1) Waterproofing Work

Analysis for 1 sqm


S. No Description Quantity Unit Rate Amount
1 Materials
Waterproofing Chemical (Planicrete SBR) 0.3 kg 575.00 172.50
OPC Cement 2.4 kg 13.00 31.20

2 Labour
1.0 sqm 182.00 182.00

3 Tools @3% of materials 6.11


a Totals of Materials, Labor & Tools and Plant 391.81
b Over head & Profit @ 10% of (a) 39.18
c Total (a+b) 430.99
Item Rate per sqm 431.00
40 Per Sqft
*