The given table shows the Scope of the PEB contractor and also the battery limits between

the PEB with


other

Sl.no. Description of work PEB CIVIL others Remarks

1 Preparation of GA and yes - - Fabrication of structure to be started


shop drawings based on only after approval of GA drawings
the Architectural drawings by the consultants.
issued by consultants.

2 Providing column reaction yes - - Reaction to be submitted within 7


and required inputs for days from the date of LOI
foundation designing
purpose

3. Supply and fixing of yes yes Anchor bolts/templates, shall be


Anchor bolts supplied by the PEB contractor and
fixing to be done by the civil vendor.
PEB contractor has to coordinate
with the civil agency while fixing the
bolts to maintain line level of bolts
with in the tolerance limits and
jointly signed by both the agencies.
Concreting of the pedestal shall be
done in presence of PEB contractor.
Post pour sign-off and post final
setting time sign off to be done by
PEB contractor.

4. Supply and Erection of PEB yes - - A programme schedule has to be


structures prepared in consultation with Client/
PMC/Architects and coordinate with
the civil vendor to achieve the
targets. A front release schedule by
PEB contractor to civil contractor to
be agreed between PEB
contractors/Civil contractor and
client/PMC

5 Gable side RCC columns - yes RCC columns at Gable side shall be
provided by the civil vendor and the
PEB contractor has to give the
priority schedule to civil contractor
building wise.
Sl.no. Description of work PEB CIVIL others Remarks

6 Supply and erection of yes - - PEB contractor to coordinate with


Roof sheeting and wall Civil contractor well in advance for
Cladding sheets. locations, space requirement for
profile machine set up and agreed to
both. Client/Architect/PMC in no
way responsible for space allocation.
Similarly PEB contractor to
coordinate with Civil contractor and
both should be agreed in advance for
requirement of level ground,
sufficient space for roofing and
cladding, if any.
Architect/PMC/Client in no way held
responsible for delay in work due to
delay in preparatory work at
whatsoever reason.

7 Supply and fixing of Ridge yes


vents

8 Necessary framed yes Where ever necessary PEB


openings for windows, contractor has to provide the framed
doors, rolling shutters, openings for fixing of Windows
ventilators etc. if any as ,Doors ,Rolling shutters etc.( Supply
applicable. and fixing of Windows, Doors,
Rolling Shutters in the scope of
civil/other agency.)
.

9 Supply and fixing of yes Necessary closures, trims, flashings


necessary closures, trims, etc. to be provided around all PEB
flashings etc. openings, junction of masonry & PEB
and wherever required in the
opinion of the client To ensure water
tightness.

Painting for steel columns yes


10 and other steel members. Shot blasting & Two coats of
& approved suitable primer as directed
by the paint manufacturer and two
coats of 35 micron enamel paint to
Sl.no. Description of work PEB CIVIL others Remarks

Fire retardant paint where be applied at factory and Touch-up


ever necessary , if paint will be applied at site to correct
applicable. the damage occurred to paint film
during the transportation and
erection .
For fabricated staircases & Where
ever necessary fire retardant paint
to be applied as per the
requirement.

11 Closing around the PEB yes Closing of PEB columns will be in the
columns scope of civil /others.

12 Coordination with yes - yes PEB and Electrical vendor to


electrical vendor to fix coordinate with each other’s to fix
lightening arrestors. the lightening arrestors in the roof.
PEB contractor has to send the basic
drawings to electrical vendors to do
the preliminary activities to fix the
lightening arrestors by the electrical
contractor.

14 Co-ordination with MEP Yes PEB contractor has to ensure that


vendors the support structures for MEP
services are installed before
covering the PEB structure (Rafters
and Purlins). It is the prime
responsibility of the PEB contractor
to make necessary openings/ holes
in the PEB sheet and liner panel
wherever required. The cost for
making holes/ openings and making
them good to the satisfaction of the
client to be part of the quoted rates.
Sl.no. Description of work PEB CIVIL others Remarks

15 Providing fall protection yes - - PEB contractor has to tie up with the
system devices specialised agency in this area for
providing safety system to access
the roof.

16 Ensure water tightness of yes - - It is necessary to provide the


structure structure leak proof from any part of
the building. PEB contractor has to
take utmost care to ensure this. PEB
contractor to provide life time
guarantee/warranty.

17 Warranties/ Guarantees yes Life time warranties/ guarantees to


be provided for structural stability
duly certified by competent
authorities, water tightness,
weather proofing, colour coating of
sheets etc.

18 Response time from PEB yes PEB contractor has to attend to any
contractor during defect kind of rectification works required
Liability Period and in his scope of work within 10-15
beyond (Life time days after getting the information
warranty) from the Owner’s representative
upto DLP period and beyond (Life
time warranty)