work.
Design calculation shall contain manual load calculation aided by
diagrams if necessary, and diagram showing applied loads on
structures.
Analysis and design of structures may be carried out using STAAD PRO
software.
3.7.20.12 Waterproofing
1) Work Included
The Contractor shall furnish materials, labour, plant, equipment and
tools to complete the work as specified.
2) Waterproofing of roof surface
On roof top 4mm thick Atactic Polypropylene modified
DSP PAGE 3.220 CONTRACT NO..
INSTALLATION OF NEW GAS FIRED BOILER
plastomeric bitumen based membrane with glass fiber
reinforcement (minimum 50gsm), finished on both sides with a
thermo fusible high molecular high density polyethylene (HDPE) film
and mineral finished on top surface (MOPLY FP MINERAL 4mm of
TEXSA INDIA Ltd. Or equivalent) Laying of the membranes shall be
done by manufacturer’s authorized applicators only. The cost
includes cleaning of the roof surfaces and filling of the joints, micro-
leveling, cutting & filling of chases in brick wall / RCC for termination
of membrane on vertical faces and necessary overlaps of the
membranes at the joint as per manufacturer specifications. Care shall
be taken for waterproofing in drain mouth and in gutter
Implementation Schedule
(Duration in months)
S.No. Activities 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19
1 Effective date of Contract
2 Preparation, Submission & approval of Basic
Engg. drawings
3 Preparation, Submission & approval of
Detail Engg. drawings
4 Manufacture & Supply of Equipment
5 Civil & Structural works
6 Erection/installation of equipment
7 Shutdown *
8 Testing & commissioning
* Required for interconnection jobs, to match with planned OPP shutdown
LIST OF EXCLUSIONS
NIL Exclusions
LIST OF DEVIATIONS
NIL Deviations
Contractor shall recommend and tabulate below the list of additional spare parts
for two years trouble free operation. Additional sheet of like format may be used if
necessary.
This list of critical operational & maintenance spares shall be finalised during
offer evaluation stage. Supply of all finalised list of spares is included in
scope of Contractor.
For electrical items, contractor shall refer the relevant clause in chapter 2.
Contractor shall tabulate below item wise the list of commissioning spares
necessary for the equipment bided. Additional sheet of like format may be used if
necessary.