Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 5

1.

Calculate the internal rate of return (IRR) as follows:

2.

Calculate the net present value (NPV) for both projects as follows:
3.

Calculate the modified internal rate of return (MIRR) as follows:


4.

Calculate the payback period (PBP) for Project B as follows:


Decision:

As per IRR: Project A should be selected as the internal rate of return is higher than the
weighted average cost of capital and project B' IRR.

As per NPV: Project A should be selected as the Net Present Value is higher than the project
B' NPV.

As per MIRR: Project A should be selected as the internal rate of return is higher than the
weighted average cost of capital and project B' MIRR.

As per PBP: Project B should be selected as the Project A's payback period is higher than the
project B.

You might also like