Professional Documents
Culture Documents
SECTION 02066 Road Work Spec
SECTION 02066 Road Work Spec
ASPHALTIC CONCRETE
1 PART 1 – GENERAL
1.1 SCOPE
A. The work covered by this section includes asphaltic concrete courses, and bitumen
coatings of the flexible pavements as indicated on the Drawings or as specified herein.
B. Where constructions of culverts, pipelines or other works are below existing roadways
complete reinstatement of the roadway is required to the original construction and
condition unless specified otherwise.
American Society for Testing and Materials (ASTM): ASTM D 6114 and as
appropriate.
TECHNICAL SPECIFICATIONS
1.4 QUALITY CONTROL
A. Complete details of the Contractor's procedures and manpower for inspection, testing
and measurement of all the work as specified herein shall be incorporated in the
approved Quality Control Program, given with the Method Statement to be submitted at
least 30 days before start of pavement construction work.
B. Previously laid pavement layers shall be approved by the Owner before such layers are
overspread. The approval shall be withheld until the Contractor's quality control reports
substantiate compliance by conclusive inspection reports, test results, survey records
and recommendations which are acceptable to the Owner.
C. The Quality Control Program shall commit the Contractor to effective control of
suppliers (vendors) by the actions taken on its inspection and reporting and from its
testing and charting the results. The only testing acceptable as part of the Contractor's
Quality Control Program shall be that conducted on its behalf by its approved materials
testing laboratory or as otherwise approved by the Owner.
D. The delivery and Contractor's acceptance of materials shall require fulltime attendance
on site of an approved Inspector from the Contractor's Quality Control Team. The
Contractor shall maintain records of each delivery of mixed material relating time,
temperature and location of placement within the area being constructed.
E. The laying and rolling operations shall be attended by the same Inspectors who are
responsible for the Contractor's acceptance of material at the site. The inspection team
shall also include the Contractor's surveyors who shall make frequent checks on vertical
control performance, which shall be made in time to modify screed control and
compaction techniques. This is particularly important where a pavement layer is
proposed for use as a datum from which to operate an "automatic levelling device" to
span hollows and lengthen humps by ramp action.
F. The survey record shall show deviations in millimetres from the required grade at 10
metre intervals longitudinally and 2 metre intervals transversely. For junctions and
intersections and non-road paved areas, the survey grid pattern shall be at 5 metre
centres in both directions. The survey shall be representative and shall be cover at least
5% of the area to be paved and as proposed by the Contractor, to attain the specified
requirements for ride quality and to provide the specified surface drainage.
TECHNICAL SPECIFICATIONS
G. Compaction control by the Contractor shall include inspection of the compaction
equipment and its operation, measurement and recording of laying temperatures and
the study of voids from cores taken from each asphalt layer between 24 and 48 hours
after completion of finish rolling. All inspection reports and analysis of test results shall
be included in the regular weekly quality control reports as prepared by the Contractor
and submitted to the Owner.
H. The frequency of sampling and testing shall be in accordance with the approved Quality
Control Program and as additionally deemed necessary by the Owner as the work
progresses. The area of asphalt layer or volume of material represented by each
sample shall be as stated in the Quality Control Program and as further determined at
the time of sampling. The entire volume of work as measured for payment shall be
represented by inspection reports, temperature records, mix analysis and field
density/voids/thickness determination shall be submitted, after being evaluated by the
Contractor, to the Owner.
1.5 SUBMITTALS
A. All submittals shall be summarised by the Contractor, on a cover sheet which shall
compare what is being proposed or has been achieved, directly with the specified
requirements such that compliance or exceptions are clearly stated.
B. At least 30 days prior to commencing any of the operations, involved for laying the
asphaltic concrete surface courses, the Contractor shall submit for the Owner's
information and approval the items described in the following clauses:
1. Method Statement:
a. This will include the Contractors proposals for execution of the works to
meet the requirements given on the Drawings and/or in the Specification.
b. A Program showing the sequence of operations and areas of works.
c. Level of supervision to be exercised.
d. Full details of the plant and equipment to be used in each phase of the
works.
e. Record sheets defining the areas of the works, with the sequence of
operation, confirmation of compliance with Specification of each stage of
the Permanent Works with its acceptance by the Owner.
TECHNICAL SPECIFICATIONS
2. The Quality Control Program as described in 1.04 above
3. Materials Report: The materials report shall include but not be limited to:
a. Details of the proposed suppliers and or sources of all ingredients for
making the asphalt mixtures
b. Details of the suppliers independent testing Program and evidence of
consistency in the quality of the products to be supplied.
c. Testing Laboratory Reports: Submit two (2) copies of laboratory test reports
for tests performed in the process of mix design and of core samples taken
after laying.
4. Proposals and permits and I or approvals from the Owner and the relevant
authorities for diversion and control of traffic.
2 PART 2 – PRODUCTS
2.1 MATERIALS
Property
Test Unit
Requirement
D36 0.1 mm
• Penetration
60/70
D92 ºC
• Flash point, minimum
232
D2398 ºC
• Softening point (ring & ball)
46/56
D113 cm
• Ductility, minimum, 250C
100
D2042 %
• Solubility (trichloroethylene)
99
TECHNICAL SPECIFICATIONS
D2415 %
• Ash content by wt maximum
1.0
D1754 %
• Thin film oven test loss on
heating
0.8
D36 %
• Penetration of residue
of 1 above 50
D113 Cm
• Ductility of residue, 25 deg. C.
60
T102 %
• Spot test ASSHTO
35
Property
Test Unit
Requirement
• Grade D2027 -
MC70
TECHNICAL SPECIFICATIONS
• Distillate at 316°C D402 % by vol
80-95
Property
Test Unit
Requirement
Property
Test Unit
Requirement
• Grade D2027 -
TECHNICAL SPECIFICATIONS
MC250
distillation at 360ºC
TECHNICAL SPECIFICATIONS
• Rate of application - l/m2
0.25-0.45
Property
Test Unit
Requirement
E. The grading of the aggregates shall be within and approximately parallel to the following
envelopes:
TECHNICAL SPECIFICATIONS
(mm) Base Course Wearing Course
37.5 - -
28 100 -
20 75-90 -
14 65-80 100
10 55-70 75-90
5 39-50 54-64
F. Filler shall be material smaller than 0.075 mm derived from the coarse and fine
aggregates, or milled limestone smaller than 0.075 mm, hydrated lime (max 2% ), or
Portland cement or a mixture of these materials. If a mixture of fine material from the
aggregates and either cement or milled limestone is used, the proportions shall be such
that the bulk density in toluene of the filler is between 0.5 and 0.9 grams per millilitre
when measured as described in BS 812. Control testing shall be made daily. The
grading of the combined aggregates and filler shall be within the limits stated in the
previous paragraph.
H. Asphalt-Rubber binder
Shall be a blend of asphalt cement, granulated reclaimed tire rubber and additives, with
a minimum rubber proportion of 20% by weight of the total blend, leading to an increase
viscosity and a higher resistance under hot desert environment, as defined by ASTM
D8.
TECHNICAL SPECIFICATIONS
• Specific gravity of 1.15 ± 0.05.
• No visible nonferrous metal particles.
• Less than 0.75% moisture and free flowing.
• No more than 0.01% ferrous metal particles by weight.
• For hot mix binder applications, fiber content shall not exceed 0.5% by weight.
Requirement Type
Property
1 2 3
Rotational Viscosity
1.5-4.0 1.5-4.0 1.5-4.0
177 °C, Pascal seconds
Penetration
4 °C, 200 g, 60 seconds (ASTM D5), 10 15 25
min
Requirement Type
Property
1 2 3
Softening Point
AASHTO t-53 or ASTM D36 57 54 52
(°C, min)
Resilence
25 °C (ASTM D5329) 30 25 15
(%, min)
Samples shall be tested for conformance with the mix design gradation in accordance
with the requirements of AASHTO T27 or C136.
The chemical composition of the ground tire rubber shall be determined in accordance
with ASTM D297 and shall meet the following requirements:
• Acetone Extract: Maximum 25%
• Rubber Hydrocarbon Content: 40 to 55%
• Ash Content: Maximum 8%
• Carbon Black Content: 20 to 40%
• Natural Rubber: 16 to 45%
TECHNICAL SPECIFICATIONS
2.2 MIX DESIGN
A. At least thirty (30) days prior to the date the Contractor intends to begin production of a
plant mix for Asphaltic Concrete; the Contractor shall make a written request for the
approval of his job-mix formula from the Owner.
B. The particle size grading of the combined aggregates and filler shall be a smooth curve
within and approximately parallel to the grading envelopes given in 2.01 D.
C. The job mixes for asphaltic concrete shall conform with the requirements for Marshal!
Stability and Flow and voids contents.
D. The Contractor shall carry out Marshal! Tests on laboratory mixes within the aggregate
grading given. Tests shall be carried out with at least 5 bitumen contents within the
following range:
The results shall be submitted to the Owner for acceptance with full details of the
proposed aggregate gradings and bitumen and filler contents to be used in the site
trials.
TECHNICAL SPECIFICATIONS
total mix
F. Full scale site trials shall be carried out using the plant and methods of construction and
the full range of aggregate gradings and layer thickness proposed for use in the Works
with the bitumen content agreed by the Owner after the laboratory tests.
G. The results of the tests on the trial areas shall be submitted to the Owner with proposals
for the Job Mix Formula which taking into account the tolerances allowed during the
mixing of the materials will ensure that Specification requirements are met. The Owner
will then either accept these proposals or give instructions for further tests which the
Contractor shall carry out. The aggregate grading envelopes and the bitumen contents
approved or instructed by the Owner shall constitute the Job Mix Formula for each
asphaltic concrete mix.
H. The Contractor shall determine a Job Mix density for each Job Mix Formula. The Job
Mix density shall be the average density of six Marshals! Specimens compacted by the
specified number of blows, in which none of the six results differs from the average by
more than 1.5%.
I. The mix design shall be controlled by the Marshal! Stability results of the tests as
scheduled below. If the mean of the results does not exceed the minimum given by a
margin of 2.33 times the standard deviation of the latest 30 stability results for a
particular mix the Contractor shall remove and replace the defective material.
Material
Sampling Property Test Standard Unit Requirement
Point
Filter in Toulene
TECHNICAL SPECIFICATIONS
Bitumen Temperature - ºC 150 – 170
On entry to
mixer
Concrete grading
of spreader
Laboratory ASTM
Marshall test D1559
Temperature - ºC 120
after laying
prior to
rolling
Layer Thickness As
specified
Levels As
specified
TECHNICAL SPECIFICATIONS
3 PART 3 – EXECUTION
NOT USED
END OF SECTION
TECHNICAL SPECIFICATIONS