Bid Bulletin Project Identification No. 2023-009

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 6

MEZ BIDS AND AWARDS COMMITTEE

Tel. No. 340-0593; www.peza.gov.ph; mez-bac@peza.gov.ph;


mezbac@peza.gov.ph

BID BULLETIN for Project No. PEZA MEZ 2023-009

27 October 2023

Notice is hereby given to all prospective bidders for the project, Supply, Delivery
and Installation of Air Conditioning Units at MEZ Ground Floor Receiving
Area (Re-bidding):

That attached Lay-out Plan, Revised Technical Specifications and


Clarifications on Questions raised during the Pre-bid Conference be part of
the PBD.

This Bid Bulletin is issued this 27 October 2023, for guidance and information of
all concerned.

Very truly yours,

MR. ARNEL M. SUYU


MEZ BAC Chairperson
Project: Supply, Delivery and Installation of Air Conditioning Units at MEZ Ground Floor Receiving Area
Subject: Revised Technical Specifications
Date: Oct. 27, 2023

Annex "B"
Technical Specifications

Statement of
Compliance
Item
Qty Specifications (State whether
No.
"Comply" or "Not
Comply")
5 brand new Split-type Floor Mounted Air
Conditioning units

*Rated Cooling Capacity: 36,000 Btu/hr


*Power Supply: 220V-60Hz- Single Phase
*Refrigerant: R32 or R410A
*Inverter technology

*Warranty 1 year on parts & labor, and at


least 5 years on compressor.
*1 year quarterly preventive maintenance and
troubleshooting, as necessary.
***submit brochure and/or Cert. of
Manufacturer as proof of compliance and
1 1 lot
Warranty Certification from the bidder.

Note: AC unit drain lines and insulated


refrigerant lines are exposed.
Electrical scope: Supply(Labor and
Materials) and Installation of the feeder wire
from MDP down to sub panel board,ECB for
each 4 unit condenser. Including ECB
(Enclosure Circuit breaker ) NEMA 3R per 5
units Brand New Split type floor Mounted Air
Conditioning unit. For 1 unit New Split type
floor Mounted ACU installed at EAD, Power
supply comes from the spare ciruit breaker at
FSD Panel down to the ECB located at
condensing area.
Panel boards, wires, ECB and accessories
are supplied by the SUPPLIER /
CONTRACTOR.

The SUPPLIER/CONTRACTOR must have a


Manufacturer’s Certification indicating the
following:

-authorized to distribute / resell / deal the


certain product being offered.
- authorized to install and to troubleshoot,
with well-verse technicality.
The SUPPLIER/CONTRACTOR must have a
technical office, within Cebu Province, that
can provide immediate response within 72
hours for troubleshooting and regular
precautionary maintenance.
***submit business permit of the
Technical office as proof of compliance.

Duration : Within 60 Calendar Days from the


issuance date of Notice to Proceed.

*Refer to Mechanical & Electrical Plans


provided for addl technical specifications &
details.

note: Bidders should specify the exact brand


and models of the units that they offer.

AUTHORIZED SIGNATORY:

_______________________________

(Signature over Printed Name)

DATE: _________________________________
Clarifications on Questios raised during the Pre Bid
Conference on 27 October 2023:
Questions Answer
1. Is there a need of Electrical Engineer for wire sizing? PEZA Electrical Engr provided the sizing computation of wires.
See electrical layout plan.
2. Is it ok to submit a photocopy of the brochure but CTC? Yes, need be CTC.

3. Is the drain line exposed? Yes, it is exposed.


4. From MDP to sub panel, 1P or 3P? MDP to sub panel is 3P.
5.Sub panel to Distribution? Yes, 1P.
6. Scope of work for electrical? Yes, see revised technical specification.
7. Manufacturing Certificate with statement of omission of " nationwide".
nationwide?
8. Power supply to panel board to service breaker. See revised technical specification.
9. Electrical scope on condenser unit is included in the See revised technical specification.
scope?
10. Specification of circuit breaker and MCCB? See revised technical specification.
11. 3 phase to Single phase Single phase 5 new Split Floor Mounted ACU
12. Power Supply including electrical supply Supply labor and installation of materials for Electrical
scope