Professional Documents
Culture Documents
Dokumen - Tips Nlc-Report
Dokumen - Tips Nlc-Report
AT
Submitted by
Shri. A.GHOPI SYLESH
B.Tech EEE (IIIrd year Completed)
NIT- PUDUCHERRY
DECLARATION
This is to declare that the In-plant training report, submitted in partial fulfillment of
the requirement is an original work carried out under the guidance of Mr. E. Sankaran,
Deputy Chief Engineer, Electrical Base Mine-II.
NIT- PUDUCHERRY
NEYVELI LIGNITE CORPORATION LIMITED
MINES CAPACITY
MINE I 10.5 MT / A
MINE I A 3 MT / A
MINE II 15.0 MT / A
NLC is generating power in its Thermal Power Station I, Thermal Power Station -II and in
Thermal Power Station I Expansion.
All the southern states are beneficiaries of this power generation project.
MINE – II
History:
In February, 1978 Government of India sanctioned the Second Lignite Mine of capacity 4.7 MT of
lignite per annum and in February `83, Government of India sanctioned the expansion of Second Mine
capacity from 4.7 Million Tonnes to 10.5 Million Tonnes. Unlike Mine-I, Mine-II had to face problems in
the excavation of sticky clayey soil during initial stage. The method of mining and equipment used are
similar to that of Mine-I. The seam is the same as of Mine-I and is contiguous to it. The lignite seam in
Mine-II was first exposed in September 1984 and the excavation of lignite commenced in March, 1985.
GOI sanctioned the expansion of Mine-II from 10.5 MTPA to 15.0 MTPA of lignite in October 2004 with a
cost of Rs. 2295.93 crore. Mine-II Expansion project was completed on 12th March 2010. The lignite
excavated from Mine-II meets the fuel requirements of Thermal Power Station-II and Thermal Power
Station–II Expansion under implementation.
Present:
Mine-II has a lignite capacity of 15 Million Tones per Annum. The earth above the lignite named
as overburden is removed in different phases of excavation viz
2. Surface bench,
3. Top bench,
5. Bottom bench.
Conveyors
Description
Bucket-wheel excavators (BWEs) are heavy equipment used for continuous overburden removal
in surface mining applications. They use their cutting wheels to strip away a section of earth (the
working block) dictated by the size of the excavator. The primary function of BWEs is to act as a
continuous digging machine in large-scale open pit mining operations. What sets BWEs apart from other
large-scale mining equipment, such as bucket chain excavators, is their use of a large wheel consisting
of a continuous pattern of buckets used to scoop material as the wheel turns.
Conveyor Belts
A Conveyor belt (or belt conveyor) consists of two or more pulleys, with a continuous loop of
material - the conveyor belt - that rotates about them. One or both of the pulleys are powered, moving
the belt and the material on the belt forward. The powered pulley is called the drive pulley while the
unpowered pulley is called the idler. There are two main industrial classes of belt conveyors; Those in
general material handling such as those moving boxes along inside a factory and bulk material
handling such as those used to transport industrial and agricultural materials, such as grain, coal, ores,
etc. generally in outdoor locations.
Spreader
Spreaders in mining are heavy equipment used in surface mining and mechanical
engineering/civil engineering. The primary function of a spreader is to act as a continuous spreading
machine in large-scale open pit mining operations. The purpose of the spreader is to receive
overburden from the haulage conveyor from the sorting area and dump it in an orderly and efficient
manner.
Types of Cables
POWER SUPPLY.
For electrical power supply requirement of all the equipment for the above said activities is fed
from a 335 MVA, 230/11 KV sub station located at the pivotal point that is centre of mines.
SOURCE OF SUPPLY
The above sub station is fed from the Thermal Power station-II, through 230KV, 250MVA tower
line feeders called MF3 & MF4
This sub station caters to the entire needs of the Mine-II project. The 230 KV received is
converted into 11 KV supply using 12 power transformers. The 11 KV switch yard has been provided
with 120 numbers outlets for connecting the mines loads. There is a control room manned round the
clock with engineers and technicians to monitor the Sub Station.
Substation Equipments.
Transformers
25 MVA TRANSFORMER
LV 11550
LV 1000 / 1250
Frequency HZ 50
30 MVA TRANSFORMER
LV 11550
LV 1200 / 1500
Frequency HZ 50
Circuit – breakers.
A device capable of making and breaking an electric circuit under normal and abnormal
conditions such as short circuits. It can operate automatically and clear fault current safely and quickly.
Isolator (Disconnecting Switch):
A switching device, which can be opened or closed only under no current condition. It provides
Isolation of a circuit for the purpose of maintenance.
Earthing Switch:
It is a switch that connects a conductor to the earth so as to discharge the charges on the
conductor to the earth. Earthing switches are generally installed on the frames of the isolators.
Relay:
It is an automatic device that closes its contacts when the actuating quantity/quantities reach a
certain predetermined magnitude/phase.
The current ratio of current transformer is generally high (e.g. 500 A/5A and volt-ampere
capacity is relatively low (e.g. 50 VA) as compared with that of the power transformers.
The volt-ampere capacity of a potential transformer is low (e.g.) 100 VA) and the voltage ratio is
relatively high (e.g. 230 KV. / 110V). The protective relays are connected in the secondary circuits of CTs
and VTs.
The equipment connected between the conductor and ground, to discharge the excessive
voltages to earth.
Distribution of 11 KV Supply
From Substation to Machines & Conveyors, The 11 KV supply comes through Landline Cables
terminating with Pillor Boxes, Couplers and Distribution Kiosk.
All the Excavators and Spreaders get supply through Trailing cables which are flexible in nature.
24 V Hand Lamps
11 KV System in Machines
Trailing cable
Bottom Isolator
11 KV Isolators
OCB / VCB
Isolators
Bimetal Relays
Thermistor Relays