alfanar Projects Standard Operating Procedures Ref.

No : ALF-PRJ-EC-QC-CHK-0004

Issue : 00 Rev. No : 00
Water Proofing Works - Preparation Phase
Issueing Date : 2023-08-07

Project

Ref No Date

RFI No ITP No

Location Specification

Contractor Sub Contractor

Client Consultant

Inspection Item Refrence Commplied Not Commplied Not Applicable Comments

1. Assessment

PTS / IFC Drawing


1.2. Are potential sources of water infiltration and vulnerable leak points
UBC / TES-P-119-
identified during this assessment?
19-R0

2. Surface Preparation

PTS / IFC Drawing


2.1. Are existing cracks, voids, or damaged areas addressed and repaired as
UBC / TES-P-119-
part of the preparatory steps?
19-R0

PTS / IFC Drawing


2.2. Is the surface meticulously cleaned, eliminating dirt, dust, grease, and
UBC / TES-P-119-
loose particles before progressing?
19-R0

3. Material Selection

PTS / IFC Drawing


3.1. Are the selected waterproofing materials appropriate for the project's
UBC / TES-P-119-
specific demands?
19-R0

PTS / IFC Drawing


3.2. Are the chosen materials evaluated for compatibility with the substrate
UBC / TES-P-119-
and the environmental conditions on-site?
19-R0

4. Safety Measures

PTS / IFC Drawing


4.1. Is adequate ventilation in place to ensure worker safety during material
UBC / TES-P-119-
application?
19-R0

PTS / IFC Drawing


4.2. Have workers been supplied with proper personal protective equipment
UBC / TES-P-119-
(PPE) for their safety while handling and applying waterproofing substances?
19-R0

Notes

Prepared By Reviewed By Approved By

Signature

Name

Date