S-79-1354-434 - R4 (ITP Plan For Field Construction)

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 14

For Construction

Issued for Construction, Client


4 Apr 12 ‘10 T.Shiraishi Y.Kurosaka J. H. Kim
Comments to incorporated
Issued for Construction, Client
3 Mar 11 ‘10 T.Shiraishi Y.Kurosaka J. H. Kim
Comments to incorporated
Issued for Construction, Client
2 Nov. 25 ‘08 T.Shiraishi Y.Kurosaka J. H. Kim
Comments to incorporated
Issued for Construction, Client
1 Oct 14 ‘08 T.Shiraishi Y.Kurosaka J. H. Kim
Comment to incorporated
0 Sep 30 ‘08 Issued for Construction T.Shiraishi Y.Kurosaka J. H. Kim

A Sep. 10 ‘08 Issued for Approval T.Shiraishi Y.Kurosaka J. H. Kim

REV.NO. DATE DESCRIPTION PREP’D CHK’D APP’D

IRAN LIQUIFIED NATURAL GAS COMPANY

IRAN LNG PROJECT LNG & LPG Storage

INSPECTION & TEST PLAN


FOR FIELD CONSTRUCTION OF MECHANICAL TANK (PROPANE)

SCALE CONTRACT NO. DOCUMENT NO. REV.

NONE ILNG-00-1356 S-79-1354-434 4

TOYO KANETSU K.K. TOKYO, JAPAN

TKK SHEET No. : P3777B-K-32


IRAN LNG PROJECT
DOCUMENT TITLE DOCUMENT NO.
Doc.
INSPECTION & TEST PLAN Unit No. FWBS Seq. Rev. Page 2 of 14
FOR FIELD CONSTRUCTION Type
OF MECHANICAL TANK (PROPANE) S 79 1354 434 4

1.0 INTRODUCTION

The purpose of this document is to describe the inspection and testing plan in connection with the metal
construction activities of full containment LPG storage tanks. This document also specifies the type and extent
of inspection and testing, applicable code, standard, specification documents, quality record requirement, and
inspection involvement by Contractor and Company.

2.0 SCOPE

This document is applicable to the field construction of LPG metal tank components of 1

Propane Storage Tanks

Tank Item No. TK7901


For

IRAN LIQUEFIED NATURAL GAS COMPANY

DAELIM INDUSTRIAL CO., LTD

IRAN LNG PROJECT

3.0 DEFINITIONS

In the context of this document, the following abbreviation, words or phrases shall be taken to have the
meaning assigned to them

Company: IRAN LIQUEFIED NATURAL GAS COMPANY (ILC)

Contractor : DAELIM INDUSTRIAL CO., LTD. (DIC)

Constructor : any firm or company subcontracted by Contractor to undertake field construction,


inspection and testing of metal LNG Tank

4.0 REFERENCES

In preparation of this document, the following documents have been used as a source of information

Code and Standards:

API Std 620 : Design and Construction of Large Welded, Low-Pressure Storage Tanks – Tenth

File: Z:\3777 Iran LNG\Iran LNG\Iran LNG\QA QC Document\LPG Spec\S-79-1354-434 P-K-32_R4.doc TKK Doc No: N3777C-K-32
IRAN LNG PROJECT
DOCUMENT TITLE DOCUMENT NO.
Doc.
INSPECTION & TEST PLAN Unit No. FWBS Seq. Rev. Page 3 of 14
FOR FIELD CONSTRUCTION Type
OF MECHANICAL TANK (PROPANE) S 79 1354 434 4

Edition, February 2002, including Addendum 1, June 2004.


Appendix R: Low-Pressure Storage Tanks for Refrigerated Products

API Std 2000 : Venting Atmospheric and Low Pressure Storage Tanks – 1998

API Std 2550 : Method for Measurement and Calibration of Upright Cylindrical Tanks – 1965

ASME B&PV Code – 2004 Edition including 2006 Addenda.


Section V :Nondestructive Examination
Section VIII Division 1: Pressure Vessels as applicable
Section IX :Welding and Brazing Procedures, Welders, Brazers, and Welding and
Brazing Operators

ASME B31.3 : Process Piping – 1999 Edition including Addenda 2000

NFPA : National Fire Protection Association


NFPA 59A-96: Standard for the Production, Storage, and Handling of Liquefied
Natural Gas (LNG)
(except 4.2.1(a) & (b). refer to project specification for LPG Storage Tank
S-00-1354-003)

Project Specifications:

S-00-1354-003 : Project Specification for LPG Storage Tanks


S-79-1354-001 : Mechanical Data Sheet for Propane Storage Tanks
S-00-1520-001 : General Welding Requirement for Tank
S-00-13A0-001 : Project Painting Specification

The following documents are considered to be an integral part of this document and shall be consulted as
necessary for information or instructions.

Contractor’s Documents (TKK Document N0.):

S-79-1354-433 Inspection & Test Procedure for Field Construction of Mechanical Tank
(P3777B-K-31) (PROPANE)
tba (by DIC) Welding Procedure Specification
tba (by DIC) Procedure of Welding Procedure Qualification Test
tba (by DIC) Procedure of Welder Qualification Test
tba (by DIC) Procedure of Production Test
S-79-1354-429 Material and Weld Traceability Control Procedure (PROPANE)
(P3777B-K-11)
S-79-1354-430 Radiographic Examination Procedure (PROPANE)
(P3777B-K-21)
S-79-1354-431 Dye Penetrant Examination Procedure (PROPANE)
(P3777B-K-22)
S-79-1354-432 Vacuum Box & Pneumatic Leak Test Procedure (PROPANE)
(P3777B-K-23)

File: Z:\3777 Iran LNG\Iran LNG\Iran LNG\QA QC Document\LPG Spec\S-79-1354-434 P-K-32_R4.doc TKK Doc No: N3777C-K-32
IRAN LNG PROJECT
DOCUMENT TITLE DOCUMENT NO.
Doc.
INSPECTION & TEST PLAN Unit No. FWBS Seq. Rev. Page 4 of 14
FOR FIELD CONSTRUCTION Type
OF MECHANICAL TANK (PROPANE) S 79 1354 434 4

S-79-1354-413 Tank Construction Procedure (PROPANE)


(P3777B-C-01)
S-79-1354-418 Hydrostatic & Pneumatic Test Procedure (PROPANE)
(P3777B-C-06)
S-79-1354-419 Purge and Cool Down Procedure (PROPANE)
(P3777B-C-07)

5.0 GENERAL

The attached Inspection and Test Plan (ITP) identifies the type of inspection and test, witness inspection
requirements, type of inspection records required for each construction item.

The inspection testing procedures and the acceptance criteria to verify the quality characteristics shall be in
accordance with the applicable standard and specifications.

6.0 MATERIAL TRACEABILITY CLASSIFICATION

The material traceability classification indicated in the attached ITP, i.e., class A to E, is defined as follows.

Class A and B material require the full traceability against the minimum lot number indicated in the material
certificate, and the individual identification number shall be marked on each piece of component. This is
required for the primary components of LPG inner tank. The difference between class A and B is that the
earlier requires preparation of the as-built map, by which the final orientation of individual material in the
completed tank can be known.

Class C material requires the traceability against the material certificate, however, the individual identification
number is not required. The group identification marking is applied on each piece of component.

Class D material also requires the traceability against the material certificate, however, no particular identificati
on number is applied. Instead, erection mark is applied to the finished component. In case of the pre-
assembled component, Erection mark is given not to each piece contained in the component but to each assemb
led component unit.

Class E material is the components made of normal grade material, and does not require the particular
traceability control. Their material specification is verified by the material marking, delivery note, etc.
The specific traceability classification for each material is provided in the right end column of material table of
the drawing. While this ITP and S-79-1354-433 (P3777B-K-31) I&T procedure provide the general
information on traceability classification, if any conflict is found, the priority shall be given to the drawing.

File: Z:\3777 Iran LNG\Iran LNG\Iran LNG\QA QC Document\LPG Spec\S-79-1354-434 P-K-32_R4.doc TKK Doc No: N3777C-K-32
IRAN LNG PROJECT
DOCUMENT TITLE DOCUMENT NO.
Doc.
INSPECTION & TEST PLAN Unit No. FWBS Seq. Rev. Page 5 of 14
FOR FIELD CONSTRUCTION Type
OF MECHANICAL TANK (PROPANE) S 79 1354 434 4

7.0 LEGENDS

DI : Dimensional Inspection
VI : Visual Inspection
RT : Radiographic Examination
UT : Ultrasonic Examination
PT : Liquid Penetrant Examination
VBT : Vacuum Box Test
PLT : Pneumatic Leak test
HT : Hydrostatic Test

Const: Constructor
DIC: Contractor (Daelim Industrial Co., LTD)
ILC: Company (Iran LNG)

A : Inspection/Testing by Constructor
W : Witnessing
H : Hold Point
R : Document Review
1 : 100%
2 : random
3 : at initial production/stage
4 : at Company’s discretion

File: Z:\3777 Iran LNG\Iran LNG\Iran LNG\QA QC Document\LPG Spec\S-79-1354-434 P-K-32_R4.doc TKK Doc No: N3777C-K-32
IRAN LNG PROJECT
DOCUMENT TITLE DOCUMENT NO.
Doc.
INSPECTION & TEST PLAN Unit No. FWBS Seq. Rev. Page 6 of 14
FOR FIELD CONSTRUCTION Type
OF MECHANICAL TANK (PROPANE) S 79 1354 434 4

Inspection Involvement
R Component / Fabrication Activity Inspection / Test Reference Code, Standard, Specification Quality Record
Const Cont ILC

1.0 PRE-INSPECTION MEETING Confirm inspection and test plan this ITP and relevant construction, inspection Minutes of PIM H H
and test procedures

2.0 WELD QUALIFICATION

2.1 Welding Procedure Qualification Welding ASME IX PQR A H W4/R


(if newly required) Visual Inspection WPQ Test Procedure (tba)
Mechanical Test

2.2 Welder Qualification Test Welding ASME IX WPQR A H W4/R


(If newly required) Visual Inspection WQ Test Procedure (tba)
RT

3.0 MATERIAL INSPECTION

3.1 Material Receiving Inspection Visual, Dimension No transport damage MRI Record A W3 W4

3.2 Material Storage Storage Condition Check Appropriate rust prevention measures NR A W4 W4

4.0 OUTER TANK

4.1 On-ground Assembly of Roof Material Identification (Class D) S-79-1354-429, S-79-1354-433 NR A W4 W4


Supporting Frame Weld Monitoring applicable WPS W. Monitoring Record A W2 W4/R
Visual, Dimension S-79-1354-433 VI/DI Record A W2 W4/R
3
IRAN LNG PROJECT
DOCUMENT TITLE DOCUMENT NO.
Doc.
INSPECTION & TEST PLAN Unit No. FWBS Seq. Rev. Page 7 of 14
FOR FIELD CONSTRUCTION OF Type
MECHANICAL TANK (PROPANE) S 79 1354 434 4

Inspection Involvement
R Component / Fabrication Activity Inspection / Test Reference Code, Standard, Specification Quality Record
Const Cont ILC

4.2 Roof Supporting Frame Erection Material Identification (Class D) S-79-1354-429, S-79-1354-433 NR A W2 W4
Weld Monitoring applicable WPS W. Monitoring Record A W2/R W4/R
Visual Inspection S-79-1354-433 VI Record A W2/R W4/R

4.3 Roof Liner incl. Roof Corner Liner Material Identification (Class D) S-79-1354-429, S-79-1354-433 NR A W2 W4
Weld Monitoring applicable WPS W. Monitoring Record A W2/R W4/R
Visual Inspection S-79-1354-433 VI Record A W2/R W4/R
PT (100%) for Roof Corner Liner S-79-1354-431, S-79-1354-433 PT Record A W2/R W4/R
VBT S-79-1354-432, S-79-1354-433 VBT Record A W3/R W4/R

4.4 Bottom Vapour Barrier Material Identification (Class D) S-79-1354-429, S-79-1354-433 NR A W2 W4


1 Weld Monitoring applicable WPS W. Monitoring Record A W2/R W4/R
Visual Inspection S-79-1354-433 VI Record A W2/R W4/R
VBT S-79-1354-432, S-79-1354-433 VBT Record A W3/R W4/R
Note : The foundation level survey Verify Foundation Level Applicable civil inspection specification Foundation Level Record R R R
record to verify prior to start outer (by Civil Constructor)
bottom installation.
4 4.5 Corner Anchor Plate Material Identification (Class D) S-79-1354-429, S-79-1354-433 NR A W2 W4
Weld Monitoring applicable WPS W. Monitoring Record A W2/R W4/R
Visual Inspection S-79-1354-433 VI Record A W2/R W4/R
VBT S-79-1354-429, S-79-1354-433 VBT Record A W3/R W4/R

4.6 Wall Vapour Barrier Material Identification (Class D) S-79-1354-429, S-79-1354-433 NR A W2 W4


Weld Monitoring applicable WPS W. Monitoring Record A W2/R W4/R
Visual Inspection S-79-1354-433 VI Record A W2/R W4/R
VBT S-79-1354-429, S-79-1354-433 VBT Record A W3/R W4/R

3
IRAN LNG PROJECT
DOCUMENT TITLE DOCUMENT NO.
Doc.
INSPECTION & TEST PLAN Unit No. FWBS Seq. Rev. Page 8 of 14
FOR FIELD CONSTRUCTION OF Type
MECHANICAL TANK (PROPANE) S 79 1354 434 4

Inspection Involvement
R Component / Fabrication Activity Inspection / Test Reference Code, Standard, Specification Quality Record
Const Cont ILC
4.7 Permanent Attachment on Roof Liner Material Identification (Class E) S-79-1354-429, S-79-1354-433 NR A W2 W4
Plate, Bottom and Wall V. Barrier Weld Monitoring applicable WPS NR A W2/R W4/R
Visual Inspection S-79-1354-433 VI Record A W2/R W4/R

4.8 Scars of Temporary Attach Weld Visual Inspection S-79-1354-433 VI Record A W2R W4/R

5.0 INNER TANK

5.1 Bottom Annular Plate Material Identification (Class A) S-79-1354-429, S-79-1354-433 M. Traceability Record A W2/R W4/R
(butt welded radial joints) Weld Monitoring applicable WPS W. Monitoring Record A W2/R W4/R
Weld Traceability S-79-1354-429, S-79-1354-433 W. Traceability Record A W2/R W4/R
Visual Inspection S-79-1354-433 VI Record A W2/R W4/R
PT S-79-1354-431, S-79-1354-433 PT Record A W2/R W4/R
RT (Spot) as per API R.7.6.5 S-79-1354-430, S-79-1354-433 API R7.6.5 RT Record A W1/R W4/R
VBT (before & after Hydotest) S-79-1354-432, S-79-1354-433 VBT Record A W3/R W4/R

5.2 Bottom Plate Material Identification (Class A) S-79-1354-429, S-79-1354-433 M. Traceability Record A W2/R W4/R
(btm-to-btm, btm-to-btm annular) Weld Monitoring applicable WPS W. Monitoring Record A W2/R W4/R
Weld Traceability S-79-1354-429, S-79-1354-433 W. Traceability Record A W2/R W4/R
Visual Inspection S-79-1354-433 VI Record A W2/R W4/R
PT S-79-1354-431, S-79-1354-433 PT Record A W2/R W4/R
VBT (before & after Hydrotest) S-79-1354-432, S-79-1354-433 VBT Record A W3/R W4/R

5.3 Shell Lowest Course Material Identification (Class A) S-79-1354-429, S-79-1354-433 M. Traceability Record A W2/R W4/R
(vertical joints) Weld Monitoring Applicable WPS W. Monitoring Record A W2/R W4/R
Production Weld Test S-79-1354-433, API 620 R.6.3 PWT Record A W1/R W4/R
Weld Traceability S-79-1354-429, S-79-1354-433 W. Traceability Record A W2/R W4/R

3
IRAN LNG PROJECT
DOCUMENT TITLE DOCUMENT NO.
Doc.
INSPECTION & TEST PLAN Unit No. FWBS Seq. Rev. Page 9 of 14
FOR FIELD CONSTRUCTION OF Type
MECHANICAL TANK (PROPANE) S 79 1354 434 4

Inspection Involvement
R Component / Fabrication Activity Inspection / Test Reference Code, Standard, Specification Quality Record
Const Cont ILC
Visual Inspection S-79-1354-433 VI Record A W2/R W4/R
PT S-79-1354-431, S-79-1354-433 PT Record A W2/R W4/R
RT (100%) S-79-1354-430, S-79-1354-433 RT Record A W1/R W4/R
Plumbness, Local Deviation Chk S-79-1354-413, S-79-1354-433 DI Record A W2/R W4/R
2 Levelness

5.4 Shell Bottom Corner Joint Weld Monitoring applicable WPS W. Monitoring Record A W2/R W4/R
(btm annular-to-shell lowest) Weld Traceability S-79-1354-429, S-79-1354-433 W. Traceability Record A W2/R W4/R
Visual Inspection S-79-1354-433 VI Record A W2/R W4/R
PT (Inside & Outside) S-79-1354-431, S-79-1354-433 PT Record A W2/R W4/R
VBT (after Hydrotest) S-71-1354-432, S-71-1354-433 VBT Record A W3/R W4/R
PLT (before Hydrotest) S-71-1354-432, S-71-1354-433 PLT Record A W2/R W4/R
Roundness Check S-79-1354-413, S-71-1354-433 DI Record A W2/R W4/R

5.5 Shell 2nd Lowest to Top Course Material Identification (Class A) S-79-1354-429, S-79-1354-433 M. Traceability Record A W2/R W4/R
(vertical and horizontal joints) Weld Monitoring applicable WPS W. Monitoring Record A W2/R W4/R
Weld Traceability S-79-1354-429, S-79-1354-433 W. Traceability Record A W2/R W4/R
Visual Inspection S-79-1354-433 VI Record A W2/R W4/R
PT S-79-1354-432, S-79-1354-433 PT Record A W2/R W4/R
RT (100%) for Vertical Joints S-79-1354-430, S-79-1354-433 RT Record A W1/R W4/R
RT (Spot) for Horizontal Joints S-79-1354-430, S-79-1354-433, API R.7.6 RT Record A W1/R W4/R
Local Deviation Chk S-79-1354-413, S-79-1354-433 DI Record A W2/R W4/R
VBT(note) S-79-1354-046, S-79-1354-433 VBT Record A W3/R W4/R
Production Weld Test (Top course) S-79-1354-433, API 620 R.6.3 PWT Record A W1/R W4/R

note: VBT is required for the portion above tank hydrotest water level, i.e.,
from 6th course vertical to top course vertical and horizontal.

3
IRAN LNG PROJECT
DOCUMENT TITLE DOCUMENT NO.
Doc.
INSPECTION & TEST PLAN Unit No. FWBS Seq. Rev. Page 10 of 14
FOR FIELD CONSTRUCTION OF Type
MECHANICAL TANK (PROPANE) S 79 1354 434 4

Inspection Involvement
R Component / Fabrication Activity Inspection / Test Reference Code, Standard, Specification Quality Record
Const Cont ILC
5.6 Shell Stiffener and Top Girder Material Identification (Class B) S-79-1354-429, S-79-1354-433 NR A W2 W4
(butt welded radial joints, attach Weld Monitoring applicable WPS W. Monitoring Record A W2/R W4/R
weld to shell, incl. rib plate weld) Visual Inspection S-79-1354-433 VI Record A W2/R W4/R
PT S-79-1354-431, S-79-1354-433 PT Record A W2/R W4/R
RT (Stiffener radial joints) S-79-1354-430, S-79-1354-433 RT Record A W1/R W4/R

5.7 Completed Tank Shell Plumbness Check S-79-1354-413, S-79-1354-433 DI Record A W2/R W4/R

5.8 Permanent Attachment to Inner Material Identification (Class C) S-79-1354-429, S-79-1354-433 NR A W2 W4


Tank (Rib, Pad, Clip, etc.) Weld Monitoring applicable WPS W. Monitoring Record A W2/R W4/R
Visual Inspection S-79-1354-433 VI Record A W2/R W4/R
PT S-79-1354-431, S-79-1354-433 PT Record A W2/R W4/R

5.9 Anchor Strap Material Identification (Class C) S-79-1354-429, S-79-1354-433 NR A W2 W4


Weld Monitoring applicable WPS W. Monitoring Record A W2/R W4/R
Visual Inspection S-79-1354-433 VI Record A W2/R W4/R
PT S-79-1354-431, S-79-1354-433 PT Record A W2/R W4/R
RT (Anchor to Anchor /cut joints) S-79-1354-430, S-79-1354-433 RT Record A W1/R W4/R
2 VBT (Weld for Anchor Strap S-79-1354-046, S-79-1354-433 VBT Record A W3/R W4/R
Cover Plate)

5.10 Scars of Temporary Attach Weld Visual Inspection S-79-1354-433 VI Record A W2/R W4/R
(include arc strike, if any) PT S-79-1354-045, S-79-1354-433 PT Record A W2/R W4/R

6.0 SUSPENDED CEILING DECK

3
IRAN LNG PROJECT
DOCUMENT TITLE DOCUMENT NO.
Doc.
INSPECTION & TEST PLAN Unit No. FWBS Seq. Rev. Page 11 of 14
FOR FIELD CONSTRUCTION OF Type
MECHANICAL TANK (PROPANE) S 79 1354 434 4

Inspection Involvement
R Component / Fabrication Activity Inspection / Test Reference Code, Standard, Specification Quality Record
Const Cont ILC
6.1 Ceiling Deck Material Identification (Class D) S-79-1354-429, S-79-1354-433 NR A W2 W4
Weld Monitoring applicable WPS W. Monitoring Record A W2/R W4/R
Visual Inspection S-79-1354-433 VI Record A W2/R W4/R

6.2 Deck Supporting Frame, Hanger, Material Identification (Class D) S-79-1354-429, S-79-1354-433 NR A W2 W4
Sleeve Pipe, Deck Hatchway, Free Weld Monitoring applicable WPS W. Monitoring Record A W2/R W4/R
Vent, etc. Visual Inspection S-79-1354-433 VI Record A W2/R W4/R

7.0 NOZZLE, MANHOLE AND TANK INTRNAL PIPING

7.1 Pump Well Material Identification (Class B) S-79-1354-429, S-79-1354-433 NR A W2 W4/R


Weld Monitoring applicable WPS W. Monitoring Record A W2/R W4/R
Weld Traceability S-79-1354-429, S-79-1354-433 W. Traceability Record A W2/R W4/R
Visual Inspection S-79-1354-433 VI Record A W2/R W4/R
PT S-79-1354-431, S-79-1354-433 PT Record A W2/R W4/R
RT (100% butt welds) S-79-1354-430, S-79-1354-433 RT Record A W1/R W4/R
Drift Test with Dummy Pump Applicable Drawings Drift Test Record A W2/R W4/R
Pressure Test Applicable Drawings, S-79-1354-413 Pressure Test Record A W2/R W4/R
2 VI,PT (Scar for Temp.Attachment S-79-1354-431, S-79-1354-433 VI, PT Record A W2/R W4/R
Weld)

7.2 Low Temperature Service Nozzle Material Identification (Class B) S-79-1354-429, S-79-1354-433 Mtl ID Record A W2/R W4/R
and Internal Pipe Weld Monitoring applicable WPS Weld Monitoring Record A W2/R W4/R
Weld Traceability S-79-1354-429, S-79-1354-433 Weld Traceability Record A W2/R W4/R
Visual Inspection S-79-1354-433 VI Record A W2/R W4/R
PT S-79-1354-431, S-79-1354-433 PT Record A W2/R W4/R

3
IRAN LNG PROJECT
DOCUMENT TITLE DOCUMENT NO.
Doc.
INSPECTION & TEST PLAN Unit No. FWBS Seq. Rev. Page 12 of 14
FOR FIELD CONSTRUCTION OF Type
MECHANICAL TANK (PROPANE) S 79 1354 434 4

Inspection Involvement
R Component / Fabrication Activity Inspection / Test Reference Code, Standard, Specification Quality Record
Const Cont ILC
RT (note) S-79-1354-430, S-79-1354-433 RT Record A W1/R W4/R
PLT (note) S-79-1354-432, S-79-1354-433 PLT Record A W2/R W4/R
2 Note: Stilling Well for Gauge Nozzles Verticality / Straightness S-79-1354-413 DI Record A W2/R W4/R
Note: PLT is required for reinforcing pad plate of nozzle and internal pipe with
closed end, e.g., thermo well pipe. RT 100% exclude internal piping of open ended
non pressure pipe, i.e., inert gas purge and stilling well of level gauge etc.,

7.3 Ambient Temp Service Nozzle/MH Material Identification (Class D) S-79-1354-429, S-79-1354-433 Note on Mtl Certificate A W2 W4/R
Weld Monitoring applicable WPS Weld Monitoring Record A W2/R W4/R
Visual Inspection S-79-1354-433 VI Record A W2/R W4/R
PLT (note) S-79-1354-432, S-79-1354-433 PLT Record A W2/R W4/R

Note: PLT is required for reinforcing pad plate of nozzle/manhole.

7.4 Permanent Attachment to L.T. Material Identification (Class D) S-79-1354-429, S-79-1354-433 NR A W2 W4


Service Nozzle and Internal Pipe Weld Monitoring applicable WPS Weld Monitoring Record A W2/R W4/R
Visual Inspection S-79-1354-433 VI Record A W2/R W4/R
PT S-79-1354-431, S-79-1354-433 PT Record A W2/R W4/R

7.5 Scars of Temp Attach Weld on L.T. Visual Inspection S-79-1354-433 VI Record A W2/R W4/R
Service Nozzle PT S-79-1354-431, S-79-1354-433 PT Record A W2/R W4/R
(include arc strike, if any)

3
IRAN LNG PROJECT
DOCUMENT TITLE DOCUMENT NO.
Doc.
INSPECTION & TEST PLAN Unit No. FWBS Seq. Rev. Page 13 of 14
FOR FIELD CONSTRUCTION OF Type
MECHANICAL TANK (PROPANE) S 79 1354 434 4

Inspection Involvement
R Component / Fabrication Activity Inspection / Test Reference Code, Standard, Specification Quality Record
Const Cont ILC
8.0 HYDROSTATIC TEST

8.1 Water Filling Pre-test Cleaning Check Client 's agreement NR A H H


Quality of Test Water API620, Q8.3 as for reference Analysis Record A H/R H/R
Water Level Check S-79-1354-418, S-79-1354-433 Hydro test Record A W2/R W4/R
Tank Settlement Monitoring S-79-1354-418, S-79-1354-433 Settlement Record A W2/R W4/R

8.2 Hydrostatic Test Water Level Check S-79-1354-418, S-79-1354-433 Hydro test Record A H/R H/R
Visual Inspection for Tank Shell S-79-1354-418, S-79-1354-433 Hydro test Record A W2/R H/R

8.3 Pneumatic Pressure Test Pressure Check S-79-1354-418, S-79-1354-433 Pressure Test Record A H/R H/R
PLT for welds uncovered by S-79-1354-418, S-79-1354-433 PLT Record A W2/R W4/R
concrete

8.4 Post-hydrotest Inspection Visual Inspection for tank Inside S-79-1354-418, S-79-1354-433 Hydro test Record A H/R H/R
VBT for Bottom Welds S-79-1354-432, S-71-1354-433 VBT Record A W2/R W4/R
Cleaning Check Company’s agreement Hydro test Record A H/R H/R

8.5 Function Test of PRV and VRV Set and Reseat Pressure Check S-79-1354-418, S-79-1354-433 Function Test Record A H/R H/R

9.0 TANK EXTERNAL ACCESSORY

9.1 Structures Material Identification (Class E) S-79-1354-429, S-79-1354-433 NR A W2 W4


(staircase, ladder, platform, handrail, Weld Monitoring applicable WPS NR A W2 W4
etc.) Visual Inspection S-79-1354-433 VI Record A W2/R W4/R

3
IRAN LNG PROJECT
DOCUMENT TITLE DOCUMENT NO.
Doc.
INSPECTION & TEST PLAN Unit No. FWBS Seq. Rev. Page 14 of 14
FOR FIELD CONSTRUCTION OF Type
MECHANICAL TANK (PROPANE) S 79 1354 434 4

Inspection Involvement
R Component / Fabrication Activity Inspection / Test Reference Code, Standard, Specification Quality Record
Const Cont ILC
9.2 Pipe Support if any Material Identification (Class (E) S-79-1354-429, S-79-1354-433 NR A W2 W4
Weld Monitoring applicable WPS NR A W2 W4
Visual Inspection S-79-1354-433 VI Record A W2/R W4/R

10.0 INSULATION (by other ITP) Applicable ITP (tba) S-79-1354-416, S-79-1354-417 Inspection Records A W2 W4
Applicable ITP

11.0 PAINTING (by other ITP) Applicable ITP (tba) S-79-1354-301 Inspection Records A W2 W4
Applicable ITP

12.0 FINAL INSPECTION

12.1 Tank Inside Cleaning Tank Inside Cleaning Check no foreign article, sufficient cleanness Box up Certificate A H/R H/R

12.2 Box-up Manhole Closing secure closing Box up Certificate A H/R H/R

13.0 DRYING AND PURGING as per S-79-1354-419 S-79-1354-419 Related Records A H/R H/R

You might also like