DATE: DECEMBER 6, 2023

TWO REGIS
ACTIVITIES: ISSUES: REMARKS:

ARCHITECTURAL:
1.INSPECTION OF ACU LEDGE AT 2ND 1. OFFSET AT 400MM: 400MM BOTH SIDES,
FLR UNIT S 150MM BOTH SIDES
2. LEDGE THICKNESS: 120MM BOTH SIDES
3. ELEVATION AT TOP OF WINDOW:
628MM AND 625MM
4. ELEVATION AT INTERIOR SIDE: 1001M
5. TOTAL LENGTH OF LEDGE (ALONG
WITH 2ND FLOOR UNIT R): 2295MM-
2297MM
2. INSPECTION OF ACU LEDGE AT 2ND 6. OFFSET AT 400MM: 400MM BOTH SIDES,
FLR UNIT R 150MM BOTH SIDES
7. LEDGE THICKNESS: 120MM BOTH SIDES
8. ELEVATION AT TOP OF WINDOW:
627MM AND 625MM
9. ELEVATION AT INTERIOR SIDE: 1002M
TOTAL LENGTH OF LEDGE (ALONG WITH
2ND FLOOR UNIT R): 2295MM-2297MM
3. REINSPECTION OF TOILET AND PUNCHLIST CLOSE OUT
BATH DOOR JAMB AT 2ND FLR UNIT V 1. ADDITIONAL LINTEL BEAM AT TOP OF
DOOR JAMB WAS ADDED, ALSO
CONCRETE EPOXY WAS APPLIED ON
CONNECTED DSB AT MASONRY WALL
4. INSPECTION OF TOILET AND BATH 1. LOCATION OF JAMB OPENING TO MAIN
DOOR JAMB AT 2ND FLR UNIT F DOOR OPENING - 1372MM
2. OPENING (HALF) - 305-306MM
3. OPENING (WHOLE) - 601MM
4. PLUMBNESS WITH 500MM OFFSET -
498MM TO 500MM
5. ELEVATION FROM 1000MM - 1114MM
AND 1115MM

WITH LINTEL BEAM AT TOP OF DOOR


JAMB WHICH WAS APPLIED WITH
CONCRETE EPOXY
5. INITIAL INSPECTION OF TILES AT 1. HOLLOW TILES - 12 TILES
2ND FLR UNIT K 2. DAMAGE TILES - 0 TILE
3. LIPPAGE - 0 TILE
4. BALANCE INSTALLATION - 7 TILES
5. OFFSHADE - 0 TILE
6. LIPPAGE THAT CAN BE REPAIRED
USING GROUT - 1 TILE

BALANCE AREA:
1. KITCHEN
2. BEDROOM TOILET AND BATH
3. BALCONY AREA

NO GROUT APPLIED YET