Download as pdf or txt
Download as pdf or txt
You are on page 1of 13

Work Inspection Request

RSG-CN-FRM-0004

AMAALA
General Information
Program Name Wellness Core Project Code 1TB03300 Project Name TB-Wellness Core Wide
Contract ref. 300C04 Package Mechanical
1TB03300-300C04-
WIR No. Version 2 Date 10-August-23
STC-WIR-ME-0014
Required Date Required Time of
11-August-23 11:00 AM
of Inspection Inspection

Inspection Details
Works to be Inspected Installation of HDPE, SDR11 Pipe for Irrigation Network

Approved Drawing Ref. ---------

Approved Method Statement Ref. 1TB03300-300C04-STC-MTS-IR-0001

Approved ITP Ref. 1TB03300-300C04-STC-ITP-ME-0008

Discipline Mechanical Type of Work Infrastructure

Building / Location ACCESSWAY - H Construction Zone “H”

Level / Floor As Per attachment Cluster

Grid / Chainage / Pile no. BOQ Element


☒ Mark up drawing for inspection element
☐ Approved Shop drawing
☒ Approved MIR Copies
Attachments
☒ ITP
☒ Photos of the Works to be inspected
☒ Any other (list here)

Contractor Site Engineer Recommendation


Ready for QA/QC Engineer’s Inspection and/or Testing: ☒ Yes ☐ No

Mahmood Syed 10-August-23


Name Signature Date

QA/QC Engineer
Comments

Recommendation
Ready for Supervision Consultant’s/Client Inspection and/or Testing: ☒ Yes ☐ No

Muhammad Abid (QC MEP) 10-August-23


Name Signature Date
We confirm that Work to be inspected has been coordinated with all related other package Contactor’s and is in compliance with approved drawings and
specifications.

RSG-CN-FRM-0004
Rev. 00, 16 Nov 2022 Page 1 of 3
Work Inspection Request
RSG-CN-FRM-0004

Contractor Authorized Signatory

Eng Subhi Al Saadi


Name Signature Date

Supervision Consultant/Client
Inspection Comments

REF ER T O T H E C OMMENT S

Actual Date of Inspection Click to enter a date. Actual Time of Inspection

Approval

☐ Accepted ☐ Accepted with Comments ☐ Revise and resubmit

☐ Rejected

1 6 .0 8 .2 3
EMERSON
Inspector Name Signature Date

Resident Engineer Name Signature Date

Attachments
1. Red Line Markup Drawings (for accepted or accepted with comments inspections only)
2. Photos (For Revise and resubmit or Rejected inspections only, showing incomplete or incorrect works)

RSG-CN-FRM-0004
Rev. 00, 16 Nov 2022 Page 2 of 3
Work Inspection Request
RSG-CN-FRM-0004

Annexure
Contractors Clearances (No Objection)

Package Comments Signature Date

Package 01 Date

Package 02 Date

Package 03 Date

Package 04 Date

Package 05 Date

Package 06 Date

Package 07 Date

Package 08 Date

Package 09 Date

Package 10 Date

RSG-CN-FRM-0004
Rev. 00, 16 Nov 2022 Page 3 of 3
THE CONTRACTOR THE OWNER THE ENGINEER

AMAALA WELLNESS CORE


SECONDARY INFRASTRUCTURE

QA/QC Check list for Installation of Underground Mech. Irrigation Service


Contract No.: ITB03-300C04 Inspection No.: WIR-ME-14

Engineer: AMAALA Inspection Date.: 10-August-23

Contractor: STL Location: Access-way "H"

Subcontractor: Element:

Item
No. Description YES NO NA Remarks

Ensure that all drawings and material Material Submittal is approved.


1.0 submittals have been approved and required Shop Drawings are in Revise & Resubmit Status.
materials are available on site.
Verify the route of the piping and supports are Yes
2.0
correct as per the approved drawings.

3.0 Ensure that the pipe and fittings are clean. Yes

Verify that the allignment of the piping ensure that


4.0 the horizontal piping is uniformly sloped. Yes

Ensure that the testing performed according to NA


5.0
specification
Ensure that welding of the pipe joint as Yes
6.0
per Specification procedure.

Suggestions for improvement:

QC Mech. QC Elec. QC Civil Engineer


Name: Eng M Abid Name: Name: Amir Name:
Signature: Signature: Signature: Signature:
Date & Time: 10.08.23 11.30 Date & Time: Date & Time: Date & Time:

17
AMAALA WELLNESS CORE SECONDARY INFRASTRUCTURE
QA/QC Department

Inspection and Test Plan

IRRIGATION NETWORK

Inspection Responsibility Assignment


Activity Activity Description Acceptance Criteria Frequency Reference or Verifying Documents Remarks
STL AMAALA

1.0 Documents Submittal & Review:

1.1 Approval of Shop Drawing 1TB03300-008D02-DSA-SPC-ME-0002 Prior to work start Approved SDR R RH All documents must be approved before commencement of activity

1.2 Approval of Material Submittal, Test Report 1TB03300-008D02-DSA-SPC-ME-0002 Prior to work start MAR R RH All documents must be approved before commencement of activity

1.3 Method Statement & Risk Assessment 1TB03300-008D02-DSA-SPC-ME-0002 Prior to work start MS R RH

2.0 Material Delivery, Receiving Inspection and Storage

1st Three Deliveries should be


2.1 HDPE, PN16 (DIN 8074) Irrigation pipes 1TB03300-008D02-DSA-SPC-ME-0002 1TB03300-300C04-STC-MIR-ME- H/ R/I W / A / RH 1st delivery lot, Check in detail and after randomly witness
witness by STL QCI

2.2 HDPE, PN16 Fittings Receiving Inspection 1TB03300-008D02-DSA-SPC-ME-0002 See Remarks 1TB03300-300C04-STC-MIR-ME- H/ R/I W / A / RH 1st delivery lot, Check in detail and after randomly witness

2.3 Duct, uPVC For Road Crossing 1TB03300-008D02-DSA-SPC-ME-0002 See Remarks 1TB03300-300C04-STC-MIR-ME- H/ R/I W / A / RH Contractor QCI to perform weekly Inspection

2.4 Control Cable 1TB03300-008D02-DSA-SPC-ME-0002 See Remarks 1TB03300-300C04-STC-MIR-ME- H/ R/I W / A / RH 1st delivery lot, Check in detail and after randomly witness

Isolation Valve, Wash out Valve, Butterfly Valve & Air


2.5 1TB03300-008D02-DSA-SPC-ME-0002 1TB03300-300C04-STC-MIR-ME- H/ R/I W / A / RH
Release Valve

2.6 Flow Sensor 1TB03300-008D02-DSA-SPC-ME-0002 1TB03300-300C04-STC-MIR-ME- H/ R/I W / A / RH

3.0 Installation

3.1 Excavation, Trench & Sand Bedding Inspection 1TB03300-008D02-DSA-SPC-ME-0002 Each Activity 1TB03300-300C04-STC-WIR-ME- H/I W/S Section 221116, Earth work

3.2 HDPE, PN16 (DIN 8074) Irrigation pipes Installation IFC & Shop Drawings Every Completed Portion 1TB03300-300C04-STC-WIR-ME- H/I W/A/S

3.3 Joint / Welding Specs, IFC & Shop Drawings Every Completed Portion 1TB03300-300C04-STC-WIR-ME- H/I W/A/S

3.4 Thrust Blocks 1TB03300-008D02-DSA-SPC-ME-0002 Every Completed Portion 1TB03300-300C04-STC-WIR-ME- H/I W/A/S

3.5 Cable Conduit for Control Cable 1TB03300-008D02-DSA-SPC-ME-0002 Every Completed Portion 1TB03300-300C04-STC-WIR-ME- H/I W/A Separate inspection for control cable installation

3.6 Hydrostatic Test H/I W/A/S

4.0 Final inspection / Pre-Commissioning

4.1 Flushing of the System 1TB03300-300C04-STC-WIR-ME- H W/A

4.2 Testing of Control Cable 1TB03300-300C04-STC-WIR-ME- H W/A

Remarks :

LEGEND
H Hold Point for QC Inspection/ Test R Review of Documents

W Witness Inspection/Test RH Review and Approval of Documents

S Surveillance I 100% Contractor Inspection

A Approval
01231245ÿ4789ÿ 

!ÿ"# $ !ÿ)* +$, ,$0$,$)1$ÿ)* +$,


%&'(ÿ"& 84488-%", )-88.9/ 84488-%", )-88.9/
0ÿ2%0-888323ÿ48818345"14 ÿ-ÿ&&6ÿ(&ÿ78 $ÿ
0& &ÿÿ(ÿ-ÿ,59-ÿÿ8
"ÿ2:3 &ÿ5=ÿ,>ÿ-ÿ,59-ÿÿ8ÿ2?/ÿ&3
1 ÿ203 8&ÿÿ7&&ÿ-ÿ,59-ÿÿ8ÿ2?.ÿ&3
5 5;5ÿÿ<ÿ2824

ÿ $55 9$
%&'(ÿ,@(ÿ7&;
"ÿÿÿ@ÿÿÿA48818345"14 ÿ-ÿ&&6ÿ(&ÿ78 $ÿAÿ(&'(ÿ(ÿÿ'(6ÿ&ÿ7
BCDEÿGHIJEKDGGILÿMIEÿINGOKIGDPILLQÿRSJSHIGSTU

8ÿ) 5 & ,@(ÿV 1


"+84488-488183-5"1- 81ÿW 1W1ÿ1 $ÿ,@& 
,- $-8884
!ÿ,@( $ÿ ÿ(ÿ1 Xÿ&&ÿ5&6ÿ
6ÿÿÿ&@ÿ
@ÿ6ÿÿ
&ÿ&&ÿ
ÿXÿ5Yÿ
5ÿ ÿ"
&@ÿ;ÿÿ$6&
Xÿ&ÿÿÿ
ÿ(ÿ&&
&ÿÿ&
&6ÿ
ÿXÿ5ÿ
&@ÿXÿ &
8@&;ÿ!6ÿÿ&
@&;ÿÿÿ
ÿ(;ÿ
ÿ'&ÿ$6&
&'&ÿXÿÿ

71111 12
01231245ÿ4789ÿ 
ÿÿÿÿ!
ÿ"

#ÿ$ÿ  ÿ% ÿ%ÿ& (ÿ$ÿÿ'!ÿ%ÿ

71111 212
01231245ÿ78977ÿ 

ÿ!"# ÿ() *#+ +#.#+#(/#ÿ() *#+


$ %&'ÿ% 84488,$ + (,8877-7 84488,$ + (,8877-7
.ÿ0$.,8882-01ÿ488/8323 /2 ÿ4ÿ  ÿ3ÿ5ÿ"%6ÿ78
"
.% %ÿÿ'ÿ,ÿ+39,ÿÿ:
ÿ0771 %ÿ3<ÿ+=ÿ,ÿ+39,ÿÿ:
%ÿÿ'ÿ,ÿ+39,ÿÿ:
%ÿ.8ÿ ÿ,ÿ+39,ÿÿ:
%ÿ+ÿ<&ÿ,ÿ+39,ÿÿ:
%ÿ*6ÿ"%ÿ,ÿ+39,ÿÿ:
%ÿ#'ÿ+>%ÿ,ÿ+39,ÿÿ:
%ÿ:ÿ9% %8ÿ,ÿ+39,ÿÿ:
%ÿ#%ÿ" ÿ,ÿ+39,ÿÿ:
%ÿÿ'&ÿ,ÿ+39,ÿÿ:
%ÿ%6ÿÿ,ÿ+39,ÿÿ:
38ÿ3ÿ,ÿ3ÿÿ
/ ÿ0;1 :%ÿÿ?%%ÿ,ÿ+39,ÿÿ:
%ÿ3ÿ%ÿ,ÿ+39,ÿÿ:
%ÿÿÿ,ÿ+39,ÿÿ:
%ÿ%ÿ @ÿ,ÿ+39,ÿÿ:
%ÿ3%6ÿ 8ÿ,ÿ+39,ÿÿ:
%ÿ.ÿ%8&ÿ,ÿ+39,ÿÿ:
%ÿ.ÿ?ÿ,ÿ+39,ÿÿ:
%ÿ%ÿA6ÿ,ÿ+39,ÿÿ:
3 %85ÿ3ÿ 8ÿ2824

ÿ #33 9#
$ %&'ÿ+>'ÿ?%8
ÿÿ ÿ>ÿ ÿÿB488/8323 /2 ÿ4ÿ  ÿ3ÿ5ÿ"%6ÿ78ÿ"Bÿ' %&'ÿ'ÿ
&'@ÿ%ÿ9
9117  11 712
01231245ÿ78977ÿ 
!ÿ#$%&!'##%(ÿ)%!ÿ%*#+'%#,%((-ÿ./&/$%#/01

2 ÿ3 4 56 789ÿ:  ; 


7<=84488>488;83>4<;> 2;ÿ@ 1@;ÿ; ÿ 
<4>?7>8887
4Dÿÿ7>ÿ:E
6ÿ68ÿF6ÿ 
9 6ÿÿ Fÿ
AB4ÿ789 Cÿ  ÿ9ÿ;   8ÿ2>ÿ46
; ÿ9ÿ G
616
6 6ÿÿ 6
6
<Eÿÿ E
Gÿ789 Hÿ5   ÿÿF6ÿ
?66Eÿ96ÿ
 ÿ4
5EÿG ÿ9 ÿ9ÿ; 


9117  11 212


01231245ÿ78978ÿ 

ÿ!"# ÿ() *#+ +#.#+#(/#ÿ() *#+


$ %&'ÿ% 84488,$ + (,8872-- 84488,$ + (,8872--
.ÿ0$.,8884341ÿ488/8323 /2 ÿ4ÿ %ÿ3ÿ3
.% %ÿÿ'ÿ,ÿ+35,ÿÿ6
ÿ0781 %ÿ38ÿ+9ÿ,ÿ+35,ÿÿ6
%ÿÿ'ÿ,ÿ+35,ÿÿ6
%ÿ+ÿ8&ÿ,ÿ+35,ÿÿ6
%ÿ*:ÿ"%ÿ,ÿ+35,ÿÿ6
%ÿ#'ÿ+;%ÿ,ÿ+35,ÿÿ6
%ÿ6ÿ5% %7ÿ,ÿ+35,ÿÿ6
%ÿ#%ÿ" ÿ,ÿ+35,ÿÿ6
%ÿÿ'&ÿ,ÿ+35,ÿÿ6
%ÿ%:ÿÿ,ÿ+35,ÿÿ6
37ÿ3ÿ,ÿ3ÿÿ
/ ÿ001 6%ÿÿ<%%ÿ,ÿ+35,ÿÿ6
%ÿ3ÿ%ÿ,ÿ+35,ÿÿ6
%ÿÿÿ,ÿ+35,ÿÿ6
%ÿ%ÿ =ÿ,ÿ+35,ÿÿ6
%ÿ3%:ÿ 7ÿ,ÿ+35,ÿÿ6
%ÿ.ÿ%7&ÿ,ÿ+35,ÿÿ6
%ÿ.ÿ<ÿ,ÿ+35,ÿÿ6
3 $75ÿ70ÿ 7ÿ2824

ÿ #33 5#
$ %&'ÿ+;'ÿ<%7
ÿÿ ÿ;ÿ ÿÿ>488/8323 /2 ÿ4ÿ %ÿ3ÿ3>ÿ' %&'ÿ'ÿÿ&'=ÿ%ÿ9
?@ABÿDEFGBHADDFIÿJFBÿFKDLHFDAMFIINÿOPGPEFDPQR

6 ÿ( 3 "% +;'ÿS  / 

9117  11 712


01231245ÿ78978ÿ 
784488488!83"! %!ÿ& 1&!ÿ! "ÿ'( 
 #887$
-.ÿÿÿ ÿ
/ÿ/5ÿ /
 ÿ
,//0
/ 
-12ÿÿÿ ÿ3
/ÿÿÿ/
,//
/ ÿ
4/5ÿÿ-! //
ÿ,3ÿ/ ÿ
3ÿ+ÿ /
 5ÿ",5
/+2ÿÿ/
-/ÿ/3ÿ/,ÿ
)ÿ'*+ ÿ+, ÿ+ÿ!  ÿÿÿÿ
ÿ//ÿÿ3
/ÿ*/3ÿÿ
-1//3ÿÿÿÿ/
'"6ÿ2ÿÿ1ÿ /
-/ÿ ÿÿ
ÿ
.ÿÿ/7/
8ÿ5/ÿ
2ÿ,ÿ/
-4/*ÿ ÿÿ
,ÿÿ,ÿ1ÿ/
,ÿ+20ÿ-
" ÿÿÿÿ/ÿ'"6
/2ÿÿ2

42ÿ)ÿ  ÿ+ ÿ+ÿ! 

9117  11 212


LEGEND
315 mm Ø HDPE PIPE, PN16 (DIN 8074)

225 mm Ø HDPE PIPE, PN16 (DIN 8074)


Thursday, July 06, 2023

160 mm Ø HDPE PIPE, PN16 (DIN 8074)

110 mm Ø HDPE PIPE, PN16 (DIN 8074)

CABLE CONDUIT SIZE 38MM(14/2 - AWG


CONTROL CABLE)

CABLE CONDUIT SIZE 50MM (3C, 4MM, CABLE


FOR POWER CABLE)
IRRIGATION DUCT
SOLENOID VALVE-SPRAY

SOLENOID VALVE-DRIP

IRRIGATION CONTROLLER

MAINLINE TAKE OFF POINT

PULL BOX
CLIENT
ISOLATION VALVE

A
ISOLATION VALVE & ELECTRICALLY
OPERATED BUTTERFLY VALVE WITH
ACTUATOR
DV56 B
2" 4.11

DV55 B
2" 3.90
ELECTROMAGNETIC FLOW METER

WASH OUT VALVE


DV57 B
2" 2.68

DV54 B

MOISTURE SENSOR
2" 2.96

2"Ø AIR RELEASE VALVE


DV59 B
2" 3.65

DV58 B
2" 5.17
THRUST BLOCK
VALVE NO. CONTROLLER No.
Sv1 A
2" 4.5
SIZE IN INCHES FLOW IN LPS

PAIR OF 14 AWG DECODER VALVE CABLES STAMP SIGNATURE


CONDUIT SIZE FOR DECODER CONTROL CABLE

DV60 B
2" 3.56

LEAD CONSULTANT
IRRIGATION DUCTS SCHEDULE
DV74 B
2" 5.95

PIPE SIZE DUCT SIZE

1.21
B

B
1.72
DV61 B

DV63

DV52
2"
2" 2.26

2"
1" 3"
DV62 B
2" 2.10

1.5" 3"
2" 4"

4.12
B
DV73
STAMP SIGNATURE

2"
4" 8"

B
9
1.8
51
DV
2"
6" 12"

B
1
2.4
DV50
2"
IRRIGATION WATER
INDICATIVE LOCATION OF RETAINING WALL AOR
TANK

2.09
B
DV64
2"

2.08
9 B
DV4
2"
1.51
NOTES

B
DV53
2"
DV 75 B
2" 5.80

1. ALL DIMENSIONS ARE IN MILLIMETERS UNLESS


DV72 B
2" 3.80

Consolidated Consultants for Engineering and Environment


DV
65
2"
B
2.31 OTHERWISE STATED
STAMP SIGNATURE
B B
DV7
2"
1 B
3.34
2. THIS DRAWING TO BE READ IN CONJUNCTION
37 DV66 4.05

WITH ALL OTHER CONTRACT DRAWINGS, AND THE

2.08
76 5.
DV 2"

B
2"

2"
91
DV
DV69 B
2" 3.19

DV68 B
DV70 B
2" 2.36
SPECIFICATIONS
2" 1.63

DV80
C
3. THE CONTRACTOR SHALL BE RESPONSIBLE FOR SIGNATURE / DESIGN ARCHITECT

2.08
2" 3.57

PRODUCING A COMPLETE SET OF CO-ORDINATED

2"
93
DV
SHOP DRAWINGS FOR ALL ELEMENTS OF THE
A

C IRRIGATION WORK FOR THE ENGINEER'S APPROVAL,

Heah & Co
1 72
5.
DV8 DV67 B
2"

PRIOR TO THE COMMENCEMENT OF THE WORKS


2" 4.58
C
78 3
DV 5.0
2"

DV 77 C
2" 2.84

4. THE CONTRACTOR SHALL MAKE HIMSELF FULLY


DV79
C
AWARE OF THE SITE CONDITIONS, EXISTING GROUND
WATER LEVELS, NECESSITY FOR BACK PROPPING
2" 4.13

EXCAVATED AREAS AND EXISTING SERVICES

2" 4.2
B
DV94
LANDSCAPE CONSULTANT
5.
6. CONTRACTOR TO PRODUCE A REPRESENTATIVE
DV785a C
2" 4.34 SAMPLE FOR THE ENGINEER'S APPROVAL FOR EACH
DV48 B
2" 4.47 ELEMENT, TO WHICH THE WORKS ON SITE MUST
CONFORM
A

DV82a C
7. THRESHOLDS TO CHANGES IN LEVEL, BUILDINGS,
ETC. TO BE FLUSH WITH NOMINAL FALLS AWAY
2" 3.63
31
4.
C

2"
2

C
DV8

DV86
2" 6.75

CONSTRUCTION DOCUMENTS
DV85 A

8. SLEEVES SHALL BE PROVIDED FOR ALL


2" 4.34
DV47 B
2" 4.04

TUNNEL IRRIGATION PIPES WHICH CROSS ANY HARD

2" 4.2
A
6.94 2"

DV94
C
DV83

LANDSCAPE / STRUCTURAL ELEMENTS. KEY PLAN

9. PIPES SHALL BE ENCASED IN CONCRETE IF


LENGTH OF CROSSING IS MORE THAN 12m OR
DV46 B
2" 3.99 SUFFICIENT DEPTH (MINIMUM 500mm) IS NOT
DV89 C
2" 4.20
AVAILABLE.
DV84 C
DV83a C 2" 4.03 DV34 A
2" 2.27 2" 3.78

A 10. ALL THE VALVE BOXES SHALL BE LOCATED IN


SOFT LANDSCAPE AREAS UNLESS APPROVED BY THE

3.20
A
ENGINEER. VALVE BOXES / MANHOLES IN HARD

DV33
2"
DV35 A

LANDSCAPE AREA SHALL BE PROVIDED WITH


2" 2.65

D.I.RECESSED MANHOLE COVERS.

DV36
2"
A
2.31
11. SINGLE PHASE POWER SUPPLY TO BE PROVIDED
AT EACH CONTROLLER LOCATION.
N
A

DV25
2"
A
2.93
N Q
N1
2023.03.30
N0
2023.01.23 VP ISSUED FOR CONSTRUCTION TLA

A
0
4.0
32
DV
2"
GENERAL NOTES

DV31
A
1. ALL STRUCTURAL, MEP, CIVIL AND LANDSCAPING QUERIES ARE TO BE REFERRED
2" 6.06
TO THE RELEVANT CONSULTANT DRAWINGS, SPECIFICATIONS AND DETAILS.
2. ALL DESIGN AND CONSTRUCTION TO COMPLY WITH APPLICABLE REGULATIONS AND
LOCAL AUTHORITY REQUIREMENTS
3. CONTRACTORS AND SUBCONTRACTORS ARE TO CHECK ALL DIMENSIONS AND
DV37 A
2" 5.03
LEVELS ON THE BUILDING SITE BEFORE COMMENCING WITH ANY WORK
DV30
A

DV
89
3"
A
7.61
2" 4.09
4. ANY DISCREPANCY IN THE DRAWINGS, DIMENSIONS & SPECIFICATIONS ARE TO BE
DV38 A
2" 6.85
BROUGHT TO THE ATTENTION OF THE ENGINEER PRIOR TO ANY WORK
BEING PUT IN HAND
DV88
A
2" 4.43

A
5. ONLY FIGURED DIMENSIONS TO BE FOLLOWED - SCALED DIMENSIONS OF
42

DRAWINGS WILL NOT BE PERMITTED


DV 3
2.4
DV92 2"
A
2"
4.16

DV24 A
2" 4.60

Rev. No. Date Description Resp. Consult

A
6
DV2
5.68
2"

DV
29
2" A
8.3
7
DV10
A
2"
4.60
4.16
A
DV90
2"

DV39 A
A
DV27 2" 5.03
DV23 A DV40 A
2" 5.05
DV28 2" 4.26 2" 2.72
A
2" 6.59

DV41 A
2" 3.89
DV22 A
2" 4.26

DV43 A
2" 1.91

DV44 A
2" 2.36
DV14 A
2" 4.74

N0 2023.01.23 VP ISSUED FOR CONSTRUCTION TLA


N1 2023.03.30 VP ISSUED FOR CONSTRUCTION TLA
N2 2023.07.06 VP ISSUED FOR CONSTRUCTION(SECONDARY INFRA ADD) TLA

OR
DV19 A
DV9 DV1 A
2" 4.24

RR R
A
2" 2" 4.09
5.43 DV11 DV21 A
A

ID
CO IDO
2" 2" 4.72
4.69
DV20 A
2" 3.21

IC RR
DV13 A
2" 3.85 DV2 A

RV CO
2" 3.48

E
SE EE
TR
DV17 A

DV12 A
DV16 A
2" 4.97

DV18 A
DV3 A
2" 4.41 REV. DATE REASON FOR ISSUE CHK
2" 5.82 2" 5.60
2" 3.36 DV4 A
2" 6.16

DV5
2"
A
4.18
DV3A A
2" 3.68
DV45 A
2" 3.37 PROJECT
Z:\1202-THE WELLNESS CORE\M-MISC\2023-06-21_IRRIGATION LAYOUT\IRRIGATION LAYOUT.DWG

DV8 A
DV6 A

AMAALA WELLNESS CORE


2" 4.40
2" 4.98

DV15 A
3" 6.74
DV7 A
2" 4.64

MEDICAL WELLNESS / INTEGRATIVE WELLNESS


(FAMILY / ADULT) / WELLNESS VILLAGE
TRIPLE BAY, SAUDI ARABIA

BUILDING NAME
MASTER PLAN

BUILDING NUMBER
00

PLOT NUMBER
TB-09

DRAWING TITLE

IRRIGATION :MAIN LINE LAYOUT


OVER ALL MASTER PLAN

MODEL FILE REFERENCE

DRAWN BY CHECKED BY APPROVED BY


HS VP RV

PROJECT NO. ISSUE DATE SCALE @ A0


1TB03300 2023.07.06 1:1500

DRAWING NUMBER REVISION


1TB03300-008D02-DSA-00-XX-DWG-LS-71001 N2
Q
N
Ø200 CHWR MH-NO 1D-08-VC-230
Ø280 FM
Ø110 PWP MH-SIZE Ø1.5 M
Ø160 PWP Ø140 SPR Ø160 PWP
Ø200 CHWR Ø200 CHWR Ø110 SP MH-COVER LL -6.66 M
Ø280 FM Ø110 WP Ø160 PWP
Ø160 PWP Ø200 CHWS Ø200 CWS MH-DEPTH 2.3 M
Ø200 CHWS Ø140 SPR Ø25 VP Ø200 FM
Ø200 CHWS REMARK- WARNING TAPE
Ø280 FM Ø200 CWS Ø140 SPR
Ø200 CWS 0.28 m 0.16 m Ø80 CHWS Ø110 IRR

1.80 m
1.20 m
0.17 m Ø80 CWS Ø80 CHWR
0.32 m 0.22 m WARNING TAPE

0.46 m
0.32 m WARNING TAPE CLIENT

1.20 m

1.20 m
1.20 m

0.27 m WARNING TAPE 0.27 m

1.80 m
1.80 m

1.80 m
0.62 m 0.26 m 0.31 m 0.21 m

2.01 m
0.60 m 1.16 m 0.18 m 0.74 m

1.44 m
0.45 m 0.70 m

2.87 m
1.28 m 0.73 m 0.38 m
0.55 m 0.45 m 0.96 m IL: -8.99 m IL: -7.82 m IL: -7.98 m
0.81 m IL: 3.65 m IL: -7.83 m
1.98 m

IL: 3.60 m IL: -8.94 m IL: -8.07 m


0.20 m IL: -9.13 m IL: -8.59 m IL: 4.13 m
0.39 m 0.80 m 0.14 m 0.17 m
IL: 2.39 m 0.25 m Ø110 IRR IL: -8.53 m IL: -7.39 m IL: 4.14 m
IL: -9.95 m Ø110 IRR 0.31 m WARNING TAPE IL: -7.89 m
IL: -8.89 m IL: -8.65 m IL: -8.50 m
IL: -9.73 m IL: -9.92 m IL: -8.41 m
IL: -9.77 m 0.39 m IL: -8.63 m IL: -8.59 m IL: -8.55 m
Ø110 IRR IL: -9.68 m IL: -8.45 m
IL: -9.94 m
IL: -10.97 m IL: -8.62 m
STAMP SIGNATURE

MEP_SHEET-3_ACCESSWAY-P_SEC A-A MEP_SHEET-4_ACCESSWAY-P_SEC B-B MEP_SHEET-4_ACCESSWAY-P_SEC C-C MEP_SHEET-4_ACCESSWAY-P_SEC D-D LEAD CONSULTANT
1 1 : 50 2 1 : 50 4 5 1 : 50
1 : 50

STAMP SIGNATURE

AOR

Ø160 PWP
Ø200 FM NOTE: UNDER THE ROAD ALL THE MEP SERVICES RUNNING BETWEEN 1.2M TO 1.8M
Ø160 PWP Ø140 SPR
Ø65 CHWS
Ø200 FM Ø160 PWP Ø65 CWS
Ø65 CHWS Ø65 CHWR Consolidated Consultants for Engineering and Environment
Ø200 FM
Ø140 SPR Ø140 SPR STAMP SIGNATURE
Ø65 CWS Ø65 CHWR
Ø65 CWS
Ø65 CHWS WARNING TAPE

Ø65 CHWR

1.20 m
WARNING TAPE 0.18 m SIGNATURE/DESIGN ARCHITECT

1.80 m
0.37 m 0.25 m 0.33 m
1.20 m
1.80 m

0.19 m
1.20 m

0.23 m 0.25 m
0.25 m 0.45 m 0.26 m 0.36 m 0.68 m 1.18 m 0.63 m
Heah & Co
1.80 m

0.48 m 0.37 m 1.41 m 0.60 m LEGENDS & ABBREVIATIONS

2.03 m
WARNING TAPE
Ø110 IRR IL: -8.94 m
0.56 m 1.30 m 0.70 m MAIN CONTRACTOR
IL: -9.11 m
1.94 m

IL: -8.50 m IL: -9.16 m CHWS CHILLED WATER SUPPLY


IL: -8.32 m IL: -9.05 m
IL: 4.17 m IL: -8.81 m IL: -9.05 m IL: -9.19 m
IL: -8.43 m IL: -8.77 m
IL: -8.85 m Ø110 IRR CHWR CHILLED WATER RETURN
Ø110 IRR IL: -8.77 m IL: -8.82 m IL: -10.52 m
IL: -8.47 m SUB CONTRACTOR
IL: -10.07 m CHILLED WATER PIPES INSULATION
IL: -8.48 m
WARNING TAPE
MEP_SHEET-4_ACCESSWAY-P_SEC G-G CCWS COOLED COLD WATER SUPPLY
MEP_SHEET-4_ACCESSWAY-P_SEC F-F 7
MEP_SHEET-4_ACCESSWAY-P_SEC E-E 6 1 : 50 1 : 50 HWR HOT WATER RETURN
3 1 : 50 KEY PLAN
CONSTRUCTION

HWS HOT WATER SUPPLY FD

FD
FD

CWS COLD WATER SUPPLY

FD
FD

FD

FD

FD

FD

FD
F
D
DF

FM FIRE MAIN PIPE/ STAND PIPE

FH
C
C
FH

FD
C
FH
C
FH

C
FH
C
FH

C
FH

FD
FD
B
A E
W
3 R
E

WR O
D
O
H
S
4
2
1
5
0
. 7
5
1
0

.2
1
5
3
0
74
.
-7
8
1
0
5
d
UP

Od
C
1 1
0
5 U
D
-.R
Y
A
T
2
3
4
0
5
7
1
.
WC

IR R

2
1
0
5
d
-.
O
3 D
3
4
2
1
5
6
0
7
6
1
0
.

O
C
SPR SPRINKLER PIPE

4
2
1
5
8
0
7
8
1
0
.
H
N
TC
K
IE
1
5
0
2 7 4
.3

3
1
5
d
-.

D
3 R
A
-2
4
1
5
d

L Md -8
9
1
0
5

U
Y
T
4
.

O
C
4
3
5
0
1
.2 7

2
1
5
9
0
7
9
1
0
.
G
O
N
R
IV
0
1

-9
1
0
5
d.

FD
R
C
N
A
E
T
4
0
1
73
2
1
-3
1
5
d

F
=
0
L

-0
2
1
5
d
.
.

-9
1
0
5
d.
.
IR R
-8
6
1
0
5
d.
3 C

O
1 D
W
N
U
S
A

E M C O
6
0
1
73
4
.2
5

-. 75
2
0
14
2
1

.4
3
0
5
7
12
.
8
1
5
d

7
1
5
d
-.
4 M

-2
1
0
5
d

-3
9
1
0
5
d

-2
1
0
5
d
.

.
O
R
H
B
A

O
S R
T
5
12
.3
5
0
1
7
PART PLAN - 4

MA G

D
1 R
-6
2
1
0
5
d

.2
5
4
0
1
7 3

-2
6
1
5
d
U
Y
A
T
.

.
O
C
.5
0
8
7
12
3
4
4 R d-2
1
0
5.
-2
3
1
5
d.
O
C O
IR
3 D
-2
4
1
5
d

2
5
0
1
7
7
1
.

.
FD
UP

FD
ZONE - 03

FD
PART PLAN - 3

1
2 1
PART PLAN - 5

2
1
WP WASTE PIPE

Q
Ø200 CHWR PWP PUMPED WASTE PIPE
Ø200 SPR GENERAL NOTES
1. ALL STRUCTURAL, MEP, CIVIL AND LANDSCAPING QUERIES ARE TO BEREFERRED
Ø160 PWP Ø200 CHWS Ø280 FM TO THE RELEVANT CONSULTANT DRAWINGS, SPECIFICATIONS AND DETAILS.

Ø200 FM Ø160 PWP SP SOIL PIPE 2. ALL DESIGN AND CONSTRUCTION TO COMPLY WITH APPLICABLE REGULATIONS AND
Ø200 CWS LOCAL AUTHORITY REQUIREMENTS
Ø140 SPR Ø200 FM 3. CONTRACTORS AND SUBCONTRACTORS ARE TO CHECK ALL DIMENSIONS AND

Ø50 CWS Ø100 SPR LPG LIQUEFIED PETROLEUM GAS LEVELS ON THE BUILDING SITE BEFORE COMMENCING WITH ANY WORK

Ø65 CHWS 4. ANY DISCREPANCY IN THE DRAWINGS, DIMENSIONS & SPECIFICATIONS ARE TO BE

1.20 m
BROUGHT TO THE ATTENTION OF THE ENGINEER PRIOR TO ANY WORK
Ø50 CWS WARNING TAPE
BEING PUT IN HAND

1.80 m
Ø65 CHWR IRR IRRIGATION PIPE
5. ONLY FIGURED DIMENSIONS TO BE FOLLOWED - SCALED DIMENSIONS OF
DRAWINGS WILL NOT BE PERMITTED
6. ALL THE LEVELS MEASURED ARE IN METER.
7. ALL THE LEVELS MEASURED FROM BENCHMARK LEVEL (+12.644M)

WARNING TAPE WARNING TAPE


1.06 m 0.93 m VP VENT PIPE
1.20 m
1.80 m
1.20 m
1.80 m

0.27 m 0.38 m 0.38 m 0.29 m 0.09 m


0.32 m 0.25 m 0.35 m 0.28 m 0.28 m
PL PUMPED LINE
1.27 m 0.32 m 1.48 m 0.65 m IL: -8.05 m
0.68 m 0.58 m IL INVERT LEVEL
IL: -7.81 m
0.46 m
1.97 m

IL: -9.48 m IL: -7.78 m


1.99 m

IL: -9.91 m MH MANHOLE


IL: -9.74 m 0.38 m IL: 4.81 m
IL: -9.78 m IL: -9.70 m IL: -9.99 m
IL: -9.78 m IL: -10.10 m IL: 4.80 m TB THRUST BLOCK
IL: -9.82 m Ø110 IRR
IL: -9.94 m
Ø110 IRR IL: -11.31 m GATE VALVE (GV)
IL: 1.53 m

BUTTERFLY VALVE (BV)


MEP_SHEET-5_ACCESSWAY-P_SEC H-H MEP_SHEET-5_ACCESSWAY-P_SEC I-I MEP_SHEET-4_ACCESSWAY-O_SEC J-J
8 1 : 50 9 1 : 50
10 1 : 50 TESTING POINT (TP)

AUTOMATIC AIR VENT (AAV)

YH YARD HYDRANT (YH)


BENCHMARK
( LEVEL C0 25-06-2023 ISSUED FOR APPROVAL MA
BENCHMARK
+12.644
+12.644 m ACV LOCATION TO SERVE GROUP OF REV. DATE REASON FOR ISSUE CHK
LEVEL ) Ø200 CHWR
Ø200 CWS VILLAS/SUITES PROJECT
Ø200 CHWS Ø200 CHWS Ø80 SPR AMAALA WELLNESS CORE
Ø280 FM BREECHING INLET MEDICAL WELLNESS / INTEGRATIVE WELLNESS
Ø200 CHWR (FAMILY / ADULT) / WELLNESS VILLAGE
Ø200 CHWR BACKDROP MANHOLE
Ø200 SPR Ø280 FM
Ø280 FM Ø200 CHWS Ø200 CWS WASHOUT CHAMBERS (WOC) BUILDING NAME
MASTERPLAN
Ø200 CWS
AIR RELEASE VALVE CHAMBER (AVC) BUILDING NUMBER
1.20 m

03
0.32 m 0.32 m 0.22 m 0.36 m
1.20 m

1.80 m

WARNING TAPE PLOT NUMBER


ISOLATION VALVE CHAMBER (IVC)
1.20 m

0.28 m
1.80 m

TB-09
WARNING TAPE
1.80 m

0.79 m
0.68 m WARNING TAPE DRAWING TITLE
1.04 m 0.29 m 0.81 m 1.34 m HOUSE CHAMBER (HC)
0.60 m
0.20 m IL: 9.16 m 0.64 m 0.39 m 1.39 m 0.27 m 0.27 m 0.50 m
0.39 m IL: 9.17 m AMAALA WELLNESS CORE
IL: 9.12 m FIRE CHAMBER (FLC)
0.39 m IL: 9.01 m ACCESSWAY_P & O
IL: -5.68 m
R OED IG ER

VACUUM CHAMBER
IL: -1.34 m
IL: -5.77 m
IL: -5.58 m IL: -1.51 m IL: -1.54 m PRESSURE BREAKING CHAMBER MODEL FILE REFERENCE
IL: -1.50 m 1TB03300-300C04-STC-00-ZZ-MOD-ME-50001
IL: -1.33 m FIC-MANHOLE
DRAWN BY CHECKED BY APPROVED BY
VACUUM STATION MR MA PD

MEP_SHEET-4_ACCESSWAY-O_SEC K-K MEP_SHEET-4_ACCESSWAY-O_SEC L-L MEP_SHEET-4_ACCESSWAY-O_SEC M-M SEWER MANHOLE PROJECT NO. ISSUE DATE SCALE @ A0

11 1 : 50 13 1 : 50 12 1 : 25 BACKDROP MANHOLE
1TB03300 25-06-2023 As indicated

DRAWING NUMBER REVISION


1TB03300-300C04- STC -03-ZZ-SDW-ME-31001 C1

You might also like