Professional Documents
Culture Documents
Quezon Power
Quezon Power
You are permitted to view the material on-line and print a copy for your personal use until 6-Mar-2016.
Please note that you are not permitted to reproduce or redistribute it for any other purpose.
Purchased for use by Philippe Wind on 06-Mar-2015. Order ref F245945.
October 2008
Veronica Bonetti
Stefano Gatti
1. The Project
You are permitted to view the material on-line and print a copy for your personal use until 6-Mar-2016.
Please note that you are not permitted to reproduce or redistribute it for any other purpose.
In the early ‘90s, the Philippines were hit by a major energy crisis. The Quezon Power Project was undertaken in
The project consisted of building and running an electric power plant. The plant would be designed, constructed,
Copyright encoded A76HM-JUJ9K-PJMN9I
and operated by the SPV Quezon Power, a Limited Company with legal headquarters in the Philippines. The
facility in question, which was to generate 440 megawatts of electricity, would be built on the island of Luzon
Order reference F245945
1
Veronica Bonetti is Strategic Equity Derivatives Analyst at Barclays Capital in London. Stefano Gatti is associate professor
of Banking and Finance and Director of the BSc. in Economics and Finance at Bocconi University in Milan. The case study
was prepared by the authors with the sole purpose of case discussion of a real project finance transaction. The case is not
intended to show better managerial practices and is based on public available information. The authors would like to thank
Emilia Garcia-Appendini, Bill Megginson and Davide Ravasi for helpful suggestions on an earlier version. The responsibility
of the contents is of the authors’ only.
2
109-041-1
You are permitted to view the material on-line and print a copy for your personal use until 6-Mar-2016.
Please note that you are not permitted to reproduce or redistribute it for any other purpose.
Purchased for use by Philippe Wind on 06-Mar-2015. Order ref F245945.
Educational material supplied by The Case Centre
Copyright encoded A76HM-JUJ9K-PJMN9I
Order reference F245945
The low-sulphur coal used as feedstock for the plant would be imported from Kalimantan, Indonesia, and a sea
water desalination facility located within the plant itself would supply the necessary water. In addition to the
power generation plant, Quezon was to operate a 31 kilometer, 230 Kilovolt transmission line.
The electricity produced by Quezon Power would be subject to a take-or-pay Power Purchase Agreement (PPA)
which obliged Manila Electric Company (Meralco) (the Philippine power distribution company) to pay both fixed
and variable costs of the plant in question. These costs would be established on the basis of parameters linked to
the progress of the construction work and the performance of the plant as set down in the relative legal
agreements.
Following the intensification of the Philippine energy crisis, PMR considered the possibility of developing a
power generation project with Meralco by founding an ad hoc SPV. PMR made an initial proposal to its partner
in August of 1992 which Meralco rejected because talks were already underway with another power developer
that the company had contacted. Only after these negotiations failed in mid-1993 did Meralco and PMR sign a
Memorandum of Agreement (MoA). Subsequent to this, PMR convened several Filipino managers who worked in
the power sector and founded PMR Power Ltd, the first sponsor of the Quezon Power Project, in early 1994.
In the meantime, the newly established company started the search for a US partner who would collaborate on
project development and become co-owner of the plant. Covanta Energy Corporation (Covanta) was chosen
among the various possible candidates who had expressed an interest in joining the project. Covanta was an
3
109-041-1
American leader in the sector of designing and developing privately-owned power plants. Originally called
Ogden Energy Corp, the company changed its name to Covanta Energy Corp following a reorganization aimed at
refocusing its core business in March of 2001. Negotiations between Covanta, PMR, and Meralco led to the
signing of the take-or-pay Power Purchase Agreement (PPA) in August of 1994 by the Philippine power
distribution company.
Finally, in September of 1994 Covanta signed a co-development agreement with Bechtel, the third project
sponsor, who granted PMR Power Ltd voting interests of 2% in Quezon Power, without requiring any equity
contribution. After InterGen was founded in 1995, Bechtel transferred its interest in the Quezon project to its
affiliate; InterGen was controlled through subsidiaries by Bechtel Enterprises (Bechtel) and Royal Dutch/Shell
Group (Shell).
InterGen was founded in early 1995 following the acquisition by Bechtel and PG&E Enterprises (“PG&E” –
You are permitted to view the material on-line and print a copy for your personal use until 6-Mar-2016.
subsidiary of Pacific Gas and Electric Company) of J. Makowski Corporation (“JMC” – a US company, founded
in 1972 as developer of small hydroelectric power plants). JMC handled co-generation and development of
Please note that you are not permitted to reproduce or redistribute it for any other purpose.
private projects for power production.
The final ownership structure of the Quezon Project was as follows (Figure A2):
Order reference F245945
72.5% 27.5%
voting
Quezon Power interests PMR
Inc. Ltd. Co.
71.875% 26.125%
2%
Quezon Power
(Philippines)
Ltd. Co.
4
109-041-1
The initial financial structure called for a debt equity ratio of 75/25. Equity amounted to US dollars (USD)
202.2m, wholly paid up by the American sponsors. In fact, the Philippine sponsor PMR was granted voting
interests in the SPV without having to contribute equity to the project company (Table A1).
You are permitted to view the material on-line and print a copy for your personal use until 6-Mar-2016.
Covanta 26.125% 27.5% USD 55.6m
PMR Power 2% - -
Please note that you are not permitted to reproduce or redistribute it for any other purpose.
Source: Kennedy (2000)
- USD 405m – loan underwritten by the Union Bank of Switzerland with a guarantee against political risk
provided by the Export-Import Bank of the United States2 (“Ex-Im Bank”);
Educational material supplied by The Case Centre
Copyright encoded A76HM-JUJ9K-PJMN9I
- USD 100m – loan granted by the Overseas Private Investment Corporation (“OPIC” – US).
Order reference F245945
- Close to the termination of the construction phase (scheduled for December 1999), Quezon would be
refinanced by:
- USD 215m –a 20-year, fixed coupon (8.86% per annum paid quarterly) project bond (2017 maturity) issued
on the US market in USD on 3 July 1997, with Salomon Brothers in the role of lead manager of the deal;
- USD 392m – loan directly issued by Ex-Im Bank.
2
Ex-Im Bank is the independent US governmental agency that promotes and finances various kinds of projects the world
over, primarily in emerging countries. Its aim is to encourage export of US goods and services on international markets.
5
109-041-1
Contractual document
Bechtel
Enterprises Participant
Contract agreement
Ownership
Bechtel Bechtel InterGen
Corp. Power N.V. Affiliation
Bechtel
Indonesia Australia Overseas InterGen Covanta Energy
Mission
Energy Overseas
Firm Firm Energy Bechtel Mgmt. Co. Group
Corp.
You are permitted to view the material on-line and print a copy for your personal use until 6-Mar-2016.
Const. Mgmt. Covanta Power
EPC
Mgmt. Service
Please note that you are not permitted to reproduce or redistribute it for any other purpose.
Development
PT Adaro Cayman Inc.
BP
Educational material supplied by The Case Centre
PLC
Copyright encoded A76HM-JUJ9K-PJMN9I
PT Kaltim Coal
Supply
Order reference F245945
In addition, payments were indexed to the USD exchange rate, thereby reducing the risk of a devaluation of the
local currency affecting the SPV’s cash flows. (The bond earmarked for refinancing would be issued in 1997 and
stated in USD.) For the entire duration of the contract, Quezon was obliged to deliver, and Meralco to receive and
pay for, at least the minimum guaranteed quantity of electricity every month (Table A2), as established in the
PPA.
6
109-041-1
You are permitted to view the material on-line and print a copy for your personal use until 6-Mar-2016.
If the plant could not supply the stipulated quantity of power, Quezon would be required to pay Meralco
Please note that you are not permitted to reproduce or redistribute it for any other purpose.
liquidated damages, which were relatively low as compared to the plant’s tariffs. The total amount of liquidated
damages would depend on Meralco’s power needs and the possibility of finding alternative energy suppliers.
More specifically, Quezon would pay Meralco 0.26 Philippine pesos (PHP) for every kilowatt hour (kWh) that it
– Capacity fees – USD 0.029546 per kWh, which would be gauged as a function of variations in the US
consumer price index from the date that the PPA was finalized (August 1994). Monthly payments would
Order reference F245945
equal the capacity fee multiplied by 1/12 of the relative annual minimum guaranteed quantity of power.
– Operating fees – One portion of these fees was stated in local currency and another in US dollars. The fixed
operating fee was set at USD 0.0104 per kWh and PHP 0.0323 per kWh; the variable operating fee instead
was USD 0.0015 per kWh and PHP 0.0937 per kWh. These per unit amounts were to be adjusted to
variations in the US and Philippine consumer price indices respectively, as measured from the date the PPA
was signed. The monthly fixed cost payment was computed as the fixed operating fee multiplied by 1/12 of
the respective annual minimum guaranteed quantity of electricity, while the monthly variable cost payment
was equal to the variable operating fee multiplied by the plant’s output.
– Energy payments – These payments were 1.06575 times the costs incurred for procuring fuel per every
million British Thermal Unit (BTU), multiplied by the product of the net output in kWh and 0.00975 million
BTUs per kWh.
The PPA allowed Quezon to deliver power in excess of the minimum quantity set in the contract priced at 70% of
the capacity fee and 100% of the fixed and variable operating fees.
If Meralco was not able to buy all or part of the plant’s output, Quezon would have the right to sell this energy to
an alternative buyer. In this case, Quezon would have the option to deduct the payments received from third party
buyers from Meralco’s payment obligations.
1.2.2. Leases
Meralco leased its property rights to the site where the power plant and transmission plants were built to Quezon
for as long as the duration of the PPA. In fact, Philippine law allows only citizens or companies controlled by
Filipinos to own land or hold property rights on land within national borders. This being the case, the project was
structured so that Meralco was listed as holding property rights and relative easements on the land where the
power plant and transmission plant were built.
7
109-041-1
Furthermore, the Transmission Line Agreement named Quezon as the party responsible for obtaining the
necessary permits, and for building, financing and running the transmission line. This accord also granted a
building lease to Quezon for the land where the transmission plant was built; Meralco was recorded as owner of
this land, in accordance with the Philippine law cited above.
Monthly payments to be made by Meralco can be broken down into two components:
You are permitted to view the material on-line and print a copy for your personal use until 6-Mar-2016.
Capital Cost Recovery Payments – Relative amounts were earmarked to compensate Quezon for costs
Please note that you are not permitted to reproduce or redistribute it for any other purpose.
–
incurred for building the transmission plant. Such monthly payment were calculated on the basis of an initial
estimated total cost of construction (equal to approximately $ 500,000 per month), to be adjusted to reflect
– Transmission Line Operating Payments – Monthly payments based on operating and maintenance (O&M)
expenses and a portion of some financing fees. 4
Educational material supplied by The Case Centre
These are agreements signed between Quezon and Bechtel subsidiaries Overseas Bechtel and Bechtel Overseas
Corp. (see Figure A3). These accords assigned the latter two the task of carrying out all actions and underwriting
all contracts needed to set up preliminary projects, to obtain permits and to build the plant.
3
The agreement was modified in April 2003 when Quezon assented to relinquish 54% of transmission costs upon request by
Meralco, a figure which amounted to USD 646,000 monthly. This came after the Energy Regulatory Commission (“ECR”)
(the authority responsible for power distribution tariffs in the Philippines) determined that Meralco was not authorized to
charge its customers for transmission costs. Later, in October 2004, following an investigation conducted to ascertain the
transmission costs incurred by Quezon, the ECR allowed Meralco to charge its customers 70% of transmission costs. Since
that time, the offtaker began to pay Quezon the sums set down in the Transmission Line Agreement, equal to the amounts
established in the 2003 amendment. Quezon assumed it could cover the lower takings with a boost in sales of USD 40m in the
six years following the agreement, sales which would be made to Meralco within the framework of the PPA. In so doing, the
impact of the changes to the Transmission Line Agreement on the SPV’s cash flows would become nearly negligible.
4
Meralco therefore bore both the risk of the possibility that actual costs for the maintenance of the transmission line might be
higher than estimated costs and the risk of any potential additional capital spending.
8
109-041-1
You are permitted to view the material on-line and print a copy for your personal use until 6-Mar-2016.
Please note that you are not permitted to reproduce or redistribute it for any other purpose.
Purchased for use by Philippe Wind on 06-Mar-2015. Order ref F245945.
Educational material supplied by The Case Centre
Copyright encoded A76HM-JUJ9K-PJMN9I
Order reference F245945
9
109-041-1
2. The problem
Suppose to be a bank invited by UBS to participate to the 5 years syndicated loan discussed in Section 1.1.
Would you feel comfortable with the contractual structure envisaged for the project? In particular, are there any
risks in the PPA agreement signed by Meralco that could create some problems to Quezon Power once the
financial close is reached? How could we measure the impact of possible troubles faced by Meralco on the
soundness of Quezon Power?
You are permitted to view the material on-line and print a copy for your personal use until 6-Mar-2016.
Please note that you are not permitted to reproduce or redistribute it for any other purpose.
Purchased for use by Philippe Wind on 06-Mar-2015. Order ref F245945.
Educational material supplied by The Case Centre
Copyright encoded A76HM-JUJ9K-PJMN9I
Order reference F245945
10